Construction Manager at Risk Services for Sacramento International Airport Airfield Maintenance Facility Project

Description

The County of Sacramento (County) owns and operates the Sacramento International Airport (SMF) through the Department of Airports (Department). SMF is a commercial service airport located 12 miles from downtown Sacramento. SMF opened in 1967 under its previous name, the Sacramento Metropolitan Airport, and in the 1990s it was renamed Sacramento International Airport (Airport). Currently, SMF is best known as the gateway between Northern California destinations and major cities across the United States and the world. The proposed Airfield Maintenance ( AFMX ) Facility project (Project) will consist of a new, approximately 20,000 square foot pre-engineered steel structure that will provide a modern, durable, and cost-effective solution to house maintenance equipment, vehicles, materials, and administrative functions in support of airfield operations in a single location at SMF. The proposed new building will be able to accommodate AFMX needs and estimated future growth. The Department invites all qualified Construction Manager At Risk (CMAR) firms interested in providing their services described in this Request for Qualifications (RFQ) to submit a Statement of Qualifications (SOQ) in compliance with the requirements stated herein. A. Eligibility to Submit a Response: Ability to provide adequate bonds and insurance commensurate with the work to be performed Hold a Class B or higher California Contractors License which is current, valid, and in good standing with the California Contractors State License Board Be registered with the California Department of Industrial Relations and qualified to perform public works as required by California Labor Code sections 1771.5 and 1725.5 Have delivered projects using the CMAR delivery method or other delivery methods that require Guaranteed Maximum Prices (GMPs) and managed work through GMP contracts Ability to deliver similar projects within performance period and budget Have experience working with government agencies and with public works projects, including applicable public contracting and labor compliance requirements In addition, experience in the following areas is desired: Working in secure public areas Working in an operational setting that interacts with the public Experience with complex equipment replacement projects Project Details Important Instructions for Electronic Submittal The County is accepting electronic bid submissions. Bidders shall create a FREE account with OpenGov Procurement by signing up at Sign Up (opengov.com) . Once you have completed account registration, browse back to this page, click on "Draft Response", and follow the instructions to submit the electronic bid. Scope of Work or Project Details Please refer to Attachment 1 - Request for Qualifications Introduction Summary Background Contact Information Any inquiries or requests regarding this solicitation must be submitted via OpenGov. Contact with unauthorized County personnel during the selection process may result in disqualification. Timeline Vendor Submissions Attachments

Published attachments
Addenda and notices
Public questions and answers
  • Please clarify the due date of the SOQ. The Cover Page states 11/19/26 at 2pm but the SOQ due date on this website and on Attachment 1: Projected RFQ Timeline states 12/1/2026.

    The County has identified an inconsistency in the solicitation regarding the response due date. The County will issue an addendum clarifying and correcting the applicable due date. Respondents should rely on the forthcoming addendum for the official and controlling due date. Please continue to monitor OpenGov for issuance of the addendum.

  • Please post the attendee list for the Non-mandatory pre-bid conference held on September 29th, 2026

    The attendee list / sign-in sheet for the Non-mandatory pre-bid conference will be provided in Addendum 2.

  • Section 3 of the SOQ Format and Content asks the proposer to provide a listing of the three (3) most recently completed projects where the CMAR has participated as the prime contractor. May we submit projects which are in progress?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Section 3 of the SOQ Format and Content asks the proposer to provide a listing of the three (3) most recently completed projects where the CMAR has participated as the prime contractor. May proposers submit projects for which they are not the prime contractor, however, proposer was responsible for construction and delivery of a similar building which is similar or larger in size than the proposed Airfield Maintenance Facility?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • "Appendix E states no fee markup is allowed on the Preconstruction Phase, but Exhibit C, Section B includes a 'Maximum Fee of ___%' line in the Preconstruction compensation summary." Please clarify.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • The Fee Proposal Form lists positions with pre-established hours marked “*Evaluation Purposes Only.” To ensure all proposals are evaluated on an equal basis, please confirm: _a. Respondents must provide a billable hourly rate for every position listed in tables (a) and (b), and may not strike, delete, or add positions. b. Respondents may not modify the pre-established hours for any position. c. A Fee Proposal Form that strikes positions, alters hours, or is otherwise modified will be deemed non-responsive. d. If a respondent believes a position or level of effort is unnecessary, please confirm this should be addressed in the SOQ narrative or during negotiation of the Preconstruction Services Agreement and GMP, not on the Fee Proposal Form.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Please confirm whether the Airfield Maintenance Facility project will be subject to the Department’s Community Workforce and Training Agreement (CWTA) executed in March 2024, or to any other Project Labor Agreement.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Public Contract Code §20146(c) requires a construction manager at-risk entity to provide an enforceable commitment to use a skilled and trained workforce, for all work in an apprenticeable occupation, unless the project is covered by a qualifying project labor agreement. Please confirm (a) whether the skilled and trained workforce requirement will apply to this project, and (b) if so, what documentation or commitment the County requires in the SOQ

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • "Addendum 2 Exhibit A, the 30% Schematic Design set is dated July 8, 2025. Please provide the design milestone schedule and the anticipated design stage at the Preconstruction NTP (April 2027)."

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Will the County consider revising the Contract Documents to include a mutual waiver of consequential damages applicable to both parties? The current contract documents contain a one-way waiver of consequential damages to the County's benefit.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Will the County confirm that liquidated damages, if applicable, will constitute the County's sole remedy for project delay?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Will the County clarify that the CMAR is not responsible for errors or omissions in design documents prepared by the Owner's design team?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Will the County consider including a mechanism for adjustment of the GMP for material cost escalation beyond the contractor's reasonable control?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Will the County consider limiting the Contractor's aggregate exposure for liquidated damages and other delay-related damages to a maximum of 10% of the GMP, recognizing that delay impacts on large aviation projects are often influenced by factors outside the Contractor's control, including owner-directed changes, permitting, stakeholder coordination, and operational constraints?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Will the County confirm that the contractor will not be responsible for pre-existing hazardous materials, contamination, PFAS, or other environmental conditions not caused by the contractor?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Confirm whether earthquake and flood coverage will be included under the Builder’s Risk policy and, if so, the applicable limits. If earthquake and/or flood coverage will not be provided, please confirm whether GC may include a contingency for Difference in Conditions (DIC) to buy coverage or, alternatively, whether the Contract will include appropriate risk-transfer language relieving GC of responsibility for losses arising from uninsured earthquake and/or flood events.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • In addition to the GC being identified as a Loss Payee, please confirm that the GC and all subcontractors of every tier will be included as insureds under the Builder’s Risk policy, as their interests may appear.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Exhibit B (Insurance Requirements, page 2) specifies Commercial Automobile Liability minimum limits of $2,000,000 Combined Single Limit for 'all airside driving.' However, Section II Project Overview and Exhibit G indicate the project site is sequestered from the Aircraft Operations Area (AOA) and will remain landside through the construction phase until post-construction fence relocation. Please confirm whether vehicles restricted exclusively to the landside construction site and Delta Road access route require airside auto liability endorsements prior to AOA fence relocation.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Exhibit B Section II states Section 3-9.07 is amended to read 'The COUNTY will procure, maintain, and keep in force, at the COUNTY's sole expense, Builder's Risk insurance... CMAR will be responsible for the first $50,000 per occurrence deductible.' However, Exhibit D Cost Matrix (page 3) marks Builder's Risk under Insurance & Bonds with 'XX' (TBD). Please clarify whether Builder's Risk coverage will be County-provided or if CMAR is expected to procure it for Phase 2 Construction.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Appendix E (page 28) establishes an $18,000,000 Construction Budget benchmark (Range $17,500,000–$18,500,000) and states that Direct Cost of Work plus General Conditions will utilize $18,000,000 for evaluation purposes. On page 30, the table lists '$XXX,XXX.00' for Direct Cost of Work Plus General Conditions. Please confirm that respondents invited to the interview should use exactly $18,000,000.00 as the evaluation multiplier on page 30.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Section VI.A.II (page 19) states that 'Each prospective CMAR shall submit bid detail for three (3) bidders for the scope of work outlined in Section II' in the sealed fee proposal envelope delivered prior to the interview. Because design documents are currently schematic and trade bidding typically occurs during the Preconstruction Phase under progressive GMPs (Exhibit A Section 3.C), please clarify what level of bid detail or trade pricing is expected in the sealed envelope at the interview stage.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Exhibit B (pages 7-8) requires Contractor's Pollution Liability (CPL) insurance of $5,000,000 per claim/aggregate if involved with asbestos/lead removal, underground tank removal/replacement, or toxic chemicals. Please confirm whether CPL is required for the prime CMAR if these specific hazardous materials scopes are performed by licensed specialty subcontractors who maintain equivalent CPL coverage.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Section II.A indicates the project includes a ~20,000 SF pre-engineered steel structure. Please clarify whether the County's Design Team will provide complete engineered foundation and structural drawings, or if the CMAR/PEMB manufacturer will be required to provide deferred submittal engineering and design calculations.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • RFQ Section VI.A.II (at the top of page 20 of 34) states, “The top-ranked CMAR will be notified and have its sealed envelope containing their CMAR Fee Proposal Form opened.” Will negotiations proceed with only the top-ranked scorer, assuming the Fee Proposal Form is correctly completed?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Appendix E: CMAR Fee Proposal Form – For parts (a) and (b), please confirm the Total Preconstruction Staff Cost Component and Total Construction Staff Cost Component lines are the totals of the extended staff position costs (hours x Billable Rate) preceding them and should not be an extension of the 3,900 and 17,368 hours, respectively times a Billable Rate.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Page 12 of the RFQ, Section IV.A, item 1.b refers to the County’s standard contract as Appendix E. Appendix E is the CMAR Fee Proposal. The Sample Contract is Attachment 3. Please confirm which the cover letter should cite.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Exhibit D Cost Matrix lists Drug Testing of CMAR Staff as a General Condition cost. Please confirm what drug testing is required.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Exhibit D Cost Matrix lists Permits and Fees as a General Condition cost. Please confirm for what Permits and Fees the CMAR is responsible.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Is there a projected start date for construction?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Is there a projected construction duration?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Is there a target date for completion or any constraint on the airport side that may need this completed by?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Does the County require that the building design for PEMB come completely turn-key for this RFQ? Or is it acceptable to have the PEMB Vendor do their own design and integrate current Architect, Civil, Structural, Mechanical, Plumbing, Electrical Engineers to integrate with PEMB Vendor to complete the design for the project?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Is there any geotechnical information available for the proposed development location?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Are there any additional Owner Project Requirements created for the operational and space needs of the facility?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Has the design team filled out a preliminary LEED scorecard to help assess the viability of the LEED Silver cert? Can this be shared?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Are there any other design disciplines required of CMAR outside of the PEMB Designer/MFGR/Vendor?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Does the 20-page limit for “CMAR’s Approach to the Project” count within the overall 80-page maximum, or is it in addition to it?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Do required Scoring Questionnaire explanations, schedules and phasing plans, charts, and similar response materials count toward the applicable page limit?

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • References: • Agreement, Section 5.D – Extensions of Time • Exhibit C, Section J – Liquidated Damages • Exhibit F, Section 8-10 – Liquidated Damages Section 5.D of the Agreement states that CMAR shall be liable to the County for “all loss and damage” suffered by the County to the extent caused by CMAR’s failure to timely perform or complete the Work. However, Section 8-10 of Exhibit F states that liquidated damages are the County’s sole and exclusive remedy for CMAR delay. These provisions appear to conflict. Please confirm whether liquidated damages are intended to be the County’s sole and exclusive remedy for CMAR delay. In addition, the first paragraph of Section J of Exhibit C is unclear and appears incomplete. It states that CMAR shall pay “the sum of either (i) $5,000/day,” but does not identify an alternative amount or explain the circumstances under which the stated amount would apply. The remaining language after “substantial completion date…” is confusing and seems out of place. Please clarify the intent of this paragraph.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

  • Page 19, Section VI requires bid detail for three bidders in the sealed envelope at interview. Please clarify what is expected for the bid detail.

    Question will be addressed in Addendum 3. Please continue to monitor OpenGov for issuance of the addendum.

Plain text

OpenGov categories

  • 30500 · Engineering And Architectural Equipment, Surveying Equipment, Drawing Instruments, And Supplies
  • 90610 · Buildings - Architectural Design
  • 90625 · Design Build Services
  • 90735 · Designing Services
  • 90740 · Engineering Services, Non-Licensed (Not Otherwise Classified)
  • 90910 · Airport Facility Construction
  • 90911 · Airport Facility Maintenance and Repair
  • 91310 · Construction: Airport Roadway, Runway and Taxiway
  • 91364 · Maintenance and Repair: Airport Roadway, Runway and Taxiway
  • 91800 · Consulting Services
  • 91815 · Architectural Consulting
  • 91819 · Buildings, Structures and Components Consulting
  • 91832 · Consulting Services (Not Otherwise Classified)
  • 92522 · Control Systems Engineering
  • 92532 · Electronic Engineering
  • 95803 · Airport Management Services
  • 95826 · Construction Management Services