State and local · OpenGov
ADA Improvements for Patterson Park and MPD
Description
The City of Murfreesboro is accepting sealed bids for ADA Improvements for Patterson Park and MPD , ITB-11-2027 to be received no later than Tuesday, November 24, 2026 , 2:00 pm CST. Bid Form Please refer to the attached bid form, located in the "Attachments" section of this ITB. Download, complete, and upload here in PDF format. Scope of Work Important Instructions for Electronic Submittal The City is accepting electronic bid submissions. Bidders shall create a FREE account with OpenGov by signing up at https://procurement.opengov.com/signup. Once you have completed account registration, browse back to this page, click on "Submit Response", and follow the instructions to submit the electronic bid. Introduction Summary Background Contact Information Timeline Forms to Complete Attachments
Published attachments
Addenda and notices
Official Notice #1: Pre-Bid Meeting Agenda and Sign-In Sheet · 1
Addendum #1 · 1
Please see Addendum #1 issued November 6, 2026
Addendum #2 · 2
Please see Addendum #2 issued November 19, 2026.
Public questions and answers
Hardware Set 01 (openings 103 and 104) schedules actuators and a receiver but no operator, while the drawing notes require new/replacement operators. Please confirm that new LCN operators are included in the work for Set 01, and identify the required operator model.
Sheet A1.02v2, Item 8 is revised to read "Replace Existing ADA pushbutton stations (actuators) with new wireless stations. Provide receiver at existing operator. Provide balance of work for a complete operational ADA door access system." Contractor to field verify existing door operator conditions at door frame heads for doors 103 and 104. See Addendum #2.
Section 01 11 00 describes the Patterson Park entrance doors as bi-parting, while Section 08 42 29.24 specifies single-slide operators. Please confirm the Patterson Park entrances are single-slide as specified in 08 42 29.24.
Patterson Park entrance doors are single-slide.
The contract time / completion date is blank in the Bid Form and in the AIA A101 agreement. Please state the contract time for this project, and confirm the retainage percentage.
Contract time will be established in the Notice to Proceed. Substantial Completion will be achieved in 2027. There is no retainage percentage. See Addendum #2.
Please confirm the bid structure created by Addendum #1 Section 01 21 15: lump-sum Base Bid plus a 5% Contingency Allowance equals the Total Bid, with no overhead and profit applied to the allowance, and no alternates or unit prices.
Lump-sum Base Bid plus a 5% Contingency Allowance equals the Total Bid, with no overhead and profit applied to the allowance, and no alternates or unit prices.
Security film is required at the MPD vestibule per Addendum #1 (Section 08 80 00). Please identify the required film product and thickness, and state which glazing units at Patterson Park are identified for security film.
See specification section 08 80 00, 2.01.H; no windows at Patterson Park receive the security film; it applies only to the Murfreesboro Police HQ, as indicated in Addendum #1 dated November 9.
For the Hardware Set 4 cylinders: please identify the existing key system and format the cylinders must match, and confirm who furnishes the cylinders.
Coordinate with owner for key system and cylinder format. Coordinate with door supplier for cylinders needed.
Does the Glass at the Police Headquarters need to be Ballistic Glass or Ballistic Film. or Ballistic. in any way
See specification section 08 80 00, 2.01.H; no windows at Patterson Park receive the security film; it applies only to the Murfreesboro Police HQ, as indicated in Addendum #1 dated November 9.