CITY OF NORTH MIAMI BEACH PUBLIC LIBRARY RESTROOM REMODEL

Description

The City of North Miami Beach, FL (the "City"), is soliciting sealed responses for CITY OF NORTH MIAMI BEACH PUBLIC LIBRARY RESTROOM REMODEL . Responses are to be submitted via the City's eProcurement Portal via https://procurement.opengov.com/portal/citynmb PRIOR TO 3:00 pm on Thursday, December 3, 2026 . Late responses will not be accepted. Project work includes the the renovation and reconfiguration of the existing public restroom facilities at the North Miami Beach Library, including the addition of two unisex restrooms, renovation of the existing men's and women's restrooms, and all related work as shown in the plans and specifications. SECTION 4.0 SCOPE OF SERVICES PURPOSE AND INTENT The City of North Miami Beach, Florida ("City") is soliciting bids from qualified Contractor(s) for the City of North Miami Beach Public Restroom Remodel (“Project”). The City expects to retain a Contractor that can meet the challenges of a dynamic City, capable of providing reliable and expedient response times to meet project deadlines, staff requests, and outstanding service delivery. In addition, the awarded Contractor shall be able to provide technical assistance and maintain industry best practices throughout the project. All work performed as part of this project shall meet standards and specifications of the City, North Miami Beach Public Works Department, Miami-Dade County and any other regulatory agency that have jurisdiction within the project limits. SCOPE OF SERVICES The Awarded Bidder shall ensure smooth and efficient project planning, staffing, communication updates, and scheduling, through project completion, as required by the scope of services herein contained. Bidders shall include in their offer all required project labor, machinery, rentals, tools, travel, transportation, delivery, materials, equipment, supplies, permits, and related incidentals necessary to meet, in its entirety, the ITB requirements specified herein. The Awarded Bidder shall be responsible for ensuring it is in possession of all required City permits prior to commencement of work, and maintaining permits throughout the contract award, as required. All costs associated with obtaining required permits shall be the responsibility of the Awarded Bidder(s). The Awarded Bidder shall minimize the impact of this project on the general public ensuring that all service interruptions are kept to a minimum and providing temporary services, structures, and facilities as required. The existing service to the Residents and businesses may not be interrupted for more than 4 hours without written permission from the City. All such facilities are considered part of this Contract and shall be provided at no additional cost to the City. The Awarded Bidder shall perform work between the hours 7:00 AM and 4:00 PM Monday through Friday, or as restricted by the local jurisdiction. Work outside these hours or on weekends and holidays is prohibited without permission from the City and local jurisdiction. The Awarded Bidder is to maintain appropriate signage, guards, and flagmen for the purpose of safeguarding the general public while work is ongoing. All work shall be completed in a safe and workmanlike manner every day and the Contractor shall secure the site prior to leaving at the end of each and every day. Specific responsibilities include but are not limited to the following; The Work to be performed under this Contract shall consist of furnishing all equipment, materials, supplies, and manufactured articles and for furnishing all transportation and services, including fuel, power, water, and essential communications, and for the performance of all labor, work, or other operations required for the fulfillment of the Contract in strict accordance with the Contract Documents. The Work shall be complete, and all work, materials, and services not expressly shown or called for in the Contract Documents which may be necessary for the complete and proper construction of the Work in good faith shall be performed, furnished, and installed by the Awarded Bidder as though originally so specified or shown, at no increase in cost to the CITY. The Work to be done under this Contract and in accordance with these Specifications and Drawings outlined in BID SET included hereafter and it consists of furnishing all equipment, superintendence, labor, skill, material, and all other items necessary for this project. The Awarded Bidder shall perform all work required for such construction in accordance with the Contract Documents and subject to the terms and conditions of the Contract, complete and ready for use. The Awarded Bidder is advised that this project will have a direct affect on the citizens living in the immediate vicinity of the work area and as such adequate notification, as approved by the City's Public Information Manager, is required prior to commencing any and all work. TECHNICAL SPECIFICATIONS Bidders are advised to thoroughly review all bid plans, drawings, and project documents to ensure a full understanding of the technical specifications and scope of work. The bid documents contain detailed construction requirements, materials standards, performance criteria, and applicable codes which are critical to the preparation of a responsive and responsible bid. It is the sole responsibility of each bidder to: Examine all drawings and technical specifications prior to submitting a bid Identify any discrepancies, omissions, or unclear items in the plans Submit any questions or requests for clarification by the deadline stated in the bid schedule Ensure that all proposed costs include compliance with the specified technical standards Failure to review the bid plans in detail shall not relieve the selected contractor from meeting all project requirements. SECTION 1.0 INTRODUCTION Bid ITB-2026-089 CITY OF NORTH MIAMI BEACH PUBLIC LIBRARY RESTROOM REMODEL Release Project Date: October 14, 2026 Pre-Bid Conference (Non-Mandatory): October 26, 2026, 11:00am North Miami Beach Public Library ( https://share.google/RPWEEEJWMqV2nf2Pk ) Question Submission Deadline: November 18, 2026, 3:00pm Response Submission Deadline: December 3, 2026, 3:00pm Bid Contact Alicia Hamm Purchasing Specialist Contract Renewal 0 annual renewals Prices Good for 1 year Pre-Bid Conference Monday, October 26, 2026 11:00 am Attendance is Non-Mandatory Location: North Miami Beach Library - 1601 NE 164th St, North Miami Beach, FL 33162 Project Site: https://maps.app.goo.gl/bu8SFWrFxQKuaod79 . ALL ATTENDEES must arrive 10 minutes before time. Bid Comments The City of North Miami Beach, Florida (“City”) is seeking bids to provide CITY OF NORTH MIAMI BEACH PUBLIC LIBRARY RESTROOM REMODEL . It will be the sole responsibility of the bidder to ensure that bid is submitted prior to the bid opening date and time listed. PAPER BID SUBMITTALS WILL NOT BE ACCEPTED. BIDS MUST BE SUBMITTED ELECTRONICALLY VIA https://procurement.opengov.com/portal/citynmb . SITE VISIT : There will be an official scheduled site visit to review the City’s expectations for this project and to discuss the overview of scope. Attendance to the site visit is optional. However, no bidder shall be allowed to visit the site at an alternative date & time. It will be the sole responsibility of the bidder to be familiar with the scope of the project prior to submitting a Bid. No variation in price or conditions shall be permitted based upon a claim of ignorance. Submission of a Bid will be considered evidence that the Bidder has familiarized themselves with the nature and extent of the work, equipment, materials, and labor required. The entire bid response must be submitted in accordance with all specifications contained in this solicitation. THE SITE VISIT WILL BE HELD ON Monday, October 26, 2026 11:00 am . The City of North Miami Beach reserves the right to waive any informality in any or all bids and to reject any or all bids. For information concerning technical specifications, please utilize the question/answer feature provided by OpenGov at https://procurement.opengov.com/portal/citynmb/projects/317010 . Questions of a material nature must be received prior to the cut-off date specified in the solicitation. Material changes, if any, to the scope of services or bidding procedures, will only be transmitted by written addendum. SECTION 2.0 GENERAL TERMS AND CONDITIONS DEFINITIONS When used in Contract Documents (defined below) or in related documents, the following terms shall have the meanings given below: Addendum: A modification of the Plans, Specifications or other Contract Documents distributed to prospective Bidders prior to the opening of Bids/Proposals. Advertisement for Bids: The public notice inviting the submission of bids for the work. Bid/Proposal Bond: A bond executed by a Bidder/Proposer and its Surety in the attached form guaranteeing that the Bidder/Proposer, if awarded the Contract will execute the same and will timely furnish the required Performance Bond, Payment Bond, and evidence of Insurance. Calendar Day: Every day shown on the calendar. Change Order: A written agreement executed by the City, the Contractor and the Contractor’s Surety, covering modifications to the Contract recommended by the Project Manager and approved by the City Manager and/or City Commission. Contract: The written agreement between the City and the Bidder for performance of the Work in accordance with the requirements of the Contract Documents and for the payment of the agreed consideration. Contract Documents: The Instructions to Bidders, Bid Form, Bid Bond, Contract, Performance Bond, Payment Bond, General Conditions, Special Conditions, and Scope of Work, together with all Addenda. Contract Manager: North Miami Beach’s City Manager or designee or duly authorized representative designated to manage the Contract. Contractor: The individual, firm, partnership, corporation, or joint venture whose bid is accepted and who enters into a Contract with the City of North Miami Beach and who is liable for the acceptable performance of the work and for the payment of all legal debts pertaining to the Work. Contract Date: The date on which the Agreement is effective. Contract Time: The number of days allowed for completion of the work. The Contract Time will be stipulated in the Bid Form, unless extended by a Change Order. All contract time shall be measured in calendar days. City: A political subdivision, Incorporated City within Miami-Dade County of the State of Florida, whose governing body is a City Commission consisting of a Mayor, Vice Mayor and five City Commission members. City Manager: The Manager of the City of North Miami Beach, Florida. Days: Reference made to Days shall mean consecutive calendar days. Deliverables: All documentation and any items of any nature submitted by the Contractor to the City’s Contract Manager for review and approval in writing pursuant to the terms of the Agreement. Key Team Member: Individuals who will be assigned to the Project who play an important role in the design, construction, or management of the Project. Lessee: Any individual, partnership or corporation having a tenant relationship with the City of North Miami Beach. Owner: The term Owner as used in this Contract shall mean the City of North Miami Beach. Owner: The term Owner as used in this Contract shall mean the City of North Miami Beach. Performance Deposit: Certified Bank Check executed by the Contractor, on the attached forms, assuring that the Contractor will, in good faith, perform and guarantee the work in full conformity with the terms of the Contract Documents and will promptly pay all persons sup plying the Contractor with labor, materials, or supplies, used directly or indirectly by the Contractor in the prosecution of the Work. Project: The construction and services required by the Contract Documents, which includes all labor, materials, equipment, and services to be provided by the Contractor to fulfill the Contractor’s obligations. Project Manager: The duly authorized representative designated to manage the Project. Bid: The written offer of a Bidder to perform the work or service. Bid Documents: Bid Guarantee or Bid deposit. The Advertisement for Bid, Instructions to Bidders, Bid Form, Bidder Bond, Contract, Performance Bond, Payment Bond, General Conditions, Special Conditions, and Scope of Work, together with all Addenda. Bid Form: The form on which Bids are submitted. Bidder: Any individual, firm, partnership, or corporation submitting a Bid in accordance with the Instructions to Bidders. Scope of Service: Document which details the work to be performed by the Bidder. Subcontractor or Sub consultant: Any person, entity, firm, or corporation, other than the employees of the Contractor, who furnishes labor and/or materials, in connection with the Work, whether directly or indirectly, on behalf of and/or under the direction of the Contractor and whether or not in privity of Contract with the Contractor. The words “Work”, “Services”, “Program”, or “Project”: All matters and things required to be done by the Bidder in accordance with the provisions of the Contract. The words “Directed”, “Required”, “Permitted”, “Ordered”, “Designated”, “Selected”, “Prescribed”, or words of like import to mean respectively, the direction, requirement, permission, order, designation, selection or prescription of the City's Contract Manager; and similarly the words "approved", acceptable", "satisfactory", "equal", "necessary", or words of like import to mean respectively, approved by, or acceptable or satisfactory to, equal or necessary in the opinion of the City’s Contract Manager. In resolving disputes and in all respects the City Manager’s decision shall be final. VENDOR REGISTRATION INSTRUCTIONS It is the policy of the City to encourage full and open competition among all available qualified vendors. All vendors regularly engaged in the type of work specified in the Solicitation are encouraged to submit Bids. At the time of contract award (including small purchase orders), Bidders must complete a Vendor Application. For information and to apply as a vendor, please visit our website at www.citynmb.com to download an application and submit it to Procurement Management Division, 17011 NE 19 Avenue, Suite 315 North Miami Beach, Florida 33162. To get solicitation document, specifications and updates go to www.citynmb.com . CONE OF SILENCE AND REQUEST FOR ADDITIONAL INFORMATION “Cone of Silence,” as used herein, means a prohibition on any communication regarding a particular Request for Proposal (“RFP”), Request for Qualification (“RFQ”) or Invitation to Bid (“ITB”). Pursuant to Section 2-11.1(t) of the County Code, all solicitations, once advertised and until an award recommendation has been forwarded to the appropriate authority are under the “Cone of Silence”. Any communication or inquiries, except for clarification of process or procedure already contained in the solicitation, are to be made in writing to the attention of the Chief Procurement Officer. Such inquiries or request for information shall be submitted to the Chief Procurement Officer and shall contain the requester’s name, address, and telephone number. The request may also be electronically mailed to bids@citynmb.com or mailed to Procurement Management Department, 17011 NE 19 Avenue, Suite 315, North Miami Beach, Florida 33162. During the Cone of Silence, the following is prohibited: Any communication regarding this solicitation between a potential vendor, service provider, Bidder, lobbyist, or consultant and the City’s professional staff including, but not limited to City Commission, the City Manager and his or her staff. All communication regarding this solicitation should be sent in writing only to the Procurement Management Division at bids@citynmb.com . BIDDERS RESPONSIBILITIES Bidders are required to submit their bids upon the following express conditions: Bidders shall thoroughly examine the drawings, specifications, schedules, instructions, and all other contract documents. Bidders shall make all investigations necessary to thoroughly inform themselves regarding site(s) and facilities for delivery of material and equipment as required by the solicitation conditions. No plea of ignorance, by the Bidder, of conditions that exist or that may hereafter exist as a result of failure or omission on the part of the Bidder to make the necessary examinations and investigations, or failure to fulfill in every detail the requirements of the contract documents, will be accepted as a basis for varying the requirements of the City or the compensation due the Bidder. Bidders are advised that all City contracts are subject to all legal requirements provided for in the City of North Miami Beach Purchasing Code and applicable Miami-Dade County Ordinances, State Statutes and Federal Statutes. SUBMISSION OF BIDS Bids and Addenda thereto shall be submitted electronically via the City’s eProcurement Portal via https://procurement.opengov.com/portal/citynmb by 3:00 pm on Thursday, December 3, 2026 . ADDENDA The Procurement Management Department may issue an addendum in response to any inquiry received, prior to the bid opening, which changes, adds to, or clarifies the terms, provisions, or requirements of the solicitation. The Bidder should not rely on any representation, statement, or explanation, whether written or verbal, other than those made in this solicitation document or in any addenda issued. Where there appears to be a conflict between this solicitation and any addenda, the last addendum issued shall prevail. It is the Bidder’s responsibility to ensure receipt of all addenda and any accompanying documents. Bidder(s) shall acknowledge receipt of any formal Addenda via https://procurement.opengov.com/portal/citynmb . Failure to acknowledge Addenda shall deem the response non-responsive provided, however, that the City may waive this requirement in its best interest. REJECTION OF BID The City reserves the right to reject any or all bids prior to award. Reasonable efforts will be made to either award the contract or reject all bids within one hundred and twenty (120) calendar days after Bids opening date. WITHDRAWAL OF BID Bids may not be withdrawn and shall be deemed enforceable for a period of 120 days after the time set for the Bid opening. Bids may be withdrawn prior to the time set for the Bid opening. Such request must be in writing. The City will permanently retain as liquidated damages the Bid deposit furnished by any Bidder who requests to withdraw a Bid after the Bid opening. LATE BIDS OR MODIFICATIONS Only Bids received as of opening date and time will be considered timely. Bids and modifications received after the time set for the Bid opening will be rejected as late. CONFLICTS WITHIN THE SOLICITATION Where there appears to be a conflict between the General Terms and Conditions, Special Conditions, Scope of Services, Bid Submittal Section, or any addendum issued, the order of precedence shall be as follows: The last addendum issued, the General Terms and Conditions, the Special Conditions, the Scope of Services, and the Bid Submittal Section. CLARIFICATION OR OBJECTION TO BID SPECIFICATIONS If any person contemplating submitting a bid for this contract is in doubt as to the true meaning of the specifications or other bid documents or any part thereof, he/she may submit to the Chief Procurement Officer on or before the date and time stated herein, a request for clarification. All such requests for clarification shall be made in writing and the person submitting the request will be responsible for its prompt delivery. Any interpr

Published attachments
Addenda and notices
  • Addendum #1 · 1

    This addendum serves to remove the paragraph referencing the exclusive invitation to firms that previously responded to RFQ No. 2025-025 - Prequalification of General Contractors for Construction Projects. All references to this language are hereby deleted from the solicitation documents. All other terms, conditions, and requirements of the solicitation remain unchanged.

  • Addendum #2 · 2

    Please use the See What Changed link to view all the changes made by this addendum. Question and Answer deadline and Closing Date extended. Updates made to Sections 3.9. Subcontractors, 3.24. Progress Payments, 5.0 Bid Schedule. Response to Bidders' Queries Bidder's Query. Please confirm the required type, quantity, accessibility requirements, approved location, and responsibilities for temporary public restrooms and the separate construction-worker restroom. Shall all facilities be self-contained and contractor-provided? Confirm whether temporary facilities must remain in place during all phases or only during periods when existing restrooms are unavailable. NMB Response No. Please refer to the temporary location of portable toilets, staging area and dumpster location below. The restroom renovation project consists of one phase only. The temporary public restrooms located outside are intended for use by library patrons during the library’s operating hours. Bidder's Query. Can the City please provide any existing hazardous material or asbestos survey reports for this project? If no prior reports exist, please clarify if the asbestos testing, abatement, monitoring, disposal, and clearance activities included in the base bid? Or alternatively, will these services be handled and funded separately by the City? NMB Response: Please refer to the attached Asbestos Report.

  • Addendum #3 · 3

    Please use the See What Changed link to view all the changes made by this addendum. Bid Submission Deadline extended. Updates made to Section 5.0 Bid Schedule. Bidders are responsible for determining quantities based on the drawings and specifications and include the complete required scope of work in their bids.

Public questions and answers
  • Cannot find how many days for completion after notice of start date?

    Substantial Completion of project shall be in 90 calendar days after Notice to Proceed. Final Completion of project shall be in 30 calendar days after Substantial Completion.

  • Will a bid bond be required?

    Please refer to Section 3.6 Bid Security and Section 3.8 Performance and Payment Bond.

  • Hello, For ITB-2026-089, North Miami Beach Public Library Restroom Remodel, can you please confirm the following: Is a bid bond or bid security required with the bid submission? Will the awarded contractor need to provide a performance and payment bond? Thank you, Naemi DBK Industries

    Please refer to Section 3.6 Bid Security and Section 3.8 Performance and Payment Bond.

  • The progress-payment provision states “ten percent (5%).” Please confirm the applicable retainage percentage.

    Please refer to Addendum No. 2

  • ITB states bid is open to GCs the city approved prior in a 2025 RFQ. Are we still able to bid without having been part of the process? We meet all requirements needed

    Please refer to Addendum No. 1

  • The current bid form requires contractors to provide pricing for numerous individual line items across multiple restroom locations (Rooms 155, 154, 143, and 145), including separate quantities for materials, labor, and associated work. As previously noted, several trades and scope items overlap between restroom locations, making it difficult to accurately allocate costs to each individual line item. Additionally, certain items reflect zero quantities, creating further inconsistencies in the pricing structure. We respectfully request that the City revise the bid form to allow for one lump-sum price per CSI division or major scope of work, rather than requiring individual pricing for each material, activity, and restroom location. For example, the revised bid form could include: Demolition – One lump-sum price Asbestos Remediation – One lump-sum price Thermal Insulation – One lump-sum price Metal Stud Framing – One lump-sum price This format would allow contractors to capture the complete scope of work outlined in the plans and specifications while providing the City with a clear, consistent, and comparable pricing structure.

    Contractor will provide an itemized bid quotation for each restroom, with pricing separated by CSI division to facilitate cost review and evaluation.

  • Are there any modification expected to the fire sprinkler system?

    No fire sprinkler modifications are required under this contract.

  • 1. Is there a budget for this project? If, so please let us know 2.- Is Bid Bond required? 3.- Is P&P Bond required?

    1. The City has not established a final approved construction budget for this project. Bidders should submit their most competitive pricing based on the scope of work and solicitation documents. 2. Please refer to Section 3.6 Bid Security. 3. Please refer to Section 3.8 Performance and Payment Bond.

  • Section 3.9 states that subcontractors may not be utilized for this contract, while Section 2.19 allows subcontracting with the City’s prior written approval. Please clarify whether the prime contractor may subcontract electrical, plumbing, HVAC, and fire alarm work to properly licensed specialty contractors. Also, please confirm whether this solicitation requires one prime contractor to bid the complete renovation or permits separate bids for individual trades, such as electrical work only.

    Please refer to Addendum No. 2

  • Section 3.9 states that subcontractors may not be utilized, although the project includes multiple specialty trades and other provisions contemplate subcontractor participation. Please confirm whether licensed plumbing, electrical, mechanical, structural, and abatement subcontractors are permitted. If not, clarify the intended self-performance requirements and applicable trade licensing obligations.

    Please refer to Addendum No. 2

  • Please confirm the required type, quantity, accessibility requirements, approved location, and responsibilities for temporary public restrooms and the separate construction-worker restroom. Shall all facilities be self-contained and contractor-provided? Confirm whether temporary facilities must remain in place during all phases or only during periods when existing restrooms are unavailable.

    Please refer to Addendum No. 2

  • ITB calls for a bid bond. There is no where on the response to attach the bid bond. Should we just submit it as an additional attachment?

    Please add the bid bond as an additional attachment.

  • Please identify the required construction phases, noise restrictions, any work required after hours or on weekends. Confirm the maximum allowable restroom shutdown duration, and whether the City requires separate turnover of restrooms.

    The contractor shall propose the construction phasing, anticipated restroom closure durations, and turnover sequence for City approval. Contractors shall maintain temporary public restroom service during closures. Base bids on the work hours and noise restrictions in the solicitation documents. Any proposed evening or weekend work is subject to prior City approval.

  • Please provide detail/specs for new Gypsum ceiling. (Framing members, framing spacing, and Gypsum board thickness)

    Contractors shall install Moisture and Mold-Resistant Gypsum Ceiling Board: ASTM C1396, D3273, C1629. 5/8” inch thick, Tapered (long Edges). USG, Georgia-Pacific Gypsum LLC or approved equal. Provide a smooth finish. For ceiling Framing: Install min. 3-5/8”x18ga spaced at 16” o.c. both ways.

  • The Specification sheet asks for Laticrete waterproofing and floors and 6 inches up the wall. Would Redgard be acceptable? And Please confirm if bathroom walls will require waterproofing.

    RedGard is acceptable for the proposed application. The proposed restrooms do not contain shower areas; therefore, full-height wall waterproofing is not required. Provide waterproofing 6 inches at the perimeter wall base only.

  • The drawings call for Temporary Restrooms. During the site visit temporary fencing/wall systems were also mentioned. Please specify what exactly will be required.

    Please refer to Addendum No. 2

  • Please note a discrepancy in the Toilet Accessories Schedule / Legend Schedule provided in the contract documents. The listed manufacturer column and the product model numbers do not align for several scheduled items. Please confirm if we are to proceed based on model numbers.

    The Contractor shall cross-reference the model numbers with the descriptions listed in the Accessory & Fixture Schedule as the Basis of Design. This information shall serve as the reference for preparation of the bid.

  • Please confirm whether the City has established an approved construction budget. If available to disclose, please provide the anticipated construction cost.

    The City has not established a final approved construction budget for this project. Bidders should submit their most competitive pricing based on the scope of work in the solicitation documents.

  • The bid sheet calls out Asbestos Abatement. There is no way to know what will be required until after asbestos testing is performed. Could you please clarify if we are to include this in our bid? Or if it would be addressed as a Change Order after testing is performed

    Please refer to Addendum No. 2

  • Can the City please provide any existing hazardous material or asbestos survey reports for this project? If no prior reports exist, please clarify if the asbestos testing, abatement, monitoring, disposal, and clearance activities included in the base bid? Or alternatively, will these services be handled and funded separately by the City?

    Please refer to Addendum No. 2

  • Please identify the designated contractor staging, material storage, waste-container, loading/unloading, and worker-access areas. Confirm any restrictions on parking, deliveries, pedestrian routes, temporary fencing, and use of adjacent library spaces. Please advise whether the City will provide any staging area or whether an off-site storage and associated handling shall be included in the bid.

    Please refer to Addendum No. 2

  • The documents conflict on stud gauge. Bid Schedule lines 11–12 say 3-5/8" x 16 ga @ 16" o.c. Sheet A501 partition types A–F say 3-5/8" x 18 ga @ 16" o.c. Sheet S101 says 20 ga minimum. Sheet S701 shows 3" x 1-5/8" x 20 ga @ 24" o.c. Q&A #14 says the ceiling is 18 ga. Please confirm the required stud size, gauge and spacing for (a) walls and (b) ceilings.

    Please refer to and follow architecture sheet A501 calling out for 18GA studs 16in O.C. for both walls and ceilings.

Plain text

OpenGov categories

  • 91000 · Building Maintenance, Installation And Repair Services
  • 91200 · Construction Services, General (Incl. Maintenance And Repair Services)
  • 92517 · Civil Engineering
  • 96800 · Public Works And Related Services