Auxiliary Lake Intake Sediment and Debris Removal

Description

The City of Murfreesboro is accepting sealed bids for Auxiliary Lake Intake Sediment and Debris Removal , ITB-15-2027 to be received no later than Friday, November 13, 2026 , 2:00 pm CST. Bid Form Please refer to the attached bid form, located in the "Attachments" section of this ITB. Download, complete, and upload here in PDF format. Scope of Work Important Instructions for Electronic Submittal The City is accepting electronic bid submissions. Bidders shall create a FREE account with OpenGov by signing up at https://procurement.opengov.com/signup. Once you have completed account registration, browse back to this page, click on "Submit Response", and follow the instructions to submit the electronic bid. Introduction Summary Background Contact Information Timeline Forms to Complete Attachments

Published attachments
Public questions and answers
  • Is it possible to review the previous dive contractors inspection report?

    There is no inspection report, there are Field Notes from the contractor as follows: LAKE NOTES: The second floor which is what we referred to as the level above the staircase that went under the water line originally had about 3-4’ of sediment. The crew was able to get it down in most areas to about 1-2’ The diver went down the ladder to pump level (ground floor). At no point was the diver able to touch the floor due to the amount of heavy build up of sediment. The diver crawled across the sediment to the pumps and small baffles that separated the pumps The sediment went over the baffle walls in some areas almost 2’. A drawing in the room above labeled the walls as being 6’ tall indicating that the sediment reached 8’ in some areas. The diver stated there were small indentations in the sediment below the pumps - more than likely from where the pumps pulled through The diver was unable to travel closer to the lake side due to sediment accumulation The pump room alone has approximately 6-8’ of sediment and the 1-2’ of sediment remains on the level above The sediment consisted of an oily substance and resembled a mud/clay mixture. Difficult to remove by suction alone and required/s a form of abrasion or shoveling/moving

  • So as to adequately evaluate this project and the technics for cleaning the wet well, traveling screen area, intake pipe and intake screens please extend the bid 7 days until 20 Nov 2026.

    At this time, we do not intend on extending the date.

  • Can vacuum trucks and support equipment stage on the intake deck or access road, or must all pumping be performed from a boat/float? What is the load rating of the intake deck? How far is it from the access road to the point at the intake where we would need to vacuum the sediment? Can we work from vehicles on that access road, or does the sediment removal have to be done from the water using a barge? Can we temporarily stop water from entering the intake while a diver or vacuum truck is removing the sediment? If yes, how long can the intake stay blocked?

    1) Not on access deck, but access road is fine as long as the trail between the fence and the water is not blocked. The trail is used for horseback riding, and we cannot block it. We do not know the load rating of the intake deck. 2) Drawing and map is provided in Bid documents. Similar to #1, you can work from access road (but not the trail). Work does not have to be done using a barge. 3) If done in January, we will stop pumping. A temporary stop is allowed for up to three days, not including weekends.

  • Can a second site visit be arranged? Who should be contacted?

    Yes. Please contact Water Resources Dept. staff, Joe Russell or Steve Toler, (615) 848-3222