Description

Henry County is issuing this solicitation for Drainage Improvements at Grove Pointe Subdivision . Submissions shall be received before 3:00PM on November 25, 2026 , via the County's eProcurement Portal at https://procurement.opengov.com/portal/henryga . Late submissions will not be accepted. Bid Price Sheet 36” Corrugated Metal Pipe (CMP) 36” Corrugated Metal Pipe (CMP) 42” Corrugated Metal Pipe (CMP)) Project Details Important Instructions for Electronic Submittals The Henry County Board of Commissioners is accepting electronic bid submissions. Bidders shall create a FREE account with OpenGov Procurement by signing up at https://procurement.opengov.com/signup . Once you have completed account registration, browse back to this page, click on "Draft Response", and follow the instructions to submit the electronic bid. Scope of Work or Project Details Please see the Attachments section for specifications and attachments. Introduction Summary Henry County is issuing this solicitation for Drainage Improvements at Grove Pointe Subdivision . Submissions shall be received before 3:00PM on November 25, 2026 , via the County's eProcurement Portal at https://procurement.opengov.com/portal/henryga . Late submissions will not be accepted. Timeline Release Project Date: October 28, 2026 Question Submission Deadline: November 12, 2026, 3:00pm Question Response Deadline: November 18, 2026, 3:00pm Bid Submission Deadline: November 25, 2026, 3:00pm Procurement Contact Shawnviez Lilly Procurement Agent II 140 Henry Parkway McDonough , GA 30253 Email: slilly@henrycountyga.gov Phone: (770) 288-6263 Cost Schedule Vendor Questionnaire Attachments

Published attachments
Addenda and notices
Public questions and answers
  • Corrugated metal pipe (CRM) and Concrete reinforced pipe (RCP) can be refurbished using a spin cast method which gives a pipe when refurbished an additional 75 to 100 year lifespan. This can be done at a fraction of the cost vs. replacing the pipe. Also, such a service can be done without completely shutting off traffic access to the road above the pipe.

    At this time we are asking for the pipes to be replaced. Please bid accordingly.

  • Will there be any plans or drawings for this project?

    See Addendum #1 for attached drawings.

  • Are there any profile drawings?

    No.

  • Are there any specifications for Corrugated Metal Pipe (CMP)

    See page 15 of the bid document for pipe size and length.

  • Can we substitute the CMP pipe with aluminized coated CMP pipe. (Corrugated Metal Pipe).

    No.

  • Is the scope of work located at driveway entrance between the tennis court and swim pool area?

    Yes. See attached drawing in Addendum #1.

  • Is the scope of work located between pedestal inlet and outfall across the main road? Also, are we doing anything with headwall?

    Yes. We do not anticipate any work to be done to the existing headwall, it shall remain in place. See attached drawing in Addendum #1.

  • 1. Are existing headwalls, Manholes, or other drainage structures included in the replacement scope, or are they to remain in place? 2. Please confirm whether Henry County will provide all traffic control devices and road closures, including flaggers and traffic-control personnel or if these items are the contractor's responsibility. 3. Please clarify whether bidders are required to provide unit prices per LF in addition to the total lump-sum amount for each location. 4. Please provide the anticipated Notice of Proceed (NTP) date and required project completion period. Also, whether work can be performed concurrently at the three locations. 5. Please clarify whether the DBE or M/WBE certification must be specific to Henry County or if certification through any other Georgia county or recognized state certification program will also qualify? 6. Project Requirement #6 states that the final topping for each crossing shall be Graded Aggregate Base (GAB). Please confirm whether GAB will serve as the permanent final surface at all three crossings or whether additional surface restoration, such as asphalt or other materials, will be required.

    1. Remain in place 2. Traffic control will be the responsibility of the contractor. 3. Please see the bid price sheet located on page 29 of the bid documents. 4. We'd like to issue the NTP the end of January/first of February 2027. Work can be performed concurrently. 5. DBE certification must be recognized by GDOT or a state affiliated program. 6. GAB will serve as permanent final surface for all three crossing. The roads in this subdivision will be resurfaced shortly after the pipe work is complete.

  • Lewis Contracting Services is 100 percent DBE. Do we still need to list a DBE Contractors? if so, Does the DBE participants we list need to be certified in Henry County?

    No, a Prime can serve as a DBE. DBE certification must be recognized by GDOT or a state affiliated program.

  • Is the scope of work located between pedestal inlet and outfall across the main road? Also, are we doing anything with headwall?

    Yes. We do not anticipate any work to be done to the existing headwall, it shall remain in place. See attached drawing in Addendum #1.

Plain text

OpenGov categories

  • 91377 · Maintenance and Repair, Pipe Culvert
  • 92528 · Drainage Engineering