CDBG Funded- Warrior Healing Center HVAC Replacement Project

Description

The City of Sierra Vista is seeking a qualified HVAC contractor to provide all labor, materials, equipment, calculations, permitting, installation, testing, and related services necessary to provide a complete, permanent, code-compliant heating, ventilation, and air-conditioning solution for the Warrior Healing Center. This project is intended to provide reliable and appropriately sized heating and cooling throughout the designated occupied areas of the facility based upon the building’s current configuration, occupancy, and use. This is a performance-based project. The City is not prescribing a specific number, size, type, manufacturer, or configuration of HVAC units. The Contractor shall evaluate existing conditions and determine the appropriate HVAC solution necessary to meet the performance requirements of this Scope of Work. It shall be the Contractor's responsibility to complete the work specified here within and supply any incidental services or accessories necessary to make the work complete and perfect in all respects and ready for operation. Any apparatus, appliance, material, or work not mentioned in the Specifications, or vice versa, or any incidental appurtenances necessary for the system to operate as to the intent of these Specifications, even if not particularly specified, shall be included in the bid price and furnished, delivered, and installed by the Contractor without additional expense to the City of Sierra Vista. Pricing Table Each line needs to reflect the total price of the solution for each Priority area, including Davis Bacon labor, equipment, warranty, materials, any applicable fees, and sales tax. Priority 1 Areas (Yellow) - Includes all inclusive pricing to replace HVAC units in Room Numbers 1, 2, 4, 6, 7, 9, 11-15, 17, 18, 20-22, 42; Front Conference Room; Endeavors; VeloVets & AFA; Legal & Finance Guidance; Quartermaster; Hero PAWS/SBF Office and Training Rooms; WHP Care Team Hotel Office; Primavera Foundation; Computer Lab CLUG; AMVETS MCL; Front Desk; and associated yellow areas. Solution does not need to be like for like, but does need to maintain appropriate temperature control in all areas. A detailed plan for your solution needs to be included in the attached proposal document, including a list of equipment with brand, model numbers, quantities and an explanation of how the equipment will address the area needs. Priority 2 Areas (Orange) - Includes all inclusive pricing to replace HVAC units in Room Numbers 25, 25a, 26-30; WHC Chapel/Meditation Room; Server Room; Live Rising Eagle Stream Network Main Studio; Phantom Lounge Studio; Production/Storage; Maintenance Room; Workshop/Storage. Solution does not need to be like for like, but does need to maintain appropriate temperature control in all areas. A detailed plan for your solution needs to be included in the attached proposal document, including a list of equipment with brand, model numbers, quantities and an explanation of how the equipment will address the area needs. Priority 3 Areas (Blue) - Includes all inclusive pricing to replace HVAC units in Room Numbers 3, 5, 8, 10, 16, 23, 24, 31-41, 43, 44; ARIZONA@WORK; WHP Care Team Hotel Offices; Thistle Rose Healing Energies; Healing with Art; Don Price Military Library; Rec Room; Flutes for Vets/Drum. Solution does not need to be like for like, but does need to maintain appropriate temperature control in all areas. A detailed plan for your solution needs to be included in the attached proposal document, including a list of equipment with brand, model numbers, quantities and an explanation of how the equipment will address the area needs. PROPOSAL RESPONSE Upload your proposal response here according to the guidelines described in this RFP. Scope of Work Project Purpose The City of Sierra Vista is seeking a qualified HVAC contractor to provide all labor, materials, equipment, calculations, permitting, installation, testing, and related services necessary to provide a complete, permanent, code-compliant heating, ventilation, and air-conditioning solution for the Warrior Healing Center. *Please see full Scope of Work in Attachments. This project is intended to provide reliable and appropriately sized heating and cooling throughout the designated occupied areas of the facility based upon the building’s current configuration, occupancy, and use. This is a performance-based project. The City is not prescribing a specific number, size, type, manufacturer, or configuration of HVAC units. The Contractor shall evaluate existing conditions and determine the appropriate HVAC solution necessary to meet the performance requirements of this Scope of Work. Existing Conditions: The Warrior Healing Center has undergone previous building and HVAC improvements. Roof repairs have been completed, and older HVAC equipment that had reached the end of its useful life has been removed. Three HVAC units have subsequently been replaced and are currently in service. Temporary window-mounted air-conditioning units are presently being used in portions of the facility. The building’s use has also changed over time. Certain areas previously accommodated specialized functions and equipment with cooling requirements that may no longer exist. The proposed HVAC system shall therefore be based upon the facility’s current and anticipated use, rather than simply replacing previously removed equipment on a one-for-one basis. The number, location, and capacity of HVAC units that historically served the facility shall not establish the number, location, or capacity of equipment required under this project. The Warrior Healing Center will provide available floor plans and information regarding current HVAC conditions and areas experiencing heating and cooling deficiencies for reference. The Contractor shall independently verify all relevant field conditions. Existing HVAC Equipment Three recently installed HVAC units are currently serving portions of the facility. The Contractor shall evaluate these units and incorporate them into the overall HVAC solution where they are appropriately sized, compatible with the proposed system, and suitable for continued service. The Contractor shall account for the heating and cooling capacity and areas served by these units when determining the additional equipment required to provide a complete HVAC solution for the facility. The City does not intend to replace recently installed equipment unless the Contractor demonstrates that replacement is necessary to achieve the required system performance or code compliance and the City approves such replacement. Temporary window-mounted air-conditioning units are currently being used in portions of the facility. These units shall not be considered part of the permanent HVAC solution. The completed project shall provide permanent HVAC service to the applicable occupied areas currently dependent upon temporary equipment. Temporary units shall be removed upon completion of the project as directed by the City. The City's total available budget for the project is approximately $135,000. Please refer to Attachment B for more details on the Scope of Work. Performance Requirements The completed HVAC system shall provide a permanent, reliable, appropriately sized, and code-compliant means of heating, cooling, and ventilating the designated occupied areas of the Warrior Healing Center. The Contractor shall determine the appropriate number, type, capacity, location, and configuration of HVAC equipment necessary to accomplish this objective. System design and equipment selection shall be based upon: Current building configuration and room uses; Heating and cooling loads; Existing HVAC equipment to remain; Existing ductwork and distribution systems; Applicable ventilation and outside-air requirements; Existing electrical and gas service; Applicable adopted codes; Energy-efficiency requirements; Manufacturer requirements; and Accepted HVAC industry practices. Equipment shall not be sized solely on the number or capacity of previously installed HVAC units. Contractor Evaluation: The Contractor shall evaluate existing conditions necessary to develop the proposed HVAC solution, including, as applicable: Existing HVAC equipment; ductwork and air distribution systems; thermostats and controls; electrical service and connections; gas service and connections; condensate systems; existing equipment curbs and supports; roof penetrations; ventilation and outside-air requirements; building configuration and current room uses; and other conditions that may affect system performance or installation. The Contractor shall be responsible for field-verifying dimensions, equipment locations, capacities, utility requirements, access requirements, and other conditions relevant to the work. Preliminary HVAC System Approach Text As part of its bid, each bidder shall provide a brief Preliminary HVAC System Approach describing the system upon which its lump-sum bid is based. At a minimum, the preliminary approach shall identify: Anticipated number and general type of new HVAC units; Approximate anticipated equipment capacities; Areas or zones anticipated to be served; Existing HVAC equipment proposed to remain in service; General approach to utilizing or modifying existing ductwork; Major anticipated electrical, gas, controls, or other building-system modifications; and Significant assumptions upon which the bid is based. The Preliminary HVAC System Approach is intended to demonstrate the bidder’s understanding of the project and provide the City with information regarding the basis of the bid. It is not intended to constitute the final HVAC design or equipment schedule . Additional Proposal Specifications Final System Sizing and Documentation Following award and prior to ordering equipment, the successful Contractor shall perform the calculations and system evaluation necessary to finalize the HVAC system configuration and equipment selection. The Contractor shall provide required heating and cooling load calculations supporting the proposed equipment capacities and system configuration. Equipment sizing shall be based upon the facility’s current configuration and use and shall account for existing equipment that will remain in service. The Contractor shall prepare and submit required COMcheck documentation, equipment schedules, manufacturer’s specifications, load calculations, and other documentation required to demonstrate compliance with applicable codes and obtain required permits. No new HVAC equipment shall be ordered or installed until required submittals have been reviewed and applicable permits or approvals have been obtained. Contractor Design Responsibility The Contractor’s lump-sum bid shall include all equipment, materials, labor, calculations, permitting, and related work necessary to provide the complete HVAC solution required by this performance specification. Equipment quantities, capacities, and configurations identified in the Preliminary HVAC System Approach may be refined following award based upon required load calculations, code compliance documentation, and permit review. Adjustments to equipment quantities, capacities, or configuration necessary to satisfy the performance requirements of this Scope of Work or obtain required permit approval shall not, by themselves, constitute a basis for additional compensation. Changes resulting from concealed or materially different existing conditions shall be addressed in accordance with the City’s contract provisions. Work Included The Contractor shall provide all work necessary for a complete and operational HVAC system, including, as applicable: HVAC equipment; equipment supports and curbs; ductwork and transitions; supply and return-air modifications; thermostats and controls; electrical connections and disconnects; gas connections; condensate drainage; ventilation components; roof penetrations and flashing; equipment anchoring; crane and lifting services; removal and disposal of equipment replaced as part of the work; removal of temporary window units as directed by the City; testing and balancing; equipment startup; commissioning; permits and inspections; and patching or restoration of areas disturbed by the work. Incidental components reasonably necessary to provide a complete and properly functioning system shall be included whether or not every component is specifically identified in this Scope of Work. Codes and Permits All work shall comply with applicable City-adopted building, mechanical, electrical, energy, plumbing, and fire codes; applicable federal requirements; and manufacturer’s installation instructions. The Contractor shall obtain all permits and inspections required for the work. The Contractor shall provide calculations, plans, specifications, equipment information, COMcheck documentation, and other materials required by the City for permit review. Where applicable law or code requires documents to be prepared or sealed by a registered design professional, the Contractor shall provide such professional services as part of the project. Testing, Balancing, and Startup Upon completion of installation, the Contractor shall test and start all new equipment and verify proper operation. The Contractor shall perform required air balancing and verify that the completed system provides appropriate airflow and temperature control to the areas served. Deficiencies identified during testing, balancing, startup, inspection, or commissioning shall be corrected prior to final acceptance. Warranty and Closeout The Contractor shall provide manufacturer warranties for all new equipment and a contractor warranty covering installation and workmanship. Prior to final acceptance, the Contractor shall provide applicable warranty documentation, equipment information, operating and maintenance information, final equipment schedules, and other required closeout documentation. The Contractor shall provide the facility representative with basic instruction regarding operation of newly installed equipment and controls. Basis of Bid Bidders shall submit a lump-sum price for providing the complete HVAC improvements necessary to satisfy this Scope of Work. The lump-sum price shall include all labor, materials, equipment, calculations, professional services where required, permits, testing, and incidental work necessary to provide the required complete and operational system. Pre-Proposal Conference and Site Visit A pre-bid site visit is mandatory due to the performance-based nature of the project. Proposers shall inspect the facility and become familiar with existing HVAC equipment, building configuration, ductwork, utilities, equipment access, roof conditions, and other reasonably observable conditions affecting the proposed work. Proposers shall be responsible for obtaining sufficient information during the solicitation period to develop their proposed HVAC approach and lump-sum for each priority category. Proposal Response Format Please submit the following information in your proposal, not to exceed to 20 pages (not including vendor questionnaire forms): Cover Letter Qualifications of personnel and Experience on relevant projects Overall HVAC System Approach outlining each Priority area. Specifications (cut sheets) for proposed HVAC replacements and proposed configurations Detailed pricing proposals for each Priority area including all costs for labor, equipment, materials, delivery, mobilization, supplies, tools, sales taxes and any applicable fees to complete the scope of work as described. Any other documentation to support your proposal. Notice The City of Sierra Vista is soliciting proposals from qualified companies to provide CDBG Funded- Warrior Healing Center HVAC Replacement Project . Proposals will be evaluated by the city's evaluation team based on selection criteria included in this RFP. It is anticipated that the highest-ranked proposal will be recommended for award of a contract. Bid documents can be found at https://procurement.opengov.com/portal/sierravistaaz A Non-Mandatory pre-proposal meeting is scheduled on 10:00 am Monday, November 16, 2026 at Warrior Healing Center 1838 Paseo San Luis Sierra Vista, Arizona 85635 All questions related to solicitation shall be submitted in writing through the OpenGov Question/Answer Tab via the City's e-Procurement portal, on or before Monday, December 7, 2026 at 12:00 pm . Please include the section title for each question, if applicable, in order to ensure that questions asked are responded to correctly. All questions submitted and answers provided shall be electronically distributed to all prospective bidders through the City's e-Procurement Portal. Electronic proposals are due by Friday, December 18, 2026 at 10:00 am . Responses must be submitted in electronic form into the City’s eProcurement system. The City may reject any proposal not in compliance with all of the prescribed solicitation procedures and requirements contained herein. The City also reserves the right to cancel the solicitation when cancellation is in the best interest of the City. For questions, contact Melani Armendariz at melani.armendariz@sierravistaaz.gov or (520) 439-2185 . Introduction Summary Background Contact Information Timeline The City anticipates the following general timeline of key events during the proposal evaluations and contract award period: Instructions to Proposers Proposal Format The RFP will describe the proper format for your proposal response. Failure to complete all required forms and signatures, as requested, will result in the RFP being rejected as non-responsive. Unsigned proposals will be considered non-responsive and will be rejected. Erasures, interlineations or other modifications in the proposal must be initialed by a duly authorized proposer representative and must be the same person that signs the proposal. In the case of error in the extension of prices in the proposal, the unit price will govern. No proposal shall be altered, amended or withdrawn after the specified RFP closing date and time. It is the responsibility of the Proposer to examine the entire request for proposal package and seek clarification for any item, service or requirement that may not be clear. It is the responsibility of the Proposer to check the Proposer responses for accuracy before submitting a proposal. The proposal shall be valid for sixty (60) days from the date it is signed. Responding proposers must include all anticipated one-time and ongoing costs, including those that may not be detailed out in the Cost Proposal Summary contained in Exhibit V of this RFP. References Proposer must provide references from customers whom the proposer is currently providing services similar in nature to the services requested herein. The RFP detail will describe how many references will be needed. References should include government agencies, when possible. References should include Company name, company address, contact name, contact's email address and phone number. Upload the list of references when asked to do so. References may be contacted during the evaluation process to confirm the Proposer’s experience, qualifications, customer satisfaction, project management/deliverable approach, and customer service levels provided during and after service implementation. Proposals Must Conform to the Requirements and or Specifications The Proposer shall adhere to the requirements and or specifications stated herein. Any exception taken to these requirements and or specifications shall be so stated on the returned Proposal. Deviations from any of the requirements in the specifications or drawings MAY RESULT IN PROPOSAL REJECTION. The City of Sierra Vista shall hold the Proposer to all specification requirements. There is no time limit on this requirement; deviations discovered after the unit(s) is accepted shall be corrected at n

Published attachments
Addenda and notices
  • Addendum #1 · 1

    In regards to the Pre-Proposal Meeting to be held on Monday, November 16th, this meeting is Non-Mandatory. Attendance is not required in order to submit a proposal.

  • Addendum #2 · 2

    Pre-Proposal Meeting Agenda for 11/16/26 with Sign-In Sheet and Initial Site Visit Photos attached . Bid Submission Date, Question Submission and Question Answer Deadlines have been extended : Bid Submission Date has been extended to 12/18/26 at 10:00AM. Question Submission Deadline has been extended to 12/7/26 at 12:00PM. Question Response Deadline has been extended to 12/11/26 at 5:00PM. Additional Site Visit has been scheduled : Site Visit #2 has been scheduled for 12/2/26 at 2:00PM at Warrior Healing Center, 1838 Paseo San Luis, Sierra Vista.

Public questions and answers
  • The main RFP identifies the November 16 pre-proposal meeting as non-mandatory, while Section 18 of the HVAC Scope of Work states that attendance is mandatory and nonattendance may render a proposal nonresponsive. Please confirm whether attendance is required for proposal eligibility and whether the City will issue an addendum clarifying this requirement.

    See Addendum 1.

  • 45 days: the scope says no equipment can be ordered until submittals and permits are approved, yet all work, including design and permits, must finish within 45 days of the Notice to Proceed. Will the city accept design, permits and procurement first, then 45 days of construction?

    The Notice to Proceed letter will address this. It will allow for immediate design, permitting, and procurement and base the 45 contracted days for construction.

  • Will the city pay monthly progress billings, including equipment stored on site?

    Yes.

  • Please define “occupied critical area” and “respond” for the 24-hour response requirement.

    Per Warrior Healing Center staff: All areas should be considered critical except the back pantry inventory storage area. A response within 24 hours should mean on-site support.

  • The scope requires room-level temperature control for every occupied room. Can adjacent rooms of similar use share a thermostat?

    Per Warrior Healing Center staff: Areas within the same priority section may share a thermostat.

  • Server room: is 24/7 cooling required, and what’s the IT equipment heat load? Do any other rooms need after-hours cooling?

    Per Warrior Healing Center staff: All areas have the same temperature requirements around the clock. Work areas may be occupied at any hour. The server room has no separate cooling requirement for this project and should be treated the same as the adjacent inventory storage areas. We do not have an equipment heat-load figure to provide.

  • What are the expected maximum occupant counts for the training rooms, conference rooms, chapel, rec room, computer lab and studios? We need these to size outside air.

    Per Warrior Healing Center staff: Conference/training rooms: 35 personnel; chapel: 5; recreation room: 25; computer lab: 15; and studios: 8. We understand the training rooms to be the same spaces as the conference rooms.

  • Is there a building fire alarm system, and who is the city’s vendor? Units over 2,000 CFM need duct smoke detectors tied into it.

    Per Warrior Healing Center staff: WHC does not have a building fire alarm system or duct smoke detectors. We ask that the installation meet applicable code requirements.

  • If the Main Conference Room unit turns out to be unsuitable, should we price its replacement as an alternate?

    Per Warrior Healing Center staff: The existing HVAC units are currently suitable and do not require replacement. However, WHC is open to innovative proposals that recommend alternatives.

  • Who holds the roof warranty, when does it expire, and is a specific roofer required?

    Per Warrior Healing Center staff: There is no current roof warranty, and no designated roofing contractor is required. Proposals that provide long-term roof support are preferred but not required by WHC.