State and local · OpenGov
CWA2603 Water Well Rehabilitation: Willow Bank and Eldridge Road
Description
The project includes removing and replacing two sets of water well downhole equipment, miscellaneous site and electrical work at Willow Bank and Eldridge Rd water well sites. The project also includes an alternate bid to add a generator at Willow Bank Well site. Bid Pricing Form MISCELLANEOUS ITEMS - Base Bid Mobilization, bonds and insurance ALLOWANCE for SCADA programming for both sites. (MUST ENTER UNIT COST $5,000) ALLOWANCE for Arc Flash Hazard Analysis per Section 16015, completed by Baird, Gilroy & Dixon, L.L.C. (MUST ENTER UNIT COST $5,000) ALLOWANCE for CenterPoint to protect overhead power at either site if needed. (MUST ENTER UNIT COST $20,000) WATER WELLS WILLOW BANK AND ELDRIDGE WATER WELL - Base Bid Near-white (SSPC-SP10) blast and recoat all above ground piping with TNEMEC three-coat zinc-rich epoxy primer/epoxy/polyurethane system with full containment if required. Remove and replace existing 8" Gate Valve Remove and replace existing 12" Gate Valve Remove and replace existing 12" Check Valve Remove and replace 4" air/vacuum release valve Remove and replace existing flow meter Remove and replace existing 12" Restrained Dresser Coupling Pull existing pump and column assembly, evaluate motor and pump equipment Replace pump and column assembly Wire brush, jet and airlift debris, preform before and after camera surveys and disinfect the well including three water samples. Provide and install electrical equipment including, but not limited to manual transfer switch, canopy, housekeeping pad, conduit, wire, and all ancillary devices as shown on construction drawings, complete in place. Partially remove existing fence and gate as shown on construction drawings. Provide rolling gate with track system Provide and install fence per plans Remove and haul off existing asphalt driveway and base 6" Concrete pavement including 6" cement stabilized sand subgrade Remove and replace existing sidewalk around wellhead. Provide aluminum access platform next to wellhead. Near-white (SSPC-SP10) blast and recoat all above ground piping with TNEMEC three-coat zinc-rich epoxy primer/epoxy/polyurethane system with full containment if required. Remove and replace existing 16" butterfly valve Remove and replace existing 16" check valve Remove and replace 3" air/vacuum release valve Remove and replace existing flow meter Remove and replace existing 16" restrained dresser coupling Pull existing submersible pump and column pipe, evaluate motor and pump equipment. Replace submersible pump, column pipe, and motor cable. Wire brush, jet and airlift debris, preform before and after camera surveys and disinfect the well including three water samples. Provide and install electrical equipment including, but not limited to manual transfer switch, canopy, housekeeping pad, conduit, wire, and all ancillary devices as shown on construction drawings, complete in place. Remove replace main braker box and junction box at wellhead with 304SS NEMA 4X enclosures Miscellaneous Pipe Work Remove and replace existing 8' tall fence w/ 8' tall cedar Fence Provide rolling gate with track system Add Alternate Bid Items NOTE: Bid Item 32 will be deleted if the Alternate Bid Items are approved. In lieu of Willow Bank Bid Item 32, provide and install natural gas generator, concrete foundation, sound attenuating enclosure, ground wells, automatic transfer switch, and all required appurtenances as shown on construction drawings, complete in place. Allowance for natural gas service. Exact amount will be reimbursed to Contractor upon submittal of invoice from Natural Gas Service Provider. (MUST ENTER UNIT COST $10,000) SCOPE OF WORK Scope of Work The project includes removing and replacing two sets of water well downhole equipment, miscellaneous site and electrical work at Willow Bank and Eldridge Rd water well sites. The project also includes an alternate bid to add a generator at Willow Bank Well site. WORK COVERED BY THIS CONTRACT: Willow Bank and Eldridge Road Water Wells Rehabilitation for City of Sugar Land, Fort Bend County, Texas. MEASURMENT AND PAYMENT No separate payment for work. Include costs for this work in Bid Items for which this work is a component part. WORK SEQUENCE Phases – None. Uses of premises: Work on site may not begin until the date of the Notice to Proceed. This is an operating facility, and all work must be coordinated with Engineer to minimize disruption of services. Do not operate valves, start/stop equipment etc. Operator will perform these functions. Stored materials and equipment Assume full responsibility for the protection and safekeeping of products stored at the site. Relocate any materials or equipment that prevents the Owner from using the site for its intended purposes at no additional cost to the Owner. Obtain and pay for the use of off-site storage or work areas needed for operations. Utilities Contractor may use site electricity. OWNER OCCUPANCY Owner may occupy the premises during the entire period of construction for the conduct of his normal operations. Cooperate with Owner's representative in all construction operations to minimize conflict, and to facilitate Owner usage. BID EXPLANATION Base bid includes new docking stations and manual transfer switches at both sites. The existing motor control centers (“MCC”) will remain at both sites. Base Bid electrical includes sun screens over all electrical panels at both sites. Alternate Bid is for Willow Bank site only. If the Alternate Bid is chosen, the Willow Bank docking station and manual transfer switch will NOT be built. The Alternate bid includes a generator, automatic transfer switch and new motor control center. Owner wants only TNEMEC coatings. See notes on plans. Owner wants only Av-Tek valves. See notes on plans. For additional information, please see the Invitation to Bid (ITB) and Plan set in the attached documents. SCHEDULE OF KEY EVENTS Advertised in local paper/Notice Posted to OpenGov Procurement: November 11, 2026 Pre-Bid Conference (Non-Mandatory): November 17, 2026, 10:00am Microsoft Teams meeting Join: https://teams.microsoft.com/meet/2419031023400622?p=Y3id03kdNTgdSIbhO6 Meeting ID: 241 903 102 340 062 2 Passcode: QL3UY3nS Questions Deadline: November 23, 2026, 5:00pm Questions Answered and Addendum posted: November 30, 2026, 5:00pm Bids Due: December 3, 2026, 11:00am NOTICE TO BIDDERS The City of Sugar Land seeks bids for furnishing all labor, material, and equipment, and performing all work required for the following project in the City: CIP PROJECT NAME: CWA2603 Water Well Rehabilitation: Willow Bank and Eldridge Road CIP PROJECT NUMBER: 2027-ITB-005 LOCATION OF WORK: Willow Bank and Eldridge Rd Water Well Sites Plans, specifications, and bidding documents may be obtained from OpenGov Procurement. One (1) original bid shall be submitted electronically, on or before 11:00 am on Thursday, December 3, 2026 , at which time bids will be publicly opened and read. Bids received after the opening date and time will not be considered. A non-mandatory pre-bid / site visit for all interested parties will be held 10:00 am on Tuesday, November 17, 2026 at Microsoft Teams meeting Join: https://teams.microsoft.com/meet/2419031023400622?p=Y3id03kdNTgdSIbhO6 Meeting ID: 241 903 102 340 062 2 Passcode: QL3UY3nS . Questions regarding this Invitation to Bid must be received on or before 5:00 pm on Monday, November 23, 2026 . Please post all questions to OpenGov Procurement. Contact with any personnel of the City other than as authorized in this Invitation to Bid, regarding this Invitation to Bid, may be grounds for elimination from the selection process. The City does not assume responsibility for not receiving questions from the Bidder or the Bidders’ receipt of any answers, addenda, or amendment. THE SELECTED BIDDER(S) WILL BE REQUIRED TO ENTER INTO THE CITY OF SUGAR LAND STANDARD CONTRACT FOR Civil Engineering Construction PROJECTS AND PROVIDE AND MAINTAIN THE MINIMUM INSURANCE COVERAGES REQUIRED UNDER THE CONTRACT. THE CONTRACT IS INCLUDED AS AN ATTACHMENT TO THIS ITB. The City Council will award the contract as provided in the Invitation to Bid. The City of Sugar Land will give notice of the contract award within ninety (90) calendar days after the opening date and time. BID PROPOSAL BID EXPLANATION: Base bid includes new docking stations, manual transfer switches, conduits and sunscreens over electrical equipment at both sites. For Base and Alternate Bid both existing motor control centers ("MCC") remain. Alternate Bid is for Willow Bank site only. If Alternate Bid is chosen, the Willow Bank docking station and manual transfer switch will not be built. The Alternate bid includes a new generator and automatic transfer switch. NOTE: If the description contains a set unit cost, you must enter the listed amount as your unit cost. VENDOR QUESTIONNAIRE
Published attachments
Public questions and answers
Is there an estimated cost or cost range for this project?
The City will not disclose that information, no engineer estimate will be provided.
Will the Pre-Bid Meeting and Site Visit sign in sheet be posted?
The online prebid was held on November 17, 2026 at 10am, however, no contractors attended.
OpenGov categories
- 33500 · Fertilizers And Soil Conditioners
- 51500 · Lawn Maintenance Equipment And Accessories (See Class 020 For Agricultural Types)
- 59500 · Nursery (Plants) Stock, Equipment, And Supplies
- 65000 · Park, Playground, Recreational Area And Swimming Pool Equipment And Supplies
- 67500 · Pesticides And Chemicals: Agricultural And Industrial
- 69000 · Power Generation Equipment, Accessories, And Supplies
- 69100 · Power Transmission Equipment (Electrical, Mechanical, Air And Hydraulic)
- 79000 · Seed, Sod, Soil, And Inoculants
- 81500 · Steam And Hot Water Fittings, Accessories, And Supplies
- 82000 · Steam And Hot Water Boilers And Steam Heating Equipment
- 88500 · Water And Wastewater Treating Chemicals
- 89000 · Water Supply, Groundwater, Sewage Treatment, And Related Equipment (Not For Air Conditioning, Steam Boiler, Or Laboratory Reagent Water)
- 90900 · Building Construction Services, New (Incl. Maintenance And Repair Services)
- 91000 · Building Maintenance, Installation And Repair Services
- 91200 · Construction Services, General (Incl. Maintenance And Repair Services)
- 91300 · Construction Services, Heavy (Incl. Maintenance And Repair Services)
- 91400 · Construction Services, Trade (New Construction)
- 95900 · Marine Construction And Related Services; Marine Equipment Maintenance And Repair
- 96800 · Public Works And Related Services
- 98800 · Roadside, Grounds, Recreational And Park Area Services