Description

The Sharp Investment LLC is soliciting competitive, lump-sum bids from licensed B General Contractors under Invitation for Bid SHARP IFB-2026-089-PS for the complete fire damage rehabilitation of a single-story triplex located in Citrus Heights, California . MANDATORY SPECIALTY LICENSES: Pursuant to CSLB guidelines, the following trades must be executed by contractors holding the specific specialty license: Electrical (C-10), Fire Protection (C-16), HVAC (C-20), Asbestos Abatement Contractor (C-22), Plumbing (C-36) and Roofing (C-39) . Additional potential subcontracting trades include C-5 Framing, C-6 Cabinets/Millwork, C-8 Concrete, C-9 Drywall, C-12 Earthwork/Paving, C-15 Flooring, C-27 Landscaping, C-33 Painting, and C-61/D-28 Doors/Gates. Interested licensed Class "B" General Building Contractors are required to attend at least one of the two pre-bid meeting(s) to be held at the location(s), date(s) and time(s) indicated in the Timeline. Attendance includes the site inspection, and contractors will be responsible for verifying existing site conditions. Bids will be received via OpenGov ONLY until 2:00 pm on Tuesday, December 1, 2026 . For bids in excess of $300,000, bidders will be required to furnish and pay for a satisfactory Bid Bond in the amount of not less than 5% of the total bid price. The successful bidder will be required to furnish and pay for a satisfactory Performance Bond and Payment Bond in the amount of not less than 100% of the contract price. Please direct all general and contractual questions to Monica Albert , Buyer – Procurement Services, at msalbert@shra.org . For any questions regarding the Technical Plans and Specifications, all questions must be submitted via OpenGov. Sharp Investment LLC reserves the right to reject any or all bids and waive any informalities in the bidding. Sharp Investment LLC is an Equal Opportunity Employment employer. 6141, 6143 and 6145 Terrell Drive SCOPE OF WORK & SERVICE REQUIREMENTS Refer to the plans and specifications in the Attachments . Project Overview & General Objectives The successful General Contractor shall furnish all labor, materials, equipment, supervision, and insurance required to complete the scope outlined in the plans. See attachments (Note: Building permits and city plan check fees are provided by the Owner.) Selective Demolition Complete selective demolition across all three (3) units as required for fire remediation, structural repairs, and rebuild. Proper disposal and haul-away of all debris according to local waste management regulations. Structural & Envelope Reconstruction Complete replacement of roof trusses, structural framing, and roofing system across all three units. Supply and installation of energy-efficient exterior windows and exterior doors. Exterior finishes, trim, and weather barriers. Mechanical, Electrical & Plumbing (MEP) Electrical: Complete rewiring, new main service panel, sub-panels, and fixtures. HVAC: Brand-new heating, ventilation, and air conditioning systems for all units. Plumbing: Complete rough-in and finish plumbing, including water heaters and fixtures. Code Compliance & Life Safety Upgrades Fire Suppression: Installation of a brand-new residential fire sprinkler system per approved plans. Fire Separations: Installation of fire-rated wall assemblies and rated footings between adjacent units to meet current California Building Code standards. Inspections: Contractor shall coordinate all required City of Citrus Heights building and fire department inspections under the Owner-supplied permit. Interior Finishes Installation of wallboard, texturing, and interior painting throughout. Supply and installation of all kitchen and bathroom cabinetry, countertops, and hardware. Installation of interior doors, trim, baseboards, and flooring. Site Work & Landscaping Hardscape repairs surrounding the perimeter damaged by fire or construction activities. Basic restorative landscaping. INTRODUCTION Summary Background Contact Information Timeline BID FORM TERMS IN THE BID FORM SUMMARY: Work: the complete fire damage rehabilitation of a single-story triplex located in Citrus Heights, California Owner: Sharp Investment LLC Property: 6141 Terrell Dr, Citrus Heights, CA 95621 and 6143 Terrell Dr, Citrus Heights, CA 95621 and 6145 Terrell Dr, Citrus Heights, CA 95621 Architect: Michael Taylor FOR: LUMP SUM BID for Work on Sharp Investment LLC owned Property. TO: Sharp Investment LLC 801 12th Street, 2nd Floor Sacramento, California 95814 SCOPE OF WORK The Contractor proposes to furnish all labor, materials, equipment, and services required to complete the work required in strict compliance with the Bidders Response Questionnaire, Project Contract Manual, Technical Specifications Manual, Drawings, Notifications, and/or any Addenda for the above referenced project. BID AMOUNT The Contractor, having become familiar with the local conditions affecting the cost of the work, submits a LUMP SUM BID in the amount auto-tabulated in the PRICING PROPOSAL section. CONTRACT PERIOD The Contractor shall complete all work required under this contract within Two Hundred Seventy (270) calendar days of the effective date of the contract, or within the time schedule established in the Notice to Proceed issued by the Contracting Officer. PERMITS The Agency will secure and pay for the building permit only. This bid shall include all other fees and permits, and include all licenses and inspections necessary for the proper execution of the work. SUPERINTENDENT At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the work site a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor. CONSTRUCTION MEETINGS Construction meetings will be scheduled by the Sharp Investment LLC representative as required. OCCUPANCY The property WILL NOT BE occupied during the performance of this contract. SUBCONTRACTING The following trade work must be performed by a Contractor/Subcontractor who holds the applicable specialty license. Trade: Specialty License C-10 Electrical C-16 Fire Protection C-20 HVAC C-36 Plumbing CONTRACT EXECUTION If written notice of the acceptance of this Bid is mailed, emailed, or delivered to the undersigned within sixty (60) calendar days after the opening thereof, or at any time thereafter before this Bid is withdrawn, in writing, the undersigned agrees to execute and deliver a contract in the prescribed form and furnish the required bonds within fourteen (14) calendar days after contract is presented for signature. RIGHT TO REJECT ALL BIDS AND WAIVERS Bidder understands that SHARP retains the right, in its sole and exclusive discretion to (1) reject all bids for the subject project(s) and (2) waive any informalities in its consideration and review of the submitted bids. EXAMINATION OF WORKSITE AND CONTRACT DOCUMENTS The undersigned represents and warrants that the undersigned has examined the locations of the proposed work and is familiar with the local conditions at the places where the work is to be done, and the undersigned has reviewed and understands the plans, specifications, and other contract documents, and the undersigned is satisfied with all conditions for performance of the work. BIDDER'S CALCULATIONS The undersigned has checked carefully all of the bid's figures and calculations and understands that SHARP will not be responsible for any errors or omissions on the part of the undersigned in preparing and submitting this bid. LIQUIDATED DAMAGES If the Contractor fails to complete the work within the time specified in the contract, or any extension, as specified in the clause entitled Default of this contract, the Contractor shall pay to the PHA as liquidated damages, the sum of $100 per unit for each calendar day of delay . If different completion dates are specified in the contract for separate parts or stages of the work, the amount of liquidated damages shall be assessed on those parts or stages which are delayed. To the extent that the Contractor’s delay or nonperformance is excused under another clause in this contract, liquidated damages shall not be due SHARP. The contractor remains liable for damages caused other than by delay. CERTIFICATION OF NONSEGREGATED FACILITIES By signing this Bid the Bidder certifies that the Bidder does not maintain or provide for employees any segregated facilities at any establishment, and that the Bidder does not permit employees to perform their services at any location under the Bidder's control where segregated facilities are maintained. The Bidder agrees that a breach of this certification is a violation of the Equal Opportunity clause in this contract. As used in this certification, the term "segregated facilities" means any waiting room, work areas, rest rooms, washrooms, restaurants and other eating areas, time clocks, locker rooms and other storage or dressing areas, parking lots, drinking fountains, recreation or entertainment areas, transportation, and housing facilities provided for employees which are segregated by explicit directive or are in fact segregated on the basis of race, color, religion or national origin, because of habit, local custom, or otherwise. The Bidder further agrees to obtain identical certifications from proposed subcontractors prior to the award of subcontracts exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity clause, to retain such certification on file, and to forward a notice to proposed subcontractors as provided in the Instructions to Bidders. Note: The penalty for making false statements of offers is prescribed in 18 U.S.C. 1001. NONDISCRIMINATION, WORKER'S COMPENSATION AND NATIONAL LABOR RELATIONS BOARD CERTIFICATION Bidder, in submitting a bid for performing the following work by contract certifies the following: Bidder is in compliance with the Nondiscriminating requirements of the General Conditions. Bidder is aware of the provisions of Section 3700 of the Labor Code which require every employer to be insured against liability for worker's compensation or to undertake self-insurance in accordance with the provisions of that Code, and bidder will comply with these provisions before commencing the performance of the work of this contract. Bidder states, under penalty of perjury, that no more than one final appealable finding of contempt of court by a Federal Court has been issued against the bidder within the immediately preceding two-year period because of the bidder's failure to comply with an order of a Federal Court ordering compliance with an order of the National Labor Relations Board. Bidder certifies, unless specifically exempted, compliance with Government Code Section 12990 and California Code of Regulations, Title II, Division 4, Chapter 5 in matters relating to the development, implementation, and maintenance of a nondiscrimination program. Bidder agrees that it will not unlawfully discriminate against employees, or applicants for employment, based on race, religion, color, national origin, ancestry, physical handicap, medical condition, marital status, sex or age (over forty). This certification constitutes a part of the Bid, and signature on the signature portion of this Bid shall constitute signature of this certification. CSLB LICENSE CSLB Per State Law - All contractors and sub-contractors, of any tier, must hold the appropriate license with the California State License Board (CSLB), that is current and in good standing. BIDDERS QUESTIONAIRE AND RESPONSE PRICING PROPOSAL ATTACHMENTS

Published attachments
Addenda and notices
  • Addendum #1 · 1

    This Addendum No. 1 clarifies mandatory California Contractors State License Board (CSLB) specialty licensing requirements for the subject solicitation. Bidders must acknowledge receipt of this addendum on the Bid Form or via OpenGov. MANDATORY SPECIALTY LICENSE REQUIREMENTS Pursuant to CSLB guidelines, the following trade scopes must be executed by contractors holding the specific specialty license listed: C-10 – Electrical C-16 – Fire Protection C-20 – HVAC (Warm-Air Heating, Ventilating & AC) C-36 – Plumbing Class B General Contractors performing as prime contractors must hold these specific C-licenses or subcontract the work to properly licensed C-specialty subcontractors. ALL OTHER TERMS, CONDITIONS, AND DEADLINES REMAIN UNCHANGED.

  • Official Notice #1: First Pre-Bid Sign in Sheet · 1

  • Addendum #2 · 2

    Project name updated to reflect corrected address location.

  • Official Notice #2: Second Pre-Bid Sign in sheet · 2

  • Addendum #3 · 3

    Notice is hereby given to all prospective bidders that the solicitation documents for the subject project are modified as follows: Addendum Inquiry / Question Due Date: Extended to Friday, November 6, 2026 Bid Submission Due Date: Extended to Tuesday, November 17, 2026 All other terms, conditions, specifications, and scope of work remain unchanged. Bidders must acknowledge receipt of this addendum as part of their submittal package.

  • Addendum #4 · 4

    Notice is hereby given to all prospective bidders that the solicitation documents for the subject project are modified as follows: Agency Addendum / Inquiry Response Deadline: Extended to Monday, November 9, 2026. All other terms, conditions, specifications, and scope of work remain unchanged. Bidders must acknowledge receipt of this addendum as part of their submittal package. Please use the See What Changed link to view all the changes made by this addendum.

  • Addendum #5 · 5

    This Addendum issues official Questions and Answers regarding Solicitation SHARP IFB-2026-089-PS. Exhibits A through G are attached hereto as supporting documentation for the responses. Both the Questions and Answers and Exhibits A through G are also available for download on the solicitation Attachments page. All other terms, conditions, and specifications remain unchanged. Please use the See What Changed link to view all the changes made by this addendum.

  • Addendum #6 · 6

    CORRECTION – REPLACEMENT OF ADDENDUM #5 This corrected Addendum replaces Addendum #5 in its entirety. Please disregard the previously issued Addendum #5 and refer to this corrected version. This Addendum issues official Questions and Answers regarding Solicitation SHARP IFB-2026-089-PS. Exhibits A through G are attached hereto as supporting documentation for the responses. Both the Questions and Answers and Exhibits A through G are also available for download on the solicitation Attachments page. All other terms, conditions, and specifications remain unchanged.

  • Addendum #7 · 7

    Notice is hereby given to all prospective bidders that the solicitation documents for the subject project are modified as follows: 1. Contract Term & Procurement Schedule Revisions Contract Term: Extended by an additional 30 working days . Agency Addendum / Inquiry Response Deadline: Extended to Tuesday, November 17, 2026 . Bid Submission Due Date: Extended to Tuesday, December 1, 2026 . 2. Licensing & Specialty Contractor Requirements Stucco Removal (ACCM): Existing stucco siding is classified as Asbestos-Containing Construction Material (ACCM) and must be completely removed. The general contractor must either possess a C-22 specialty license or subcontract the removal and disposal work to a licensed C-22 contractor. Roofing Work: All roofing scopes must be performed by a contractor holding a C-39 Roofing license . General contractors who do not possess this license are strictly prohibited from self-performing roofing work. Fire Protection: The required C-16 Fire Protection license covers, but is not limited to, the installation and testing of the project's fire sprinkler system. 3. Architectural & Material Specifications (Detail 1/A502) Skylight Shaft Sheathing: Sheathing on the vertical walls of the skylight shaft must be cementitious soffit board matching the entire ceiling of the covered front courtyard area. Specified Material: James Hardie HZ10 Primed Cedarmill Fiber Cement Soffit Panel. Ventilation & Details: Use vented Hardie soffit panels at the perimeter of the courtyard (finish to match the remainder of the courtyard ceiling). Additionally, at least one eyebrow roof vent must be positioned over the covered front courtyard area. 4. Window & Sliding Glass Door Schedule Revisions Reference Note: The complete window layout is provided as Exhibit I in the project attachments. Schedule Revisions: The following revisions apply to the window schedule, inclusive of sliding glass doors organized by room number: Room Number Specified Windows & Doors Room 101 One (1) 5'-0"W x 4'-0"H window (front-facing); One (1) 6068 sliding glass door (courtyard-facing) Room 103 One (1) 5'-0"W x 4'-0"H window (front-facing); One (1) 3'-0" x 2'-0" window (south-facing) Room 105 One (1) 2'-0"W x 3'-0"H window Room 110 One (1) 5'-0"W x 4'-0"H window Room 111 One (1) 3'-0"W x 3'-0"H window Room 122 One (1) 6'-0"W x 4'-0"H window Room 124 One (1) 6068 sliding glass door Room 128 One (1) 5'-0"W x 4'-0"H window Room 130 One (1) 5'-0"W x 4'-0"H window Room 142 One (1) 6'-0"W x 4

  • Addendum #8 · 8

    Please use the See What Changed link to view all the changes made by this addendum.

Public questions and answers
  • Have any environmental inspections been done to determine if any hazardous materials are present on the stucco or brick that will require abatement or is all the be standard demolition and removal of construction debris ?

    See attached test results.

  • After siding is removed, will any dry rot or pest damage uncovered around pony wall foundation be priced via change order?

    Extent of dry rot/ pest damage, if any, is unknown and will be treated as a change order.

  • On page A702 what is the R11 Roof Deck Insulation? Is it spray foam, batts, foam board, rockwool? Is the roof considered vented or unvented? Should the roof deck insulation be installed on top of the roof deck with a secondary layer of plywood? What was the intent of the T24 compliance person?

    Roof is vented. See Exhibit A

  • Will the Gas meters be removed or just capped? Did the design team or SHARP contact the utility to gather any information about the removal of the meters?

    Contractor will initiate and coordinate with natural gas utility to remove existing meters.

  • The plumbing plans appear to be in conflict A101 floor note 3. Will an updated plumbing plan be provide without plumbing in fire walls?

    There will not be an updated plumbing plan because 5/A501 addresses this condition.

  • Is ABS acceptable for DWV piping? Is pex or copper press acceptable for water supply?

    Plumbing piping: ABS for drain/waste/vent are OK and Pex is OK for water supply lines

  • Are the provided plans Approved by the local jurisdiction?

    bid plan set has passed building plan check.

  • Are windows being cased, 3-way drywall wraps with wood sill or 4-way drywallwraps?

    3-way drywall wraps, see Exhibit B

  • Since this job isn't prevailing wage and subject to DIR registration, are bidders required to list all subcontractors that will be utilized on the project or are we able to utilize subcontractors not listed in the our bids? AS long as we include the C10, C16, C20 and C36 is that sufficient for bid purposes?

    Post-award subcontractor substitutions are not permitted. Naming specific entities and their CSLB license numbers at the time of bid submission is mandatory, and no subsequent substitutions are allowed without the agency's prior written approval.

  • Can you please confirm whether engineered truss calculations are available for the roof trusses? If so, please provide a copy for our review.

    Truss design drawings and calcs have been provided by El Dorado Truss and will be included in bid addendum. See Exhibit H for Truss Calculation Package document.

  • Is contractor or SHARP paying for special inspections for epoxied hold downs? Has E.O.R. provided SHARP with cost for special inspection?

    Owner will retain special inspector and be responsible for their fee. Contractor will schedule special inspection at appropriate time so as to limit required visits to/time at project site.

  • Plans state design team has not corresponded with SMUD about proposed 400 amp service upgrade. Will any SMUD utility costs for service upgrade be eligible for change order?

    Owner has initiated project with SMUD, who in-turn has reviewed project design requirements and awaits contractor's scheduling/coordination referred to in plan set. Any service upgrade fees invoiced by SMUD will be paid by Owner.

  • Are kitchen sinks allowed to have water supply and DWV piping in fire wall? If not are additional walls required as in the bathrooms? How are DWV lines intended to pass through the common walls/foundation below the floor? Are sleeves required at every location where DWV lines pass below the new 1 hour firewall footing?

    See addendum Exhibit C for revised furring wall locations in 6143 & 6145 kitchens. Sleeves and steppe footings are required per 'PIPES AND CONDUITS AT FOUNDATION' detail on sheet SC-1a.

  • AOO1 mentions Civil Plans. Are there separate civil. plans for this project? Will an encroachment permit be required for the driveway replacement or any sidewalk upgrades?

    There are no civil plans for this project. Encroachment permit application(s) are the contractor's responsibility however owner will pay fee.

  • Should temporary power provisions be included in the bid, i.e. temp pole and? Seems likely that the existing main service panel will have to be demoed prior to installation of the new panel. Will SHARP pay all utility fees for service upgrade, temp service, etc?

    Arrangements for temp power will be contractor's responsibility. Owner will pay SMUD fees associated with new service as described in contract documents if assessed.

  • What is the stucco texture? A501 Detail 2 calls for 2" comfortboard 80 and A501 Detail 1 calls for 1" Comfortboard 80. Which is it? Is EPS foam board acceptable insulation rather than the listed Rockwool product?

    Base bid shall include 1" EPS CI as typical per Detail 7/A502. No Comfortboard 80 on exterior walls.

  • Which rooms get Carlsbad and which get Triple Bock flooring, who levels the subfloor for glue-down LVP, and is a specific adhesive or attic stock required? Is there a painting or finish schedule (colors, products, coats, surfaces) for the three units, and if not, what should the bid carry?

    See Addendum Exhibit E for revised Interior Finish Specification schedule which includes material spec for floating LVP. Contractor will be responsible for leveling floor as needed.

  • Spec 01010 bars 7 pm to 7 am and Sundays and Owner holidays. Are Saturdays allowed, and are there delivery, crane or boom-truck limits? Where are the designated areas for staging, laydown, dumpsters, toilets and parking, and may the street be used for truss delivery and crane set-up? Who provides board-up, weather protection, site security and temporary fencing until dry-in?

    Owner will not advise on contractor's means and methods.

  • Sheet 000 and A201 show ridge 19'-11" but elevation notes show 18'-9". Which is correct, and what are the roof pitch, plate height and overhang? No truss specification is included. Are trusses a deferred submittal, and who pays any City deferred plan-check fees? Spec 07311 says "rafter tails to match existing" but D20 removes the whole roof structure. Is all roof framing replaced (including porch and breezeway beams, posts, masonry column), how many layers of roofing are on the skip sheathing, and does the newer 2x attic bracing remain? Are W17 and W18 new skylights, what quantity and where, and are the light wells on A201, A202 and A502 in the base scope? Which unit is the "reconfigured front unit," and do D001 and A101 show the full extent including structural, plumbing, mechanical and electrical? What fire rating and assembly (1 or 2 hour, UL or GA number) is required for new walls between units, do they extend to the roof deck, and are FRT sheathing or a parapet required? Is temporary shoring required at the party wall? Is DF #2 and better acceptable instead of DF #1, and is ACQ or CA-C acceptable since CCA lumber is unavailable? What does dry-in include? The spec says one layer of #15 paper, but stucco normally needs two layers of Grade D.

    a) Ultimate ridge heights are estimates shown to convey to Bldg. Dept. that height restriction is not exceeded. Roof pitch, plate height and overhang information is shown on the plans. b) Truss calcs have been submitted to the City (Nathan, is this true?) and owner will pay for any associated permit fees. c) all roof framing is to be removed, so reference to existing roof framing is not applicable. d) yes, skylights shown are new and the light wells are in the base scope. e) Reconfigured front unit is 6141 Terrell. See cover sheet. f) plans show full extent of work required on this project. Contractor is responsible for examining the entire set of bid documents. g) new fire-rated unit separation walls are detailed in the plans. Parapets are not required due to the use of fire rated sheathing per parapet exception in the code. h) Any shoring is contractor’s responsibility. Where DF#1 is specified, substitution with DF#2 is not acceptable. i) not sure about the ACQ or CA-C question. j) 2 layers of class D specified in details

  • Sheet 000 says drywall and flooring are already removed, IFB 2.2 says complete selective demolition, and D001 shows dashed walls. What demolition must be included in each unit? D001 legend shows "(E) slab to be removed." Is any concrete slab removed, and where? How are damaged framing (studs, plates, joists, girders), subfloor beyond the 400 SF on D001, and wiring paid for: base bid, allowance, or unit prices? Is there an engineer or insurer fire-damage or building-condition report, and will it be provided? Have asbestos, lead and mold surveys been done (mold was seen in wall cavities at the walk), and will reports be provided? Who tests, abates, clears and disposes (Spec 02055 refers to missing hazmat specs)?

    a) scope of demolition is detailed in the plans. Flooring has been completely removed, but floor framing remains. b) plans show where existing slab is located c) replacement of damaged framing and other building components not shown to be removed will handled through change order process, d) fire department report will not be provided, e) building was fully abated after the fire, with the exception of the stucco, which is addressed elsewhere in this addendum f) Owner will abate any existing mold

  • Please confirm the design-build design, hydraulic calcs, shop drawings and Metro Fire submittal are in the Contractor's scope, and whether Metro Fire plan review, permit and inspection fees are paid by the Owner.

    Metro Fire review is completed and approved. Owner will pay plan review and permit fees. No shop drawings are required. The Fire Sprinkler system can be installed per contract document plan set.

  • What is the existing water meter and service size, what are the static/residual pressure and flow data behind FP1, and is a larger meter, service or backflow assembly required? Does the Owner pay all water and sewer tap, connection and capacity fees (including upsizing), with the Contractor limited to coordination and building-side work? Has the Owner submitted a SMUD service request or obtained SMUD's requirements for the new 400A service? Is it overhead or underground, who does which work (pole, transformer, conductors, trenching, conduit, meter), and who pays SMUD fees? E1 and E2 show EV load and a 40A "EVCS provision" breaker but no equipment. Are chargers furnished and installed, or breaker provision only? If equipment, give make, model, locations and wiring. D001 removes the gas meters and lines, but P1 and P3 show gas notes. Is the building all-electric with no new gas service? Has the Owner requested AT&T and Comcast service, and is Contractor scope limited to in-building work (Sections 16740, 16800)? Please confirm no site power or water is available and the Contractor provides temporary power, water (including G002 note 40 fire-protection water) and sanitary facilities. Overhead lines cross the 6145 courtyard roof. Will the Owner coordinate de-energizing or guarding with the utility (E1 shows SMUD)? Please confirm full driveway and courtyard replacement is in the base bid with area, thickness, reinforcement and finish, whether right-of-way work is included, when the

    a) SMUD has reviewed proposed design and awaits Contractor's scheduling. See Exhibit D for additional requirements provided by SMUD. b) chargers are not required to be installed; only breaker and conduit to J-box locations shown on the plans, c) Yes, building will be all electric since gas service is being removed. There may be general notes on the sheets that do not apply to the specific information on the plans. d) See #15 answer regarding temp power; site water should be available, but if not, we will pay to have it turned back on temporarily. Contractor provides their own sanitary facilities e) Overhead lines. Contractor will coordinate with respective utility companies. f) See Addendum Exhibit F site concrete section detail. Contractor will submit for and obtain all required permits for right of way work. Right of way permit fee costs incurred by contractor will be reimbursed via change order. Tree trimming will be by contractor.

  • Please confirm the OpenGov Pricing Proposal is one lump sum and whether alternates, allowances or unit prices are required. IFB 1.1 says bid bond above $300,000 and Questionnaire 4.1 says 5% of the bid. Is a bid bond required for all bids? Questionnaire 4.2 says bonds within 10 days of award and IFB 3.10 says 14 days from contract presentation. Which governs IFB 1.2 says no prevailing wage, but it has nonsegregated-facilities and "PHA" provisions. Please confirm no state or federal prevailing wage (Davis-Bacon, Section 3, federal funding) applies. Please confirm no Owner-furnished items, and that appliances (A701 AP-1 to AP-4), cabinets, countertops, fixtures and hardware are Contractor furnished and installed.

    Thank you for your questions: Pricing: Submit pricing strictly as requested in the solicitation documents. Bonds & Contract Execution: Upon receipt of the Notice of Award, the selected contractor must provide required bonds within 10 business days and execute/deliver the contract within 14 calendar days of presentation (bid offer remains valid for 60 calendar days post-opening unless withdrawn in writing). Federal Requirements: This is a privately funded project. It is not subject to Davis-Bacon, Section 3, or federal funding regulations. Owner-Furnished Items: None. The contractor is responsible for furnishing all appliances (A701 AP-1 through AP-4), cabinets, countertops, fixtures, and hardware.

  • Sheet 000 says "Permit Submittal" with a 9/14 plan-check revision. What is the permit status, and will remaining revisions be issued by addendum before bid day? Beyond the Owner's building permit and plan-check fee (IFB 2.1, 3.5), which permits and fees does the Contractor pay (electrical, mechanical, plumbing, encroachment, grading, school fees)? Does the CALGreen 65% recycling requirement and a City waste management plan apply, and who pays the deposit? Will the Owner pay for special inspections (shear nailing, hold-downs, epoxy anchors)? What are the anticipated Notice of Award and Notice to Proceed dates? Please confirm the 270 calendar days run from Notice to Proceed to Substantial Completion. Please confirm liquidated damages of $100 per unit per day ($300 per day total) and identify the "PHA" payee.

    Plan set included in bid documents has passed Citrus Heights building and safety division plan review. All review and permit fees with respective agencies having jurisdiction will be paid by owner. Refer to question 11 regarding special inspections. Depends on bid and bonding process. Confirmed. There will be only one construction contract, not three. Not applicable.

  • Landscape/civil drawings referenced on A001 Note 3 are not in the 37-sheet index. Please provide them or confirm none exist and A001 and Specs 02810, 02822, 02900 govern. The Specs Manual has no plumbing, HVAC, sprinkler or electrical sections (header reads "Project Name Here / IFB No. 0") and the SHARP sample agreement is missing. Do the M, P, FP and E sheet notes govern, and please provide the agreement with payment, retention and warranty terms. Structural title blocks read "6141, 6134, 6145." Please confirm 6134 should be 6143. Are the original high-resolution bid-walk photos available, plus any crawlspace or party-wall photos?

    There are no civil or landscape sections in bid drawing set. See A001 for landscape scope.