City of Stuart Water Treatment Plant FA- 2 Raw Water Main Project
Description
The City of Stuart Utilities & Engineering Department would like to request an Invitation to Bid (ITB) for the City of Stuart Water Treatment Plant FA-2 Raw Water Main Project. We would like to solicit qualified underground utility & excavation contractors to submit bid proposals for construction of the City of Stuart Water Treatment Plant FA-2 Raw Water Main Project. The project consists of erosion control, installation of 12-inch, 14-inch, 16-inch HDPE raw water main, 2-inch HDPE fiber optic conduit via horizontal direction drill (HDD) and open trench, installation of fiber optic pull boxes, installation of all valves, manual air release valves, appurtenances necessary and pressure testing & chlorinating, asphalt roadway removal and replacement including pavement markings, chain link fence removal and replacement, sod, and miscellaneous restoration. Work shall include furnishing all labor, materials, and equipment, unless specified otherwise, to complete the work as specified and in accordance with the drawings, specifications, and other contract documents. CITY OF STUART WATER TREATMENT PLANT FA-2 RAW WATER MAIN BID SCHEDULE Mobilization/Demobilization (Includes General Conditions and Safety) Maintenance of Traffic Preconstruction Video Construction Survey Record Drawings Pollution / Erosion Control 2" DR-11 IPS HDPE Fiber Optic Conduit (Open Cut) 12" DR-11 DIPS HDPE Raw Water Main (Open Cut) 14" DR-11 DIPS HDPE Raw Water Main (Open Cut) 16" DR-11 DIPS HDPE Raw Water Main (Open Cut) 12" DR-11 DIPS HDPE Raw Water Main & 2" DR-11 IPS HDPE Fiber Optic Conduit (HDD) 16" DR-11 DIPS HDPE Raw Water Main 14" Fused Adapters (HDPE x FLG) 16" Fused Adapters (HDPE x FLG) 14" Butterfly Valve (Lug Style) 16" Butterfly Valve (Lug Style) Manual Air Release Valve 12" 45 deg Fused HDPE Bend 12" 22.5 deg Fused HDPE Bend 12" 11.25 deg Fused HDPE Bend 16" 45 deg Fused HDPE Bend 16" 11.25 deg Fused HDPE Bend 16" x 14" HDPE Tee 16" x 12" HDPE Reducer Sample Point Fill & Flushing Assembly Pressure Testing & Chlorinating New Water Mains Fiber Optic Pull Boxes Mill Existing Asphalt (1" Depth) Asphalt Trench Repair Asphalt Overlay (1" Depth) Sod Restoration Chain Link Fence Repair Miscellaneous Restoration Scope of Work PURPOSE The project consists of erosion control, installation of 12-inch, 14-inch, 16-inch HDPE raw water main, 2-inch HDPE fiber optic conduit via horizontal direction drill (HDD) and open trench, installation of fiber optic pull boxes, installation of all valves, manual air release valves, appurtenances necessary and pressure testing & chlorinating, asphalt roadway removal and replacement including pavement markings, chain link fence removal and replacement, sod, and miscellaneous restoration. Work shall include furnishing all labor, materials, and equipment, unless specified otherwise, to complete the work as specified and in accordance with the drawings, specifications, and other contract documents. START OF WORK AND TIME FOR COMPLETION It is hereby understood and mutually agreed by and between parties hereto that the time of completion is an essential condition of this contract. By submitting a proposal response, successful respondent agrees to start the work within ten (10) days of issuance of Notice to Proceed. All performance of the Contract Work shall be completed within one hundred eighty (180) calendar days from of the date of issuance of the NTP. Commencement of the Contract Work by the Contractor shall be deemed a waiver of the NTP and shall constitute the date of commencement for the purpose of the completion deadline. SITE INSPECTION A. It is the bidder's responsibility to become fully informed as to the nature and extent of the work required and its relation to any other work in the area, including possible interference from other site activities. B. The contractor is to verify to his own satisfaction the figures appearing in these specifications. After award, no extra charge or compensation will be allowed by the City as a result of differences between actual materials and labor, unless by reason of unforeseeable causes beyond his control and without fault or negligence, including, but not restricted to acts of God or neglect of any other contractor. EQUIPMENT Equipment to be utilized by the successful bidder to perform, as detailed herein must be approved by the Utilities & Engineering Director; or his designee. The contractor specifically agrees to remove and replace any equipment judged by the City to be poorly operating excessively noisy or dirty or in any other meaningful way disturbing to the public welfare. INSPECTION AND DIRECTION The work will be conducted under the general direction of the Utilities & Engineering Director or designee, and is subject to inspection to insure compliance with the terms of the bid. The Utilities & Engineering Director or designee will make final inspection of the work covered by this contract when it is completed and finished in all respect in accordance with specifications and must be approved before payment is made. The contractor will notify the City upon completion of replacement, repair or maintenance and the City agrees to provide inspection of the reported work within two (2) working days following the report of work completion. Any work found to be unsatisfactory by the City shall be reported to the contractor within that same period. The contractor agrees to finish all work to the satisfaction of the City, at no additional cost, prior to receiving payment for such work. INVOICING AND PAYMENT The City requires a firm price for each contract period. Invoices will be checked to confirm compliance with quoted pricing. Failure to hold prices firm through each contract term will be grounds for contract termination. Payment will be made upon completion and acceptance of the work, net 30 days. BUSINESS OPERATIONS A. Hours of Operation: Unless otherwise directed by the Utilities & Engineering Director; or his designee, the successful Contractor(s) shall insure that the following schedule is adhered to and services as required must be scheduled to ensure that all work occurs between the hours of 7:00 AM and 5:00 PM; All work performed outside of hours of operation must be approved in advanced by an authorized representative of the City. B. Inclement Weather Conditions: Upon approval by the Utilities & Engineering Director or designee, the Contractor may cease operations of services during inclement weather conditions. C. Observed Holidays New Year's Day, Martin Luther King Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day & Day After, Christmas Eve & Day. PUBLIC SAFETY AND CONVENIENCE In the Contractor’s use of streets and parking lots for the work to be done under these specifications, he/she shall conform to all Municipal, County, State and federal laws and regulations as applicable. The Contractor shall at all times so conduct his/her work so as to ensure the least possible obstruction to normal pedestrian and vehicular traffic including access to all public and private properties during all stages of work, and inconvenience to the general public and the residents in the vicinity of the work, and to ensure the protection of persons and property, in a manner satisfactory to the Utilities & Engineering Director or appointed designee. There shall be no obstruction of the travel lanes between the hours of 7:00-9:00 am and 4:00-6:00 pm without approval from the Utilities & Engineering Director or designee. PROTECTION OF PROPERTY The Contractor shall provide all signs, barricades, and/or flashing lights, and take all necessary precautions to protect buildings and personnel. All work shall be complete in every respect and accomplished in a satisfactory, workmanlike manner. The Contractor shall at all times guard against damage or loss to the property of the City of Stuart, including but not limited to safeguard sidewalks, curbing, road surfaces and motor vehicles on or around all job sites. Damage to public or private property shall be the responsibility of the Contractor and shall be held responsible for replacing or repairing any such loss or damage at the expense of the Contractor. The City of Stuart may withhold payment or make such deductions, as deemed necessary, to ensure reimbursement or replacement for loss or damage to property through negligence of the successful bidder or their agents. TIME OF STARTING WORK The work embraced in this contract shall be actively begun within ten days after notice has been given by the Utilities & Engineering Director or Owner to commence construction. The work shall be carried on regularly and uninterruptedly with sufficient force to ensure its completion within the time specified in the bid. Days when weather conditions prevent the continuance of the work shall not be charged against the contract time. Failure to do so shall render the Contractor liable to the City of Stuart in the amount of one hundred dollars ($100.00) as liquidated damages for each and every day's delay in commencing work. For reasons satisfactory to the Owner, said Owner may, at its own option, waive any claims on the Contractor for damages here referred to. The Contractor shall be responsible for the protection of property in the areas in the adjacent vicinity of the project(s); and for the protection of his own equipment, supplies, materials and work, against any damage resulting from the elements (such as flooding, rainstorms, wind damage, or other acts of God) or vandalism. ACCESSIBILITY STANDARDS In respect to the supply and/or installation of the services and/or items as outlined under this bid/contract; the Bidder/Contractor certifies that the work will be done or the item provided is in compliance with the applicable ADA Standards and/or in compliance with the Florida Accessibility Code for Building Construction. All applicable shop drawings will be submitted for review to ensure that the product or the work as required by this bid is in compliance with the applicable ADA Standards and/or in compliance with the Florida Accessibility Code for Building Construction. CONTRACTOR’S UNDERSTANDING The party of the second part hereby admits and agrees that he has carefully read and considered the instructions to bidders herewith, and that he has made his proposal and hereby makes this Contract with full knowledge and acquiescence therein. SUBCONTRACTOR The Contractor shall not sublet the whole or any part of the work without the written consent and approval of the Procurement & Contracting Services Manager. Within ten (10) days after official notification of starting date, the Contractor must submit in writing, to the Procurement Manager, a list of all subcontractors. No work shall be done by any subcontractor until such subcontractor has been officially approved by the Procurement Coordinator. A subcontractor not appearing on original list will not be approved without written request submitted to the Procurement Coordinator and approved by the Owner. In all cases, the Contractor shall give his personal attention to the work of the subcontractors and the subcontractor is liable to be discharged by the Engineer for neglect of duty, incompetence or misconduct. NIGHT WORK OR WEEKEND WORK Night work or weekend work may be required for various areas within the project limits. The CONTRACTOR is responsible for costs associated with all night work including but not limited to, inspector costs, sound/noise attenuation costs, police or flagmen costs, signage and maintenance of traffic (MOT) costs and all other costs associated with night or weekend work. MAINTENANCE OF TRAFFIC The Contractor is responsible for all maintenance of traffic (MOT) required for work associated with this Contract. All MOT shall be in accordance with City of Stuart and FDOT Standard Plans, latest edition, including revisions. MAINTENANCE BOND As a condition precedent to final payment and acceptance of the work, the Contractor shall furnish the Owner with a Maintenance Bond in an amount equal to one hundred (100%) percent of the first Five Thousand ($5,000.00) Dollars, plus ten (10%) percent of the balance of the final contract price. The bond shall be executed by a surety company authorized to do business in the jurisdiction where the project is located and must be acceptable to the Owner. This security shall be retained for a period of twelve (12) months from the date of completion and acceptance of the improvements, to provide for maintenance of improvements occasioned by faulty engineering, workmanship or materials. CONTRACTOR DUTIES a. Mobilization and demobilization. b. Coordination and scheduling of work. c. Maintenance of Traffic (pedestrian and vehicular) d. Labor, materials, and equipment. e. Tools, construction equipment, and fuel. f. Electric, water and utilities required for construction. g. Freight and sales tax. h. Testing and laboratory services. i. Surveying and field engineering. j. Record Drawings in a format acceptable to the Engineer/Owner. Information will be used by the Engineer for any Permit Certification Requirements. k. Compliance with all the conditions of the permits issued for this project. l. Any other incidental labor, materials, and equipment required to construct the project. m. Maintain an accurate record of communication and coordination with the owner for all scheduling, installation, and all other items. WORK SEQUENCE A. Sequence of work will be discussed with the Owner, Engineer, Contractor, and decided prior to the start of the project. The contractor shall proceed in a manner that is logical for the progression of work. B. Certain areas may be assigned priority to accommodate Owner's needs. C. Work shall only be performed during the authorized construction days/hours as specified by the City of Stuart. CONTRACTORS RESPONSIBILITIES 1. Review and incorporate Owner-reviewed shop drawings, product data, and samples into the construction of the project. 2. Receive and unload products at site or off-site storage yard; inspect for completeness or damage jointly with Owner. 3. Repair or replace items damaged after receipt. 4. Arrange and pay for product delivery to site. 5. Handle, store, and install delivered products. 6. Submit claims for transportation damage and replace damaged, defective, or deficient items. 7. Arrange for manufacturers' warranties, inspections, and service. CONTRACTOR'S USE OF THE PREMISES A. All work shall be within the limits of the property as shown on the plans. Work beyond the limits of this project shall be coordinated closely with the City of Stuart during the construction. B. Contractor shall be responsible for maintenance of traffic when working. C. The contractor shall maintain vehicular and pedestrian access to the driveway entrances to the greatest extent practical. Exceptions will be made on a case by case basis to facilitate the work. D. NOTE: The proposed raw water main will be tied to the existing RO Water Treatment Facility, which is a secure facility. The contractor must coordinate working within the RO Water Treatment Facility and tie-ins with the City staff and maintain the security of the facility in the work area at all times. PERMITS REQUIRED A. Contractor shall prepare, submit, procure and obtain the appropriate permits. B. Contractor shall prepare, submit, procure and obtain the appropriate permits from the City of Stuart including City of Stuart Building Department permits. PRICING PROPOSAL CITY OF STUART WATER TREATMENT PLANT FA-2 RAW WATER MAIN BID SCHEDULE Advertisement CITY OF STUART 2027-107 City of Stuart Water Treatment Plant FA-2 Raw Water Main Project Advertisement The City encourages E-Bidding through OpenGov Procurement at https://procurement.opengov.com/portal/stuartfl . City of Stuart Water Treatment Plant FA-2 Raw Water Main Project will be received by the City of Stuart at the Procurement Office, 301 SE Ocean Blvd., Suite 303, Stuart, Florida, 34994, until Friday, December 18, 2026 at 2:00 pm . A Non-Mandatory pre bid meeting will be held at City of Stuart Public Works Annex conference room at 2:00 pm , Friday, November 13, 2026 . If submitting a hard copy, please submit an original, two (2) copies and one (1) electronic copy (PDF format preferred) on a flash drive. It must be submitted in sealed envelopes/packages addressed to Purchasing Division, City of Stuart, and marked “ 2027-107 , City of Stuart Water Treatment Plant FA-2 Raw Water Main Project . Submittals received after that date and time will not be accepted or considered and will be retained in the Procurement Office unopened A complete bid package can be obtained by contacting the Procurement Office at 772-288-5320, purchasing@ci.stuart.fl.us or from OpenGov Procurement at https://procurement.opengov.com/portal/stuartfl or by calling (800) 711-1712. The City of Stuart is not responsible for the content of any bid package received through any 3rd party bid service or any source. Mail/Overnight/Hand Deliver Submittal Responses to: Procurement Office 301 SE Ocean Blvd., Suite 303 Stuart, Florida 34994 Mark outside of envelope: 2027-107 , City of Stuart Water Treatment Plant FA-2 Raw Water Main Project Published: Friday, November 6, 2026 Introduction Summary Background Contact Information Timeline Instructions to Bidders Submittal Each bidder shall furnish the information required on the bid schedule and each accompanying sheet thereof on which he makes an entry. Offers submitted on any other format are subject to disqualification. The City of Stuart is registered with OpenGov Procurement, you may submit your bid electronically by registering on the City's e-Procurement Portal https://procurement.opengov.com/portal/stuartfl . Otherwise, all bids must be submitted in a sealed envelope plainly marked on the outside with the invitation to bid number, date and time of opening. If not submitting electronically then an original, two (2) copies and one (1) electronic copy (PDF format preferred) on a flash drive must be submitted in sealed envelopes/packages addressed to Purchasing Division, City of Stuart by the due date and time. Submittals received after that date and time will not be accepted or considered and will be retained in the Procurement Office unopened. It is the bidder’s responsibility to assure that Bids are received in the City of Stuart Procurement Office, 301 SE Ocean Blvd., Suite 303 Stuart, Florida 34994, not later than 2:00 pm , on the day and date shown above. Any received after this date and time will not be accepted or considered and will be returned unopened to the bidder. No telegraphic or facsimile offers will be considered. City Representative Bidders are requested not to contact the City Commission, requesting/evaluating Departments or Divisions from the time of the issuance of the solicitation or advertisement until such time as the agency provides notice of an intended decision or until thirty (30) days after opening ‘the bids, whichever is earlier. Any questions from bidders or evaluating Departments or Divisions will be answered through the Procurement Division. Anthony Cooling Budget & Procurement Manager acooling@stuartfl.gov (772) 288-5321 Bid Opening Bids will be opened and read aloud via Microsoft Teams: Microsoft Teams meeting Join: https://teams.microsoft.com/meet/2411183592990821?p=bbsGbYAzbH12p6xeu6 Meeting ID: 241 118 359 299 082 1 Passcode: v4xZ6bZ7 Dial in by phone +1 872-242-8065,,549324210# United States, Chicago Find a local number Phone conference ID: 549 324 210# For organizers: Meeting options | Reset dial-in PIN ________________________________________________________________________________ Withdrawal of Bids Bids may not be withdrawn for a period of 30 days after the public opening date. Protest Any actual or prospective bidder who protests the reasonableness, necessity or competitiveness of the terms and/or conditions of the invitation to
Published attachments
Addenda and notices
Addendum #1 · 1
Guy Davis Park Upcoming Schedule
Public questions and answers
What is the engineer's estimate.
RESPONSE: $732,000.00
Are there any SBEs / DBEs requirements for this project?
EQUAL OPPORTUNITY: The City recognizes fair and open competition as a basic tenet of public procurement and encourages participation by minority and women owned business enterprises. However, there are no requirements.
Is there a bid bond form the city would like us to use or is a standard bond form acceptable
The guarantee would come from a carrier duly licensed and authorized to do business in the State of Florida, and would have the required legal language. A standard notarized bid bond form is acceptable, the City does not have a specific format. The bond shall be in an amount equal to ten percent (10%) of the total amount. If you're submitting electronically in OpenGov, then it would part of the response document.