Carport Repair - 920 West Capitol Ave

Description

The City of West Sacramento is accepting sealed responses for a small repair to the wood beam spanning the north side of the 20' x 20' carport damaged during a vehicle collision. Access to the exterior of the building is open on all sides and there is an area available in the parking lot that can be used for storing and staging the Contractor’s materials and equipment. to be received no later than Tuesday, December 1, 2026 at 2:00 pm . The bid specifications, including instructions on how to bid, standards for a responsive bid, and project specifications, are attached hereto in Attachments and incorporated herein by reference as if set forth in full Electronic Cost Table Mobilization / Demobilization Building Permit(s) (Fees paid by the City) Demolition Carpentry, Rough and Finish Minor Roofing and Rain Gutter with Downspout Please upload a signed W-9 form Please download the IRS 2024 Form W-9 and upload a completed, signed copy. Acceptable signatures include either a handwritten (wet) signature or a valid electronic signature. Please enter Legal Company Name and related DBA Please state your company name and any related DBA's based on your California Secretary of State Filing. Cost Proposal using Electronic Pricing Table The bidder acknowledges that a Cost Proposal must be completed using the electronic pricing table provided in the City’s e-Procurement Portal and that this information will be kept separate from the rest of the bid response. The bidder further acknowledges that all pricing and related costs will be based solely on the information entered in the electronic pricing table. The City will not be responsible for any errors, omissions, or discrepancies contained in any additional or supplemental pricing documents submitted by the bidder. Response (without Cost Proposal) Please Upload Your Response Here, excluding your Cost Proposal. Statement of Offer Submission of a proposal is an offer to complete the Scope of Work. The offer, including the Cost Proposal rates and budget, must remain valid for at least ninety (90) business days after the Proposal due date. Bid Bond Bid contents, including requisite declarations and forms to be signed and included in the Bid, are included in the Attachments - Bid Docs California Contractors State License Board Please enter your contractor license number for verification. City Contract The Proposer acknowledges and is presumed to have accepted the Contract and be capable of completing the Scope of Work, as well as all reasonably associated managerial tasks, without reservation or qualification pursuant to the Contract. Insurance Requirements The Proposer acknowledges the City's insurance requirements and endorsements as outlined in the Insurance Checklist in Attachments . Any Proposal unable to meet the Insurance Checklist requirements shall be considered nonresponsive and ineligible for Contract award. Project Details Important Instructions for Electronic Submittal The City of West Sacramento is only accepting electronic bid submissions and only through its online bidding platform, OpenGov. Bidders may create a FREE account by signing up at OpenGov.com. Once you have completed account registration, browse back to this page, click on "Submit Response", and follow the instructions to submit the electronic bid. The bid specifications, including instructions on how to bid, standards for a responsive bid, and project specifications, are attached hereto in Attachments and incorporated herein by reference as if set forth in full Project Scope This project is to safely remove and replace a cracked beam ply and return the facility to its pre-loss configuration. The wood beam spanning the north side of the carport was damaged (cracked) during a vehicle collision (See PHOTOS in the Attachments.). Access to the exterior of the building and carport is open on all sides and there is an area available in the parking lot that can be used for storing and staging the Contractor’s materials and equipment. The Contractor will remove the affected exterior wood paneling and trim as needed, and remove the rain gutter and downspout. Temporary shoring will be installed to allow removal and replacement of the north ply of the affected/damaged wood beam. The Contractor will then replace the affected framing connections and exterior finishes in a logical repair sequence returning the facility to its pre-loss configuration using contemporary materials of like kind and quality. Include all minor roof repairs and drip edge replacements as necessary. Replace the rain gutter and down spout. All field measurements to be confirmed by the Contractor. Any existing conduit or electrical will be removed by others prior to Contractor's work. Any painting or staining will be done by others after the Contractors work. The Contractor will pull any Permits. Permit Fees will be paid by the City. Permit Drawings and plan check reviews are the responsibility of the Contractor. Building Permit(s) - The Contractor will pull any Permits. Permit Fees will be paid by the City. Permit Drawings, and Plan Check Reviews are the responsibility of the Contractor. For your permit application please note these requirements: Scope of Work: Clearly note what is being removed, replaced, or reinforced, specifying the exact construction materials and sizes. Site Plan: Show the exact location of the commercial carport on the property, property lines, setbacks, and distances to other buildings or driveways. Structural Plans: Detail the existing and repaired roof framing, posts, beams, bracing, and connection details. Demolition Demolition of wood soffit, trim, rafter outrigger, and fascia Selectively remove 12" wood ply members at built-up wood beam Remove aluminum gutter/downspout Carpentry, Rough and Finish Temporary shoring Replace outrigger and 12” wood ply members at built up wood beam Replace framing connector hardware Replace exterior trim. soffit, trim and fascia Minor Roofing Replace drip edge and repair roofing Replace aluminum gutter/downspout Project Estimate The City anticipates a project value of: $10,000.00 . Introduction Summary Background Contact Information Timeline Terms and Conditions Prevailing Wages Contractor Registration. Pursuant to Labor Code section 1725.5, no contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations (DIR) pursuant to Labor Code section 1725.5. No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the DIR pursuant to Labor Code section 1725.5. The work contemplated by this ITB is subject to compliance monitoring and enforcement by the DIR. Prevailing Wages. Proposers are hereby notified that the DIR has determined the general prevailing rate of wages for each craft, classification, or type of worker needed to execute the work. Copies of the current schedules for California prevailing wages are located in the City’s office, and the contents of those schedules are included herein as if set forth in full. Licensure and Special Certification. Statement of Offer Submission of a proposal is an offer to complete the Scope of Work. The offer, including the Cost Proposal rates and budget, must remain valid for at least ninety (90) business days after the Proposal due date. Project Management Documentation & Administration Virtual Project Manager (VPM) The City anticipates using an online cloud-based project management system to manage, assign, and coordinate specific tasks with the City's selected Contractor within the Scope of Work. By way of this section, the City reserves the right to utilize an online cloud-based project management system. By submitting a bid, bidder acknowledges and agrees that they are prepared to use the system, as may be required by the City. The City's specific system is Virtual Project Manager (VPM). VPM allows for paperless documentation and project administration. For more information on VPM, go to www.virtual-pm.com Submittal Procedures and Construction Progress Documentation for requirements for administering and using VPM. The Contractor shall submit the items associated with this section via Virtual Project Manager (VPM), an online cloud-based project management system, as specified below. Virtual Project Manager (VPM) allows for paperless documentation and project administration. All posted information is available to all personnel involved with the project at any time using the internet. The use of VPM by the Contractor is mandatory. Access to VPM will be provided at no cost to the contractor. In order to utilize VPM, the contractor needs a computer, internet access, a digital camera, and a scanner. For more information, go to www.virtual-pm.com. To Login, from the homepage, select LOGIN and enter the Username and Password that will be provided to you by the agency. The contractor shall use the following features: Daily Logs: Contractor’s daily reports shall be entered electronically via VPM. Change Order Manager: Contractor requests for change order shall be submitted electronically via VPM. Transmittals: Schedules, Pay applications, etc. shall be submitted electronically via VPM. Submittals: Submittals requiring approval shall be submitted electronically via VPM. RFIs: Requests for information (RFIs) shall be submitted electronically via VPM. Technical Submittals Submittal Procedure The Contractor shall utilize the agency’s online cloud-based project management system (Virtual Project Manager) for submittals. Questions and/or Objections It is to the City and Proposer's benefit that questions and objections are brought to the City's attention so it may issue necessary amendments to the ITB and help prevent the opening of defective proposals upon which the City could not award a Contract. Proposer should carefully review this ITB and all attachments for comments, questions, defects, objections, or any other matter requiring clarification or correction (collectively, “Questions”). A Proposer may submit Questions related to this ITB to the City through the City’s e-Procurement Portal at or before: Tuesday, November 17, 2026 at 2:00 pm . Questions shall be considered waived and invalid if not brought to the attention of the City in conformity with this subsection. Questions not submitted through the City's e-Procurement Portal will not be accepted or responded to. Questions submitted after the deadline will not be accepted or responded to. Questions and answers will be posted on the City's e-Procurement Portal and visible to all. Amendment and Cancellation The City reserves the right to amend, cancel, or reissue this bid at any time and at its sole discretion. Any amendment shall be in writing and posted to the City's e-Procurement portal. A potential Proposer is solely responsible for clicking "Follow" on the main page to receive notifications and shall be solely responsible for complying with such notifications. Right of Rejection The City reserves the right, at its sole discretion, to reject any and all Proposals, no matter their level of responsiveness, or to cancel this ITB in its entirety. A Proposer must comply with all of the terms and instruction of this ITB, and all applicable state and local laws and regulations. Any Proposal that does not meet the requirements of this ITB may be considered to be nonresponsive and rejected. A Proposer may not restrict the rights of the City or otherwise qualify a Proposal. If a Proposer does so, the City may determine the Proposal is a nonresponsive counteroffer, and the Proposal may be rejected. The City reserves the right, at its sole discretion, to waive variances in a Proposal, provided such action is in the best interest of the City. Where the City waives variances in a Proposal, such waiver does not modify the ITB requirements or excuse the Proposer from full compliance with the ITB. Notwithstanding any variance, the City may hold any Proposer to strict compliance with the ITB. Prohibition of Respondent Terms and Conditions A Proposer shall not submit their own contract terms and conditions in a Proposal. If a Proposal contains such terms and conditions, the City, at its sole discretion, may reject the Proposal. A Proposer may either submit Questions to gain clarification on a term of the City's standard contract or submit proposed revisions to the City's standard contract in redline as part of the Proposal Transmission Letter, both pursuant to the terms of this ITB. Joint Ventures and Partnering A Proposal from joint ventures or entities partnering for a specific service must be designed to minimize any administrative burden on the City as a result of the participation of multiple entities. Joint proposals must adhere to the following: The Proposal shall respond to each section and subsection of this ITB. The Proposal shall clearly set forth the respective responsibilities and functions that each Principal of the joint venture or partnering entities would perform if awarded a Contract pursuant to this ITB. The Proposal must include a copy of the joint venture or partnering agreement(s) that identify the Principals involved, as well as their rights and responsibilities regarding the Contract pursuant to this ITB. The Proposal Transmittal Letter must be signed by each Principal of the joint venture and include all required information. Proposal of Alternate Services A Proposal for alternate services (i.e., proposals that offer something different from that requested by the ITB) will be considered nonresponsive and rejected. Proposal of Additional Services A Proposal may indicate and offer services in addition to those required by this ITB. These additional services may be added to the Contract, at the sole discretion of the City. The cost for any such additional services shall be mutually agreed upon by the Contractor and the City, and incorporated into the Contract before execution. Severability If any provision of this ITB is declared by a court to be illegal or in conflict with any law, the validity of the remaining terms and provisions shall not be affected, and the rights and obligations of the City and Proposers shall be construed and enforced as if the ITB did not contain the particular provision held to be invalid. Licensure and Special Certification Before executing the Contract pursuant to this ITB, the Contractor must hold all necessary business and professional licenses and certifications to complete the Scope of Work. The City may require any or all Proposers to submit evidence of proper licensure and certifications. Disclosure of Proposal Contents All Proposals and other materials submitted to the City related to this ITB shall become the property of the City. Selection or rejection of a Proposal does not affect this right. All proposal information, including detailed price and cost information, shall be held in confidence during the evaluation and selection process. Upon the completion of the evaluation and selection process, or by rejection of all Proposals, the Proposals shall be open for review by the public to the extent required by the California Public Records Act, Government Code section 7920.000 et seq.. By submitting a Proposal, a Proposer acknowledges and accepts that the contents of the Proposal and associated documents shall become open to public inspection. Portions of a Proposal exempt from public disclosure by law may be protected from public disclosure by the City. A Proposer is required to clearly label such portion of a Proposal "CONFIDENTIAL" and list the grounds for non-disclosure. In doing so, the Proposer thereby agrees to indemnify and defend the City from any action arising from the non-disclosure of the information. The failure to so label any information shall constitute a complete waiver of all claims for damages caused by or related to any release of the information. Conflict of Interest and Restrictions By submitting a Proposal, the Proposer certifies that no amount shall be paid directly or indirectly to an employee or official of the City as wages, compensation, or gifts in exchange for acting as an officer, agent, employee, subcontractor, or consultant to the Proposer in connection with the procurement under this ITB. Proprietary Information A copy of each Proposal shall be retained for official files and will become public record after the award of a contract unless the Proposal, or specific parts of the Proposal, can be shown to be exempt by law. Each Proposer may clearly label any part of a Proposal as "CONFIDENTIAL." In doing so, the Proposer thereby agrees to indemnify and defend the City for withholding the information from public inspection. Failure to label information shall constitute a complete waiver of all claims for damages caused by or related to any release of the information. If a public records request for appropriately-labeled information is received by the City, the City will endeavor to notify the Proposer of the request and delay access to the material until seven (7) working days after the City’s notice. Within that time delay, it will be the duty of the Proposer to act in protection of its labeled information. Failure to so act shall constitute a complete waiver. Bid Submittal Cost Table Attachments Contract Award Opening & Award of Contract Bids will be opened publicly and read aloud at the time and date established in the invitation to Bidders. Bid Summaries may be made available to Bidders after the Bid Date. The City reserves the right to accept or reject any and all Bids for a period of sixty (60) days after the date of opening, and to waive any informality or irregularity in any Bid. No Bid can be withdrawn during that period, except pursuant to Public Contract Code section 5102, et seq. 1751480.1 7203-001 The City reserves the right to reject any or all Bids, including, without limitation, the right to reject any non-conforming, non-responsive, or conditional bids. Before a Bid is considered for award, the City may, in addition to the Experience & Qualifications form included in the Bid documents, require a Bidder to submit a statement of facts and detail as to its business, technical organization and financial resources and equipment available and to be used in performing the work. Additionally, the City may require evidence that the Bidder has performed other work of comparable magnitude and type. The City expressly reserves the right to reject any Bid if it determines that the business and technical organization, equipment, financial and other resources or other experience of the Bidder (including the bidder’s Subcontractors) is not sufficiently qualified for the work Bid upon and, therefore, justifies such rejection. Award of Contract The award of the Contract, if it is awarded, will be to the lowest responsive, responsible Bidder whose Bid complies with the requirements set forth herein. The City reserves the right to award the Contract based on the Base Bid alone or the Base Bid plus any combination of Additive Alternate Bid items, in any order, as determined to be in the best interest of the City. The issuance by the City of a notice to the successful Bidder of the award of the Contract (“Notice of Award”) shall be deemed the Award of Contract. Bid Protests The lack of a prompt procedure to resolve disputes regarding the bidding process would impair the City’s ability to carry out its purpose of constructing this project in a timely manner. Therefore, to the maximum extent authorized by law and notwithstanding any other procedures specified in documents referenced herein, all disputes and/or protests regarding the bidding process shall be subject to the following procedure. In submitting a Bid to the City for this project, the Bidder agrees to comply with and to be bound by this procedure. Any Bid

Published attachments
Addenda and notices
  • Official Notice #1: SIGN IN Sheet for Mandatory Pre-Bid Site Walk on 11/12/2026 · 1

    SCANNED Pre-Bid Walk Sign-In Carport Repair 920 West Cap Ave Flamingo on 11/12/2026

  • Addendum #1 · 1

    Mandatory Pre-Bid Walk Sign-in Sheet posted. Please use the See What Changed link to view all the changes made by this addendum.

  • Addendum #2 · 2

    Be advised that the response to Question #1 has been changed. Builder's risk insurance is required. See all formal responses to all questions in the "Question & Answer" section. Question #1: Tim Gutshall Nov 11 2026 at 7:06 AM TriVel Construction, Inc. Please confirm if a builders risk is required for this size of a job? Revised Response to Question #1: Jim Johnston Nov 16 2026 at 4:18 PM City of West Sacramento Yes. Builder's risk insurance is required per 5.24(h)(3) which states, "Builder’s Risk or Installation Floater “All-Risk” Insurance. Before commencement of the Work, the Contractor shall submit written evidence that it has obtained for the period of the Contract, Builder’s Risk “All-Risk” Completed Value Insurance and/or Inland Marine “All-Risk” Installation Floater Insurance, as may be applicable, upon the entire project which is the subject of this Contract, including completed work and work in progress. The policy or policies of insurance shall name the Contractor, City, and Engineer as insured’s as their respective interests may appear, and shall include an insurer’s waiver of subrogation rights in favor of each. Such insurance may have a deductible clause, but the amount of the deductible shall be subject to the approval of the City, except that the deductible on earthquake coverage may be in accordance with the underwriter’s requirements."

Public questions and answers
  • Please confirm if a builders risk is required for this size of a job?

    Yes. Builder's risk insurance is required per 5.24(h)(3) which states, "Builder’s Risk or Installation Floater “All-Risk” Insurance. Before commencement of the Work, the Contractor shall submit written evidence that it has obtained for the period of the Contract, Builder’s Risk “All-Risk” Completed Value Insurance and/or Inland Marine “All-Risk” Installation Floater Insurance, as may be applicable, upon the entire project which is the subject of this Contract, including completed work and work in progress. The policy or policies of insurance shall name the Contractor, City, and Engineer as insured’s as their respective interests may appear, and shall include an insurer’s waiver of subrogation rights in favor of each. Such insurance may have a deductible clause, but the amount of the deductible shall be subject to the approval of the City, except that the deductible on earthquake coverage may be in accordance with the underwriter’s requirements."

  • Contract is noted as 15 working days from NTP. Please confirm if NTP will be provided after the permit is received. It will take about 2 to 3 months to get drawings & a permit from the City.

    Time waiting for the Permit from the City will not be counted against working days in the Contract.

  • Are there any asbuilts of the existing space so we can see what is currently there and what is to be replaced with?

    No. This structure is old and no drawings are known to exist. Replacement materials are to meet or fit original size and material bringing structure back to a safe and usable condition.

  • Can you post the list of prebid attendees?

    Official Notice #1: SIGN IN Sheet for Mandatory Pre-Bid Site Walk on 11/12/2026, has been uploaded.

  • The contract lists liquidated damages (LDs) at $1,000.00 per day, which appears carried over from larger capital projects. Would the City consider removing the LDs all together or at least reducing this rate (for example, to $250/day) to better reflect the $10,000.00 scale of this carport repair

    Per Item 9 in the “Bid Submittal”, “The Proposer acknowledges and is presumed to have accepted the Contract and be capable of completing the Scope of Work, as well as all reasonably associated managerial tasks, without reservation or qualification pursuant to the Contract.” No, the City will not modify the standard contract for this small repair. Typically, liquidated damages are only assessed for gross negligence, and minor schedule delays can be tolerated.

  • Given the $10,000 estimated project value - if the City will not waive LD’s will the City delete Section 6.06(a)(2) of the General Conditions. This way the City cannot recover both liquidated damages and actual administrative/engineering delay costs.

    See answer to question 5 above.

  • Thank you for confirming that Builder’s Risk insurance is not required. Regarding the bonding requirement, since the estimated construction cost is $10,000.00—and noting that California Civil Code Section 9550 only statutorily requires payment bonds on public works contracts exceeding $25,000—would the City be open to reconsidering a waiver for the 100% Payment and Performance Bonds, as well as the Escrow of Bid Documents requirement, to help keep overall administrative costs down for this smaller repair?

    If a bid comes in under $25,000, the Payment and Performance Bonds would not be required. See also REVISED answer to Question 1 above.