City of Santa Cruz Lifeguard Headquarters Repairs

Description

The existing Lifeguard Headquarters facility located at 1 Municipal Wharf, Santa Cruz, CA 95060 requires near-term repairs to protect personnel, maintain operational continuity, and preserve the City’s ability to provide effective marine and public safety services. Introduction Summary Background Contact Information Timeline Attachments Vendor Questionnaire

Published attachments
Addenda and notices
Public questions and answers
  • Can the City confirm whether funding has been secured for both the architectural services and construction phases of this project, or if either phase is contingent upon future funding approval?

    Funding has been secured for both the architectural services and construction phases of this project.

  • Addendum #1 deletes Item 2 (sistered 3x12 caps at Bents 48 and 49), which was the only below-deck work. Task 1.2.b still says the 30% set will be used for USACE, NOAA, USFWS, Coastal Commission and RWQCB permits. Does the City still expect any of those permits for above-deck Items 1, 3 and 6? If so, what does the City expect the architect to provide?

    Tasks 1, 3, and 6 are permitted under the existing SC Wharf Five-Year Maintenance Plan approved by the USACE, Coastal Commission, and RWQCB. If any of those agencies require additional information related to Task 2, the 30% plan set will inform the discussion with those agencies.

  • Item 1 (Replace Stairs): should the design assume full replacement of the stairs, landings and support frame, or should it first evaluate salvaging any part of the stairs and railing?

    The design should assume full replacement of the stairs, stair railings, landings, and support frame.

  • Replacing the top-landing roof beam may require opening the roof. How much reroofing is in scope?

    The Architect should exercise due diligence in determining conditions and requirements associated with the top landing roof beam, and should include any necessary roof-related work in conjunction with the replacement of the top landing roof beam.

  • Item 6 (Cut Exposed Roof Beams): does this cover every exposed rafter tail on the building, or only particular elevations? Is fascia replacement along the cut ends in scope?

    From the Moffatt & Nichol Santa Cruz Wharf Lifeguard Building Inspection memo dated Feb. 16, 2025: "6 - Cut Exposed Roof Beams - The exposed roof beams are at risk of rot due to the end grain being exposed to the weather. Many of the beams on the west side have already rotted. The beams should be cut close to the face of the building and capped with copper or galvanized sheeting.". All exposed roof beams are on the east and west side of the building should be included in Architect's plans. Proceed under the recommendation of Moffatt & Nichol i.e. "The beams should be cut close to the face of the building and capped with copper or galvanized sheeting." No repairs or replacement of the fascia is contemplated under this approach.

  • At the site walk, City staff noted the fire sprinkler riser under the stairs needs replacing. It feeds the sprinkler heads in the roof soffits. Is replacing the riser in the architect's scope? If so, may it be specified as a performance requirement with a deferred submittal designed by the fire sprinkler contractor? Does the City have record drawings of the sprinkler system?

    Replacement of the heavily rusted fire suppression piping directly under the stairs should be included in Architect's scope and can referenced in the 100% plan set as a required deferred submittal designed by a fire sprinkler contractor. There are no record drawings of the sprinkler system.

  • Accessibility: what construction valuation will the Building and Safety Division use for Items 1, 3 and 6 when applying the CBC 11B-202.4 valuation threshold? Is there an existing CASp report for the building?

    It's unknown at the present time what construction value the Building and Safety Division will use. Moffatt & Nichol engineer estimates the following costs for Items 1, 3, 6: 1. Replace Stairs: $40,000 3. Repair Deteriorated Guardrail: $4,500 6. Cut Exposed Roof Beams (16 ea.) $4,800 There is no CASp report for the building.

  • Is there a hazardous materials survey (lead paint, asbestos, treated-timber disposal) for the building? If not, will the City handle hazardous materials separately?

    There is no hazardous materials survey for the building. Architect should include contracting and paying for a hazardous material survey, the results of which should inform Architect's plans for the repairs.

  • Before the 30% set, may the architect do limited destructive investigation at the stair support frame and top-landing roof beam? Or should we assume conditions and resolve them during construction?

    Architect may do limited destructive investigation at the stair support frame and top-landing roof beam. Architect shall coordinate any limited destructive investigation with City's Wharf crew prior to beginning.

  • Will the City share the following with the selected architect: Moffatt & Nichol's field notes, calculations and photos/videos; the pile load capacity reports and side-scan pile survey mentioned at the site walk; and any record drawings of the 1986 additions and the fire sprinkler system?

    All Moffatt & Nichol information related to the above deck work (Items 1, 3, and 6) is available in the Moffatt & Nichol Santa Cruz Wharf Lifeguard Building Inspection memo dated Feb. 16, 2025 included in the RFQ. All available and unofficial drawings of the 1986 additions are available in the RFQ. There are no record drawings of the fire sprinkler system.

  • The schedule has the 30% set due January 29 and the 100% set due February 15. How many working days will the City take to review the 30% set? Also, Section C says the 100% set must be completed by "Feb. 15, 2026." Please confirm this should read February 15, 2027.

    City expects to review the 30% completed plan set and return comments to Architect no later than five working days after City receives the 30% set. As published, the RFQ, Section C "Anticipated Project Schedule", Item 10, "Task 2 100% Plan Set Complete" identifies the completion date for that item as Fe. 15, 2027.

  • Does the city have a construction budget for Items 1, 3 and 6?

    See answer to Question #7 above.

  • Task 5 assumes 5 RFIs, 10 submittals, 4 site visits, 5 change orders and 4 payment requests. If construction runs past the August 30, 2027 Substantial Completion date, or these counts are exceeded, will the extra work be paid as additional services?

    Any extra work by Architect under Task 5 would be handled by a change order to Architect's Professional Services Agreement with City.

  • Who prepares the bid front-end documents (Division 00 and 01, bid forms, prevailing wage provisions): the City or the architect?

    City will prepare and release its Project Bid Package for competitive procurement. Architect's plans and specifications will be part of the Project Bid Package.

  • Will the City retain the special inspection and materials testing agency during construction?

    City does not anticipate the need for special inspections or material testing given the limited conventional scope of repairs.

  • What is the source of the grant funding the project? Does it add requirements to the specifications or bid documents (for example federal contract provisions or reporting)?

    Finding for the project is through a state appropriation. City will ensure compliance with state requirements related to specifications, bid documents, and procurement.

  • Are there page limits, font or tab requirements for the SOQ? May resumes and project sheets go in appendices?

    There are no page or font limits. Response materials should follow the requirements in the RFQ Section E "Organization of RFQ Submittal".

  • Section I lists Norman Daly's phone number as "(831) 420-____". Please provide the full number.

    831-420-5150

  • The City’s Q&A response #5 states that no fascia repair or replacement is contemplated. At the site walk, City staff noted that fascia work may be needed after the beam ends are cut flush and capped. If the Architect finds during design that fascia or trim repair is needed to close out and weatherproof the cut beam ends, should it be included in the 100% plan set and the Architect’s fee?

    The Moffatt & Nichol Santa Cruz Wharf Lifeguard Building Inspection memo dated Feb. 16, 2025 states: "6 - Cut Exposed Roof Beams - The exposed roof beams are at risk of rot due to the end grain being exposed to the weather. Many of the beams on the west side have already rotted. The beams should be cut close to the face of the building and capped with copper or galvanized sheeting.". As currently envisioned these beams will not be cut flush with the face of the building. Accordingly, there will be no need to repair or replace fascia. Architect should assume this will be the case in preparing the plans. If during the course of construction it's determined that some or all of the beams would require them being cut flush with the face of the building, a change order to the construction contract would be executed.

Plain text

OpenGov categories

  • 90600 · Architectural Services, Professional
  • 90607 · Architect Services, Professional
  • 90610 · Buildings - Architectural Design
  • 90638 · General Construction - Architectural
  • 91107 · C.I.P., Architectural/Engineering Services