City of Stuart Floridian Aquifer Production Well FA- 2
Description
The purpose of this bid is to solicit qualified licensed general contractors to submit bids for construction of one (1) Floridan Aquifer production well (FA-2) for the City of Stuart’s Water Treatment Facility located at 1002 SE Palm Beach Road, Stuart, FL 34994. The qualified Bidder shall hold a current and active Florida Water Well Contractor license and a Florida Certified General Contractor (CGC) license. The proposed location of the Floridan well is approximately 1,500 LF west of the water treatment facility. Scope of work includes, but is not limited to drilling, setting of steel and PVC casings, grouting, flow testing, wellhead assembly, acidizing (if necessary), well logging, pump testing, formation water disposal system (including temporary piping, pumps, and settling tanks), well facility disinfection and restoration of well site. Work shall include furnishing all labor, materials, and equipment to complete the work as specified and in accordance with the drawings, specifications, and other contract documents. NOTE: Additive Alternate Bid Items The following work shall be included under additive alternate bid items which the Owner may elect to construct under this contract in the priorities listed. The work under this additive alternate is depicted on the drawings and specified herein: Additive Alternate 1 : Work shall include all mechanical, electrical, structural, civil, instrumentation, etc. to provide a complete and operational wellhead and connection to raw watermain for FA-2 (completed by others). Floridan Aquifer Production Well FA-2 PROJECT BASE BID SCHEDULE MOBILIZATION / DEMOBILIZATION BONDS AND INSURANCE PREPARE SITE FOR DRILLING INCLUDING CLEARING, GRUBBING AND FILL FURNISH AND INSTALL 36-INCH STEEL CASING, INCLUDING GROUT TO 20 FEET BLS DRILL A NOMINAL 36-INCH BOREHOLE FROM 20 FEET TO 190 FEET BLS FURNISH AND INSTALL 30-INCH STEEL CASING, INCLUDING GROUT TO 190 FEET DRILL NOMINAL 12-INCH PILOT HOLE FROM 190 FEET TO 880 FEET GEOPHYSICAL LOGGING (COMPLETE) REAM 12-INCH BOREHOLE TO NOMINAL 28-INCH FROM 190 TO APPROX. 850 FEET FURNISH AND INSTALL 20-INCH STEEL CASING FROM 170 FEET TO 850 FEET CEMENT GROUT 20-INCH STEEL CASING IN PLACE DRILL NOMINAL 12-INCH PILOT HOLE FROM 850 FEET TO 1,700 FEET USING REVERSE AIR METHOD SET UP TO BACK PLUG BOREHOLE BACK PLUG BOREHOLE WITH NEAT CEMENT GROUT FROM 1,700 TO 1,625 FEET REAM 12-INCH BOREHOLE TO NOMINAL 19-INCH USING REVERSE AIR METHOD FROM 850 FEET TO APPROX. 1,625 FEET GRAVEL BACKFILL NOMINAL 19-INCH DIAMETER BOREHOLE FROM 1,625 TO 1,100 FEET FURNISH AND INSTALL 12-INCH SDR17 CERTA-LOK PVC FROM 150 TO 1,100 FEET FURNISH AND INSTALL 16-INCH SDR17 CERTA-LOK PVC FROM 3 TO 150 FEET CEMENT GROUT 12-INCH/16-INCH PVC CASING STRING IN PLACE PERFORM PLUMBNESS & ALIGNMENT TEST CLEAN OUT GRAVEL FROM BOREHOLE 1,100 TO 1,625 FT JETTING AND CLEAN OUT BOREHOLE INSTALL AND REMOVE PUMP DISCHARGE APPARATUS PUMP DEVELOP WELL STEP-RATE PUMPING TEST DISINFECTION AND WATER QUALITY SAMPLING PERFORM COMPLETE VIDEO LOG FORMATION WATER DISPOSAL SYSTEM WELL ACIDIZATION SETUP WELL ACIDIZATION FINAL WELLHEAD SITE RESTORATION ADDITIVE ALTERNATE BID ITEMS ADDITIVE ALTERNATE 1A - FA-2 SITE WORK/CIVIL ADDITIVE ALTERNATE 1B - FA-2 WELLHEAD ADDITIVE ALTERNATE 1C - ELECTRICAL & INSTRUMENTATION COMPONENTS ADDITIVE ALTERNATE 1D - OUTDOOR GENERATOR Scope of Work SCOPE OF WORK The project consists of construction of one (1) Floridan Aquifer production well (FA-2) for the City of Stuart’s Water Treatment Facility located at 1002 SE Palm Beach Road, Stuart, FL 34994. Scope of work includes, but is not limited to drilling, setting of steel and PVC casings, grouting, flow testing, wellhead assembly, acidizing (if necessary), well logging, pump testing, formation water disposal system (including temporary piping and pumps), well facility disinfection and restoration of well site. Work shall include furnishing all labor, materials, and equipment to complete the work as specified and in accordance with the drawings, specifications, and other contract documents. NOTE: Additive Alternate Bid Items The following work shall be included under additive alternate bid items which the Owner may elect to construct under this contract in the priorities listed. The work under this additive alternate is depicted on the drawings and specified herein: Additive Alternate 1 : Work shall include all mechanical, electrical, structural, civil, instrumentation, etc. to provide a complete and operational wellhead and connection to raw watermain for FA-2 (completed by others). This shall be a complete system and not necessarily linked to the following as depicted on the project drawings. The general conditions of the contract also apply to all of these components: Wellhead components including site work, fencing, wellhead, well pump and motor, piping and appurtenances, startup, testing and warranties. Electrical components including FPL service to well, service equipment, meter, ATS, equipment rack, power and control wiring, conduits, grounding, well control panel, outdoor generator, site lighting, field instruments, equipment configuration, startup, testing and warranties. Fiber optic communication improvements to include new fiber optic cable from FA-2 to Reverse Osmosis Water Treatment Plant pull box on site. SITE INSPECTION A. It is the bidder's responsibility to become fully informed as to the nature and extent of the work required and its relation to any other work in the area, including possible interference from other site activities. B. The contractor is to verify to his own satisfaction the figures appearing in these specifications. After award, no extra charge or compensation will be allowed by the City as a result of differences between actual materials and labor, unless by reason of unforeseeable causes beyond his control and without fault or negligence, including, but not restricted to acts of God or neglect of any other contractor. INSPECTION AND DIRECTION The work will be conducted under the general direction of the Utilities & Engineering Director or designee, and is subject to inspection to insure compliance with the terms of the bid. The Utilities & Engineering Director or designee will make final inspection of the work covered by this contract when it is completed and finished in all respect in accordance with specifications and must be approved before payment is made. The contractor will notify the City upon completion of replacement, repair or maintenance and the City agrees to provide inspection of the reported work within two (2) working days following the report of work completion. Any work found to be unsatisfactory by the City shall be reported to the contractor within that same period. The contractor agrees to finish all work to the satisfaction of the City, at no additional cost, prior to receiving payment for such work. BUSINESS OPERATIONS A. Hours of Operation: Unless otherwise directed by the Utilities & Engineering Director; or his designee, the successful Contractor(s) shall insure that the following schedule is adhered to and services as required must be scheduled to insure that all work occurs between the hours of 7:00 AM and 5:00 PM; All work performed outside of hours of operation must be approved in advanced by an authorized representative of the City. B. Inclement Weather Conditions: Upon approval by the Utilities & Engineering Director or designee, the Contractor may cease operations of services during inclement weather conditions. C. Observed Holidays New Year's Day, Martin Luther King Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day & Day After, Christmas Eve & Day. PUBLIC SAFETY AND CONVENIENCE In the Contractor’s use of streets and parking lots for the work to be done under these specifications, he/she shall conform to all Municipal, County, State and federal laws and regulations as applicable. The Contractor shall at all times so conduct his/her work so as to ensure the least possible obstruction to normal pedestrian and vehicular traffic including access to all public and private properties during all stages of work, and inconvenience to the general public and the residents in the vicinity of the work, and to ensure the protection of persons and property, in a manner satisfactory to the Public Works Director or appointed designee. There shall be no obstruction of the travel lanes between the hours of 7:00-9:00 am and 4:00-6:00 pm without approval from the Public Works Director or designee. PROTECTION OF PROPERTY The Contractor shall provide all signs, barricades, and/or flashing lights, and take all necessary precautions to protect buildings and personnel. All work shall be complete in every respect and accomplished in a satisfactory, workmanlike manner. The Contractor shall at all times guard against damage or loss to the property of the City of Stuart, including but not limited to safeguard sidewalks, curbing, road surfaces and motor vehicles on or around all job sites. Damage to public or private property shall be the responsibility of the Contractor and shall be held responsible for replacing or repairing any such loss or damage at the expense of the Contractor. The City of Stuart may withhold payment or make such deductions, as deemed necessary, to ensure reimbursement or replacement for loss or damage to property through negligence of the successful bidder or their agents. START OF WORK AND TIME FOR COMPLETION It is hereby understood and mutually agreed by and between parties hereto that the time of completion is an essential condition of this contract. By submitting a proposal response, successful respondent agrees to start the work within ten (10) days of issuance of Notice to Proceed (NTP). If only Based Bid awarded, all performance of the Contract Work shall be substantially completed within two hundred ten (210) calendar days of the date of issuance of the NTP and final completion shall be achieved thirty (30) calendar days after substantial completion. If Based Bid and Additive Alternative is awarded, all performance of the Contract Work shall be substantially completed within three hundred sixty (360) calendar days of the date of issuance of the NTP and final completion shall be achieved sixty (60) calendar days after substantial completion. Commencement of the Contract Work by the Contractor shall be deemed a waiver of the NTP and shall constitute the date of commencement for the purpose of the completion deadline . Substantial Completion : Substantial completion shall be defined as beneficial use of the Floridan Aquifer production well (FA-2), including functional use of ancillary equipment. The Contractor shall deliver to the Engineer the Record Drawings; A draft copy of the Operations and Maintenance manuals for review; Deliver to the Owner a complete set of all spare parts; The items that affect operational integrity and function of the Project must be capable of continuous use; All permits and other regulatory requirements must be satisfied; and Where required, a Certificate of Occupancy must be issued. Final Completion : The completion of all the Work called for under the Contract Documents, including, but not limited to: Satisfactory operation of all equipment supplied by the CONTRACTOR; Correction of all punch list items to the satisfaction of the CITY; Payment of all trade contractors, subcontractors, and materialmen; Settlement of all claims, if any; Payment and release of all mechanic's, materialmen's, and similar liens; Delivery of all guarantees, equipment operation and maintenance manuals, Record Drawings, required certificates, and all other required approvals and acceptances by any municipality, the CITY itself, the State of Florida or other authorities or agencies having jurisdiction; and removal of all rubbish, tools, scaffolding, and surplus materials and equipment from the Work site. LIQUIDATED DAMAGES The Contractor shall pay to the party of the first part, as damages for non-completion of the work within the time stipulated for its completion, one hundred dollars ($100.00) for each and every day for the first thirty (30) days and five hundred dollars ($500.00) for each and every day thereafter, which may exceed the stipulated time for its completion, is hereby agreed upon, fixed and determined by the parties hereto as liquidated damages that the party of the first part will suffer by reason of such default and not by way of penalty. The party of the first part is hereby authorized to deduct the said sum (as specified above) from the moneys which may be due or become due said Contractor for the work under this contract, or as much thereof as the Owner may, at its own option, deem just and reasonable. EQUIPMENT Equipment to be utilized by the successful bidder to perform, as detailed herein must be approved by the Utilities & Engineering Director; or his designee. The contractor specifically agrees to remove and replace any equipment judged by the City to be poorly operating excessively noisy or dirty or in any other meaningful way disturbing to the public welfare. INSPECTION AND DIRECTION The work will be conducted under the general direction of the Utilities & Engineering Director or designee, and is subject to inspection to insure compliance with the terms of the bid. The Utilities & Engineering Director or designee will make final inspection of the work covered by this contract when it is completed and finished in all respect in accordance with specifications and must be approved before payment is made. The contractor will notify the City upon completion of replacement, repair or maintenance and the City agrees to provide inspection of the reported work within two (2) working days following the report of work completion. Any work found to be unsatisfactory by the City shall be reported to the contractor within that same period. The contractor agrees to finish all work to the satisfaction of the City, at no additional cost, prior to receiving payment for such work. INVOICING AND PAYMENT The City requires a firm price for each contract period. Invoices will be checked to confirm compliance with quoted pricing. Failure to hold prices firm through each contract term will be grounds for contract termination. Payment will be made upon completion and acceptance of the work, net 30 days. BUSINESS OPERATIONS A. Hours of Operation: Unless otherwise directed by the Utilities & Engineering Director; or his designee, the successful Contractor(s) shall insure that the following schedule is adhered to and services as required must be scheduled to ensure that all work occurs between the hours of 7:00 AM and 5:00 PM ; Al l work performed outside of hours of operation must be approved in advanced by an authorized representative of the City. B. Inclement Weather Conditions: Upon approval by the Utilities & Engineering Director or designee, the Contractor may cease operations of services during inclement weather conditions. C. Observed Holidays New Year's Day, Martin Luther King Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day & Day After, Christmas Eve & Day. PUBLIC SAFETY AND CONVENIENCE In the Contractor’s use of streets and parking lots for the work to be done under these specifications, he shall conform to all Municipal, County, State and federal laws and regulations as applicable. The Contractor shall at all times so conduct his work so as to ensure the least possible obstruction to normal pedestrian and vehicular traffic including access to all public and private properties during all stages of work, and inconvenience to the general public and the residents in the vicinity of the work, and to ensure the protection of persons and property, in a manner satisfactory to the Utilities & Engineering Director or appointed designee. There shall be no obstruction of the travel lanes between the hours of 7:00-9:00 am and 4:00-6:00 pm without approval from the Public Works Director or designee. TIME OF STARTING WORK The work embraced in this contract shall be actively begun within ten days after notice has been given by the Utilities & Engineering Director or Owner to commence construction. The work shall be carried on regularly and uninterruptedly with sufficient force to ensure its completion within the time specified in the bid. Days when weather conditions prevent the continuance of the work shall not be charged against the contract time. Failure to do so shall render the Contractor liable to the City of Stuart in the amount of one hundred dollars ($100.00) as liquidated damages for each and every day's delay in commencing work. For reasons satisfactory to the Owner, said Owner may, at its own option, waive any claims on the Contractor for damages here referred to. The Contractor shall be responsible for the protection of property in the areas in the adjacent vicinity of the project(s); and for the protection of his own equipment, supplies, materials and work, against any damage resulting from the elements (such as flooding, rainstorms, wind damage, or other acts of God) or vandalism. ACCESSIBILITY STANDARDS In respect to the supply and/or installation of the services and/or items as outlined under this bid/contract; the Bidder/Contractor certifies that the work will be done or the item provided is in compliance with the applicable ADA Standards and/or in compliance with the Florida Accessibility Code for Building Construction. All applicable shop drawings will be submitted for review to ensure that the product or the work as required by this bid is in compliance with the applicable ADA Standards and/or in compliance with the Florida Accessibility Code for Building Construction. SUSPENSION OF WORK DUE TO WEATHER During inclement weather, all work which might be damaged or rendered inferior by such weather conditions shall be suspended. The orders and decisions of the Utilities & Engineering Director as to suspension shall be final and binding. During the suspension of the work for any cause, it must be suitably covered and protected so as to preserve it from injury by the weather or otherwise. If the Engineer shall so direct, the rubbish and surplus material shall be removed. The Contractor shall not be entitled to any extension of time for delays resulting from weather unless the Contractor has requested, in writing, to the City by 11 am the day of the weather delay. If the Utilities & Engineering Director or Owner orders the suspension of work due to inclement weather, the Contractor shall receive an extension of time for the full period when such suspension is in effect until the suspension is lifted by the Utilities & Engineering Director or Owner CONTRACTOR’S UNDERSTANDING The party of the second part hereby admits and agrees that he has carefully read and considered the instructions to bidders herewith, and that he has made his proposal and hereby makes this Contract with full knowledge and acquiescence therein. SUBCONTRACTOR The Contractor shall not sublet the whole or any part of the work without the written consent and approval of the Procurement & Contracting Services Manager. Within ten (10) days after official notification of starting date, the Contractor must submit in writing, to the Procurement Manager, a list of all subcontractors. No work shall be done by any subcontractor until such subcontractor has been officially approved by the Procurement Coordinator. A subcontractor not appearing on original list will not be approved without written request submitted to the Procurement Coordinator and approved by the Owner. In all cases, the Contractor shall give his personal attention to the work of the subcontractors and the subcontractor is liable to be discharged by the Engineer for neglect of duty, incompetence or misconduct. NIGHT WORK OR WEEKEND WORK Night work or weekend work may be required for various areas within the project limits. The CONTRACTOR is re
Published attachments
Addenda and notices
Addendum #1 · 1
FA-1 lithology log
Addendum #2 · 2
ITB 2027-106 City of Stuart Floridian Aquifer Production Well FA-2. Addendum #2 is a revised pdf of Technical Specification Section 01010 that has revised language, but also shows the language being replaced as crossed out. In addition.. please add the Contractor Duties (WORK SEQUENCE, CONTRACTORS RESPONSIBILITIES, CONTRACTOR'S USE OF THE PREMISES, PERMITS REQUIRED) as well.
Addendum #3 · 3
Contractor Duties, Work Sequence, Contractor Responsibilities, Contractor's Use of the Premises, Permits Required
Public questions and answers
Is dual rotary permitted for 36" pit casing and 30" surface casing? Or only the 36" pit casing?
Response: Use of a dual rotary rig is acceptable. All casings shall be installed in accordance with contract specifications.
Are you able to provide estimater water level above existing grade? At what depth is the artesian aquifer expected?
Response: Static water level in artesian aquifer at the site is anticipated to be ~35-40 feet above land surface and the top of the artesian aquifer is expected to be between approximately 800’-900’ BLS.
Are you able to provide well lithology for the 2 existing wells; SAS Well 1 and Well FA-1
Response: FA-1 lithology log will be uploaded as addendum 1. SAS Well 1 lithology not available.
section 02785 mentions HDPE piping or lined ditch and existing stormwater sewer. The discharge plan shows the proposed discharge path in red. Is this all intended to be HDPE piping? or is there existing stormwater infrastruture along the path?
Response: See drawing C-1 for formation water disposal plan and formation water discharge location. The red path shown in Appendix A of the specifications only depicts the flow path.
Please provide the Engineer's estimated budget for this project.
RESPONSE: Floridan Aquifer Production Well FA-2 (Base Bid): 2.5M Floridan Aquifer Production Well FA-2 (Base Bid) including additive alternate bid items ( AA-1A, AA-1B, AA-1C, AA-1D) : 3.6M
Please provide the anticipated NTP date. Does this date have some flexibility?
RESPONSE: A ninety (90) day Administrative NTP or Limited Notice to Proceed (LNTP) will be issued to authorize preliminary, non-physical, or administrative tasks—such as submitting submittals, securing specific permits, drafting project management plans, or mobilizing initial staff—before full physical construction begins. Immediately following the administrative NTP or Limited Notice to Proceed (LNTP) expiration date, a Notice to Proceed (NTP) will be issued by the city that authorizes the contractor to begin work and formally activates the contract performance duration.
Can you clarify that this bid includes the installation of the vertical steel casings? The provided plans on Sheet S-1 identify the vertical 36", 30", and 16" casing pipes as "Exist."?
Response: All casings shall be provided as specified in section 02745 of specifications. Sheet S-1 is a structural sheet for aboveground structural components.
Is a 24/7 work schedule allowable for this project? If not, please state the maximum allowable work schedule. Also, in the event 24 hour work schedule is not allowable, please confirm certain construction activities such as casing installations / critical cementing operations will be allowable in a continuous fashion (including nights/weekends), until complete.
Response: Refer to section 01010.1.06 of specifications relating to time restrictions for performing work. Refer to section 02720.3.01 and section 02740.3.01 regarding time restrictions relating to well construction sequence and well drilling activities. Extended working hours (including nights/weekends) may be requested in writing by the contractor for critical construction activities including but not limited to casing installations and critical cementing operations that must be performed in a continuous fashion. Extended working hours will be reviewed by OWNER and approved on a case-by-case basis.
In lieu of gravel backfilling the open hole, is it allowable to install the Final Certa-Lok PVC casing with an external casing packer to isolate the open hole from cementing operations?
Response: CONTRACTOR may submit an alternative plan for installation of the final Certa-Lok PVC casing such as the use of an external casing packer to isolate the open hole from cementing operations for review and approval by OWNER and ENGINEER. CONTRACTOR shall be prepared to complete construction of the well in accordance with contract documents if OWNER does not approve of CONTRACTOR’S alternative PVC casing installation and grouting plan.