The City of Murfreesboro is accepting sealed bids for Bradley Academy Museum Exterior Renovations , ITB-08-2027 to be received no later than Tuesday, November 17, 2026 , 2:00 pm CST. Bid Form Please refer to the attached bid form, located in the "Attachments" section of this ITB. Download, complete, and upload here in PDF format. Scope of Work Important Instructions for Electronic Submittal The City is accepting electronic bid submissions. Bidders shall create a FREE account with OpenGov by signing up at https://procurement.opengov.com/signup. Once you have completed account registration, browse back to this page, click on "Submit Response", and follow the instructions to submit the electronic bid. Introduction Summary Background Contact Information Timeline Forms to Complete Attachments

Published attachments
Addenda and notices
Public questions and answers
  • Has anyone (or the owner) performed a lead-based paint and asbestos survey of the building components affected by this work, including the window sashes, stops, glazing compound, perimeter caulk, wood trim, cornice, and entry doors? If so, please issue the survey to bidders by addendum. If not, please confirm whether bidders should assume lead-containing paint is present on all painted wood surfaces in the scope of work. Reference spec: Ref: 09 91 13 1.4.B; 01 41 00 1.6

    No survey is available. Bidders shall assume existing painted surfaces contain lead-based paint, and contractor is to include EPA Lead-Safe removal practices, OSHA Lead in Construction Standards, and Secretary of Interior's Standards for Rehabilitation.

  • Spec 09 91 13 states that the painting section is not an abatement design. If asbestos-containing material is found in the window glazing compound, perimeter caulk, or other materials to be removed, will abatement be performed by the Owner under a separate contract, or added to this contract by change order? Please confirm that asbestos abatement is excluded from the Base Bid.

    Third party testing of existing plaster for asbestos materials will be added to Contractor's scope by addendum. If abatement is determined to be required, Owner will pay for it via contingency at Unit Prices (which will also be added by addendum).

  • Within the specification section 013213, it provides the contract time at execution of the agreement. The bid form says the Notice to Proceed will not be issued until bonds, insurance, the subcontractor list, the schedule of values, and builder's risk have been delivered and reviewed. Will ownership consider starting the 112-day contract time on the notice to proceed date instead of the execution date?

    Construction start date will be revised by addendum to be the Notice to Proceed date. Addendum will be issued shortly.

  • Drawing Index lists sheets A1.1 through A4.2 but does not list A3.2 Roof Details, which is included in the drawing set. Please confirm the complete list of sheets in the bid documents, so bidders know we have a full set.

    Sheet A3.2 should have been included in the index on the drawing cover sheet. This will be corrected by addendum.

  • I have a question about the cornice area and the gutters. I didn't see a scope breakdown for these items in the general notes, but the plans seem to call for new gutters and repairs or replacement of the cornice area. Can you clarify that for me?

    A careful review of the plans shows that the drawings do not call for a gutter at the main building cornice. Please review detail 1/A3.2. The small roof at the front entry vestibule has an integral gutter and downspout that are to be replaced - refer to detail 3/A3.2 for this condition.

  • The roof details direct the Contractor to inspect the existing sheathing for deterioration and notify the Architect. Will sheathing replacement found during this inspection be paid by change order or a unit price? Or should a quantity of sheathing replacement be included in the Base Bid? If so, please state the quantity

    A Unit Price for sheathing replacement will be added by addendum.

  • Reference: Specification Section 09 91 13, Paragraph 1.4.B; Drawings A1.1, A2.1, and A4.1. The contract documents require removal and stripping of existing paint from historic wood window trim, sills, casing, and cornices. Section 09 91 13, Paragraph 1.4.B addresses procedures where lead is present; however, we could not locate any existing lead-based paint testing reports. Please confirm whether the existing painted surfaces have been tested for lead-based paint and provide any available reports. If lead-based paint is present, please clarify whether the contractor is to include lead-safe removal, containment, and disposal in the base bid, or whether this work will be addressed separately.

    No survey is available. Bidders shall assume existing painted surfaces contain lead-based paint and contractor is to include EPA Lead-Safe removal practices, OSHA Lead in Construction Standards, and Secretary of the Interior's Standards for Rehabilitation.

  • Please confirm whether interior painting at plaster repairs is limited to the repaired areas, or extends to the full wall surface to the nearest corner or natural break so the color and sheen match. If full walls are intended, please identify the rooms and wall surfaces to be painted.

    A separate Unit Price will be added by addendum for painting of existing surfaces beyond area of plaster repair.

  • Specification section 084113 requires safety glazing "where required by applicable codes and indicated on Drawings," but no locations are indicated and the sill heights are not dimensioned. Please identify which window units, if any, require tempered or laminated safety glazing, or give the existing sill heights above the finished floor for the Type A and Type B openings. Please advise. This is a large portion of the SOW.

    No locations are indicated on drawings as no locations of new windows require safety glazing.

  • The TOC lists the aluminum windows section as 085113. The section is bound and footed as 084113, with an October 22, 2022 date in its footer. Please confirm that the bound section 084113 dated with this bid set is the governing aluminum window specification.

    This was a typo and will be corrected by addendum. The specification section entitled "Aluminum Windows" governs the project for aluminum windows regardless of the typo.

  • Generally speaking, for basis of design custom aluminum windows, we see it rakes typically need 8–10 weeks of fabrication after shop drawing approval. With field measuring, a 14-day est shop drawing submittal, and Architect review, that leaves little time to install the windows and do the plaster and painting that follow them within our allotted 112 calendar days. Will the Owner consider extending Substantial Completion to 150 calendar days? If not, what Architect review period should bidders assume for window shop drawings?

    Contract time will be extended by addendum to 130 days.

  • Spec 011100 includes repair and replacement of deteriorated wood framing and trim "as required," but the drawings give no quantity. Spec 09913 also requires the Contractor to report decay that needs consolidation or dutchman repairs. To put all bidders on the same basis, will the Owner please set a quantity allowance or a unit price for wood framing and trim repair beyond minor filling? If not, please define the extent of wood repair to include in the Base Bid. Thank you

    No removal of deteriorated wood framing and trim is expected with this project and should not be included in bid price. Should deteriorated wood requiring replace be encountered as work is uncovered, replacement will be handled under the Owner's Contingency Allowance.

  • The roofing, sealants, concrete, and exterior painting all have minimum temperature limits, and much of the Contract Time will fall in December through March. Will days when work cannot proceed because air or surface temperatures are below the manufacturers' published limits be considered for time extension? Or should bidders treat all such days as normal weather already included in the Contract Time? (Reference: Specification 013213 section 1.6 and 079200 section 3.1.B; 099113 section 1.5.B)

    Contractor should treat them as normal weather included in contract time. Contract time is being revised to 130 days by addendum.

  • (Reference: sheet A4.1, elevation keyed note 2; sheet A3.2; specification 099113 section 1.1) Keyed Note 2 on A4.1 says to "remove existing paint from existing painted surfaces of cornice, prime and paint." Please clarify: (a) does this mean stripping to bare wood over the whole cornice, or removing loose and failing paint down to a sound layer? (b) Do the requirements of Spec 09 91 13 (hand methods only, test areas, moisture limits, two-year installer warranty) apply to the cornice? That section's summary covers only the woodwork at window openings.

    Specifications will be added for the cornice paint and preparation by Addendum.

  • Drawing sheet A 4.2 calls for PPG PP515 primer with two coats of PPG PP649 at new exterior wood, and PPG PP1129 primer with two coats of PPG PP1139 at new interior wood. The specification section 099113 specifies SEAL GRIP 17-941NF / PERMANIZER 769 for exterior wood and SEAL GRIP GRIPPER 17-921XI / BREAK-THROUGH! V52-410 for interior wood. Please advis which coating systems govern at the existing entry doors, frame, sidelights, and transom?

    Exterior wood paint specification applies to the exterior painting of the door and associated framing. Painting requirements shown on Drawing A4.2 will be removed via addendum.

  • Specification 084113 in section 2.1 names the basis of design as the Winco 1150S Series "2-inch Heavy Commercial Thermally Improved Window." In part 2.3 of same section, names it as the Winco 1150S Series "4-inch Heavy Commercial Thermally Improved Window." The 2.3.D.4 calls for a 2-inch nominal frame depth while the sheet A4.2 labels the units "2″ ALUM. WINDOW UNIT." Please advise if the 2-inch frame depth governs.

    Winco 1150S is a 2 inch system - we will delete reference to 4" via addendum.

  • Rebuilding the main entry stoop will close the main west entrance for a period of time. Please identify the alternate public entrance and accessible route the museum will use during this work. Please also confirm whether ownership will provide signage and notices to the public, or whetherwe should include them.

    This is not the main entrance to the building nor the accessible entrance. The main and accessible entrance is on the South face of the building and will remain as the primary entrance during the rebuild of the front porch. Contractor to place temporary signage on interior and provide temporary barriers on the exterior.

  • Specification sections 014100 lists both the 2018 and 2021 editions of the International Building Code. Please provide which edition the City of Murfreesboro will use for plan review and inspection of this project. Thanks

    2021 IBC will govern - will clarify by Addendum.

  • (Reference: sheet A4.2 - New Door Hardware schedule and Detail 4/A4.2 ) The hardware schedule lists two thresholds: one NGP 457-DKB (opening width + 4″, with returned closed ends) and one NGP 896N-DKB. The detail 4/A4.2 shows a half-saddle threshold plus a bumper latching threshold, with the existing wood threshold to remain. Please advise if both thresholds are to be installed at the single main entry opening as shown in Detail 4.

    Both thresholds are required to be installed as scheduled and detailed on the drawings.

  • Exhibit A section 8 requires a completed-value, all risk builder's risk policy for the "Project (not merely the Work)," and it lets the Owner accept an installation floater instead. Please confirm the Owner will accept an installation floater, or builder's risk written for the value of this contract's Work only, rather than coverage for the full value of the existing museum building and its contents.

    We have consulted our Risk Manager on this; he has stated that this is a reasonable request. However, the COI is not required upon submittal of the bid; this can be be negotiated and addressed upon the project being officially awarded.

  • This contract includes no design or delegated-design services. Will the Owner waive the $1,000,000 professional liability requirement (with two-year tail) in Exhibit A section 4 for the General Contractor? If the requirement stands, please identify the scope of work it is meant to cover.

    See answer to Question #20.

  • Please confirm the following for a contract of this size: (a) the $5,000,000 umbrella is required of the General Contractor only, not of subcontractors; (b) a follow-form umbrella over the required primary policies is acceptable; and (c) a Contractor's Pollution Liability limit of $1,000,000 that includes lead and mold, carried by the General Contractor or by the painting subcontractor who performs the lead-safe work, meets section 5

    a) $1,000,000 will be sufficient and required of prime contractor b) A standard follow-form coverage amount will be acceptable c) The prime contractor is responsible for ensuring coverage is in place and provide such coverage proof to the City Again, as in Questions #20, 21, and 22, this will be addressed upon official award. If in doubt, include cost of insurance coverage in the bid submitted.