Skip to content
← Back to search

State and local · OpenGov

Opportunityopen

Covered Walkway Phase 2

Description

The Board of County Commissioners of Okaloosa County, FL, are seeking bids for the “COVERED WALKWAY PHASE 2” project, at Destin-Fort Walton Beach Airport. The project can generally be described as: Installation of canopy structures in Parking Lot B, main terminal slip-resistant coating, signage, PA/CCTV upgrades, Wi-Fi booster nodes, rehabilitation of lighting and public announcement system, and landscaping. The anticipated completion time for the BASE BID scope of work is 200 calendar days to achieve Substantial Completion. If bid alternates are awarded, contract time will be extended per the construction and safety phasing plan. Exact time requirements are defined in the Issued for Bid Plans. Base Bid Contractor Quality Control Program (CQCP) 1% Temporary Pollution, Erosion, and Siltation Control Mobilization As-Built Survey Demolition of Asphalt Sidewalk Demolition of Existing Landscaping Install Slip Resistant Coating Pressure Washing Existing Phase 1 Canopy Structure Repainting Existing Phase 1 Canopy Structure Pedestrian Wayfinding and Signage Pre-Engineered Fabric Column-Supported Canopy (Parking Lot A to 2nd Curb) Digital Message Sign (Large Overhead Gantry Display) Electrical Trash Can and Compactor Allowance for Cameras and Access Control Installation in Communications Rooms B127, C211, D213 and only providing and Installing Camera for Room A109 Install CCTV Complete (Fixture, Mounting Brackets, Mounting Arm, Connections, Hardware) Structural rehabilitation mail terminal cover walkway Landscaping Irrigation Electical Bid Alt # 1 Contractor Quality Control Program (CQCP) 1% Temporary Pollution, Erosion, and Siltation Control Mobilization As-Built Survey Pre-Engineered Fabric Column-Supported Canopy (Parking Lot B) Emergency Phone, Complete with Mounting Hardware, and Data Cabling Electrical Bid Alt # 2 Contractor Quality Control Program (CQCP) 1% Temporary Pollution, Erosion, and Siltation Control Mobilization As-Built Survey Demolition of Concrete Sidewalk Demolition of Existing Shuttle Stop Structure Install New Concrete Sidewalk, 4" Thick Pre-Engineered Fabric Cantilever Canopy (Parking Lot B) Electrical Introduction 1.1 Timeline Release Project Date: October 26, 2026 Pre-Bid Conference (Non-Mandatory): November 5, 2026, 10:00am, 1701 FL-85, Eglin AFB, FL 32542 Question Submission Deadline: November 12, 2026, 3:00pm Response Submission Deadline: November 24, 2026, 3:00pm 1.2 Procurement Contract Erin Howze Purchasing Agent II 5749A Old Bethel Road Crestview , FL 32531 Email: ehowze@myokaloosa.com Phone: (850) 689-5960 Scope of Work ENGINEER OF RECORD Mohsen Design Group MDG The Board of County Commissioners of Okaloosa County, FL, are seeking bids for the “COVERED WALKWAY PHASE 2” project, at Destin-Fort Walton Beach Airport. The project can generally be described as: Installation of canopy structures in Parking Lot B, main terminal slip-resistant coating, signage, PA/CCTV upgrades, Wi-Fi booster nodes, rehabilitation of lighting and public announcement system, and landscaping. The anticipated completion time for the BASE BID scope of work is 200 calendar days to achieve Substantial Completion. If bid alternates are awarded, contract time will be extended per the construction and safety phasing plan. Exact time requirements are defined in the Issued for Bid Plans. Advertisement for Bids OKALOOSA BOARD OF COUNTY COMMISSIONERS CRESTVIEW, FLORIDA NOTICE TO RESPONDENTS ITB AP 09-27 Covered Walkway Phase 2 Notice is hereby given that the Board of County Commissioners of Okaloosa County, FL, will accept bids until 3:00 pm , Wednesday, December 2, 2026 for the Covered Walkway Phase 2 , ITB AP 09-27 . The project can generally be described as: Installation of canopy structures in Parking Lot B, main terminal slip-resistant coating, signage, PA/CCTV upgrades, Wi-Fi booster nodes, rehabilitation of lighting and public announcement system, and landscaping. The work is further defined as shown on the Plans and as described by the Contract Documents. Interested respondents desiring consideration shall submit their response online at OpenGov Procurement through the link provided below: https://procurement.opengov.com/portal/myokaloosa Unless otherwise stipulated in the bid/proposal description, all responses must be submitted using OpenGov Procurement only. No other means of submission of responses will be accepted. Responses will be accepted by OpenGov Procurement until 3:00 pm , Wednesday, December 2, 2026 , at which time all bids that are timely submitted will be opened and reviewed. The County reserves the right to award the bid to the lowest responsive respondent and to waive any irregularity or technicality in bids received. Okaloosa County shall be the sole judge of the bid and the resulting Agreement that is in its best interest and its decision shall be final. Bids will be received for a single prime Contract. Bids shall be on a unit price basis as indicated in the Bid Form. All terms, specifications and conditions set forth in this ITB are incorporated into your response. A bid will not be accepted unless all conditions have been met. Bidding documents are only available as electronic portable document format (PDF) and may be downloaded free of charge from the OpenGov Procurement link above. Bid security shall be furnished in accordance with the Instructions to Bidders. A Non-Mandatory pre-bid conference will be held at 10:00 am local time on Thursday, November 5, 2026 at 1701 FL-85, Eglin AFB, FL 32542 . OKALOOSA COUNTY BOARD OF COUNTY COMMISSIONERS Robert A. "Trey" Goodwin, III ______ DeRita Mason _______________________ Chairman Purchasing Manager END OF DOCUMENT 00020 - ADVERTISEMENT FOR BIDS Instructions to Bidders Owner and Owner’s Representative The Owner as stated herein refers to the Okaloosa County Board of County Commissioners. The Owner’s authorized representative as stated herein refers to the Owner’s Consultant, Mohsen Design Group MDG ., herein referred to as “Engineer”. Bidder Representations By submittal of a proposal (bid), the BIDDER represents the following: The Bidder has read and thoroughly examined the project documents. The Bidder has a complete understanding of the terms and conditions required for the satisfactory performance of project work. The Bidder has fully informed themselves of the project site, the project site conditions and the surrounding area. The Bidder has familiarized themselves of the requirements of working on an operating airport and understands the conditions that may in any manner affect cost, progress or performance of the work. The Bidder has correlated their observations with that of the project documents. The Bidder has found no errors, conflicts, ambiguities or omissions in the project documents, except as previously submitted in writing to the owner that would affect cost, progress or performance of the work. The Bidder is familiar with all applicable Federal, State and local laws, rules and regulations pertaining to execution of the contract and the project work. The Bidder has complied with all requirements of these instructions and the associated bid documents. Bid Documents/Project Manual The bid documents are comprised of the following; Invitation to Bid, Notice to Bidders, Instructions to Bidders, Okaloosa County Standard Clauses, Federal Contract Provisions, Wage Rates, General Provisions, Technical Specifications, Project Drawings, Proposal Forms with attachments, Form of Contract Agreement, any authorized addenda issued by the Owner, and any document incorporated in whole or in part by reference therein. All documents comprising the Bid Documents are complementary to one another and together establish the complete terms, conditions and obligations of the successful bidder. Those individual elements of the Contract Documents that are bound together shall also be referred to as the Project Manual. Complete sets of the Project Documents may be obtained from OpenGov and the Okaloosa County website. Modifications to Project Documents Modifications to the project documents may only be made by written addendum issued by the Owner or the Engineer. Verbal explanations, interpretations or comments made by the Owner or Owner’s representative shall not be binding. Addenda will be transmitted to all known official plan holders. Each bidder shall certify at the time of bid submittal that they acknowledge receipt of all issued addenda. Errors and Discrepancies in Project Documents Should Bidder find an error, discrepancy, ambiguity or omission in the project documents prior to submittal of a proposal, the Bidder is obligated to contact the Owner or Engineer with written notice of the error, discrepancy, ambiguity or omission. The written notice shall identify the nature and location of the error, discrepancy, ambiguity or omission. Corrections or modifications to the project documents will only be made by written addendum as prescribed herein. By submittal of a Bid Proposal, Bidder represents that they have thoroughly reviewed the project documents and that they have not identified any error, discrepancy, ambiguity or omission that would affect cost, progress or performance of the project work. Clarifications and Interpretations All questions about the meaning or intent of these Project Documents are to be directed to the County. Interpretations or clarifications considered necessary by the County in response to such questions will be issued by Addenda on the Purchasing website and OpenGov as mentioned above. Questions received after the question deadline may not be answered. Only questions answered by formal written Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect. Addenda may also be issued to modify these Project Documents as deemed advisable by Owner or Architect/Engineer. Interpretations of Estimated Proposal Quantities An estimate of quantities of work to be done and materials to be furnished under these specifications is stated within the project manual. This estimate is a result of careful calculations and is believed to be correct. The estimated quantities are given only as a basis for comparison of proposals and the award of contract. The Owner does not expressly or impliedly agree that the actual quantities involved will correspond exactly with the estimated quantities. The Bidder shall not plead misunderstandings or deception because of such estimates of quantities, or of the character, location, or other conditions pertaining to the work. Payment to the Contractor will be made only for the actual quantities of work performed or materials furnished in accordance with the plans and specifications. It is understood that the quantities may be increased or decreased as hereinafter provided in the subsection titled “Alteration of Work and Quantities” of the general provisions without in any way invalidating the unit bid prices. Examination of Plans, Specifications and Site Conditions As stated within the “Bidder Representations” and reaffirmed herein, the Bidder is expected to carefully examine the site of the proposed work, the proposal, drawings, specifications, terms and conditions of the proposed agreement and the form of agreement. The Bidder shall satisfy themselves as to the character, quality, and quantities of work to be performed, materials to be furnished and as to the requirements of the proposed contract. The submission of a proposal shall be prima facie evidence that the Bidder has made such examination and is satisfied as to the conditions to be encountered in performing the work and as to the requirements of the proposed c Insurance Requirements 5.1. CONTRACTORS INSURANCE The Contractor shall not commence any work in connection with this Agreement until he has obtained all required insurance and the certificate of insurance has been approved by the Okaloosa County Risk Manager or designee. All insurance policies shall be with insurers authorized to do business in the State of Florida and having a minimum rating of A, Class X in the Best Key Rating Guide published by A.M. Best & Co. Inc. All insurance shall include the interest of all entities named and their respective officials, employees & volunteers of each and all other interests as may be reasonably required by Okaloosa County. The coverage afforded the Additional Insured under this policy shall be primary insurance. If the Additional Insured have other insurance that is applicable to the loss, such other insurance shall be on an excess or contingent basis. The amount of the company’s liability under this policy shall not be reduced by the existence of such other insurance. With the exception of Workers’ Compensation policies, the County shall be shown as an Additional Insured with Endorsement for each policy on the Certificate of Insurance. The County shall retain the right to reject all insurance policies that do not meet the requirement of this Agreement. Further, the County reserves the right to change these insurance requirements with 60-day notice to the Contractor. The County reserves the right at any time to require the Contractor to provide copies (redacted if necessary) of any insurance policies to document the insurance coverage specified in this Agreement. Any subsidiaries used shall also be required to obtain and maintain the same insurance requirements as are being required herein of the Contactor Any exclusions or provisions in the insurance maintained by the Contractor that excludes coverage for work contemplated in this agreement shall be deemed unacceptable and shall be considered breach of contract. 5.2. Workers' Compensation Insurance The Contractor shall secure and maintain during the life of this Agreement Workers’ Compensation insurance for all of his employees employed for the project or any site connected with the work, including supervision, administration or management, of this project and in case any work is sublet, with the approval of the County, the Contractor shall require the Subcontractor similarly to provide Workers’ Compensation insurance for all employees employed at the site of the project, and such evidence of insurance shall be furnished to the County not less than ten (10) days prior to the commencement of any and all sub-contractual Agreements which have been approved by the County. Contractor must be in compliance with all applicable State and Federal workers’ compensation laws, including the U.S. Longshore Harbor Workers’ Act or Jones Act, if applicable. No class of employee, including the Contractor himself, shall be excluded from the Workers’ Compensation insurance coverage. The Workers’ Compensation insurance shall also include Employer’s Liability coverage and a Waiver of Subrogation in favor of the County on the Certificate of Insurance. If there is an existing approved State of Florida Exemption for Workers’ Compensation it must be provided to Okaloosa County. Limit: State Statutory Employer's Liability $500,000 each accident 5.3. COMMERCIAL GENERAL LIABILITY INSURANCE The Contractor shall carry Commercial General Liability insurance against all claims for Bodily Injury, Property Damage and Personal and Advertising Injury liability caused by the Contractor. All liability insurance (other than Professional Liability) shall be written on an occurrence basis and shall not be written on a claims-made basis. If the insurance is issued with an aggregate limit of liability, the aggregate limit of liability shall apply only to the locations included in this Agreement (Project Aggregate). If, as the result of any claims or other reasons, the available limits of insurance reduce to less than those stated in the Limits of Liability, the Contractor shall notify the County representative in writing. The Contractor shall purchase additional liability insurance to maintain the requirements established in this Agreement. Umbrella or Excess Liability insurance can be purchased to meet the Limits of Liability specified in this Agreement. Commercial General Liability coverage shall include the following: Premises & Operations Liability Bodily Injury and Property Damage Liability Independent Contractors Liability Contractual Liability Products and Completed Operations Liability Contractor shall agree to keep in continuous force Commercial General Liability coverage for the length of the contract. Limit $1M each occurrence for Bodily Injury & Property Damage $1M each occurrence Products and completed operations $1M each occurrence Personal and Advertising Injury 5.4. BUSINESS AUTOMOBILE LIABILITY Coverage must be afforded for all Owned, Hired, Scheduled, and Non-Owned vehicles for Bodily Injury and Property Damage. If the contractor does not own vehicles, the contractor shall maintain coverage for Hired & Non-Owned Auto Liability, which may be satisfied by way of endorsement to the Commercial General Liability policy or separate Business Auto Policy. Contractor must maintain this insurance coverage throughout the life of this Agreement. Limit: $1M each accident (a combined single limit) 5.5. POLLUTION LIABILITY Contractors shall provide proof of Pollution Liability insurance arising out of all operations of the Contractors and subcontractors, due to discharge, dispersal, release or escape of contaminants or pollutants into or upon land, the atmosphere or any watercourse or body of water with bodily injury and property damage limits of not less than $1,000,000 per occurrence and $2,000,000 annual aggregate. Okaloosa County Board of County Commissioners is to be listed as Additional Insur Pricing Proposal BIDDER will complete the Work in accordance with the Contract Documents for the following price(s): Vendor Questionnaire Okaloosa County, Florida solicits your company to submit a response for referenced goods or services listed in this ITB All terms, specifications and conditions set forth in this ITB are incorporated into your response. A response will not be accepted unless all conditions have been met. All responses must be submitted by an authorized representative. All responses must be submitted electronically by 3:00 pm on Wednesday, December 2, 2026 . Responses may not be withdrawn for a period of ninety (90) days after the response opening unless otherwise specified. Attachments and Exhibits Grant Funded Clauses This Exhibit is hereby incorporated by reference into the main Procurement . FEDERAL PROVISION RELATED TO GRANT FUNDS THAT MAY BE USED TO FUND THE SERVICES AND GOODS UNDER THIS SOLICITAT ION This solicitation is fully Federally Grant funded. To the extent applicable, in accordance with Federal law, respondents shall comply with the clauses as enumerated below. Proposer shall adhere to all grant conditions as set forth in the requirements of Grant # N/A Including, but not limited to, those set forth below, as well as those listed below, which are incorporated herein by reference: 2 CFR. 25.110 2 CFR Part 170 (including Appendix A), 180, 200 (including Appendixes), and 3000 Executive Orders 12549 and 12689 41 CFR s. 60-1(a) and (d) Consolidated Appropriations Act, 2021, Public Law 116-260 related to salary limitations These cited regulations are hereby incorporated and made part of this Solicitation as if fully set forth herein. As stated above, this list is not all inclusive, any other requirement of law applicable in accordance with the Federal, State or grant requirements are also applicable and hereby incorporated into this Solicitation . If Proposer cannot adhere to or objects to any of the applicable federal requirements, Proposers proposal may be deemed by the County as unresponsive. The provisions in this exhibit are supplemental and in addition to all other provisions within the p rocurement. In the event of any conflict between the ter

Published attachments
Addenda and notices
  • Addendum #1 · 1

    Addendum is being added to upload pre-bid notes and attendance. The opening date is being moved to November 24, 2026, at 3:00 P.M.

  • Addendum #2 · 2

    Please use the See What Changed link to view all the changes made by this addendum.

  • Addendum #3 · 3

    Please use the See What Changed link to view all the changes made by this addendum. Submission deadline has been extended to December 2nd, 2026 at 3:00pm.

Public questions and answers
  • Is there a set of plans for this project?

    These have been added to the list of attachments.

  • Are there drawings/plans for this project? The spec book was uploaded twice. The only drawings in there are the Phasing Plan. C031-D says, "See Demolition Plan," but no demo plan was provided.

    These have been added to the list of attachments.

  • Is there a general ITB Document listing the bid requirements? (When and where bid is to be submitted? The Bid Form? What the insurance requirements will be? Whether Davis Bacon will apply? etc.)

    The section General Instructions to Bidder's, the Overview, and the Insurance requirements are all listed in the Project Documents sections. The bid is electronically submitted.

  • What is the budget for this project so we can let our bonding companies know for the bid bond? Thanks

    The budget is considered the lowest bidder, so whatever your bid price will be is the number you should give to your bonding company.

  • Usually at VPS they will send a meeting link can you please provide the link for the pre bid meeting.

    https://teams.microsoft.com/meet/2909058647639691?p=jBXAJMOZuKB4yHLwpb

  • Bid date / time is currently set for 3pm the day before Thanksgiving. This is a terrible time for GC's to be collecting subcontractor bids. Please consider either moving the bid date up to the 24th, or back to the following week.

    The County has extended the bid opening to Wednesday December 2nd, 2026 at 3:00 p.m.

  • Are these demolition areas limited to landscaping materials like sod, mulch, and plants, or do they also include concrete and hardscape materials?

    Most are landscaping but some areas, specifically the existing walkways on the west side of Concourse C, include removing old concrete sidewalk and bus shelters, as well as the asphalt on the east side of Concourse C where landscaping will be installed coming out of the concourse covered walkway exit lane; see Sheets L-101, L-102, and L-103 for landscape removals and Sheets C221 and C222 for concrete, asphalt, and hardscape removals.

  • As Okaloosa County pointed out to the Airport during the pre-bid meeting, would it be possible to extend the bid deadline to the following week later in the week? Having the bid due the day before Thanksgiving creates a significant issue for subcontractors and Vendors to get quotes out. Many trade partners will be traveling or unavailable due to the holiday, which makes it difficult to obtain the necessary quotes and ensure all portions of the project are covered. Extending the deadline by one week would give contractors and subcontractors a more reasonable opportunity. We all would appreciate your consideration of this request.

    The County has extended the bid opening to Wednesday December 2nd, 2026 at 3:00 p.m.

  • The bid form notates sales tax separately? is this tax exempt or is the airport looking to do ODP?

    Sales Tax should be included in your bid prices and not treated as a separate line item. The project is not tax exempt and normal state and county taxes would apply to material and subcontract costs. This appears to be a formatting flaw in OpenGov that breaks sales tax out on the bid tab. Bidders should leave this ‘Sales Tax’ line blank as it will not be considered as part of the final bid price.

  • Does the airport have any specific contractors tied to the facility for CCTV, and the PA system? These systems get complicated at the airport.

    Security Engineering Inc. out of Pensacola is the current contract vendor for VPS for security cameras and access controls. Glaze Communications also has a County contract for similar services and is familiar with the Airport. Additionally, the Airport also has a current contract with Atlas IED for support services on the PA System. Charles Kowalkczyk should be able to provide more details to contractors/vendors for the PA system. Charles.Kowalczyk@AtlasIED.com

  • Is Span Systems Inc. an approved equal?

    Yes, Span Systems, Inc. is approved as an equal material vendor for the canopy system. This approval is conditional upon all final shop drawings, engineering calculations, and product submittals being formally reviewed, approved, and verified to meet all project technical specifications during the construction submittal process.

  • Previously when we have worked with other municipalities, they would allow us to bill for the Shade systems with an invoice as they require a large deposit upon ordering. Will the County allow us to bill for the shade systems after shops are approved and we execute the order?

    Typically, we have allowed for deposits to be paid with proper documentation. Billing can cover design services and stored materials with photo evidence.

  • Is Sherwin Williams manufacture an approved equal to FPT Infrastructure Matacryl TPO Thin Polymer Overlay System for traffic coatings?

    Not without specific product verification. Approval as an "or equal" is evaluated on a product-by-product basis, not by manufacturer name alone. To be considered as an approved equal to the basis-of-design, the bidder/manufacturer must submit the specific proposed product data sheets, technical performance/testing data (demonstrating conformance to all performance, slip-resistance, durability, and dimensional requirements), and installation instructions for Engineer review in accordance with the substitution procedures. No unapproved substitutions will be permitted unless formally approved by written addendum prior to bid opening (or as reviewed during formal submittal if permitted by the Contract Documents).

  • Span Systems is seeking formal approval as a designated qualified bidder for the Tensile Membrane Structures scope on the project. We have uploaded a qualifications document along with W9 & Insurance form. Please note that in addition to the qualifications provided, Span Systems is a Licensed Specialty Structure Contractor in the State of Florida.

    Span Systems, Inc. is approved strictly as a material vendor for the Tensile Membrane Structures scope, with AISC accreditation accepted in lieu of IAS. This approval is contingent upon all final submittals meeting project technical specifications during construction. If bidding as a subcontractor rather than solely supplying materials, all solicitation licensing, insurance, and bonding requirements still apply.

  • In the bid sheet for the Base Bid Line item 8 for pressure washing existing canopy shows 13,200 sqft of area but line item 9 for repainting shows 7,000 sqft. Do these areas reflect surface areas of fabric to be pressure washed and steel surfaces to be repainted?

    Line Item 8 (05 01 12 – Pressure Washing Existing Phase 1 Canopy Structure): The governing quantity is revised to 15,000 SF (superseding all prior quantity references,). This includes pressure washing all exposed surfaces of the existing Phase 1 canopy structure from the ground up to the roof—including the canopy roof/fabric, structural steel framing, columns, and associated surfaces. Line Item 9 (09 96 00 – Repainting Existing Phase 1 Canopy Structure): The governing quantity is revised to 10,000 SF (superseding all prior quantity references,) and applies to existing structural steel surfaces. The specific 10,000 SF of structural steel areas/members to be repainted will be designated in the field by the Owner/Engineer prior to painting operations.

  • n the Base Bid For the repainting of the existing Column Supported Canopies, should the specification section 13 31 33 - 2.2A be used or should section 09 91 00 Painting be followed or perhaps the intent for repainting already painted components is not three coats. Please clarify. Additionally please confirm with this response that the intent is to have a full repainting within the requirements of the appropriate specification section.

    Section 13 31 33 applies only to the new pre-engineered custom waterproof walkway canopies. For repainting the existing Phase 1 Canopies (10,000 SF, Base Bid Line Item 15), contractors shall follow Section 09 91 00 (Painting) after completing pressure washing (05 01 12). The intent is a full repainting of the designated 10,000 SF structure—not spot touch-up alone—consisting of thorough surface cleaning and mechanical removal of rust and loose scale.

  • For the Alternate 1 Column Supported canopy shown in detail 2/dwg C430 can the offered system by visually slightly different to reduce costs and be most efficient while maintain the requirements of the bid documents?

    Visual and structural profile variations from Detail 2/C430 may be acceptable provided the proposed system maintains the required project footprint, vertical/horizontal clearances, overall architectural intent, and all structural, wind-load (145 mph to 170+ mph (3-second gust, Exposure C), live-load (5 psf), coating, fabric, and code requirements (IBC 2021/Florida Building Code) of Section 13 31 33. Per Section 13 31 33, Paragraph 2.1.C, any alternate/equivalent system must be submitted with product documentation, fabric samples, and Quality Assurance documentation at least 10 days prior to the bid date, and approved equals will be issued by written Addendum only prior to bid opening

  • 1.4 includes a requirement for a minimum of $ 25,000,000 aggregate bonding capacity. Is this correct? Why would a subcontractor need a bonding capacity 50 times larger than this scope of work? Why is bonding capacity a requirement for bidding this scope at all.

    Only general contractors have to submit the required bonds, not subcontractors. The $25M referenced in 1.4 should be reduce to $5M.

  • 2.1B: It states that “foundations are also required”. Please clarify if this is related to foundation design or also installation? Section 133133- 3.1C-a also discusses foundations design, but it is not clear the intent of who carries the foundation design/installation responsibility?

    Per Section 13 31 33 (Paragraphs 1.2, 1.5, and 2.1), "foundations are also required" applies to both foundation engineering/design and physical foundation installation—including excavation, removal of dirt spoils, reinforcing, concrete placement, and ASTM F-1554 Grade 55 galvanized anchor bolts—with all associated costs included in the 13 31 33-1 canopy Bid Form items. A single waterproof walkway canopy contractor is responsible for designing, engineering, manufacturing, supplying, and installing both the fabric canopy structures and their building-code-appropriate foundations. The reference to "General Contractor's Engineer" in Paragraph 3.1.C does not transfer foundation design or installation responsibility away from this single-source requirement.

  • 2.7 and 2.8 outline the gutter and downspout requirements. These specifications seem to be somewhat generic. Is the intent to provide gutters for the new canopies and is so please clarify where gutters are located. Also we find no locations on the drawings for the canopies (old or new) where gutters are indicated. Please clarify and advise.

    Yes. Commercial-grade gutters and downspouts are required for the new canopies and shall be included in the 13 31 33-1 canopy Bid Form items. The canopy manufacturer shall design the drainage layout and show all gutter runs, downspout locations, and discharge points on their signed and sealed Shop Drawings for Engineer approval prior to fabrication. All gutters and downspouts must meet Section 13 31 33 (Paragraphs 2.7–2.8 / 2.1.K–2.1. L) and SMACNA standards, with downspouts routed along canopy columns to discharge away from ADA pedestrian paths, curb ramps, and vehicular lanes.

  • 1.6 The steel warranty for structural integrity relies on maintenance of the system. Structural integrity is based on inspected and approved design, fabrication and installation, but not long-term performance of the system to which the designer/fabricator has no control. We ask that this requirement be modified to be more specific or be eliminated because this is undefined.

    The structural steel warranty requirement in Section 13 31 33 (1.6) remains in effect and is clarified as follows: Provide a 12-month contractor warranty covering labor and materials, a 15-year manufacturer warranty on fabric, and a 10-year manufacturer warranty on structural steel, all commencing at Substantial Completion. These warranty periods supersede any conflicting references to a 10-year fabric warranty or a 20-year steel warranty elsewhere in the contract documents. The 10-year structural steel warranty is limited to structural failure resulting from defects in design, materials, welds, or fabrication under normal use and specified design loads. The warranty does not cover damage resulting from lack of routine maintenance, vehicle or other physical impacts, unauthorized modifications, misuse, or loading conditions that exceed the design criteria.

  • 2.6A-1 requires aluminum clamping to be 6016-T6, Due to the need for material ductility of the aluminum clamping, 6061-T5 or equivalent would be less brittle and a better choice. Please advise if this is acceptable.

    Yes — 6061-T5 (or an equivalent structural aluminum alloy) is acceptable for the membrane clamping hardware, provided the canopy manufacturer's Florida-licensed Professional Engineer verifies its structural adequacy for the specified wind and live load and Exposure in the signed and sealed structural calculations and shop drawings. All clamping assemblies must conform to the applicable Florida Building Code / IBC requirements and include proper isolation between dissimilar metals to prevent galvanic corrosion.

  • Is there any requirement for the structural steel in this scope of work to be galvanized prior to the application of the high-performance coating system outlined in section 099100. Section 05 50 00 – 2.7 seems to require galvanizing prior to paint, but the high-performance paint system should mitigate the requirement for Galvanizing of the steel and eliminate that extra cost and time frame.

    §055000-2.7-A. clarifies application for items "shown or specified" if items are not shown or specified then the galvanization is not required. Only galvanization anticipated is for light gauge framing required for the stucco assembly and/or touch up required for exposed galv. Elements restored prior to installation of the stucco systems. See notes calling out Galvanized Metal Studs.

  • Does the project incorporate any Buy America or Buy American requirements? Also do prevailing wage (Davis/Bacon) compliance guidelines govern the field work?

    There are no Federal grant funding streams in this project so buy American and Certified Payrolls are not required. Federally regulated Passenger Facility Charges (PFCs) are being utilized towards eligible project scope items, but per FAA Order 5500.1, Passenger Facility Charge, Chapter 1, Paragraph 1-22(i), states: "Projects funded totally with PFC revenue or with financing other than Federal funds are not subject to the labor minimum wage rates under the Davis-Bacon Act, Disadvantaged Business Enterprise (DBE) requirements, Buy-American Preferences, or the Uniform Relocation Assistance and Real Property Acquisition Policy Act requirements."

  • How should the bidders handle sales and use taxes for material being incorporated into the work? Is there a flow down tax exemption or do we have to include these taxes in our bid or as an allowance

    There is no flow down tax exemption. Normal state and county taxes would apply when calculating bid prices. Sales Tax should not be treated as a separate line item in the bid and left blank. This sales tax line item is an anomaly in the OpenGov template for the bid tab.

  • Are there any mock-up requirements for the Tensile Membrane Canopies or their components? Mockups are mentioned in the 09 91 00 section 1.7 in Painting, but the requirements for this scope of work are not clear. This same section also mentions possible AESS areas to be designated by the architect. Please identify these areas for the walkway canopies if applicable before the bid date.

    §099100-1.7-A.-1. a. has designated the mock-up as a “[single] surface to represent surfaces and conditions” the only coating system mock-up is for the AESS. The architect’s designated location will be the “Mast” located at column line intersection (C)(1). The “Mast” is defined as: Round HSS Tube AESS from “TOP OF WALL” to “TOP OF MAST” as indicated A11/A611 inclusive of closure plate at Top of Mast. There is no specified Mock-Up for Tension Fabric system defined in §095443. However, finish samples are specified in §095443-1.4-A. If there is concern on the responding contractor’s part on quality control or assurance or expected outcomes the sample can include tension system. Client expectation is a tension system in rectilinear orientation installed to meet §095443-3.2-A. “without wrinkles, creases or visible sagging”.

  • Who is the firm that currently maintains the airports Wi-Fi and access points?

    These are managed by the County IT department.

  • On drawing C430 the structure in Section 1/C430 is the Cantilevered Canopy for Terminal B that is described as a “Pre-Engineered Fabric Cantilever Canopy (Parking Lot B)” on the bid sheets and elsewhere and is included as Alternate 2. Section 1/C430 calls out a the roofing to be: TYP. 8 MM MULTIWALL POLYCARBONATE PANEL (VEROLITE OPAL OR APPROVED SUBSTITUTION) This is not a fabric material. Please clarify if this is to be fabric. Additionally, if the structure is to be Fabric Cantilever Canopy, the roof must have curvature for proper membrane behavior under maximum hurricane wind loads. Please clarify the intent and the flexibility of the roof cantilevered shape.

    The roofing shall be 8 mm Multiwall Polycarbonate Panel (Verolite Opal or approved substitution) rather than tensioned fabric, and the Base Bid line item (13 31 33-1, 1,225 SF) is revised accordingly to reflect polycarbonate roofing. All applicable structural steel, coating, foundation, wind and live load and Exposure, requirements remain in effect for the canopy frame and panel attachment.

  • For section 1/C430 should the Cantilevered free edge be a curved cable edge or straight beam for maximum coverage. For Section 2/430 should the long edges be a curved cable edge or is a straight edge the intent? Please clarify.

    Section 1/C430 (Cantilever Canopy): A straight beam edge is required to support the 8 mm multiwall polycarbonate roofing. Section 2/C430 (Column-Supported Canopies): Either a straight edge or a curved cable edge is acceptable, provided the proposed configuration is submitted for review and approved by the Owner/Engineer prior to bid in accordance with Section 13 31 33 (2.1.C). Any approved configuration shall maintain the required coverage, clearances, and design loads, including (145 mph to 170+ mph (3-second gust, Exposure C) and 5 psf live load requirements.

  • For installation and wiring of lighting signage and other Power/Audio/CCTV etc. that is mounted to the new canopies, would the desired intent to be for the wiring/conduit be run inside the steel components for clean appearance and should the requisite hand holes and mounting lugs be included in the canopy proposal.

    Wiring/conduit can be run internal or external. Currently it is external in conduit and acceptable for existing walkways. Internal is acceptable and would provide a cleaner look but would need to be incorporated in the structural design for any new canopies.