22275 RB - Hague NE Bulkhead Rehabilitation
Description
The Hague Bulkhead is undergoing rehabilitation to replace sections of the concrete bulkhead: Design and two phased constructions from near Botetourt Ped Bridge to Chrysler Museum, then to Hague Tower property. Coffer dams will be installed during the construction and areas around the bulkhead will be blocked off for safety. SCHEDULE OF UNIT PRICES For Hague NE Bulkhead Rehabilitation The unit prices have been computed in accordance with Paragraph 7.3.3.2 of the General Conditions of the Contract for Construction (as amended). Bidder acknowledges that estimated quantities are not guaranteed and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Bid items will be based on actual quantities provided, determined as provided in the Contract Documents. The prices quoted shall include, without exception, all materials, labor, equipment, appliances, clean-up, applicable sales, use and other taxes, building permits or fees, and the Contractor's labor, overhead, profit, mobilization, and other mark-ups, and in full accordance with the Specifications. Include allowance for waste where appropriate. The unit prices shall be maintained throughout the contract period. Unit prices shall be used in determining additions or deductions from the TOTAL CONTRACT AWARD amount in the event of changes in the work. Offeror will provide a complete Bulkhead Rehabilitation solution at the Lump Sum pricing below. Lump Sum Bid Project Details Important Bid Details Work to be Substantially Completed in: 700 calendar days Liquidated Damages: one thousand dollars ($1,000.00) per day Performance Bond: one hundred percent (100%) Payment Bond: one hundred percent (100%) Bid Bond: five percent (5%) Closing Date/Time: Tuesday, December 15, 2026 4:00 pm Physical Correspondence All physical correspondence will be sent to the address shown below and include the Project ID and Project Title. Ken Peacock , Design & Construction Contracting Specialist Project - 22275 RB : 22275 RB - Hague NE Bulkhead Rehabilitation City of Norfolk, Public Works 810 Union St, 7th Floor Norfolk VA, 23510 Plan Holders List / Project Followers Upon request, contact Ken Peacock at kenneth.peacock@norfolk.gov . Please also check the Followers Tab on this e-Procurement Portal. Other Methods to Receive Bidding Documents Bidding Documents are available from the Department of Public Works at no cost by download at https://procurement.opengov.com/portal/norfolk/projects/290651 or from the City of Norfolk’s website, http://www.norfolk.gov/bids.aspx . A Bid Bond, certified check, or cashier’s check made payable to the Treasurer, City of Norfolk, for five percent (5%) of total bid must accompany each bid. Offerors shall upload a copy of the bid guarantee with the Offeror’s acknowledgement to mail the original sealed document to the Owner, within two (2) business days. State Contractor registration class and number is required by electronic bidding via the Vendor Questionnaire. The City reserves the right to cancel the bid opening or to reject any or all bids in whole or part, when it is in the best interest of the City. The right to waive informalities and to determine responsiveness of any bid and responsibility of all bidders is reserved to the City. Withdrawal of bids will be in accordance with Section 33.1-42.1 of the Norfolk City Code and Section 11-54 of The Code of Virginia, 1950 (as amended). Introduction Summary Background Contact Information Timeline Vendor Questionnaire Lump Sum Bid Bid Award shall be based on the lowest responsive and responsible Total Bid regardless of whether the City elects to award any or all of the Add Alternates. Attachments
Published attachments
Addenda and notices
Addendum #1 · 1
ADDENDUM NO. 1 Dated: November 17, 2026 22275 RB - Hague Bulkhead Rehabilitation Except as may be otherwise described, bidding requirements, materials, and workmanship for the work described herein shall conform to all requirements of the original Contract Documents. The following Addendum to the drawings and specifications are made a part of the project and takes precedence over the section of the specifications, in part, and/or drawings, as originally written. This Addendum consists of one (1) page. ITEM NO. DESCRIPTION Complete Bid Package Delete: Original Replace with: 22275 RB – Complete Bid Package – Rev 111726 Front End and Back End updated. Technical Specifications – Section 109 has been updated. RFI/Question Submission Deadline and Response/Proposal Submission Deadline Extension RFI/Question Submission Deadline – Extended to December 7, 2026, at 4 PM. Response/Proposal Submission Deadline – Extended to December 15, 2026, at 4PM Receipt of this addendum shall be acknowledged on page 1.3-1 of the Bid Form Prepared by: Ken Peacock, Design & Construction Contracting Specialist Issued by: Ken Peacock, Design & Construction Contracting Specialist
Addendum #2 · 2
ADDENDUM NO. 2 Dated: November 18, 2026 22275 RB - Hague Bulkhead Rehabilitation Except as may be otherwise described, bidding requirements, materials, and workmanship for the work described herein shall conform to all requirements of the original Contract Documents. The following Addendum to the drawings and specifications are made a part of the project and takes precedence over the section of the specifications, in part, and/or drawings, as originally written. This Addendum consists of three (3) pages. ITEM NO. DESCRIPTION QUESTIONS AND RESPONSES 1. Pre-bid meeting Question: The last time this project was advertised there was a mandatory pre-bid meeting. The current bid documents do not indicate that there is a pre-bid meeting at all. Please confirm this is the case. Answered by Ken Peacock: There will be no pre-bid meeting per the project manager. There are answers from the questions received from the previous version of this project in the supporting documents section. 2. Measurement and Payment Question: This is now a Lump Sum Bid with only one Item. The Measurement and Payment Section (109) indicates that several items of Pile Extraction, Pile Cutoff, Timber Piles, and Disposal of Contaminated Soils are to be paid as Unit Prices. There are currently no Bid Items for these on the Bid Form. Will the Bid Form be revised to add these Items? Answered by Ken Peacock: The Measurement and Payment Section will be used to define additional work items should they be issued through a change order. This will be a lump sum solution for the base and all additives. One bid for all the work. 3. Lump Sum Bid Question: Does the Lump Sum Bid Price include the Base Bid and all three (3) of the Additive Bid Items? Answered by Ken Peacock: This will be a lump sum solution for the base and all additives. One bid for all the work. Base and additives will not be separated as separate bid items. 4. Monday Bid Question: Can the bid date be moved from Monday to a mid-week submission? Monday bids impact the sub and supplier solicitation process, requiring Contractors to complete final quote review and selection, bid review and closeout by the preceding Friday. A mid-week bid date provides Contractor's with a much more efficient work flow of receiving and reviewing critical sub and supplier pricing prior to bid submission. Answered by Ken Peacock: Bid response date is being adjusted and extended in upcoming addenda. 5. Project Duration Question: The bid documents stipulate 700 cal
Public questions and answers
The last time this project was advertised there was a mandatory pre-bid meeting. The current bid documents do not indicate that there is a pre-bid meeting at all. Please confirm this is the case.
There will be no pre-bid meeting per the project manager. There are answers from the questions received from the previous version of this project in the supporting documents section.
This is now a Lump Sum Bid with only one Item. The Measurement and Payment Section (109) indicates that several items of Pile Extraction, Pile Cutoff, Timber Piles, and Disposal of Contaminated Soils are to be paid as Unit Prices. There are currently no Bid Items for these on the Bid Form. Will the Bid Form be revised to add these Items?
The Measurement and Payment Section will be used to define additional work items should they be issued through a change order. This will be a lump sum solution for the base and all additives. One bid for all the work.
Does the Lump Sum Bid Price include the Base Bid and all three (3) of the Additive Bid Items?
This will be a lump sum solution for the base and all additives. One bid for all the work. Base and additives will not be separated as separate bid items.
Can the bid date be moved from Monday to a mid-week submission? Monday bids impact the sub and supplier solicitation process, requiring Contractors to complete final quote review and selection, bid review and closeout by the preceding Friday. A mid-week bid date provides Contractor's with a much more efficient work flow of receiving and reviewing critical sub and supplier pricing prior to bid submission.
Bid response date is being adjusted and extended in upcoming addenda.
The bid documents stipulate 700 calendar days to complete the project. Is this for base bid only? How will the bid additives effect the project duration if awarded?
The revised bid package will be issued with the breakdown of project durations.
Can the deadline for questions be extended? Perhaps by 2-3 weeks to allow Contractors additional time to review the bid documents.
The deadline for the Q&A will not be extended.
Can the bid date please be extended to allow Contractors and Suppliers more time review the bid documents and plans? The upcoming Thanksgiving holiday will hinder the bidding window.
Response date is being extended in upcoming addenda.
Epoxy overlay placement meeting mentioned in 100.05 Project Meetings but no epoxy overlay mentioned in list of items or in plans. Please confirm no epoxy overlay required as part of this contract.
No epoxy overlay is required for this project.
Please confirm that the Quality Control Organization is permitted to be the Prime Contractor's own work force and won't require a third party agency.
Yes, the contractor can be the quality control organization. Testing must be done by a certified testing lab.
Spec Section 100.08 states that a bridge maintenance project plan is required to be submitted to the Coast Guard. Please confirm this will not be required as no bridge work is being performed on this project.
No bridge work is required for this project.
Please provide more information on what is required for "Record Drawings"
Record Drawings shall be marked up to show field changes, change orders and other project changes.
The bid forms require a singular, LS price for the project- please provide clarification on how the additive bids are to be included into the bid submission.
The bid form has been revised to separate the base bid and three additive bid items.
The bid forms require a singular, LS price for the project- please provide clarification on how the items that are to be paid on a unit price basis (shown in section 109-4 through 109-6) are to be incorporated into the bid submission.
Section 109 has been revised, and the unit price information has been removed. The base bid and additive bids are lump sum.
Drawing G-003, “General Notes” states in note No. 50 “THE CONTRACTOR WILL BE REQUIRED TO POST CASH, A CHECK, OR A SURETY BOND OR LETTER OF CREDIT TO EXCAVATE IN THE RIGHT OF WAY.” Please provide an anticipated rate or amount for this?
For City of Norfolk contract no additional bond will be required beyond what should be provided to the City in the contract.