Airside and Landside On-Call Engineering Services

Description

The Kenton County Airport Board (“KCAB”) will receive proposals for Airside and Landside On-Call Engineering Services . A pre-proposal meeting will be held on Thursday, November 12, 2026 at 10:00 am at Conference Center D, CVG Centre 77 Comair Blvd. Erlanger, KY 41018 . Questions are due at 11:59 pm on Thursday, November 19, 2026 and answers will be posted no later than Wednesday, November 25, 2026 at 11:59 pm . Proposals must be received by Thursday, December 3, 2026 at 2:00 pm . No proposals will be accepted after that time unless such date or time is extended pursuant to an addendum issued by KCAB. SCOPE OF SERVICES Scope of Services/General Requirements There will be five (5) phases for each project as follows: 1. Preliminary Phase: This phase involves those activities required for defining the scope of a project and establishing preliminary requirements, including but not limited to the following: feasibility studies, project phasing, procurement, perform necessary surveys, geotechnical investigations, field investigations, architectural/engineering studies for design considerations, perform condition assessments, grant administration assistance, CAD support, and realistic cost estimates. The goal of this phase will be to provide KCAB with options that balance operational impact, construction schedule, cost, and design life. Consultant may be asked to prepare multiple options, schedules and costs, including lifecycle costs for the different options and will be required to participate in at least 4 scoping sessions. 2. Design Phase: This phase includes all activities required to undertake and accomplish a full and complete project design consistent with all applicable code, regulations and specifications, including but not limited to the following: attend and conduct design meetings with KCAB and applicable stakeholders to obtain information and coordinate or resolve design issues, and prepare detailed plans and specifications, cost estimates, construction phasing and schedules. Consultant must include 3 robust design review sessions with CVG stakeholders. In addition, the Consultant must obtain criteria required for funding such as “passenger areas” and include a detailed plan for mapping square footages. A quality control program is required to be in place for the duration of the design and construction. Consultant must provide its quality control program for approval prior to beginning the design. Quality control reports must be submitted with each milestone submittal. 2a. Environmental Phase: The Consultant must provide KCAB all applicable environmental project information for KCAB to complete applicable environmental documents and coordination. At the option of KCAB, the Consultant may be required to submit and coordinate the environmental documentation with the FAA and any other applicable agencies. 3. Bidding Phase: This phase includes activities including preparation of Consultant’s probable construction cost, attend and present at the pre-bid meeting, answer all requests for information (RFI’s) from prospective bidders, prepare addenda, evaluate bids, and provide a cost analysis/comparison as part of the written recommendation regarding the award of the bid. 4. Construction Phase: This phase includes all basic services required after the award of a construction contract, including attending and conducting the pre-construction conference, review and approve contractor submittals including shop drawings, inspect the work in progress for adherence to the project documents, prepare daily inspection reports, review contractors’ pay requests recommending payment, track Disadvantage Business Enterprise participation, prepare change orders and/or supplemental agreements, conduct quality assurance testing, observe and review performance tests required by the specifications, conduct final inspections, and prepare punch lists. 5. Close-out Phase: This phase includes the preparation of final record drawings. Record drawing submittals must include electronic CAD files in accordance with KCAB CAD standards and a PDF of the record drawing set. Consultant will be responsible for preparing and providing the Asset Commissioning Data Tables (to be provided by KCAB) for all assets being commissioned, decommissioned, or modified. These requirements define the overall set of data and information to be collected and provided by the designer/contractor to KCAB as part of all design/construction projects. Consultant is required to prepare all applicable permits on behalf of KCAB throughout all phases. KCAB anticipates the use of federal and mixed funding for the projects under this RFQ. The projects may also be accomplished during the course of multiples grants. The Consultant shall provide the following design, plan, plan review, and construction services for airfield projects at CVG: 1. Provide plan reviews for projects affecting the airfield to ensure compliance with KCAB and FAA guidelines, including Part 139 requirements. 2. Provide construction inspection support staff for any projects affecting the airfield to ensure compliance with construction plans, and compliance with KCAB and FAA guidelines, including Part 139 requirements. These assignments will typically include reviewing plans submitted to KCAB for airfield construction (i.e., tenants). Potential assignments also include providing construction inspection support staff for projects taking place on CVG’s airfield. Assignments will vary in complexity and duration. KCAB reserves the right to issue individual procurement solicitations for the services listed in this RFQ for related projects. The above services fit within one of the five general project life cycle phases which are generally described below to assist proposers in better understanding KCAB’s expectation of work by phase for each project assigned. Scope of Work/Expertise The scope of work includes, but is not limited to, the design of runways, taxiways, aprons, roadways, parking facilities, drainage systems, and utility infrastructure. The selected firm(s) will be required to adhere to the following detailed specifications and standards: Airside Design Runways and Taxiways Design must comply with Federal Aviation Administration (FAA) Advisory Circulars, including but not limited to AC 150/5300-13A, "Airport Design." Incorporate pavement design standards as per FAA AC 150/5320-6F, "Airport Pavement Design and Evaluation." Ensure compliance with FAA AC 150/5340-1M, "Standards for Airport Markings." Aprons Design must adhere to FAA AC 150/5300-13A and AC 150/5320-6F. Include provisions for aircraft parking, fueling, and ground support equipment (GSE) operations. Lighting and Signage Design must comply with FAA AC 150/5340-30J, "Design and Installation Details for Airport Visual Aids." Ensure compliance with FAA AC 150/5345-53D, "Airport Lighting Equipment Certification Program." Landside Design Roadways and Parking Facilities Design must comply with American Association of State Highway and Transportation Officials (AASHTO) standards. Incorporate guidelines from the Manual on Uniform Traffic Control Devices (MUTCD). Ensure compliance with local and state regulations. Drainage Systems Design must comply with FAA AC 150/5320-5D, "Surface Drainage Design." Ensure compliance with Environmental Protection Agency (EPA) regulations and local stormwater management requirements. Utility Infrastructure Design must comply with local utility standards and regulations. Ensure coordination with existing utility services and infrastructure. The selected firm(s) may be required to provide the following services: Project Management Develop and maintain a detailed project schedule. Coordinate with CVG staff, stakeholders, and regulatory agencies. Provide regular progress reports and updates. Design Services Conduct site assessments and surveys. Develop preliminary and final design plans, specifications, and cost estimates. Prepare and submit all necessary permit applications. Construction Support Provide construction administration and inspection services, including an on-site RPR and multiple inspectors. Respond to Requests for Information (RFIs) and issue design clarifications as needed. Review and approve contractor submittals and shop drawings. Primary areas of expertise are disciplines where task leadership by subject matter expertise is likely, but not exclusively, expected: • Airfield Civil Engineering • Commercial Development Site Design and Engineering • Commercial Parking and Staging Facilities • Highway Civil Engineering • Hydrology and Storm Water Management • Structural Engineering • Traffic Engineering and Intelligent Transportation Systems • Utility Systems (Communications, Electrical, Gas, Sanitary and Storm Sewers, Water) Supporting Expertise Supporting expertise is expected to be necessary as part of the above major task initiatives but these areas may be the sole focus of stand-alone tasks (survey controls setting, general cost estimating support task, etc.): • Aircraft Hydrant Fueling and Fuel Storage • Airfield Lighting and Signage • Airspace Obstruction and Airspace Procedures Evaluation • Cost Estimating • Construction Delivery Methods • E-Information Management Support, GIS and CADD • Building/Facility Design Development • Environmental Permitting and Mitigation Design • Environmental Testing • Facilitation • Geotechnical Services • Landscape Architecture • Materials Testing • Modeling and Simulation (Landside and Airside) • Safety and Risk Management Assessment and Planning • Scheduling and Project Controls • Surveying and Controls • Utility Location and Condition Assessment • Pavement design • Existing pavement evaluation • Construction Administration • Wayfinding and signage • Sustainable design • Passenger conveyance systems • Aircraft / Terminal gate layout evaluation • Independent Fee Estimates Minimum Qualifications Firms submitting a response must show evidence of qualifications and experience related to successfully performing the requested services on similar projects. Firms must be qualified to work in the State of Kentucky and must be able to stamp the plans by a licensed professional Architect, Engineer, and/or Surveyor registered in the State of Kentucky. AOA Safety And Security A. SAFETY A.1 Contractor and all subcontractors shall comply with their site-specific safety plan and Owner’s recommendations regarding employee safety. Owner may shut down the job site/project if it deems necessary for any single or recurrent safety violation by Contractor or any subcontractor. In the event the job site/project is shut down under this section, Contractor agrees it will not file or pursue any claim including but not limited to a claim for delay against the Owner, in relation to such shutdown; and, each day elapsing during shutdown is counted as a contract day for purposes of calculating liquidated damages. The Contractor shall acquaint his supervisors and employees with the activity and operations that are inherent to an active air carrier airport; and shall conduct his construction activities to conform to all routine and emergency air traffic requirements and guidelines on safety as specified in this section of the specification. The applicable safety provisions of the latest FAA Advisory Circular 150/5370 prevail throughout this construction contract. This information is used by the Contractor as guidance in implementing and administering its own safety program during the term of this Contract. These requirements are minimum. Not all of the specific references may pertain to this Contract. A.2 Construction Activity and Aircraft Movements During the time the Contractor is performing the work under this Contract, existing terminal aprons, taxiways, and runways at the Airport will remain in use by aircraft, except as provided herein. To the extent feasible and convenient, in the opinion of the Engineer and to the extent permitted by the Federal Aviation Administration, the access by aircraft of runways and use of taxiways adjacent to areas where the Contractor is working will be routed as to reduce disturbance to the Contractor's operations. Aircraft operations, unless otherwise specified in the Contract Specifications, shall always have priority over any and all of the Contractor's operations, and the Contractor shall not allow his employees, subcontractors, material suppliers, or any other persons over whom he has control to enter or remain upon or allow any plant or materials to be brought or to remain upon any part of the Airport which, in the opinion of the Engineer, would be a hazardous location. Should aprons, runways, or taxiways be required for use by aircraft, and should the Engineer deem the Contractor to be too close to the portion used by aircraft for safety, he may, in his sole discretion, order the Contractor to suspend his operations; remove his personnel, plant, equipment, and materials to a safe distance; and stand by until the runway and taxiways are no longer required for use by aircraft. The Contractor shall not allow his/her employees, subcontractors, material suppliers, or any other persons under the Contractor's control to cross any active runway or taxiway without an escort by authorized Airport personnel. The Contractor shall pay a fine of up to Ten Thousand Dollars ($10,000) per occurrence for any unauthorized crossing of an active runway or taxiway by any such person under the Contractor's control. Any breach of security requirements is subject to a fine of up to Ten Thousand Dollars ($10,000). If any portion of the work area under this Project is contained within the Aircraft Operations Area (“AOA”), then these areas of work are considered critical areas. Work will be performed in the proximity of and directly adjacent to active taxiways, therefore, the Contractor shall become familiar with the Obstacle Free Areas and Safety Areas associated with active areas of the Airport. A.3 Airfield Safety Requirements The Contractor shall adhere to the following requirements when working in close proximity to aircraft: Brief each equipment and vehicle operator to thoroughly acquaint him with the absolute necessity of exercising discretion and proper judgment while in the vicinity to aircraft operations. Assist the Engineer and the Airport Security Personnel in monitoring the conduct of each vehicle and equipment operator. Require all operators to maintain a safe and reasonable speed and to utilize equipment strictly in accordance with prevailing weather conditions. At the direction of the Engineer, dismiss from the project any person operating unauthorized vehicles or equipment in an unauthorized area, or operating vehicles or equipment in a reckless and unreasonable manner. Shall not allow trash or debris to accumulate in his work or operations area. Extreme caution will be taken to keep all trash and debris from taxiways, runways, and apron areas. Shall not allow his vehicles or equipment to be operated within 130 feet of the centerline of an active taxiway or within 250 feet of the centerline of an active runway, unless they are using a designated haul route or have the express consent of the Engineer. Immediately cease and remove his operations from any operations or work area at any time he is instructed to do so by the Engineer, the FAA Control Tower, or by the Airport Staff. These instructions will be issued by radio or other means, if appropriate. The Contractor will not allow his operations to return to the area until he has received permission to do so by the Engineer. Shall provide, erect, and maintain all necessary barricades, signs, danger signals, and lights for the protection of the work and the safety of the public for both land and air traffic. Obstructions shall be illuminated as required by the Engineer. Tall but relatively low visibility units such as cranes, drills and the like must have appropriate obstruction lighting mounted and operational in accordance with FAA Advisory Circular 70/7460-1. Booms are also required to have an orange checkered flag attached to the top of the boom when elevated. In the event of poor weather, visibility, emergency issue, the equipment operator may GENERAL INFORMATION & SUBMITTAL INSTRUCTIONS NOTICE TO BIDDERS The Kenton County Airport Board (“KCAB”) will receive proposals for Airside and Landside On-Call Engineering Services at the Cincinnati/Northern Kentucky Int’l Airport (“CVG”). Proposals must be received by Thursday, December 3, 2026 at 2:00 pm . No proposals will be accepted after that time unless such date or time is extended pursuant to an addendum issued by KCAB. A pre-proposal meeting and will be held on Thursday, November 12, 2026 at 10:00 am at Conference Center D, CVG Centre 77 Comair Blvd. Erlanger, KY 41018 . Please RSVP by November 11, 2026 through KCAB’s online bidding system https://procurement.opengov.com/portal/cvgairport . Select Invitation 26-053-RFQ and provide the name of the person(s) attending. See Attachments for RSVP instructions. NOTE: Although attendance at the pre-proposal meeting is not limited, the subsequent walkthrough is limited to a maximum of two (2) persons per company. KCAB reserves the right to waive any informality or irregularity in any proposal or bid guaranty, to reject any or all proposals, to award or refrain from awarding a contract for the work, and to negotiate with the apparent qualified responsible proposer to such extent as may be beneficial to KCAB. Further information and copies of the Request for Proposal (RFP) may be downloaded from our website www.cvgairport.com/bids - KCAB's e-Procurement Portal. KENTON COUNTY AIRPORT BOARD Lawrence J. Krauter, Chief Executive Officer CINCINNATI /NORTHERN KENTUCKY INTERNATIONAL AIRPORT Hebron , Kentucky 41048 SCHEDULE OF EVENTS Release Project Date: November 4, 2026 Pre-Proposal Meeting (Non-Mandatory): November 12, 2026, 10:00am Conference Center D, CVG Centre 77 Comair Blvd. Erlanger, KY 41018 Deadline For Questions To Be Submitted: November 19, 2026, 11:59pm Answers To Questions Issued: November 25, 2026, 11:59pm Proposals Due: December 3, 2026, 2:00pm Interviews: December 10, 2026 - December 18, 2026 Anticipated Contract Implementation: March 1, 2027 KCAB reserves the right to modify or alter the schedule of events to such extent as may be beneficial to KCAB. PRE-SUBMITTAL MEETING To facilitate a comprehensive understanding of the scope of services and expectations for the Airside and Landside On-Call Engineering Services , a pre-submittal meeting will be held on Thursday, November 12, 2026 at 10:00 am , at Conference Center D, CVG Centre 77 Comair Blvd. Erlanger, KY 41018 . During the pre-submittal meeting, KCAB staff will provide an overview of the scope of services and expectations of the project and will address questions. The meeting will also provide an opportunity for prospective prime and sub-consulting firms to network. Attendance at the meeting is STRONGLY encouraged. BACKGROUND The Cincinnati/Northern Kentucky International Airport (CVG) is seeking qualified firms to provide comprehensive civil design services for both airside and landside projects. The selected firm(s) will be responsible for delivering high-quality, cost-effective, and timely design solutions that meet all regulatory and operational requirements. The scope of work includes, but is not limited to, the design of runways, taxiways, aprons, roadways, parking facilities, drainage systems, and utility infrastructure. KCAB intends to select one or more qualified consultant, or proposed team of consultants and engineers, to provide the requested ser

Published attachments
Addenda and notices
Public questions and answers
  • Is there a virtual option to attend the pre bid meeting?

    Yes, the details are posted in the pre-bid meeting agenda under Addenda & Notices.

  • The RFQ states that firms submitting a response must demonstrate successful performance of the requested services on three similar projects within the last five years. Because the RFQ permits respondents to form teams that combine airside and landside capabilities, please confirm that the three-project minimum qualification may be demonstrated through the relevant qualifications and experience of the proposed team collectively, including both the prime consultant and its subconsultants.

    Yes, the relevant qualifications and experience can be of the proposed team collectively.

  • For purposes of satisfying the minimum qualification requiring successful performance of the "requested services" on three similar projects within the last five years, please confirm that qualifying projects may consist of similar airside and/or landside engineering projects encompassing services identified in the RFQ, and are not required to have been performed specifically under an on-call/master services agreement.

    Yes, they did not have to be performed specifically under an on-call/master services agreement.

  • Please verify what information is requested in Section 1- Minimum qualifications of the Vendor Questionnaire. Is that intended to be an executive summary of the other sections?

    Section 1 is intended to be evident throughout the response. An executive summary is allowed in the Cover Letter to highlight the overall approach philosophy.

  • In the Supporting Expertise section beginning on page 9, please provide additional detail on these areas: a. Environmental Permitting and Mitigation Design b. Facilitation c. Passenger conveyance systems. Does this include any areas in addition to elevators, escalators, moving walkways and automated people movers?

    a. CVG operates its own water treatment plant, detention facility, sanitary forcemain system, etc., all of which could result in projects under this on-call contract. b. Facilitation is a catch-all for additional project management duties. This could include creating small Maintenance of Traffic diagrams for short term inspections, etc. c. This would include elevators, escalators, moving walkways and people movers. We understand this is a specialty. The prime doesn't necessarily need a subconsultant on their team who specializes in this at the time the response is due. They should have an idea of who they'd pull in if design of these systems were necessary.

  • In the Primary Areas of Expertise section beginning on page 9, please provide additional detail on the Airport’s goals related to Intelligent Transportation Systems

    Intelligent Transportation Systems may be included in CVG-owned roadway intersections, parking guidance systems, dynamic signs, etc.

  • Is there anticipated to be a specific DBE goal for each individual task order or a general goal for the contract as a whole?

    As regulations are influx, DBE goals may be set for individual task orders versus the contract as a whole.

  • The RFQ requires the organizational chart to identify all proposed disciplines, discipline leads, subject matter experts, specialty resources, subconsultants, and reporting relationships. To present this information clearly and legibly, please confirm that respondents may use one 11 × 17-inch page for the organizational chart, with that sheet counting as one page toward the applicable page limit.

    11x17 is acceptable for the organizational chart.

  • Can the PM slide deck presentation provided during the Pre-Bid Meeting be posted under Project Documents?

    Yes.

  • Section 1.7.3, Minimum Qualifications, indicates that firms must be able stamp the plans by a licensed professional Architect, Engineer, and/or Surveyor registered in KY. In the Key Staff section of the Vendor Questionnaire on Page 22, it states that the Project Manager shall be a Registered Professional Engineer in KY. Does the PM need to be registered in KY or is it acceptable that proposed staff from the prime firm are registered in KY?

    The proposed staff from the prime firm should have a PE registered in KY, not necessarily the project manager.

  • D. Technical Resources states: Include examples of project visuals, public-facing presentations, stakeholder outreach materials, or decision-support tools utilized on comparable airport projects within the last five (5) years. With the limited page count, can the examples be included as an appendix?

    Yes, this is acceptable.

  • Would CVG consider firm qualifications for Construction Inspection/RPR and Materials Testing services independently?

    Please include Construction Inspection/RPR and Materials Testing Services under "Key Staff Experience & Availability." 11x17 is acceptable when creating an organizational chart to include the full team.

  • Can firms submit for ONLY landside or airside or must they team to submit a response that includes both?

    It's acceptable to submit for only airside or landside. Responses do not need to include both. CVG intends to make multiple selections based on the responses received.

  • The RFQ does make mention of construction services. Do you anticipate any additional RFQs being released for construction services?

    Please clarify your question construction services for this RFQ or in general?

  • 1. Sections 4 and 5A both request an organizational chart depicting the proposed team structure, personnel assignments, reporting relationships, and client point of contact. Given the page limitations for these sections, may Proposers provide one comprehensive organizational chart in either Section 4 or Section 5 and cross-reference that chart in the other section, rather than providing a duplicate organizational chart in both sections?

    Yes

  • Should the Certificate of Insurance be provided by the Prime alone or by every member of the team?

    Certificates of insurance are required for Prime and should be provided. Yes, Subconsultants should have and provide COI’s to prime and upon request to KCAB.

  • The RFQ states "Detailed resumes for key team members may be provided in Appendix C." What are the expectations for appendices A and B?

    There is not an appendix A or B. You may create an additional appendix for additional information or images you'd like to display in your response.

  • Section 3, Firm’s Qualifications and Experience, is limited to five pages and requests relevant project examples. May proposers provide abbreviated project information within Section 3 and include supplemental detailed project sheets in an appendix?

    Yes, this is acceptable.

  • Can you please clarify what is the scope includes for the Facilitation supporting expertise?

    Facilitation is a catch-all for additional project management duties. This could include creating small Maintenance of Traffic diagrams for short term inspections, etc.

  • To clarify, are we to submit subconsult COI's or just have them on hand ready to send if requested after submitting?

    Ready on hand if KCAB request.

  • Staying within the pages counts, would CVG consider a single 11x17 page in the submittal?

    Yes, that's acceptable.

  • Given the proposal is due right after a holiday weekend, would the CVG consider extending the deadline?

    Responses are due December 3rd as of right now the schedule will remain the same.

  • Given the page limitation for Section 4, Key Staff Experience & Availability, may proposers provide our three references in an appendix?

    Yes

  • Are we supposed to provide the Subcontractor list as an Excel file separate from the Proposal or should we print it to pdf and include in the proposal document?

    It can be attached back to question #6 in the vendor questionnaire, excel or PDF. No DBE, subcontract amount or subcontract value is (not) required for this.

  • Since respondents may pursue airside services, landside services, or both, would KCAB consider proportional page limits based on the scope proposed, either by allowing additional pages for teams proposing both service areas or by establishing reduced limits for responses addressing only one? This would allow each respondent to present a comparable level of detail for the personnel, disciplines, qualifications, and execution approach applicable to its proposed scope and would support KCAB's consistent evaluation of competing teams.

    No, the page limit remains the same for all responses. Additional information can be displayed in the appendix or during the interview process.

  • When filling out the Subcontractors List, is TBD acceptable for the Subcontract Value and Subcontract Amount since this is an on-call contract and amounts will vary based the assignment? Similarly, should we fill out N/A for the DBE portions?

    Yes, N/A is acceptable for DBE, Subcontract Value and Subcontract Amount.

Plain text

OpenGov categories

  • 236220 · Commercial and Institutional Building Construction
  • 237310 · Highway, Street, and Bridge Construction
  • 2379 · Other Heavy and Civil Engineering Construction
  • 237990 · Other Heavy and Civil Engineering Construction
  • 541320 · Landscape Architectural Services
  • 54133 · Engineering Services
  • 541330 · Engineering Services
  • 541350 · Building Inspection Services
  • 541360 · Geophysical Surveying and Mapping Services
  • 541611 · Administrative Management and General Management Consulting Services