Description

Installation of new splash pad and concession building at Homer Wheaton Park - Mountainview Ave, Syracuse, NY 13224 Homer Wheaton Park General Construction Bid Table The undersigned bidder shall provide unit prices for the items listed below. Unit prices shall include all costs to provide, install, and/or repair work items including, but not limited to, labor, materials, equipment, miscellaneous shoring, supervision, overhead & profit, etc. All work indicated on the Contract Drawings and the Specifications that do not have a specific unit price item # listed below shall be considered as part of the base bid price item GC-1. General Construction, Moblization, & Miscellaneous Items not listed below Removal of existing asphalt pavement and associated subbase material hauled offsite Removal of existing chain link fence, posts and footings Removal of existing flagpole and base Remove exist. benches, brick rip rap, and misc. items Lawn removal and strip topsoil Trenching - Utilities, electric, water and Sanitary including shoring Install silt fence and erosion control measures Install Concrete Pavement - full assembly, including concrete, reinforcement, subbase course, expansion joints, control joints, subbase Install structural stone pad for pre-engineered building ( supplied by owner) Install new block seat wall Install new flagpole and base Restore existing brick steps and cheek walls Install Site Electric Lines, Including backfill and lawn restoration Install water service (including meters, stops, valves, and connection to existing municipal service) Install sanitary service (including manhole, vent, trap and shoring) Coordinate the delivery and installation of the concession building Spread topsoil and install lawn Plant trees Asphalt Paving- Including geotextile, base material and asphalt Electrical service - Install all electrical equipment and connections to new amenities from the existing service Plumbing Service - Install all plumbing lines, and fixtures, including permits and inspections - jetting and scoping Bid Alternate 1 - Splash Pad Install concrete splash pad - ( including deduct for area of topsoil in base bid area) Install Electric Line - Site Install splash pad features and drain Plumbing Service- Install all plumbing lines and fixtures including permits and inspections Electrical Service - Install all equipment and connections, including permits and inspections Bid Alternate 2 - Splash Pad WDS Drainage Install sanitary line from splash pad, WDS box to sanitary main (including vent and trap) SECTION 00100: INSTRUCTION TO BIDDERS ELECTRONIC SUBMISSION INSTRUCTIONS Bids may be received up to but not later than Tuesday, November 24, 2026 at 2:30 pm via the City eProcurement Portal located at https://procurement.opengov.com/portal/syrgov . The City eProcurement Portal Clock is the official clock for the determination of all deadline dates and times. Without exception, responses will not be accepted after the submission deadline regardless of any technical difficulties such as poor internet connections. City of Syracuse strongly recommends completing your response well ahead of the deadline. Bidders shall create a FREE account with OpenGov Procurement by signing up at https://procurement.opengov.com/signup . Once you have completed account registration, browse back to this page, click on "Draft Response", and follow the instructions to submit the electronic bid. HARD COPY INSTRUCTIONS The City prefers electronic submission. If you choose to subm it hard copy, p lease submit prior to Tuesday, November 24, 2026 at 2:30 pm to: Office of Management & Budget, Division of Purchase Room 213 City Hall Syracuse, New York 13202 Bid packages must: Be sealed and clearly marked on the exterior showing the Bidder's name and reference number as listed in this solicitation. Clearly indicate the responsible Bidder's status and be signed by an individual authorized to enter into and bind that proposer into a contractual agreement. Please retain a copy of this complete document for your records. You will be forwarded notice of the awarded items only. BID BOND Each bid must be accompanied by a certified check or bid bond payable to the "Commissioner of Finance" of the City of Syracuse, New York for each Division of work in the amount of 5% of the Contractor's Bid Price. FORM OF BID PRICE Each Bidder is required to state a price as specified for each and every item enumerated in electronic price proposal. If submitting physically: Each Bidder is required to state a price as specified for each and every item enumerated in the bid sheet upon which the bid is made. Price(s) must be written with ink, in words, and in figures. Do not round off numerals. Do not remove the bid forms from this book. All Contract Documents, except the separately bound Contract Drawings must be submitted with the Bid. PERSONS INTERESTED IN BID Each Bidder is required to state in his bid the names and places of residence of any and all persons interested in the bid; that the bid is made without any connection with any persons making another bid for the same contract, and that it is in all respects fair and without collusion or fraud; also, that no member of the Common Council, or other office of the City of Syracuse, or any person in the employ of said City is directly or indirectly interested in the bid, or in the supplies or the work to which it relates, or in any portion of the profits thereof. WITHDRAWAL OF BID Electronic Bids: may be withdrawn prior to the bid deadline by selecting "unsubmit" button at the bottom of the vendor's response. Hard Copy Bids: any bid can be withdrawn upon notice to Purchase up to three days after the bid opening if based on a legitimate error that would prevent the municipality from enforcing the bid. REJECTION OF BID The Director of the Office of Management & Budget, Division of Purchase reserves the right to reject any and all bid and to reject as informal such bids as, in his opinion, are incomplete, conditional, obscure, or which contain irregularities of any kind. INDEPENDENCE OF BIDS Each Bidder is required to form his own opinion of the quantities and character of the work by personal examination of the ground where it is to be done and of the Plans and Specifications relating to it, or by such other means as he may prefer. He shall satisfy himself as to the character, quality, and quantities of work to be performed, materials to be furnished and as to the requirements of the proposed Contract. The submission of a proposal shall be prima facie evidence that the Bidder has made such examination and is satisfied as to the conditions to be encountered in performing the work and as to the requirements of the proposed Contract, Plans and Specifications. No allowance shall be made subsequently in this connection in behalf of the Contractor. Additional information pertinent to the work, e.g. boring / coring logs, other records of subsurface investigations, and other relevant information related to the work of these Contract Documents may be available for inspection by Bidders. It is understood and agreed that such information, whether included in the plans, specifications or otherwise made available to the Bidder, was obtained and is intended for the Owner's design and estimating purposes only. Such information has been made available for the convenience of all Bidders. It is further understood and agreed that each Bidder is solely responsible for all assumptions, deductions, or conclusions which he may make or obtain from his examination of the boring logs and other records of subsurface investigations and tests that are furnished by the Owner. SURETY BOND The person or persons whose bid has been accepted will be required to furnish a bond in the amount of One Hundred percent (100%) of the total bid on which the contract shall be let, from some responsible surety company authorized to do business in the State of New York, and to attend at the office of the Director of the Office of Management & Budget, Division of Purchase with the sureties offered by him or them and execute the contract and bond within 10 (ten) days from the date of the service of a notice to that effect, delivered to him or them in person, or mailed to the address given in the bid. In the case of failure to do so, he or they will be deemed to have abandoned the contract, and the amount of the deposit made by him or them will be forfeited to and retained by the City of Syracuse as liquidated damages for such failure, but if he or they shall execute the contract and bond within the time aforesaid, the amount of his or their deposit will thereupon be returned to him or them. PAYMENT The Contractor will be paid monthly approximate estimates to a total amount of ninety-five percent (95%) of the value of the work done to date. CLAIMS The Contractor shall have no claim against the City of Syracuse by reason of any variance between the quantities of the approximate estimate and the quantities of work done, nor on account of any misunderstanding or misconception of the nature and character of the work, or of the ground where it is executed. Payment to the Contractor will be made only for the actual quantities of work performed or materials furnished in accordance with the Contract, Plans and Specifications. SUBSTITUTIONS If the Contractor proposes to use materials or devices other than those specified, equal in quality and workmanship in all respects thereto, he shall attach to the Bid Documents the materials or devices which he proposes to furnish for review by the Engineer. At a minimum, the Contractor will provide a detailed breakdown of all materials or devices to be used, which shall be subject to the approval of the Engineer. Failure to propose a substitution shall be deemed to mean that the Contractor proposes to use material or devices chosen by the Specifications as standards. The Owner reserves the right to reject any substitutions proposed, and the Contractor will be required to advance all work in accordance with the Contract Documents. BIDS Bids are solicited on a lump sum or unit price basis for each item listed in the proposal. The total price bid for each item shall be for the completion of all parts of the work as shown on the plans and prescribed by specifications, together with all work incidental thereto, for each item listed in the Form of Proposal. Bids will be compared, computed and canvassed on the basis of the approximate estimate and quantities stated in the bid. MINIMUM REQUIREMENTS FOR BIDDING Bidders must be skilled and regularly engaged in the class of work bid, and, if required by the City Engineer, must submit satisfactory evidence of mechanical facilities and financial ability to do the work within the agreed time and in accordance with all the requirements of the Contract. The successful bidder will be required to keep the entire work of the Contract at all times under his control. Other requirements for bidding are included elsewhere in these Specifications. PLAN DEPOSIT Upon returning set promptly and in good condition within 30 days after the date of the Bid Opening, plan deposits shall be refunded as follows: A. If the Contract Documents returned are in good condition, 100% of the plan deposit shall be returned to the Bidder. B. If the Contract Documents are returned in good condition by a non-bidder, 50% of the plan deposit shall be returned. C. No refund shall be made in any case for Plans and Specifications not in good condition. INSURANCE A. No Contractor shall commence work under this contract until he has obtained all the insurance required hereinafter issued by a company duly authorized to do business in the State of New York and which has a Best's rating and financial size of at least A-, X, and such insurance has been approved by the Owner. The Contractor shall not allow any subcontractor to commence work on his subcontract until all similar insurance required of the subcontractor has been obtained and approved. Approval of the insurance by the Owner shall not relieve or decrease the liability of each contractor. CLAIMS MADE INSURANCE SHALL NOT BE ACCEPTABLE. B. Worker's Compensation and other Mandated Insurance. Each Contractor shall take out and maintain during the life of this contract the statutory Worker's Compensation and Employer's Liability Insurance, and all other insurance required by law, for all of his employees engaged in work under this contract, and in case any such work is sublet, the Contractor shall require the subcontractor to provide all similar insurance. Policy or policies covering the obligations of the Contractor in accordance with the provisions of any applicable Workmen's Compensation or Disability Benefits Law, including for the State of New York, Chapter 41, Laws of 1914, as amended, known as the Workmen's Compensation Law, and amendments thereto, and Chapter 600 of the Laws of 1949, as amended, known as the Disability Benefits Law, and this Agreement shall be void and of no effect unless the Contractor procures such policy or policies and maintains the same in force during the term of his Contract. C. Bodily Injury and Property Damage Liability Insurance. Each Contractor shall take out and maintain during the life of the contract a Comprehensive General Liability Insurance policy for Bodily Injury, including accidental death, and Property Damage, as shall protect him and any subcontractor performing work covered by this contract from claims for damages which may arise from operations under this contract, whether such operations be by himself, or by any subcontractor or by anyone directly or indirectly employed by either of them. The liability policy should include a waiver of subrogation in favor of the City. The hazards insured against shall be as checked below: X Premises-Operations X Products/Completed Operations X Contractual Insurance X Broad Form Property Damage X Independent Contractors X Personal Injury X Automobile Liability, Including Owned, Hired, & Non-Owned Automobiles X Explosion & Collapse X Underground X Pollution _ Asbestos The contractor shall maintain Commercial General Liability Insurance providing both bodily injury (including death) and property damage insurance in a limit not less than Two Million Dollars ($2,000,000) per occurrence. For contracts involving asbestos, the policy shall be endorsed to provide coverage for the City of Syracuse for the asbestos removal, treatment, or abatement activities which are the subject of this bid or in case the Contractor subcontracts any such asbestos removal, treatment, or abatement activities, the Contractor shall require the Subcontractor to provide an insurance policy which shall be endorsed to provide coverage for the City of Syracuse for the asbestos removal, treatment, or abatement activities which are subject of this bid. The City of Syracuse shall be named as additional insured on a primary and non-contributory basis on the certificate of insurance. Claims made insurance does not meet this requirement. D. Owner's & Contractor’s Protective Liability. Each Contractor, at his own cost and expense, shall secure an Owner's & Contractor’s Protective (OCP) Liability Insurance Policy, acceptable to the Owner, designating the Owner as the named insured, with respect to liability arising out of operations performed by the Contractor, any Subcontractor or supervisory acts and omissions of the Owner with respect to such operations. The insurance shall be maintained in full force during the life of this Contract. The limits of this insurance shall be in an amount not less than Two Million dollars per occurrence. INSURANCE CERTIFICATES AND POLICIES The Certificate of Contractor's General Liability Insurance is to be filed with the Owner through this office. This certificate of Insurance shall contain the following "IT IS UNDERSTOOD THAT THE __________________________ INSURANCE COMPANY WILL NOTIFY THE DIRECTOR OF THE OFFICE OF MANAGEMENT & BUDGET, DIVISION OF PURCHASE OF THE CITY OF SYRACUSE, NEW YORK, 213 CITY HALL, SYRACUSE, NEW YORK, AND THE ENGINEER BY REGISTERED MAIL THIRTY (30) DAYS PRIOR TO ANY CHANGES OR CANCELLATION OF THE POLICY." A copy of the Owner's Protective Liability Insurance Policy MUST be submitted to the Director of the Office of Management & Budget, Division of Purchase within ten (10) days after Notice of Award. The Certificate of Owner's Protective Insurance alone is not sufficient. BID MISTAKES AND ERRORS When a bidder claims to have made a mistake or error in his bid, such shall be called to the attention of the Director of the Office of Management & Budget, Division of Purchase by delivering to the Director of the Office of Management & Budget, Division of Purchase a written notice setting forth the nature of the mistake or error accompanied by documentary evidence or other proof of such mistake or error within seventy-two (72) hours after the opening of the bid or prior to award, whichever is shorter; otherwise the bid may not be withdrawn. A bidder's failure to deliver either said notice or documentary evidence or proof within seventy-two (72) hours of bid opening or prior to award, whichever is shorter, shall constitute a waiver of the bidder's right to claim an error or mistake. If such notice and documentary evidence or proof have been provided within seventy-two hours of bid opening or prior to award, whichever is shorter, the Director of the Office of Management & Budget, Division of Purchase will determine if an error or mistake has been made and whether such is excusable. If the Director of the Office of Management & Budget, Division of Purchase shall determine that an excusable error or mistake has been made, he may permit the bid to be withdrawn. The determination of the Director of the Office of Management & Budget, Division of Purchase as to whether a bidder made an excusable error or mistake shall be conclusive upon the bidder, his surety, and all who claim rights under the bidder. ELIGIBILITY The City of Syracuse reserves the right to disqualify a bidder who is delinquent on property taxes or liable to the City pursuant to any judgement or order, or otherwise indebted to the City. SYRACUSE FAIR EMPLOYMENT AND LICENSURE ORDINANCE V1 Effective March 22, 2015 this Contract is subject to General Ordinance No. 45-2014 entitled the Fair Employment and Licensure Ordinance of the City Of Syracuse. This Ordinance requires that all City Contractors shall not include any question about a job applicant’s prior criminal history on the job application and shall defer making any criminal history inquiry about a job applicant’s past criminal convictions until after a conditional offer of employment is made. The City shall have the authority to suspend and terminate the contract for violations of the Fair Employment and Licensure Ordinance. A complete copy of the ordinance is available at the City of Syracuse website (www.syrgov.net). SYRACUSE RESIDENT EMPLOYMENT ORDINANCE V2 Effective December 15, 2016, this Contract may be subject to General Ordinance No. 9-2016 entitled the Syracuse Resident Employment Ordinance. This Ordinance requires that City Construction contracts, Public Works contracts or Service contracts with a value of $100,000 or more employ City of Syracuse residents. Compliance requires that one or more City residents perform twenty percent (20%) of total in-state Work Force Hours. Potential bidders will be informed in detail as to compliance with this ordinance at pre-bid meetings. Small businesses that employ the equivalent of ten or fewer full-time employees are exempt. The City shall have the authority to suspend and terminate the contract for violations of the Syracuse Resident Employment Ordinance. A complete copy of the ordinance is available at the City of Syracuse website (www.syr.gov). SYRACUSE MINORITY AND BUSINESS ENTERPRISE PROGRAM V2 Please be advised

Published attachments
Addenda and notices
Public questions and answers
  • Please confirm contractors are only responsible for electrical and plumbing permit. Building permit is either not required or will be handled by the pre-manufactured building supplier.

    This project will require 3 permits with the City of Syracuse Permit Office - Site Permit, Ball Ave ROW - road cut permit, Electrical Permit. These are zero cost permits that can be procured digitally. The plumbing permit will be pulled though the Onondaga County WEP Plumbing Control Office. The Contractor is not responsible for the concession building permit

  • Detail 2 / E-501 has splash pad bonding listed as 'by others'. The vortex drawings also show bonding as 'by others' on E-001. Detail 1 / L-302, has another detail showing bonding solid wire, conduit, cable 2 wires, etc. is to be supplied by the installer. Who is the installer / others for the splash pad bonding?

    The bonding and all electrical work relating to the Vortex system will be performed by the successful bidder's licensed electrical contractor. There is no work to be self-performed by the City of Syracuse on this project.

  • If the item is listed 'By Others' in the Vortex drawings, is that to be completed by the contractor the City is hiring?

    In the Vortex drawings - all references to "by others" means that the work will not be performed by Vortex or is relating to an element of the manufacturer's supplied assemblies that will be field assembled or installed by the qualified contractor selected by the City of Syracuse.

  • Who is responsible for the backflow preventer for the splash pad. PE-001 has it listed as 'by others' and 8.2 on the cover sheet has it listed as 'Provided By Vortex'.

    Awarded contractor is responsible for the back flow prevention device installation

  • On P-102 General Note 4 states all final connections will be made by the CXT Installers. With exception of the light fixture L1 and 20A-1P GFCI breaker, conduit, and wire to the splash pad. Confirm the rest of the electrical work within the concession building by the CXT Installers. Who is responsible for making the power connections from the service box to the concession building panel?

    Awarded contractor will make final service connections to the building. All internal and branch wiring is completed by the building manufacturer and is read for primary energization once the building is set.

  • What are the invert elevation and rim elevation for the manhole proposed on detail 4 of L-102?

    San MH Rim elevation is 198.64 and the invert is 195.64

  • Since the building manufacturer must leave out several small floor areas for the MEP connections, who will be responsible to infill the concrete once the connections are made? Will the supplier return to infill these? If not, please provide the quantity and sizes of openings we should plan to infill after connections are made?

    Any MEP access openings created by the building manufacturer will be in filled by others and are not part of this bid.

  • What is the intended crane pad and access location for the building installation? The existing access road is not wide enough per the requirements set by LB Foster. Is the plan to build east of the existing access road? Or will they need to access via Hazelwood Ave? Either option will incur costs related to access and will also impact the sequencing of activities.

    The trailer and building width for the building delivery is 11'-6" which will be accessible from Ball Ave and its stone pillars measuring over 14' in distance. CXT are responsible for their crane and delivery considerations, and are not part of the general construction contract

  • On the site plan keyed note 4, please clarify the provisions which should be part of base bid and what portion should be included in alternate as the statement is conflicting each other. The area is already covered as Add Alternate and in base bid they are asking for circuits, breakers and boxes where as if alternate is not accepted then there should be just conduit. Please clarify.

    Please note this clarification in the bid table on Section 00300 - Pricing Table Alternates GAB-1 through GAB-2. There are no utility considerations for the splash pad in the base bid.