Description
PUBLIC NOTICE IS HEREBY GIVEN that sealed bids will be received by the City Clerk of the chartered City of Vista (“Agency”) for furnishing all plant, labor, services, materials, tools, equipment, supplies, transportation, utilities and all other items and facilities necessary therefore, as provided in the Contract Documents, for the “As-Needed Concrete Construction, CIP No. 8290” in strict accordance with this Specifications on file in the City of Vista Engineering Department. Bid Schedule SDRSD Traffic Control Plans, Traffic Control for all work (per Task Order) Site-Specific Traffic Control Plans, Traffic Control for all work (per Task Order) Relocate Existing Roadside Signs and Poles per City of Vista Standard Drawing TRF-06. Relocate, Reconstruct, Rotate and/or Replace Existing Mailbox and Post per City of Vista Standard Drawing SRF-04 Including Reflective Address Numbers on Front and Side of Mailbox (2-inch minimum). Remove and Reconstruct 6” PCC Curb (separate), per SDRSD No. G-01 on 6-inches of Class II Aggregate Base, Average of 50 LF for any Task Order. Remove and Reconstruct 6” PCC Curb and Gutter, per SDRSD No. G-02 on 6-inches of Class II Aggregate Base, Average of 50 LF for any Task Order. Remove and Reconstruct 6” PCC Curb and Gutter, per SDRSD No. G-02 on 6-inches of Class II Aggregate Base, = 700 LF for larger Task Orders Remove and Reconstruct 8” PCC Curb and Gutter, per SDRSD No. G-02 on 6-inches of Class II Aggregate Base, Average of 50 LF for any Task Order. Remove and Reconstruct 8” PCC Curb and Gutter, per SDRSD No. G-02 on 6-inches of Class II Aggregate Base, = 700 LF for larger Task Orders. Remove and Reconstruct 4” PCC Sidewalk per SDRSD No. G-07 on 6- inches of Class II Aggregate Base, Average of 250 SF for any Task Order. Remove and Reconstruct 4” PCC Sidewalk per SDRSD No. G-07 on 6- inches of Class II Aggregate Base, = 3000 SF for larger Task Orders. Remove and Reconstruct PCC Cross Gutter per SDRSD No. G-12 on 6- inches of Class II Aggregate Base, Average of 200 SF for any Task Order. Remove and Reconstruct PCC Driveway Entrance per SDRSD Nos. G-14A -- G-14F on 6-inches of Class II Aggregate Base, Average of 200 SF for any Task Order (see Appendix C). Remove and Reconstruct PCC Alley Type Driveway per City of Vista Standard Drawing SRF-05A & -05B on 6-inches of Class II Aggregate Base, Average of 200 SF for any Task Order (see Appendix C). Remove and Reconstruct 4” PCC Pavement for Private Driveway or Flatwork on 6-inches of Class II Aggregate Base, Average of 200 SF for any Task Order. Remove and Reconstruct PCC ADA Curb Ramp SDRSD G-27 Type A or B, on 6-inches of Class II Aggregate Base, Average of 35’ Radius/Length for any Corner or Straight Curb Ramp; SDRSD G-27 Type A or B will include all work from PCR to PCR and shown on Appendix C Remove and Reconstruct PCC ADA Curb Ramp SDRSD G-27 Type A or B with Spandrel on 6-inches of Class II Aggregate Base, Average of 35’ Radius/Length for any Corner or Straight Curb Ramp; SDRSD G27 type A or B will include all work from PCR to PCR and shown on Appendix C Remove and Reconstruct PCC ADA Curb Ramp SDRSD G-28 Type A-1 or B-1 on 6-inches of Class II Aggregate Base, Average of 35’ Radius/Length for any Corner or Straight Curb Ramp; SDRSD G28 Type A-1 or B-1 will include all work from PCR to PCR and shown on Appendix C Remove and Reconstruct PCC ADA Curb Ramp SDRSD G-28 Type A-1 or B-1 with Spandrel on 6-inches of Class II Aggregate Base, Average of 35’ Radius/Length for any Corner or Straight Curb Ramp; SDRSD G28 Type A-1 or B-1 will include all work from PCR to PCR and shown on Appendix C Remove and Reconstruct PCC ADA Curb Ramp SDRSD G-29 Type C on 6-inches of Class II Aggregate Base, Average of 35’ Radius/Length for any Corner or Straight Curb Ramp; will include all work from PCR to PCR and shown on Appendix C Remove and Reconstruct PCC ADA Curb Ramp SDRSD G-29 Type C w/ Spandrel on 6-inches of Class II Aggregate Base, Average of 35’ Radius/Length for any Corner or Straight Curb Ramp; will include all work from PCR to PCR and shown on Appendix C Remove and Reconstruct PCC ADA Curb Ramp SDRSD G-31 Type D on 6-inches of Class II Aggregate Base, Average of 35’ Radius/Length for any Corner or Straight Curb Ramp; will include all work from PCR to PCR and shown on Appendix C Remove and Reconstruct Truncated Domes (Grey Color, 4-foot Long by 3-foot Wide) SDRSD G-30. Introduction Summary Background Contact Information Timeline Vendor Questionnaire Pricing Proposal Document Uploads
Published attachments
Public questions and answers
Is there a map for where and how much the item quantities are spread around the City?
There is no map provided with the As-Needed Concrete Project Specifications. This is an as-needed contract; therefore, a map will be provided with each task order. All work related to bid items will use the unit prices as bid; unit prices will prevail. All work not related to bid items will be negotiable with each task order. Some bid items refer to an average amount per task order for your use in bidding; for example: Bid Item 6, refers to “average of 50LF for any Task Order”, while Bid Item 6B, refers to larger task orders "greater than or equal to 700 LF for larger Task Orders". Task Orders can range from smaller single pedestrian ramp task orders to larger sidewalk task orders. Example Task Orders: Task Order X: Install 2EA Type C Curb Ramps with Spandrel. Task Order Y: Install 50LF 6" PCC Curb. Install 350SF PCC Cross Gutter & Spandrel. Task Order Z: Install 94LF Curb & Gutter, 182SF 4" PCC Sidewalk, 215SF PCC Driveway and other misc. items.
Do the line items listed in the pricing proposal account for afterhours/weekend/holiday work?
Refer to project specifications section 6-7.2 Working Days / Hours. "Unless otherwise specified, the Contractor’s activities shall be confined to normal working hours between 7:00AM and 5:00PM, Monday through Friday. Lane closures will be confined to the hours between 8:30AM and 3:30PM, Monday through Friday. No work shall be done on Saturdays, Sundays, or holidays without authorization by the Engineer...."
The bonding agency requests that the following information be clarified: Please advise whether the contract renewal is mutually negotiated or at the agency's sole discretion. Please advise, if contract renewal is at the agency's sole discretion, whether an annual performance and payment bond will be acceptable at each renewal per the following example: https://acrobat.adobe.com/id/urn:aaid:sc:VA6C2:1e521f4b-2802-49f8-9c4d-bf0bb1c7a128
We will not be clicking on the provided link. Contract renewal process: • Written notice of the City’s intension to renew (at the Agency’s full discretion), given approximately 90 calendar days prior to the expiration date of each contract period. • City and Contractor sign an Amendment extending the contract date. Bonds and insurance that include the extension timeline will need to be in place prior to execution of an amendment.