St. Paul's Blue-Greenway - Stormwater Phase State and local opportunity open City of Norfolk 19263 Posted: 2026-10-15T12:00:01.418Z Response deadline: 2026-12-18T21:00:00.000Z The St. Paul's Blue-Greenway Stormwater Phase includes daylighting of approximately 1,200 linear feet of existing box culvert, excavation, active-flow management, deep foundations, retaining structures, a pedestrian bridge, drainage work, erosion and sediment controls, and restoration. SCHEDULE OF UNIT PRICES For St. Paul's Blue-Greenway - Stormwater Phase The unit prices have been computed in accordance with Paragraph 7.3.3.2 of the General Conditions of the Contract for Construction (as amended). Bidder acknowledges that estimated quantities are not guaranteed and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Bid items will be based on actual quantities provided, determined as provided in the Contract Documents. The prices quoted shall include, without exception, all materials, labor, equipment, appliances, clean-up, applicable sales, use and other taxes, building permits or fees, and the Contractor's labor, overhead, profit, mobilization, and other mark-ups, and in full accordance with the Specifications. Include allowance for waste where appropriate. The unit prices shall be maintained throughout the contract period. Unit prices shall be used in determining additions or deductions from the TOTAL CONTRACT AWARD amount in the event of changes in the work. Mobilization and Demobilization Construction Surveying Silt Fence Inlet Protection Outlet Protection, VDOT Standard EC-1 Construction Entrance Temporary Dewatering Structure Temporary Sediment Basin A Flow Bypass Operations Temporary Seeding Erosion Control Matting, Jute EC-2 Tree Protection Demolish Asphalt Paving Demolish Concrete Paving Demolish Concrete (miscellaneous) Demolish Concrete Curb and Gutter Demolish Chain Link Fence Demolish Goal Post Demolish Tree Demolish Sanitary Sewer Piping Demolish Hot and Cold-Water System Piping Demolish Water Piping Demolish Storm Drain Piping Demolish Storm Drain Structure Demolish Storm Drain Flared End Section and Outlet Protection Cap Utility Demolish Box Culvert Complete Demolish Box Culvert General Abandon Box Culvert Timber Pile Removal Regular Excavation and Disposal Select Material, VDOT Type II Slope Protection Rip Rap Storm Drain Manhole (5’ Diameter) Storm Drain Manhole (8’ Diameter) Standard Grate Inlet 18” RCP 24” RCP 30” RCP Affidavit (Form of Bid, Page 1.3-4) Please upload a certified copy of the Affidavit with the Form of Bid, page 1.3-4 . The successful apparent low bidder, plus 2nd and 3rd placed bidders shall MAIL the Affidavit certified no later than the bid date. Failure to provide an original Affidavit matching the electronic Affidavit accompanying the bid may be grounds for debarment from future bidding. Project Details Important Bid Details Work to be Substantially Completed in: 360 calendar days Liquidated Damages: one thousand two hundred dollars ($1,200.00) per day Performance Bond: one hundred percent (100%) Payment Bond: one hundred percent (100%) Bid Bond: five percent (5%) Closing Date/Time: Friday, December 18, 2026 4:00 pm Partial funding for the project is being provided by the Land and Water Conservation Fund of the National Park Service administered in Virginia by The Department of Conservation and Recreation and must be undertaken in accordance with the Land and Water Conservation Fund guidance of the NPS, 2, 36, and 43 CFR, and the Build America, Buy America Acts. This agreement is for services related to a project that is subject to the Build America, Buy America Act (BABAA) requirements under Title IX of the Infrastructure Investment and Jobs Act (“IIJA”), Pub. L. 177-58. Absent an approved waiver, all iron, steel, manufactured products, and construction materials used in this project must be produced in the United States, as further outlined by the Office of Management and Budget’s Memorandum M-22-11, Initial Implementation Guidance on Application of Buy America Preference in Federal Financial Assistance Programs for Infrastructure, April 18, 2022. Physical Correspondence All physical correspondence will be sent to the address shown below and include the Project ID and Project Title. Ken Peacock , Design & Construction Contracting Specialist Project - 19263 : St. Paul's Blue-Greenway - Stormwater Phase City of Norfolk, Public Works 810 Union St, 7th Floor Norfolk VA, 23510 Plan Holders List / Project Followers Upon request, contact Ken Peacock at kenneth.peacock@norfolk.gov . Please also check the Followers Tab on this e-Procurement Portal. Other Methods to Receive Bidding Documents Bidding Documents are available from the Department of Public Works at no cost by download at https://procurement.opengov.com/portal/norfolk/projects/308994 or from the City of Norfolk’s website, http://www.norfolk.gov/bids.aspx . A Bid Bond, certified check, or cashier’s check made payable to the Treasurer, City of Norfolk, for five percent (5%) of total bid must accompany each bid. Offerors shall upload a copy of the bid guarantee with the Offeror’s acknowledgement to mail the original sealed document to the Owner, within two (2) business days. State Contractor registration class and number is required by electronic bidding via the Vendor Questionnaire. The City reserves the right to cancel the bid opening or to reject any or all bids in whole or part, when it is in the best interest of the City. The right to waive informalities and to determine responsiveness of any bid and responsibility of all bidders is reserved to the City. Withdrawal of bids will be in accordance with Section 33.1-42.1 of the Norfolk City Code and Section 11-54 of The Code of Virginia, 1950 (as amended). Introduction Summary Background Contact Information Timeline Vendor Questionnaire Unit Price Bid Bid Award shall be based on the lowest responsive and responsible Total Bid regardless of whether the City elects to award any or all of the Add Alternates. Attachments Source: OpenGov https://procurement.opengov.com/portal/norfolk/projects/308994 Canonical URL: https://govcontractfinder.com/contracts/st-pauls-blue-greenway-stormwater-phase-opengov-757-project-308994