FURNISH AND INSTALL GENERATOR AT LOVE LANE State and local opportunity open Town of Manchester 26/27-20 Posted: 2026-11-05T13:00:01.079Z Response deadline: 2026-11-30T16:00:00.000Z The Town of Manchester is soliciting bids to furnish and install a complete standby diesel generator at the Love Lane Pump Station. The station is a critical sewage pump station and must keep pumping, and keep its alarms, during a utility outage. Work is turnkey and includes the generator, dual-wall sub-base tank sized for 48 hours at 100 percent of the standby rating, sound-attenuated enclosure, automatic transfer switch, concrete pad at the required flood elevation, conduit and wiring, startup, load-bank testing, training, and initial fuel fill. FURNISH AND INSTALL GENERATOR AT LOVE LANE TOTAL BID SHALL INCLUDE ALL WORK DESCRIBED IN THIS BID. Diesel generator set (standby, sound-attenuated Level 2 enclosure, sub-base tank, controller, battery/charger, breaker, and all appurtenances) Automatic transfer switch (UL 1008, 100 A min., open transition, including any new enclosure if required) Concrete pad, anchorage, trenching, conduit (min. 3), wiring, grounding, surface restoration, and all civil/electrical work Startup, factory test report, 2-hour load-bank test, building-load test with pump start, alarm demonstration, and 2 hours of training Initial fuel fill (ULSD to 85–90% of usable capacity) Electronic O&M manuals and as-builts Project Details Scope of Work The Contractor shall furnish and install a complete turnkey system including the following: • Diesel generator, minimum 60 Hz standby, electronic isochronous governor, unit-mounted radiator rated for high ambient, jacket-water heater, coolant and oil drain extensions, low-coolant shutdown • Alternator with increased motor-starting capability as required to meet the dip limits; 100 A, 3-pole generator breaker • Aluminum sound-attenuated Level 2 enclosure, green, wind rating not less than 180 mph, sound not more than 72 dBA at 23 feet • Digital controller with English display, emergency stop on the unit, and a remote emergency stop in a NEMA 4X enclosure • Battery, rack, and regulated charger, 6 A minimum, with charger-failure alarm • Dual-wall sub-base tank, UL 142, sized for 48 hours at 100 percent of the standby rating using the published full-load burn rate. State usable gallons, gallons per hour, and calculated hours of runtime. A 24-hour tank, or a tank sized only on the running load, is non-responsive • Tank appurtenances: mechanical gauge; low level at 40 percent; high level at 90 percent; rupture-basin leak switch; 5-gallon lockable spill-containment fill; normal and emergency vents. No biodiesel • UL 1008 automatic transfer switch, 100 A minimum, 208/120 V, 3-pole solid neutral, open transition, in-phase monitor. Fit the switch to the existing cabinet. If it will not fit, furnish a new enclosure in the base bid. Withstand rating shall meet available fault current • New concrete pad at the required flood elevation, anchorage, trenching, minimum three conduits (power, control, spare), backfill, and surface restoration • All wiring, grounding, auto-start, and alarm landings. Label both ends • Dry contact outputs for the alarm points listed under TR-16, wired and landed at the existing telemetry panel. Demonstrate the contacts. SCADA head-end programming is not included and will be performed by the Town or its integrator • Factory full-load test report; on-site startup; 2-hour load-bank test at rated kW; building-load test with a pump start; alarm demonstration • Two hours of training for Operations Staff, Process Control Supervisor, and Superintendent • Initial fill of ultra-low-sulfur diesel to 85–90 percent of usable tank capacity • Electronic O&M manuals and as-builts Not included: Pump or motor replacement, Eversource fees (Town-paid; contractor prepares applications), Town permit fee (waived), and SCADA head-end programmin g. Design Basis A September 2, 2026 load study is the basis of design. Any manufacturer may be proposed provided the performance requirements below are met. • 60 Hz, 3-phase, 120/208 V, 4-wire • Standby duty, diesel, EPA stationary emergency use only • Site conditions: 500 ft elevation • Minimum rating: 25 kW standby after enclosure, altitude, and temperature derates, or larger as required to meet the voltage and frequency dip limits stated below • Motor Load 1: 3 HP, 208 V, 3-phase, across-the-line, NEMA Code K. Start 16.75 kW / 25.48 kVA. Run 2.74 kW / 3.34 kVA • Miscellaneous loads: start 7.5 kW, run 5.0 kW, PF 0.9 • Step B (second motor start with Step A already running): start 31.99 kW / 42.7 kVA; run 10.48 kW / 12.23 kVA • Voltage dip: 20 percent preferred, 30 percent maximum. Frequency dip: 10 percent maximum • Bidder shall submit a generator sizing report demonstrating compliance with the loads and dip limits above • Site Address: 90 Love Lane, Manchester, CT 06040 Codes and Standards Install the current adopted edition of each of the following. The stricter requirement governs. • NEIWPCC TR-16, Guides for the Design of Wastewater Treatment Works (2016 and 2026 editions) • CT DEEP wastewater requirements applicable to this station • NFPA 110, Level 1, Type 10 (power available within 10 seconds) • NFPA 70, NFPA 30, NFPA 37, and the Connecticut State Fire Safety and Building Codes • UL 2200 generator, UL 1008 transfer switch, UL 142 fuel tank • EPA 40 CFR Part 60 Subpart IIII, Tier 3 or the tier required for the model year, stationary emergency use only TR-16 minimums for this station: • Permanently installed generator. A portable unit is not acceptable. • Automatic start and transfer within 10 seconds. • Capacity to start and run the pumps and the auxiliaries needed to pass peak flow and keep the station monitored: controls, telemetry, lighting, ventilation, and heat. • Generator, tank, and transfer switch at or above the base flood elevation plus 2 feet, or the stricter TR-16 / building-code flood elevation. • Alarm contacts to existing station telemetry: generator run, fail-to-start, low fuel, high fuel, rupture basin, ATS position, and common alarm. • On-site fuel for not less than 48 hours at 100 percent of the standby rating, without refueling. NOTES Total bid shall include all work described in this bid. State usable tank gallons, gallons per hour at full load, and calculated runtime in the technical proposal. Generator sizing report demonstrating compliance with Step A / Step B loads and voltage/frequency dip limits is mandatory. Bid prices shall be firm for 60 days. Warranty Generator: minimum 2 years / 1,000 hours from accepted startup. Transfer switch: 2 years. Workmanship: 1 year. State service-shop address and typical emergency response time. Introduction Summary Background Contact Information Timeline Instructions to Bidders INSTRUCTIONS TO BIDDERS In accordance with the provisions of the Town Charter, sealed proposals will be received not later than the date and time set forth above, for furnishing the commodities and/or services listed herein. Proposals must be executed in accordance with and subject to instructions and specifications contained herein. The Town of Manchester is an equal opportunity employer and requires an affirmative action policy for all of its Contractors and Vendors as a condition of doing business with the Town, as per Federal Order 11246. By submitting the Proposal for this bid, all vendors and contractors agree to this condition of doing business with the Town, and should the Town choose to audit their compliance, the vendor agrees to cooperate fully. ELECTRONIC BIDDING INFORMATION Important Instructions for Electronic Submittal Specifications and bid forms must be obtained online at Town of Manchester Procurement Portal (opengov.com) . The exclusive means by which all prospective bidders may obtain bid packages, direct inquiries, request and receive addenda and supplemental information, and submit bids and proposals, shall be through the Town of Manchester’s OpenGov portal. Bids may be received up to the deadline date and time listed in the solicitation documents, via the Town’s e-Procurement Portal. The Town e-Procurement Portal Clock is the official clock for the determination of all deadline dates and times. Without exception, responses will not be accepted after the submission deadline regardless of any technical difficulties such as poor internet connections. The Town of Manchester strongly recommends completing your response well ahead of the deadline. Addenda Notification and Acknowledgement Addenda Notification: Bidders are required to register for an account via the Town’s e-Procurement Portal hosted by OpenGov. Once the bidder has completed registration, you will receive addenda notifications to your email by clicking “Follow” on this project. Ultimately, it is the sole responsibility of each bidder to periodically check the site for any addenda at Town of Manchester Procurement Portal (opengov.com) . Submitting Questions and Receiving Responses Bidders shall submit all inquiries regarding this bid via the Town’s e-Procurement Portal. Please note any deadline for submitting inquiries. All answers to inquiries will be posted on the Town’s e-Procurement Portal. Bidders may also click “Follow” on this bid to receive an email notification when answers are posted. It is the responsibility of the bidder to check the website for answers to inquiries. When applicable, state bids will be considered for this service. The Purchasing Authority reserves the right to waive any informality or reject any and all bids. In addition to the bid specifications, all bids are subject to the terms, provisions and conditions of the Manchester Charter, Code of Ordinances, and Purchasing Guidelines. By bidding on the proposed purchase, the bidder agrees to such terms, provisions and conditions. An Equal Opportunity/Affirmative Action Employer RULES AND REGULATIONS FOR COMPETITIVE BIDDING These rules and regulations have been adopted by the Board of Directors of the Town of Manchester pursuant to Section 5-22 of the Town Charter. They are standard for all competitive bidding proposals issued by the Town of Manchester, Connecticut for contracts of all types where labor, materials, and necessary equipment to complete work is to be furnished to the Town, where the Town is to purchase supplies, materials, and equipment, where the Town is to sell surplus materials and equipment, or where the Town is to sell real estate. These rules and regulations shall be binding upon all prospective bidders and the Town of Manchester. GENERAL RULES 1. The Purchasing Authority may delete or modify any of the instructions to bidders for a particular proposal, indicating such change in the appropriate section of the proposal documents. The Purchasing Authority may insert special instructions in any special contracts which are subject to competitive bidding. 2. The proposal is signed by the bidder with full knowledge of, and agreement with, the general specifications, conditions, and requirements of this bid. In addition to the bid specifications, all bids are subject to the terms, provisions and conditions of the Manchester Charter, Code of Ordinances, and Purchasing Guidelines. By bidding on the proposed purchase or service, the bidder agrees to such terms, provisions, and conditions. 3. The Town has transitioned to electronic bidding. Vendors should submit solicitation responses electronically via the Town of Manchester Procurement Portal. Vendors will be asked to register and should do so prior to submitting bid documents. 4.This bid and any addenda will be issued on the Town of Manchester website bidding portal. It shall be the responsibility of the bidder to download this information. THE TOWN OF MANCHESTER WILL NOT MAIL A SEPARATE HARD COPY OF ADDENDUM TO BIDDERS. Failure of any bidder to receive any such addendum or interpretation shall not relieve such bidder from any obligation under his bid as submitted. All addenda so issued shall become part of the Contract Documents. 5. Bid prices may not be withdrawn by bidder for 90 days after bid opening. 6. Proposals received later than the time and date specified will not be considered. Amendments to, or withdrawals of bids received later than the time and date set for bid opening will not be considered. 7. All bids shall be opened via a virtual meeting link posted and read aloud. All bids shall be tabulated and copies of said tabulation shall be posted on the website 8. All deliveries of commodities or services hereunder shall comply in every respect with all applicable laws of the Federal Government and/or the State of Connecticut. 9. Purchases made by the Town of Manchester are exempt from payment of Federal Excise Taxes and the Connecticut Sales Tax and such taxes must not be included in bid prices. Federal Excise Tax exemption certificates, if requested, will be furnished. 10. The Bidder, where applicable, shall insert/include the price per stated unit and extend a total price for each item. In the event there is a discrepancy between the unit price and the extension, the unit price will govern. The total cost shall be the sum of the extended prices. 11. Bidders shall, where applicable, submit terms for payment in spaces provided in the proposal form, showing the amount of cash discount which shall apply to bid prices when paid within the stated number of days in the proposal. 12. All inquiries shall be submitted within the time limitations specified in the bid documents and shall be requested via the online portal Q&A. All information given by the Town other than through the OpenGov portal shall be informal and shall not be binding upon the Town nor shall it furnish a basis for legal action by any bidder or prospective bidder against the Town. 12A. The Town reserves the right to reject any and all bids, to waive technical defects and to make such awards including accepting a bid, although not the low bid, as it deems in its sole discretion to be in the best interest of the Town. The Town reserves the right to reject any bid if the bidder, any officer of the bidder, or any other company owned in whole or in part by any officer(s) of the bidder, is delinquent in the payment of any taxes or fees owed to the Town. The Town reserves the right to require a disclosure statement from the bidder listing the name(s) of all officers of the company. 12B. In the event the Town determines that a contractor is delinquent in any payment due the Town, then the Town may offset the delinquent amount due to the Town against the sums owed the contractor. 13. The Town of Manchester may make such investigation as deemed necessary to determine the ability of the bidder to discharge a contract. The bidder shall furnish the Town with all such information and data as may be required for that purpose. The Town reserves the right to reject any bid if the bidder fails to satisfactorily convince the Town that he is properly qualified by experience and facilities to carry out the obligations of the contract and to satisfactorily complete the work called for herein, or if the bid is conditional in nature. 14. Except where otherwise provided, a contract between the Town and a successful bidder shall consist of the Invitation to Bid, Specifications, Plans, Bid including Proposal form and these Rules and Regulations. Acceptance by the Town may be by purchase order for the portion of the work awarded to a contractor. 15. All Invitations to Bid shall be publicly advertised in a newspaper having a general circulation within the Town of Manchester, Connecticut. 16. Bids shall be made available on the Town of Manchester Purchasing Web Site via the Bidding site . 17. Alternate bids shall not be accepted unless otherwise specified in the bid documents. 18. Any act or acts of misrepresentation or collusion shall be a basis for disqualification of any bid or bids submitted by such persons guilty of said misrepresentation of collusion. In the event that the Town enters into a contract with any bidder who is guilty of misrepresentation or collusion and such conduct is discovered after the execution of said contract, the Town may cancel said contract without incurring liability, penalty, or damages. 19. In the event that any bidder wishes to protest the potential award of a bid, the bidder must make it’s protest in writing identify the protesting party and the bid number, title and shall include a factual summary of the basis of the protest including any documents that shall be considered and request a conference with Bid Opening Information Bid responses will be received by 11:00 am on Monday, November 30, 2026 Bid openings will be held virtually through Zoom. ZOOM meeting instructions are as identified in the Introduction Section above. The virtual bid opening will be exactly the same as a regular bid opening – Purchasing staff will open the bids and read the results out loud. Results are not final until reviewed, tabulations compiled and then posted/distributed to participants. In addition, the requesting department will recommend an award after a complete review of the submissions. Insurance and Indemnification Requirements GENERAL CONDITIONS: Within ten (10) business days of the award or notice, or prior to the start of work, whichever comes first, the contractor will provide, pay for, and maintain in full force and effect the insurance outlined here for coverage’s at not less than the prescribed minimum limits of liability. Such coverage is to remain in force during the life of the contract and for such additional time as may be required, and will cover the contractor/ independent insured’s activities, those of any and all subcontractors, or anyone directly or indirectly employed by any of them, or by anyone for whose acts any of them may be liable. Any failure to comply with reporting requirements and provisions of the policies shall not affect coverage provided to Town, its officers, officials, agents, or employees. A. Certificates of Insurance : The contractor will give the owner a certificate of insurance completed by a duly authorized representative of their insurer certifying that at least the minimum coverage’s required here are in effect and specifying that the liability coverage’s are written on an occurrence (or claims-made where applicable) form and that the coverage’s will not be canceled, non-renewed, or materially changed by endorsement or through issuance of other policy(ies) of insurance without sixty (60) days advance written notice to the Purchasing Division. Failure of the owner to demand such certificate or other evidence of full compliance with these insurance requirements or failure of the owner to identify a deficiency from evidence provided will not be construed as a waiver of the contractor’s obligation to maintain such insurance. Any failure to comply with reporting requirements and provisions of the policies shall not affect coverage provided to Town, its officers, officials, agents, or employees. B. Insurer Qualification : All insurance will be provided through companies authorized to do business in the State of Connecticut and considered acceptable by the owner. Insurance Companies shall maintain a minimum A.M. Best rating of A-/VIII. C. Additional Insured : The policy or policies providing insurance as required, with the exception of professional liability and workers’ compensation, will defend and include the owner, directors, officers, representatives, agents and employees, and where applicable owner’s architects or engineers, as additional insureds on a primary and noncontributory basis for work performed under or incidental to this contract. D. Retroactive Date and Extended Reporting Period : Coverage, whether written on a claims made or occurrence basis, shall be maintained Source: OpenGov https://procurement.opengov.com/portal/townofmanchester/projects/322534 Canonical URL: https://govcontractfinder.com/contracts/furnish-and-install-generator-at-love-lane-opengov-3998-project-322534