Demolition and Debris Removal Service for 7540 Fairfield Road and 7544 Fairfield Road.

Description

Richland County (the County) is seeking electronic bids from qualified suppliers to provide residential demolition and debris removal services for two (2) locations: 7540 Fairfield Road and 7544 Fairfield Road, Columbia SC 29203 REQUIREMENTS Scope of Services – Residential Demolition and Debris Removal of two structures Richland County is seeking bids for demolition and debris removal services for properties in Richland County. The structures range in size and are of various types of construction and includes mobile and manufactured homes. The contractor shall provide all materials, tools, machinery, labor and supervision. The demolition service shall include excavation of any footings and foundations and removal of all demolition debris from the demolition site. Click the link ATTACHMENTS & EXHIBITS to see property's information. The contractor must complete the demolition of the structure in its entirety and submit Request for Payment within 30 days of Procurement awarding the contract (unless otherwise specified by the Code Official) . Structures to be Demolished and Removed: Main Structures (Only) – Shown in Property Information 1. Fences: (if applicable) Fences surrounding structures may be temporarily removed to complete the demolition. Fences should be restored to their original condition immediately following the demolition of the structure. Fences that are damaged during the demolition shall be repaired/replaced by the contractor. The Scope of Work shall include but is not limited to the requirements below. Richland County may add or make changes with any service of a similar nature to those specified in this Scope of Work as mutually agreed upon. a. A Richland County demolition permit shall be purchased, posted and visible from the street PRIOR to beginning demolition. b. To be knowledgeable of all/current state, federal and Environmental Protection Agency (EPA) regulations and laws and to provide services accordingly. c. To ensure that all disconnections have been made and properly secured by contacting all utility providers. (water, sewer, electric, gas, cable, etc.…) Including the location of such utilities. Contractors will be responsible for repairing damaged utilities and cost associated with the damage. d. Verify that appropriate rodent control measures have been taken as per departmental and state regulations. e. If it is determined that a septic tank is located on the property it must be inspected by a SC DHES inspector to determine the proper method that will be used for removal/handling. f. No materials shall be salvaged, stored or accumulated in any area. g . Structure shall be checked by the contractor to ensure no one is occupying the structure prior to the start of demolition. Contractor will ensure there is no unauthorized entry into the structure during demolition. 2. The method of demolition shall be at the discretion of the contractor. However, contractor shall protect the surrounding properties from damage, erosion and dust pollution. a . Contractor shall use the best method for controlling erosion and sediment releases. b. Any damages caused by the contractor will be repaired and restored to the original goods or the acceptable condition of the owners of the surrounding properties, at the expense of the contractor. 3. Keep the construction site clean. Removal and proper disposal of all materials shall be done on a daily basis. 4. Cover and secure all loads prior to and during transport. 5. Demolish dwelling, clear grade, compact and seed property to where one could run a mower over the lot without dislodging rocks, stone or debris. Demolishing the existing structures including excavating all foundations, slabs, and/or footings and removing all surface pavement found upon private property. Must be complete within 30 days from receiving Order to Execute Demolition by Procurement. 6. Provide year, make and model of all vehicles that will be used to transport and dispose of debris. Also, contractor will provide the type of trailers that will be used. 7. Provide the name, address and phone number of an approved C&D Landfill that will be used to dispose of debris. 8. Provide copies of landfill slips to show debris was disposed of at said landfill. 9. Contractor must be able to respond to emergency calls within two hours once notified. 10. Contractor is responsible for keeping pedestrian passageway clear and free of debris at all times. 11. Ensure proper protection and safe passage ways are provided during demolition at all times. 12. Ensure address numbers are removed from buildings/structures to be demolished and replaced on a temporary fixture. 13. Ensure proper markings are displayed during the operation of powered mechanical equipment in the area where demolition service is being conducted. 14. Ensure all flammable goods are removed from the site. 15. Contractors may not store equipment of the property overnight unless written permission is provided by the Code Official. This will only be provided if it is Richland County property. 16. Pre-Demolition: a. The demolition contractor is responsible for obtaining all required permits prior to beginning any work. b. The Demolition Contractor will be required to identify and make-safe all utilities associated with the property. This includes, yet is not limited to: Marking easements and underground utilities. Removing utility meters. Capping wells, water, sewer, and septic lines to the mains. Disconnecting electrical and gas service and propane tanks. c. The County’s designee will perform a Pre-Demolition Inspection with the contractor to confirm that all utilities have been marked and disconnected and the site is ready for demolition. Failure to do so will be reported to Procurement for violation of Scope of Work. d. The Contractor shall be responsible to mobilize all equipment for demolition activities and be responsible for providing a DHES approved loading container to transfer the materials to a landfill. 17. Demolition: a. Proper Demolition of Residential Structures and disposal of all materials resulting from the demolitions which will include, yet is not limited to: Disposal of Household Hazardous Waste items per SC DHES and EPA regulations. Demolition Contractor will assume lead-based paint contamination INTRODUCTION Project Information Richland County (the County) is seeking electronic bids from qualified suppliers to provide residential demolition and debris removal services for two (2) locations: 7540 Fairfield Road and 7544 Fairfield Road, Columbia SC 29203 Richland County is located in the center of South Carolina and covers a total area of 756 square miles. The County surrounds the state capital city of Columbia, which is also the County seat. Established in 1785, the County has grown to become home to just over 400,000 residents, and represents a thriving business, industrial, governmental, and educational center. The County employs approximately 1765 people and operates a general fund budget in excess of $100 million dollars. The County is governed by an 11-member council, which in turn appoints an Administrator to handle daily operations and to provide professional expertise in government management. Under state law, the County is the primary governmental unit for the administration of law enforcement, justice, health, education, taxation, social service, library service, agricultural service, and the maintenance of public records. Timeline Release Project Date: November 5, 2026 Question Submission Deadline: November 19, 2026, 3:00pm Response Submission Deadline: December 7, 2026, 3:00pm Procurement Contact Yolanda Davis Contract Analyst davis.yolanda@richlandcountysc.gov Questions Vendors shall submit all inquiries regarding this bid via the County's eProcurement Portal, located at https://procurement.opengov.com/portal/richlandcountysc by 3:00 pm on Thursday, November 19, 2026 . Please note the deadline for submitting inquiries. All answers to inquiries will be posted on the county eProcurement Portal. Bidders may also click “Follow” on this bid to receive an email notification when answers are posted. It is the responsibility of the bidder to check the website for answers to inquiries. Addendum Vendors are required to register for an account via the county eProcurement Portal hosted by OpenGov. Once the bidder has completed registration, they will receive addenda notifications to their email by clicking “Follow” on this project. Ultimately, it is the sole responsibility of each bidder to periodically check the site for any addenda at https://procurement.opengov.com/portal/richlandcountysc . INSTRUCTIONS TO BIDDERS To be considered a timely filing, bids, and amendments thereto, or withdrawal requests must be submitted via OpenGov by the time advertised as the deadline for submissions. It is the vendor's sole responsibility to ensure that the bids and other documents are submitted at the time indicated in the bid document. The County will not accept liability for any incidental or consequential damages arising from or as a result of the electronic transmission of the bid submittal, addendums, or any other data hereunder. CORRECTION OF ERRORS ON THE BID TABLE: All prices shall be entered in OpenGov. Errors and corrections may be entered up until the deadline for submissions. No bid shall be altered or amended after specified time for opening. BIDDERS SCHEDULE: Enter all information, as applicable, and your bid price in the space provided on the bid form. NOTIFICATION: The bid tabulation will be posted as soon as practicable after opening. Notification of Intent to Award/Statement of Award will be posted in OpenGov. RIGHT TO PROTEST: Any prospective bidder, offeror, or contractor, who is aggrieved in connection with the solicitation of a contract shall protest in writing to the Procurement Director within ten (10) calendar days of the date of issuance of the Invitation to Bid, Requests for Proposals or other solicitation documents, whichever is applicable, or any amendment thereto, if the amendment is at issue. Any actual bidder, offeror, or contractor, who is aggrieved in connection with the intended award or award of a contract, shall protest in writing to the procurement manager within ten (10) calendar days of the notification of intent to award or statement of award. PROTEST PROCEDURE: A protest shall be in writing, submitted to the procurement director, and shall set forth the specific grounds of the protest with enough particularity to give notice of the issues to be decided. QUESTIONS REGARDING SPECIFICATIONS AND/OR THE BIDDING PROCESS: To ensure fair consideration for all bidders, the County prohibits any type of communications to or with any department, employee, or County official during the solicitation process, except as provided on the "Invitation For Bids" of the solicitation. This includes any communications initiated by a bidder to any County Official or employee evaluating or considering the bidder, prior to the time an award decision has been made public. Communications between the bidder and the County shall be initiated by the Procurement Office or the appropriate County representative in order to obtain necessary information or clarification needed to develop a proper and accurate evaluation of the bid. Any communications initiated by a bidder concerning the submitted bid shall be grounds for disqualifying the offending bidder from consideration for award of the bid and/or any future solicitations. It will be the sole responsibility of the bidder to contact the Procurement Office prior to submitting a bid to ascertain if any amendments or addendums have been issued in order to obtain all such documentation, and to return the executed documentation with their bid. Any question concerning this document, the specifications, or the bid process must be made in writing via the County's eProcurement Portal for this project located at https://procurement.opengov.com/portal/richlandcountysc/projects/321899 . WORK HOURS: The normal working hours per day will be limited from 7 AM to 7 PM Monday through Friday provided sufficient daylight is available. The Contractor shall not perform work on Holidays. The following days are recognized as holidays by the owner: New Years’ Day Martin Luther King Day Presidents Day Good Friday Memorial Day Juneteenth Independence Day Labor Day Veterans Day Thanksgiving Day Day after Thanksgiving Christmas Eve Christmas Day Day after Christmas When such recognized holidays fall on a Saturday or Sunday, the Owner may, at its discretion, declare the preceding Friday or following Monday as a holiday. In the event that the Governor of the State/Board of County Commissioners shall declare any day or days preceding or following a holiday as a holiday, the Owner may, at its discretion, also declare such day or days as holidays. GENERAL PROVISIONS BID EVALUATION Bids received will be evaluated by the Procurement Director or designee. However, based on bid total, final decision for bid award may rest with the Richland County Council. ESTIMATED QUANTITIES The Owner has endeavored to estimate the proposed quantities as accurately as possible using the latest information available for the project. Within fifteen (15) calendar days after the issuance of the Notice to Proceed, the Contractor shall provide written verification of the quantities. Failure to do so shall imply the Contractor's acceptance of the quantities. In addition, it will be the Contractor's responsibility to inform the Engineer/Inspector when any item of work (excluding lump sum items) is within 90% of the proposed quantity. To affect the increase, deletion, and/or substitution, a "no cost" or "cost" change order signed by the Contractor must be submitted to the Procurement Director by the engineer. No work shall be performed prior to approval of such change order. CONTINGENT ITEMS Construction Item(s) identified as being contingent on the "Summary of Quantities" sheets of the plans, in the column headed "Contingent" and/or listed herein are provided in the Contract for use as directed by the Engineer and shall be included as part of the proposal base bid unless otherwise specified. The quantities for these items are established for the purpose of obtaining a bid price and shall be included as part of the proposal base bid unless otherwise specified. The quantities for these contingent items may be increased or decreased without any adjustment to the Contract unit price bid or the contingent items may be deleted entirely from the Contract by the Engineer without negotiation. The Contractor will not be allowed to submit a claim against the Owner for any adjustment to the Contract unit price bid should the contingent items be increased, decreased or eliminated entirely. Payment for any contingent items used will be made on the basis of the quantities as actually measured. Materials, Construction Requirements, and Basis of Payment shall be as specified in the Specifications, Supplement to the Specifications, Interim Specifications or Addenda, Plans or Special Provisions. ABATEMENT OF WATER POLLUTION BY SEDIMENTATION The Contractor's attention is specifically directed to the fact that it is of the utmost importance during the life of this contract that control of water pollution due to sedimentation be accomplished as shown on the engineering drawings and/or in accordance with South Carolina D.H.E.C. requirements. The restrictions contained therein shall be strictly enforced and the Contractor is cautioned, therefore, to make every effort possible to comply with these regulations, and shall conduct his operations in such a manner as to keep to an absolute minimum amount of sedimentation introduced in to any stream or watercourse. CONTRACTORS OBLIGATIONS The Contractor shall and will, in good workmanlike manner, do and perform all work and furnish all supplies and materials, machinery, equipment, facilities and means, except as herein otherwise expressly specified, necessary or proper to perform and complete all the work required by this contract, within the time herein specified, in accordance with the Plans and Plan Drawings covered by this contract and any and all supplemental Plans and Drawings, and in accordance with the directions of the Engineer as given from time to time during the progress of the work. It shall furnish, erect, maintain and remove such construction plant and such temporary works as may be required. The Contractor shall observe, comply with, and be subject to all terms, conditions, requirements, and limitations of the Contract and Specifications, and shall do, carry on, and complete the entire work to the satisfaction of the Engineer and the Owner. SUPERINTENDENCE BY CONTRACTOR At the site of work, the Contractor shall employ a superintendent or foreman who shall have full authority to act for the Contractor. It is understood that such representative shall be acceptable to the Engineer. ENGINEER AUTHORITY The Engineer shall give all orders and directions contemplated under this Contract and Specifications relative to the execution of the work. The Engineer shall determine the amount, quality, acceptability, and fitness of the several kinds of work and materials which are to be paid for under the construction thereof. The Engineer's estimates and decisions shall be final and conclusive, except as herein otherwise expressly provided. In case any questions shall arise between the parties hereto relative to said Contract or Specifications, the determination or decision of the Engineer shall be a condition precedent to the right of the Contractor to receive any money or for work under Contract affected in any manner or to any extent by such question. The Engineer shall decide the meaning and intent of any portion of the Specifications and any Plan or Drawings where the same may be found obscure or be in dispute. Any differences or conflicts in regard to their work which may arise between the Contractor under this Contract and other contractors performing work for the Owner shall be adjusted and determined by the Engineer. INSPECTION AND INSPECTOR AUTHORITY The authorized representatives and agents of the Owner shall be permitted to inspect all work, materials, payrolls, records of personnel, invoices materials and other relevant data and records. Inspectors, employed by the Engineer, shall be authorized to inspect all work done and materials furnished. Such inspection may extend to all or part and to the preparation or manufacture of the materials to be used. An inspector or inspectors will be stationed on-site and will report to the Engineer as to the progress of the work and the manner in which it is being performed; also to report whenever it appears that the materials furnished and work performed by the Contractor fail to fulfill the requirements of the Specifications and Contract; and to call to the attention of the Contractor any such failure and other default; but no inspection nor any failure to inspect, at any time or place, however, shall relieve the Contractor from any obligation to perform all of the work strictly in accordance with the requirements of the Specifications. In case of dispute arising between the Contractor and any inspector as to the materials furnished or the manner of performing the work, the inspector shall have the authority to reject materials or suspend the work until the question at issue can be referred to and decided by the Engineer. The inspectors shall perform such other duties as are assigned to them. They shall not be authorized to revoke, alter, enlarge, or release any requirements of these Specifications, not to approve or accept any portion of work, not to issue instructions contrary to the Plans and Specifications. Inspectors shall in no case act as foremen to perform other duties for the Contractor, nor interfere with the m

Published attachments
Addenda and notices
  • Official Notice #1: Notice of Cancellation for Demolition and Debris Removal Service for 7540 Fairfield Road and 7544 Fairfield Road · 1

    See Notice of Cancellation

Public questions and answers
  • Is county perform any testing regarding asbestos. To finishing the project what is the final inspection required.

    Asbestos testing is not required for residential structures. Final inspection requirements are listed in the scope of work.

  • 1. The property addresses are zoned commercial; can you confirm if this is a residential demolition for permitting purposes? 2. Does an asbestos survey exist and who is responsible for testing payment? 3. Does the surrounding fence need to be restored or removed? 4. Are bonds required and at what amounts? I see the consent-of-surety closeout form.

    1. Yes, these are residential structures for permitting purposes. 2. Asbestos survey is not needed for residential structures. 3. Fences surrounding structures may be temporarily removed to complete the demolition. Fences should be restored to their original condition immediately following the demolition of the structure. Fences that are damaged during the demolition shall be repaired/replaced by the contractor. 4. Bonds are not required.