Bay Colony Water Main Improvements

Description

The purpose of this project is to replace about 10,100 FT of aging and deficient water main on the following streets in the Bay Colony Subdivision: Waxwing Avenue, Fredrick Lane, Carol Lane, Bay Colony Drive, Terrance Drive and Olympus Drive. The existing 6” to 10” water mains are cast iron pipe installed in the 1970s. These will be replaced and upsized to 8” and 12” ductile iron pipe in accordance with City Standards. Base Bid REMOVAL AND DISPOSAL OF CONTAMINATED SOIL TREE ROOT PRUNING TREE TRUNK PROTECTION TREE PROTECTIVE FENCING TREE REMOVAL SODDING, SPECIAL SUPPLEMENTAL WATERING INLET FILTERS COLD-MIX ASPHALT CLASS D PATCHES, 6" HOT-MIX ASPHALT SURFACE REMOVAL – 2” BITUMINOUS MATERIALS (TACK COAT) HOT-MIX ASPHALT SURFACE COURSE, MIX D, N50 HOT-MIX ASPHALT DRIVEWAYS, REMOVAL AND REPLACEMENT, 4" PCC DRIVEWAYS, REMOVAL AND REPLACEMENT, 6" PORTLAND CEMENT CONCRETE SIDEWALK, REMOVAL AND REPLACEMENT COMBINATION CURB AND GUTTER REMOVAL AND REPLACEMENT DETECTABLE WARNINGS DUCTILE IRON WATER MAIN, 6" DUCTILE IRON WATER MAIN, 8" DUCTILE IRON WATER MAIN, 12" DUCTILE IRON WATER MAIN, 16" STEEL CASING PIPE, 16" DUCTILE IRON WATER MAIN, 8" (PUSHED INTO CASING) STEEL CASING PIPE, 16" (BORED AND JACKED) WATER SERVICE, NEAR SIDE, 1 1/2" WATER SERVICE, FAR SIDE, 1 1/2" GATE VALVE 6", VALVE VAULT 4' DIA, TYPE 1 FRAME, CLOSED LID GATE VALVE 8", VALVE VAULT 4' DIA, TYPE 1 FRAME, CLOSED LID GATE VALVE 12", VALVE VAULT 5' DIA, TYPE 1 FRAME, CLOSED LID GATE VALVE 16", VALVE VAULT 5' DIA, TYPE 1 FRAME, CLOSED LID WATER MAIN LINE STOP, 8" WATER MAIN CONNECTION "A" (NON-PRESSURE) WATER MAIN CONNECTION "B" (PRESSURE) WATER MAIN CONNECTION "C" (NON-PRESSURE) WATER MAIN CONNECTION "D" (PRESSURE) WATER MAIN CONNECTION "E" (NON-PRESSURE) WATER MAIN CONNECTION "F" (NON-PRESSURE) WATER MAIN CONNECTION "G" (NON-PRESSURE) WATER MAIN CONNECTION "H" (NON-PRESSURE) Bid Alternate A REMOVAL AND DISPOSAL OF CONTAMINATED SOIL TREE ROOT PRUNING TREE TRUNK PROTECTION TREE PROTECTIVE FENCING TREE REMOVAL SODDING, SPECIAL SUPPLEMENTAL WATERING INLET FILTERS COLD-MIX ASPHALT CLASS D PATCHES, 6" HOT-MIX ASPHALT SURFACE REMOVAL – 2” BITUMINOUS MATERIALS (TACK COAT) HOT-MIX ASPHALT SURFACE COURSE, MIX D, N50 HOT-MIX ASPHALT DRIVEWAYS, REMOVAL AND REPLACEMENT, 4" PCC DRIVEWAYS, REMOVAL AND REPLACEMENT, 6" PORTLAND CEMENT CONCRETE SIDEWALK, REMOVAL AND REPLACEMENT COMBINATION CURB AND GUTTER REMOVAL AND REPLACEMENT DETECTABLE WARNINGS PVC C900 WATER MAIN, 6" PVC C900 WATER MAIN, 8" PVC C900 WATER MAIN, 12" PVC C900 WATER MAIN, 16" STEEL CASING PIPE, 16" PVC C900 WATER MAIN MAIN, 8" (PUSHED INTO CASING) STEEL CASING PIPE, 16" (BORED AND JACKED) WATER SERVICE, NEAR SIDE, 1 1/2" WATER SERVICE, FAR SIDE, 1 1/2" GATE VALVE 6", VALVE VAULT 4' DIA, TYPE 1 FRAME, CLOSED LID GATE VALVE 8", VALVE VAULT 4' DIA, TYPE 1 FRAME, CLOSED LID GATE VALVE 12", VALVE VAULT 5' DIA, TYPE 1 FRAME, CLOSED LID GATE VALVE 16", VALVE VAULT 5' DIA, TYPE 1 FRAME, CLOSED LID WATER MAIN LINE STOP, 8" WATER MAIN CONNECTION "A" (NON-PRESSURE) WATER MAIN CONNECTION "B" (PRESSURE) WATER MAIN CONNECTION "C" (NON-PRESSURE) WATER MAIN CONNECTION "D" (PRESSURE) WATER MAIN CONNECTION "E" (NON-PRESSURE) WATER MAIN CONNECTION "F" (NON-PRESSURE) WATER MAIN CONNECTION "G" (NON-PRESSURE) WATER MAIN CONNECTION "H" (NON-PRESSURE) Special Work Allowance SPECIAL WORK ALLOWANCE Scope of Work Scope of Work Please see the Attachments section for specifications and attachments: Technical Specifications Construction Drawings Geotechnical Exploration Report and LPC-663 Introduction Timeline Release Bid Date / Advertised: October 28, 2026 Pre-Bid Meeting (Non-Mandatory): November 5, 2026, 1:00pm https://teams.microsoft.com/meet/239986354373922?p=vc3nWGDUNbwsJrYulY Meeting ID: 239 986 354 373 922 Passcode: Xk6Sv9Th Dial in by phone +1 630-733-1095 Phone conference ID: 908 039 367# Question Submission Deadline: November 11, 2026, 5:00pm Question Response Deadline: November 13, 2026, 5:00pm Bid Opening: November 20, 2026, 2:00pm Project Overview The purpose of this project is to replace about 10,100 FT of aging and deficient water main on the following streets in the Bay Colony Subdivision: Waxwing Avenue, Fredrick Lane, Carol Lane, Bay Colony Drive, Terrance Drive and Olympus Drive. The existing 6” to 10” water mains are cast iron pipe installed in the 1970s. These will be replaced and upsized to 8” and 12” ductile iron pipe in accordance with City Standards. Title: Bay Colony Water Main Improvements Bid No: 26-174 Bid Due Date/Time: Friday, November 20, 2026 , 2:00 pm Virtual Bid Opening To attend the Virtual Bid Opening on your computer or mobile app: Click here to join the meeting Or call in (audio only) +1 630-733-1095. Phone Conference ID: 515 682 5 14# app roximately 5 minutes prior to the Due Date/Time. Attendees should join approximately 5 minutes prior to the Due Date/Time. Due at Bid Opening: Affidavit of Compliance Responsible Bidder Ordinance Form Bid Worksheet Bid Deposit (10% of Total Bid) References Subcontractor Bid Form IDOT Prequalification Certificate IDOT Form BC 57 Affidavit of Availability (Contractor shall also provide owner contact information for all projects included on the form) Due Before Award: Certificate of Insurance (with signed endorsements) Performance and Labor and Material bond Substance Abuse Prevention Program Due within thirty (30) days of Award: Contractors Safety Checklist (before work begins) If you choose not to respond, please select NO BID on https://procurement.opengov.com/portal/naperville . Disclaimer Document Distribution The City of Naperville Procurement Services and its e-Procurement Portal https://procurement.opengov.com/portal/naperville are the only authorized sources of solicitation documents. Solicitation documents and forms obtained from any other source may be an incomplete set of documents. Reproduction of these documents without the express permission of the City of Naperville is prohibited. Instructions to Bidders The City of Naperville Procurement Services and its service provider OpenGov are the only authorized sources of bidding documents/proposal forms. Bidding documents/proposal forms obtained from any other source may be an incomplete set of documents. Reproduction of these documents without the express permission of the City of Naperville is prohibited. Description of Work Contractor shall perform all Work in accordance with this Contract. Contractor shall furnish all materials, equipment, tools, and labor which is reasonably and properly inferable and necessary for the proper completion of the Work, whether specifically indicated in this Contract. Pre-Bid Meeting A Non-Mandatory Pre-Bid Meeting will be held on Thursday, November 5, 2026 at 1:00 pm virtually. Bidders are encouraged to send a representative to attend the Pre-Bid meeting. This is your only opportunity to speak directly with staff from the Public Utilities (Water) | DPU-W regarding the project. Questions During the Bid Process All questions concerning this bid shall be submitted in writing prior to the question due date. The deadline for questions is Wednesday, November 11, 2026 5:00 pm If required, a written response in the form of an addendum will be issued no later than Friday, November 13, 2026 5:00 pm . No contact with the Public Utilities (Water) | DPU-W shall be made during the bid process. Questions asked after the deadline are not guaranteed a response. Civic Access Portal for Vendors The City of Naperville has developed a new portal for vendors to register and update existing information within Civic Access. The City of Naperville will only accept vendor forms from vendors currently working with the Procurement and/or Accounts Payable teams. It will allow you to: Register as a new vendor. Sign up for ACH payments. Update existing vendor information (e.g. new mailing address, new TIN/W9, new banking information). How do I register? To create an account, please visit the City of Naperville Civic Access portal . Once you have created an account, submit your vendor information Accounts Payable – Vendor Form Submission application. Vendors can find step-by-step instructions in the Knowledge Center . An accounts payable staff member will verify your submission and follow up if there are any questions on your submission. Please send an email message to FSDAccountsPayable@naperville.il.us for assistance if needed. Insurance Requirement (A) Commercial General Liability: Coverage shall be at least as broad as Insurance Services Office Commercial General Liability coverage (Occurrence Form CG 00 01) and include Premise/Operations, Products/Completed Operations, Independent Contractors, Contractual and Personal Injury/Advertising Injury. Limits: General Aggregate $2,000,000.00 Products/Completed Operations $2,000,000.00 Each Occurrence $2,000,000.00 Personal Injury $2,000,000.00 (B) Automobile Liability: Coverage shall be at least as broad as Insurance Services Office Form CA 00 01 to include all Owned, Hired, Non-owned vehicles. Limits: Combined Single Limit Per Accident $2,000,000 (C) Workers’ Compensation: Coverage shall be as required by the State of Illinois, with Statutory Limits, and Employers’ Liability insurance with a limit of no less than $1,000,000 per accident for bodily injury or disease. (D) Employers’ Liability Limits: Each Accident $1,000,000 Each Employee Bodily Injury by Disease $1,000,000 Policy Limit Bodily Injury by Disease $1,000,000 (E) Other Insurance Provisions The Commercial General Liability and Automobile Liability policies are to contain, or be endorsed to contain, the following provisions: 1. The City, its officers, officials, employees and volunteers are to be covered as insured’s with respect to liability arising out of automobiles owned, leased, hired or borrowed by or on behalf of the Contractor; and with respect to liability arising out of work or operations performed by or on behalf of the Contractor including materials, parts or equipment furnished in connection with such work or operations. General Liability coverage shall be provided in the form of an Additional Insured endorsement to the Contractor’s insurance policy, or as a separate owner’s policy. 2. For any claims related to this project, the Contactor’s insurance coverage shall be primary insurance as respects the City, its officers, officials, employees and volunteers. Any insurance or self-insurance maintained by the City, its officers, officials, employees or volunteers shall be excess of the Contractor’s insurance and shall not contribute with it. The Workers’ Compensation policy shall be endorsed with a waiver of subrogation in favor of the City for all work performed by the Contractor, its employees, agents and subcontractors. The Contractor understands that the acceptance of Certificates of Insurance, policies and any other documents by the City in no way releases the contractor from the requirements set forth herein. Illinois Prevailing Wage Act This contract calls for the construction of a “public work” within the meaning of the Illinois Prevailing Wage Act (820 ILCS 130/1-12 et seq.). Contractors and subcontractors shall comply with the requirements of the Illinois Prevailing Wage Act including, but not limited to, all wage requirements and notice and recordkeeping duties including paying laborers, workers and mechanics performing work under this contract no less than the currently prevailing rate of wages in the county where the work is performed and filing a copy of the certified payroll with the public body in charge of the project as well as the State; see link below for additional details. The Contractor is advised that the Illinois Department of Labor (IDOL) revises the prevailing wage rates and the Contractor/subcontractor has an obligation to check the IDOL website for revisions to prevailing wage rates. For information regarding the current prevailing wage rates, please refer to the DOL website: https://www2.illinois.gov/idol/laws-rules/conmed/pages/prevailing-wage-rates.aspx . If IDOL revises the prevailing rates of wage during the term of the contract, the Contractor/subcontractor is required to pay the then current prevailing rate of rages. Any increases in costs to the Contractor due to changes in the prevailing rate of wage during the term of any contract shall be at the expense of the Contractor and not at the expense of the Owner. The Contractor shall defend and hold harmless the City, for any claim, suit or action, including costs of defense, expert witness and attorney fees, either at law, equity or in an administrative proceeding, arising from any alleged violation of the Prevailing Wage Act. The requirements of this Section shall survive the termination of the Agreement formed hereunder. Pursuant to PA 100-1177 and in accordance with 820 ILCS 130/5.1, the Illinois Department of Labor (DOL) launched the Certified Transcript of Payroll Portal and contractors are now required to submit all of their certified payroll documentation to the State rather than local government agencies. Certified Payroll must have the bid number clearly identified. The link to the DOL portal is below: https://www2.illinois.gov/idol/Laws-Rules/CONMED/Pages/certifiedtranscriptofpayroll.aspx Employment of Illinois Workers on Public Works Act Contractor agrees to comply with the Employment of Illinois Workers on Public Works Act ( 30 ILCS 570/0.01 et seq.) and employ Illinois laborers if, at the time this contract is executed or during the term of this contract, there is excessive unemployment in Illinois as defined in the Act. To review the statute, please click on the link found here . Substance Abuse Prevention on Public Works Projects Act The successful bidder must be in compliance with State of Illinois HB-1855 ( Public Act 095-0635 ), which amends the Prevailing Wage Act. Before an employer commences work on a public works project, the employer shall have in place a written program which meets or exceeds the program requirements in this Act, to be filed with the public body engaged in the construction of the public works and made available to the general public, for the prevention of substance abuse among its employees. The testing must be performed by a laboratory that is certified for Federal Workplace Drug Testing Programs by the Substance Abuse and Mental Health Service Administration of the U.S. Department of Health and Human Services. Responsible Bidders Ordinance (RBO) Section 1-9B of the Naperville Municipal Code requires that bidders for City of Naperville construction contracts in excess of $34,999.99 must participate in active apprenticeship and training programs approved and registered with the United States Department of Labor’s Bureau of Apprenticeship and Training to be considered a responsible bidder. A bidder must affirm such participation with a signed Responsible Bidder Affidavit submitted with any bid. Freedom of Information Act Contractor acknowledges that the Freedom of lnformation Act, 5 ILCS 140/1 et seq. (the "ACT") places an obligation on the City to produce certain records that may be in possession of the Contractor. Contractor shall comply with the retention and documentation requirements of the Local Records Retention Act 50 ILCS 205/1 et seq. and the Act and shall maintain all records relating to this Agreement in compliance with the Local Records Retention Act (complying in all respects as if the Contractor was, in fact, the City). Upon notice from the City, Contractor shall review its records promptly and produce to the City within two business days of said notice from the City the required documents which are responsive to a request under the Act. If additional time is necessary to comply with the request, the Contractor may request the City to extend the time to do so, and the City will, if time and a basis for extension under the Act permits, consider such extensions. In the event Contractor fails to produce the requested records or fails to produce the requested records within the time period required above and the City is assessed a fine, fee or penalty for failure to timely comply with Act do to Contractor’s actions, Contractor shall reimburse City for all fines, fee or penalties, including reasonable attorney’s fees, paid by the City. Contractor Safety Orientation Checklist Prior to the start of any work, the Contractor and the Jobsite Manager/Supervisor will be required to complete the City’s Contractor Safety Orientation Checklist at a pre-construction meeting. No work can begin until the completed form has been received and signed by the Jobsite Manager/Supervisor. A sample of the Contractor Safety Orientation Checklist is included as part of the bid document. Basis of Award The City of Naperville intends to award a contract to the responsible bidder submitting the lowest responsive bid for either the Total Base Bid or the Total Alternate A Base Bid. Pricing for both the Total Base Bid and Total Alternate A Base Bid must be submitted in order to be considered responsive. The City reserves the right to award the Total Base Bid or the Total Alternate A Bid, whichever serves in the best interest of the City. The lowest price shall be determined by the Total Base Bid amount listed on the Bid Worksheets, resulting from multiplying the actual number of acceptable units by the unit price items incorporated into the work or service, all as set forth in the bid worksheets. In addition, if requested within the bid documents, the City may elect to include, within the Total Bid, any combination of additive, alternate, or optional Bid items for which the City determines funds will be available at the time of award. The City will review and make adjustments associated with arithmetic errors to ascertain whether the order of bids is correct. In the event of arithmetic errors in any of the line items, the unit price will be the controlling factor to correct the arithmetic error. The City will not assume that the error exists in the unit price. Bids submitted are offers only, and the decision to accept or reject is a function of quality, reliability, capability, reputation, and expertise of the bidders. The City reserves the right to reject any and all bids or to waive any non-conformity in bids received whenever such rejection or waiver is in the best interests of the City. The City also reserves the right to reject the bid of a bidder who has previously failed to satisfactorily perform a contract, has not completed contracts on time, or whom investigation shows is not in a position to perform the contract. The City of Naperville reserves the right to award individual bids to more than one vendor if it is deemed to be in the best interest of the City. The City reserves the right to increase or decrease the contract quantity without penalty from the contractor to the City. Amounts listed on the Bid Worksheets are estimated amounts only and are not to be considered a guarantee of work. City of Naperville General Terms and Conditions General Terms and Conditions and Instructions to Bidders THE GENERAL TERMS AND CONDITIONS WHICH FOLLOW APPLY TO ALL PURCHASES AND BECOME A DEFINITE PART OF EACH FORMAL INVITATION TO BID, PURCHASE ORDER, OR CONTRACT ISSUED BY THE CITY OF NAPERVILLE, UNLESS OTHERWISE SPECIFIED. BY SUBMITTING A BID, THE BIDDER AGREES TO BE BOUND BY THESE TERMS AND CONDITIONS. BIDDERS OR THEIR AUTHORIZED REPRESENTATIVES ARE EXPECTED TO FULLY INFORM THEMSELVES OF THE CONDITIONS, REQUIREMENTS, AND SPECIFICATIONS BEFORE SUBMITTING BIDS, FAILURE TO DO SO WILL BE AT THE BIDDER'S OWN RISK AND HE CANNOT SECURE RELIEF ON THE PLEA OF ERROR. BIDDING PROCEDURES The first three items must be performed by the bidder in order for the bid submittal to qualify for consideration by the City. Bidding Forms Bids must be accompanied by

Published attachments
Addenda and notices
  • Addendum #1 · 1

    The attention of bidders is called to the following changes, clarifications and/or additions/deletions to the original contract specifications and drawings and they shall be taken into account in preparing proposals and shall be part of the Contract Documents: INFORMATION: A non-mandatory pre-bid meeting was held on Thursday November 5 virtually via teams . The notes from the meeting are attached. Below are questions answered at the meeting: Question: Does all paving need to be done in 2027? Answer: Yes Question: Where is the curb replacement occurring? Answer: The curb replacement is only meant for water main patch work Question: Surface quantity listed covers mill area only, Is this enough? Answer: The Surface Course quantity covers the full lane width (milled area plus Class D Patch area). The full lane where the water main is constructed will be milled, however in accordance with the Technical Specifications, the area over the Class D Patching will not be quantified for payment. Please note, Item 11 (HMA Surface Removal) has been updated accordingly. REVISIONS: School Restrictions on page 48 are changed from "Work in front of Lincoln Junior High School (Olympus Dr between 75th St and Waxwing Ave, and Waxwing Ave between Olympus Dr and Clyde Dr) shall be restricted to between June 1, 2026 and August 8, 2026. Work while school is in session is not permitted" to, " Work in front of Lincoln Junior High School (Olympus Dr between 75th St and Waxwing Ave, and Waxwing Ave between Olympus Dr and Clyde Dr) shall be restricted to between June 6, 2027 and August 8, 2027. Work while school is in session is not permitted." Quantity updated in item 11 of bid worksheet in the Base Bid and Bid Alternate A tables ATTACHMENTS: Q&A Report Pre-Bid meeting notes C2.29 Schedule Please use the See What Changed link to view all the changes made by this addendum.

Public questions and answers
  • The special provisions call for a 6" HMA binder patch which will be surfaced after 2" milling is performed. The total quantity included in the pay item for HMA Surface does not include the surface quantity over the Class D Patches, it only accounts for the HMA Surface Removal area. Can you confirm whether the 2" surface over the Class D Patches is intended to be included in the pay item for Class D Patches or revise the pay quantity for the HMA Surface pay item to account for this area?

    The Surface Course quantity covers the full lane width (milled area plus Class D Patch area). The full lane where the water main is constructed will be milled, however in accordance with the Technical Specifications, the area over the Class D Patching will not be quantified for payment. Please note, Item 11 (HMA Surface Removal) has been updated accordingly.

Plain text

OpenGov categories

  • 72141121 · Water main construction service