Description

The County of San Mateo is soliciting proposals from qualified independent certified construction auditing firms with experience in potential misuse of government funds to provide construction auditing services of four San Mateo County Event Center Improvement Projects that were partially funded by the County General Fund. The Projects include San Mateo County Resiliency Center (SMCRC); Cypress Restroom Project; RV Park Project; and CalOES Generator Project The selected firm will review the project management procurement, payment procedures and records, bidding and selection process, construction expenditures, contractor payment applications, invoices, change orders, contract modifications, labor and material costs, and supporting documentation to determine whether amounts billed were properly supportable under the applicable contract, and consistent with approved project records. The purpose of these services is to investigate allegations of financial accountability, identify potential overpayments, mis payments and/or unsupported costs, verify compliance with contractual requirements, and provide findings and opportunities for improvement to the County's financial contributions construction procurement contract administration and financial controls. Scope of Work SCOPE OF SERVICES The selected consultant shall be prepared to provide fast-track construction auditing services as requested by the County and to be completed no later than 60 days. Services may include, but are not limited to, the following: 2.1 Pre-Award and Contract Review Review Procurement and Bidding Records including, but not limited to, Requests for Proposals (RFPs), bid submissions, bid tabulations, evaluation and scoring sheets, procurement documentation, and award resolutions Evaluate bidding procedures and compliance with existing policies related to selection process Review executed construction contracts, amendments, approved change orders, task orders, and other applicable contract documents. 2.2 Payment Application and Invoice Auditing Examine contractor payment applications, invoices, and supporting documentation. Verify that amounts billed are consistent with contract terms, approved pricing, and authorized work. Review the approved project budget, schedule of values, and contract expenditure history. Reconcile contractor billings with Event Center’s payment records and project accounting records. Verify quantities, unit prices, labor charges, equipment costs, materials, subcontractor billings, and other applicable charges. Review documentation supporting stored materials, mobilization, and other advance or progress payments, where permitted by the contract. Identify duplicate billings, mathematical errors, unsupported costs, and potential overpayments. Verify retainage calculations and release requirements. 2.3 Change Orders and Contract Modifications Analyze the validity, scope, pricing methodologies, and authorization chains for field directives and change orders. Review proposed and approved change orders for appropriate authorization and supporting documentation. Evaluate cost breakdowns, labor and equipment rates, material costs, markups, and subcontractor pricing. Compare modifications against the original contract, approved budget, and applicable contract provisions. Identify potential cost duplication, unsupported pricing, or work billed outside the approved scope. 2.4 Compliance and Documentation Review Review compliance with applicable contract requirements and project payment procedures. Examine certified payroll records, prevailing wage documentation, subcontractor payment records, and other labor compliance documentation when included in the audit scope. Review applicable insurance, bonding, and other required documentation as directed by the County. Identify missing, inconsistent, or incomplete records that may affect the validity of project payments. 2.5 Findings and Recommendations Document all findings with supporting evidence and references to applicable contract provisions. Quantify questioned costs, potential overpayments, and other financial discrepancies when reasonably determined. Distinguish confirmed errors from costs requiring further investigation or clarification. Recommend corrective actions and improvements to the County's internal controls and construction payment procedures. 2.6 Required Deliverables The selected consultant shall provide the following deliverables for each assigned audit: Audit Work Plan: Audit objectives, procedures, records required, anticipated schedule, and proposed methodology. Document Request List: Detailed list of contracts, payment records, change orders, payroll records, and other required documentation. Preliminary Findings Report: Summary of potential discrepancies, unsupported costs, compliance concerns, and requests for clarification. Final Construction Audit Report: Audit scope, methodology, records reviewed, findings, supporting evidence, financial impact, and recommended corrective actions. Management Response and Resolution Log: Tracking of County responses, contractor explanations where applicable, corrective actions, and outstanding issues. Supporting Workpapers: Organized documentation sufficient to substantiate findings and support authorized County or independent auditor review. Closing Meeting: Presentation of results to designated County representatives. All reports and work papers shall be delivered electronically in formats approved by the County. The consultant shall comply with applicable County requirements for records retention, confidentiality, and access to audit documentation. Introduction and Schedule The County of San Mateo (the “County” or “SMC”) covers most of the San Francisco Peninsula. The region covers 744 mi and is home to nearly 800,000 residents and 20 incorporated cities. The County provides for the health and welfare of all people within its borders and serves as the local government for the unincorporated areas. Innovation thrives here in industries including bioscience, computer software, green technology, hospitality, financial management, health care, education and transportation. The County prides itself on how that prosperity fosters its commitment to protecting and enhancing the health, safety, welfare and natural resources of the community. Summary Background Contact Information Timeline Submission Requirements Submission Deadline Proposals must be electronically received by 12:00 pm , on Monday, November 2, 2026 , via eProcurement system . Allow sufficient time for the upload to complete by the Due Date and Time. Partial uploads will automatically terminate, and proposals will be rejected. The eProcurement system submission time will be the official submission time. The County will not be responsible for and may not accept proposals that are late due to slow internet connections or for any other failure of the eProcurement system. NOTE: The County does not maintain the eProcurement system and is not liable for site failures or technical problems. To resolve technical issues, contact OpenGov Technical Support by using the real time chat located in the lower right hand corner of the screen, or via email at procurement-support@opengov.com https://procurement.opengov.com/portal/smcgov Pre-submission Registration Organizations or individuals interested in responding to this solicitation must register online with the County of San Mateo at: https://procurement.opengov.com/portal/smcgov It is recommended that organizations complete this registration as soon as possible. The County will not be responsible for and may not accept proposals that are late due to a failure to register in the eProcurement system. Submission via eProcurement Portal Required Documents Please refer to the Technical Proposal section for submittal documents and requirements. Electronic Submissions Include the proposer name and the RFP title and number in each filename. Submit proposals via the eProcurement website, allowing sufficient time for the upload to complete by the Due Date and Time. As noted above, the eProcurement portal submission time will be the official submission time, and partial uploads will automatically terminate, and proposals will be rejected. Contact eProcurement Portal with technical questions regarding this site. Conflicts between Certain Requirements Prior to the submission deadlines and solely relating to a determination of the timeliness of questions, comments, and proposal submissions, information displayed on the eProcurement portal site will take precedence in the event of a discrepancy between that information and the information within the solicitation documents. For all other discrepancies, the information in the solicitation documents will take precedence. Format Documents should be created in the following format: Text should be Times New Roman (12-point minimum font size) and unjustified (i.e., with a ragged-right margin) Pages should have margins of at least one inch on all sides (excluding headers and footers) If the proposal is lengthy, a Table of Contents should be included. PDF format is preferred. Errors in Proposals The County will not be liable for any errors in proposals. Proposals may be rejected as unresponsive if they are late, incomplete, missing pages or information, or cannot be opened for any reason. The County may waive minor irregularities, but such waiver will not modify any remaining RFP requirements. County Rights an General Requirements The County reserves the rights stated in the final solicitation, including the right to reject proposals, request clarifications, amend the solicitation, cancel the procurement, or negotiate with selected firms, as permitted by applicable law and County policy. The selected firm shall comply with applicable County contracting requirements, insurance provisions, confidentiality obligations, records access requirements, and other terms included in the executed agreement. Minimum Qualifications and Technical Proposal Evaluation and Selection Criteria The proposals will be evaluated by a selection committee with relevant expertise. The County intends to evaluate the proposals generally in accordance with the criteria itemized below. Proposers with the highest scoring proposals may be interviewed by the committee to make the final selection. Instructions to Proposers Instructions There will be no pre-proposal conference or site visit for this project. Communications As of the issuance date of this RFP and continuing until it is canceled or an award is made, no proposer or person acting on behalf of a prospective proposer may discuss any matter relating to the RFP with any officer, agent, or employee of the County, other than through eProcurement portal, to the Authorized Contact Person, or as outlined in the evaluation or protest procedures. Proposers (including any agent, owner, employee, board members, or other such affiliates) shall not offer any gift, favor, or other personal benefit to any County officer or employee during the procurement process for this agreement, including during the solicitation period and contract negotiations. Violation of the foregoing prohibitions may result in a proposer being found non-responsible and barred from participating in this or future procurements. Contract Award Award Procedure Contract negotiations are neither an offer nor guarantee that a contract will be executed. A contract award, if any is made, will be to the responsive, responsible proposer offering the overall best value to the County for the services and goods described in this solicitation, or as applicable, for a specific portion of the services and goods described. Any agreement reached will be memorialized in a formal agreement using the attached template, executed by the appropriate authority. Notice of Intent to Award If a decision is made to take steps to enter into an agreement with one or more proposers, the County will post a Notice of Intent to Award or otherwise notify proposers the remaining proposers of their non-selection. Notice may instead be provided by including approval of the agreement as an item on an agenda for a meeting of the Board of Supervisors. Commencement of Performance After all parties have signed the agreement, the County will notify the contractor and performance may proceed. Prior to execution of the agreement by the County, no County employee may authorize work under the agreement. Any work performed prior to the full execution of the Agreement may not be compensated. Levine Act Disclosure The Levine Act (California Government Code Section 84308) imposes certain requirements on parties contracting with the County of San Mateo related to campaign contributions to County “officers,” including elected County officers and candidates seeking elective office, who may participate in making a decision on certain County contracts. Elected County officers in San Mateo County include: the San Mateo County Board of Supervisors, Assessor-County Clerk-Recorder, County Controller, Coroner, District Attorney, Sheriff, and Tax Collector-Treasurer. Generally, under current County policy, approval by the Board of Supervisors is required for any agreement for services above $200,000, and agreements for services below that threshold may be approved by Department heads. If your proposal is selected, you will be required to certify compliance with the Levine Act. As part of this process, you will need to certify and warrant that you have fully complied, and will remain in full compliance, with all applicable requirements of the Levine Act in connection with the Agreement, including making any required disclosures of campaign contributions to County Officers, which includes but may not be limited to elected County Officers. Elected County Officers include members of the San Mateo County Board of Supervisors, as well as the Assessor-County Clerk-Recorder, Controller, Coroner, District Attorney, Sheriff, and Tax Collector-Treasurer. Any campaign contribution required to be disclosed under the Levine Act in connection with this Agreement shall be disclosed on the County of San Mateo Levine Act Disclosure Form, a copy of which is available from the County upon request. Parties are solely responsible for accurate certification and disclosure. The Levine Act is complex, and this brief description is not legal advice. For example, certain contributions must be aggregated when determining whether contributions have exceeded the $500 threshold. If your proposal is selected, you are urged to review the Levine Act and consider consulting an attorney. Term County Executive's Office is issuing Request for Proposal (RFP) No. 2027-RFP - Informal-00183 for Construction Auditing Services – San Mateo Event Center Improvement Projects . The agreement shall have a term of one (1) year . In addition, the County shall have three (3) optional extensions, subject to County approval and the final agreement. , which the County may exercise in its sole, absolute discretion. To exercise this option, the County shall provide written notice to the Contractor at least thirty days before the end of the agreement’s term. The County’s standard contract template has been included with this solicitation. T he awarded contractor will be expected to sign an agreement prepared by the County using this template. Please ensure that your firm has completed legal review of these contract terms. If your firm wishes to request exceptions to these standard terms, submit a Contract Exceptions Request by the Deadline for Contract Exceptions listed in the Solicitation Schedule. The County will consider Contract Exceptions Requests but reserves the right to reject requested modifications to its standard terms. Attachments

Published attachments
Public questions and answers
  • Section 6.4 references a contract template, but I saw no template attached. Where can we get this?

    I have attached the contract template into OpenGov.

  • Under what section in the "Response" should we provide any exceptions to the contract template?

    Please download the template and provide your edits in track changes, then re-upload the template with your exceptions as part of their proposal.

  • Are the 60 days referenced in the RFP timeline presented as Work/Business days, or Calendar Days?

    Work / business days

  • What is/are the data format(s) that data audits will be provided in?

    The data provided to firm that is selected will mostly be in PDF format and potentially in Microsoft Excel and Word.

  • Given the importance and critical nature of the proposed work, a one-week time extension to the submittal date is requested to ensure that the Team and Project Approach is calibrated to ensure a high-quality outcome that can be used in any follow up analysis and assessments by law enforcement.

    Unfortunately, we are unable to extend the timeline for this RFP.

  • Will all audit-essential documents be available immediately at contract award?

    Both the County and the Event Center are compiling documents in preparation for the results and award of this RFP and those documents will be available upon execution of an agreement with the successful proposer.

  • What section of the response do you want the template uploaded to?

    It can be attached as an exhibit to the main proposal.

  • What is the total amount of subcontractors that exist amongst all referenced primary Projects?

    This information will be made available upon execution of an agreement with the successful proposer.

  • Is there an estimation of the quantity of changes that occurred on each Project? Please provide a document count for every line item included in the RFP.

    This information will be made available upon execution of an agreement with the successful proposer.

  • 2. Will all parties associated with the project be available to interview regarding workflows, and audit documentation?

    All County and SMCEC staff will be available to assist with the audit.

  • 3. Are there documented standard operating procedures available?

    All relevant documented operating procedures will be made available upon execution of an agreement with the successful proposer.

  • 4. Are all related contract documents available in soft copy? And if not, where are the hard copy documents located?

    Most contracts and related documents are available electronically and any hard copies of such documents would be located and available for review at the SMCEC Office.

  • 5. What type of entity is Expo Center?

    The San Mateo County Exposition and Fair Association is a nonprofit corporation.

  • 6. Is fund accounting system in use to track the projects in question?

    It is unclear what is meant by "fund accounting system." SMCEC uses Activity AccountingWare to track receipts, disbursements, and budgetary performance.

  • 7. What type of computerized accounting system are you using to track the receipts, disbursements, and budgetary performance?

    SMCEC uses Activity AccountingWare for such accounting purposes.

  • 8. Are the financial auditor's work papers available to the firm selected for this engagement?

    All financial audit reports will be made available upon execution of agreement with the successful proposer.

  • 9. What is the budget for the audit engagement?

    Proposers are required to submit a detailed fee proposal that meets the requirements set forth in the RFP.

  • Does the County anticipate that the selected firm’s report, workpapers, analyses, or calculations may be used in litigation, criminal proceedings, recovery actions, or other legal proceedings?

    It is possible that the report and associated materials may be used in connection with legal proceedings, subject to the County’s reservation of all rights and privileges that may apply.

  • 10. What, if any, construction management software does the Expo Center utilize?

    SMCEC does not itself utilize any constructional management software.

  • 11. Will the workpapers be used for any other purpose?

    It is possible that the report and associated materials may be used in connection with legal proceedings, subject to the County's reservation of all rights and privileges that may apply.

  • How many payment applications are there for these projects? How many change orders? Also, will there be a complete job cost detail report for each provided from the construction manager?

    All project payment related information will be made available upon execution upon agreement with the successful proposer.

  • We understand that each section of the proposal must be uploaded separately. Is there also a designated field to upload the complete proposal as a single PDF document?

    Proposers may upload a single large file into any of the response sections and then state in the other response sections, 'see upload in section X.X'.

  • Can the County provide a copy of the original RFQ/P's for the four projects to be audited?

    If the requested RFPs will not be provided, say the RFPs are not being provided at this time, but will be made available in connection with the audit.

  • What are the values of the approved change orders for each of the 4 projects?

    All project payment related information, including approved change orders, will be made available upon execution of agreement with the successful proposer.

  • Would the County accept a blended hourly rate for the engagement rather than separate billing rates by staff classification, provided the proposal identifies the anticipated staffing approach and overall not-to-exceed amount?

    The proposal should identify the rates for each staff classification that will be working on this engagement.

  • Given that the volume and condition of available records and the extent of potential investigative procedures may not be known until work begins, may proposers provide an initial not-to-exceed amount based on clearly stated assumptions, with material scope changes subject to prior County approval?

    Proposers may provide an initial not to exceed amount, however, work beyond the proposed not to exceed amount will have to be approved prior to the beginning of the new scope of work.

  • Will the engagement be directed by or coordinated with County Counsel or outside counsel, and are there specific protocols the selected firm must follow for legally sensitive communications and work product?

    Proposers should provide their fee proposal in accordance with the RFP requirements and based on the scope of work. This should not be considered an “initial” fee proposal.

  • Will the selected firm be provided access to relevant findings, reports, evidence, or other documentation developed to date through the related court case or investigation that may inform the construction audit?

    The selected firm will have access to public records and information, subject to any privileges that may apply.

  • 1. What auditing standards are required to perform this engagement?

    The engagement is intended to provide an independent assessment of the identified projects, supporting records, controls, and processes. The selected firm shall apply professional standards appropriate to the scope of work, including generally accepted government auditing standards (GAGAS), where applicable, and any additional standards the proposer determines are necessary to support its methodology and conclusions. This engagement is not intended to constitute a financial-statement audit or attestation engagement unless specifically identified in the final scope of work.

  • 12. Will the firm partner or other staff be involved in post-engagement activities or interviews?

    The County may require the engagement partner, project manager, or other key personnel to participate in post-engagement presentations, briefings, interviews, clarification discussions, or follow-up activities related to the final deliverables. Proposers should identify anticipated post-engagement availability, hourly rates, and any assumptions or limits associated with such services.

  • What are the contract values of the 4 projects in the RFP?

    The County will provide the contract values for the four projects identified in the RFP through a formal addendum or other written procurement communication, as applicable. Proposers should rely only on information formally issued by the County when preparing their proposals.