Sarasota County is requesting quotes from bidders to provide all labor, supervision, equipment, tools, materials, and incidentals necessary to evaluate and perform hand clearing, sediment removal, and drainage restoration. The purpose of this project is to remove accumulated sediment and obstructions restricting drain flow, restore the ditch bottom to the appropriate elevations, and reestablish positive drainage to reduce backup. Remove accumulated sediment, restore drainage flowline, protect existing trees and roots, maintain existing drainage conditions, remove and dispose of materials, and restore the work area. Please refer to Scope of Work for exact details. Introduction Summary Background Contact Information Timeline Quick Quote Requirements and Attachments Insurance Requirements Please see the attached Sarasota County insurance requirements with the Certificate Holder address for Sarasota County Transportation (attachment G). QQ Pricing Table Line item quantities represent estimated needs. Sarasota County may at its sole discretion purchase additional quantities at the unit price quoted during the 30 day period following award of this Quick Quote. If the vendor is willing to honor unit prices after the initial 30 day period, the County may purchase additional quantities for up to one year following award of this Quick Quote. Under no circumstances may total purchases exceed $50,000.00. Quick Quote Vendor Questionnaire General Terms and Conditions of Purchase Orders THE FOLLOWING TERMS AND CONDITIONS APPLY TO ALL PURCHASE ORDERS FOR SARASOTA COUNTY. WHEN SOLICITATION OR CONTRACT TERMS, CONDITIONS AND SPECIFICATIONS DIFFER FROM THOSE SHOWN ON THE PURCHASE ORDER, THE SOLICITATION/CONTRACT SHALL TAKE PRECEDENCE OVER THE PURCHASE ORDER. Revised 07/01/2026 The term “Vendor” shall mean the party furnishing the goods, materials, equipment and/or services. The term “County” shall mean Sarasota County. This Purchase Order contains the complete and final agreement between the Vendor and the County to buy the materials/services at the prices stated. No amendments will be made without specific written authorization (change order) issued by the County’s Procurement Official. Vendor is responsible for full compliance with all applicable local, state and federal laws, ordinances and regulations. County may require proof of such compliance. Vendor shall not assign, or otherwise dispose of its responsibilities under this Purchase Order without prior written approval of the County which may be withheld in the County’s sole discretion. All materials must be shipped F.O.B. Destination unless otherwise specified. County will not pay freight or express charges, except by previous agreement. Purchase Order number must appear on all invoices, packages, bills of lading, correspondence and any other documents pertaining to the order. Time is of the essence for Vendors performance of its obligations under this Purchase Order. No delays in shipment of material or rendition of services will be permitted except as authorized by the County in writing. The County reserves the right to reject receipt of shipment and cancel this Purchase Order if Vendor is unable to provide delivery as required. Materials/services are subject to County inspection and approval. The County may return materials not meeting specifications at the Vendor’s expense and risk. If applicable, Vendor shall provide County with all safety data sheets (SDSs) upon delivery of materials. This Purchase Order and the rights and obligations of the County and Vendor shall be governed by the laws of the State of Florida, without regard to its conflict of law principles. The exclusive venue for any legal or judicial proceedings in connection with the enforcement or interpretation of this Purchase Order shall be in the Twelfth Judicial Circuit in Sarasota County, Florida. County and Vendor hereby waive any right to trial by jury for disputes arising out of this Purchase Order. This Purchase Order is subject to the availability of lawfully budgeted and appropriated funds by the County. Vendor shall save, defend, indemnify and hold harmless Sarasota County Government from and against any and all claims, actions, damages, fees, fines, penalties, defense costs, suits or liabilities which may arise out of any act, neglect, error, omission or default of the Vendor arising out of or in any way connected with the Vendor or subcontractor’s performance or failure to perform in accordance with this Purchase Order or any related contract. Vendor shall maintain insurance acceptable to the County for this Purchase Order and shall submit proof of such insurance to the County upon request. Insurance requirements are available at https://www.scgov.net/government/procurement. All invoices must be mailed to the Sarasota County Finance Department, Clerk of the Circuit Court, P.O. Box 8, Sarasota, FL 34230-0008. Invoices must contain the Purchase Order number. Invoices containing deviations or omissions will be returned to the Vendor for correction and resubmission. The County shall pay Vendor through payment issued by the Clerk of the Circuit Court in accordance with Section 218.70 et seq., Florida Statutes, Local Government Prompt Payment Act, upon receipt of Vendor’s properly submitted invoice. Vendor shall be required to confirm the employment eligibility of all employees through participation in E-Verify or an employment eligibility program approved by the Social Security Administration and will require its subcontractors to confirm employment eligibility. Beginning January 1, 2021, Vendors are required to comply with §448.095, F.S., and register and use the E-Verify system for all new hires. In accordance with §448.095, F.S., the County shall terminate a Purchase Order with any Vendor where the County has a good faith belief that the Vendor has knowingly violated §448.09(1), F.S. In that event, the County shall not contract with the Vendor for at least one year after such termination. Sarasota County is exempt from paying state and local tax when payment is made directly by the County (Section 212.08(6), Florida Statutes). Department of Revenue Certification No. 85-8012515235C-5. Vendor travel expenses which are approved for reimbursement by the County shall be subject to the limitations set forth in Section 112.061, Florida Statutes and Sarasota County Resolution #2016-170 or current County resolution related to reimbursement of travel expenses. Unless otherwise stated in this Purchase Order, in addition to any warranty implied by law or fact, and any other express warranties, the Vendor expressly warrants all items to be free from defects (whether patent or latent) in title, design, workmanship and materials, to conform strictly to applicable specifications, drawings, approved samples, if any; and to be fit and sufficient for the purpose intended and to be merchantable. Such warranties, together with all other services warranties of the Vendor, shall run to the County. All warranties shall survive inspection, testing, acceptance of, and payment by the County. The County may terminate this Purchase Order at any time upon written notice to the Vendor. The County shall pay to the Vendor and the Vendor shall accept as full payment for its performance under this Purchase Order, a sum of money equal to the work completed or the products provided under this Purchase Order. §287.135, F.S., prohibits the County from contracting with companies for goods or services that are on the Scrutinized Companies or other Entities that Boycott Israel List, or with companies that are engaged in a boycott of Israel, and from contracting with companies for goods or servi
Published attachments
Public questions and answers
References (Scope Section 2, Experience) — Kennedy South Group LLC would perform this work through a qualified subcontractor that specializes in ditch and drainage work. May the three required references demonstrating experience with similar services be those of the subcontractor who will actually perform the work, provided the subcontractor is identified in the response?
The references must demonstrate experience with similar work performed directly by the prime contractor.
The scope specifies hand clearing and hand removal of accumulated sediment, with protection of existing trees and root systems and no cutting of major roots. May mechanical equipment (for example, a mini-excavator working from the bank or from access points) be used for sediment removal in portions of the ditch where access permits, provided trees and root systems are protected and no major roots are cut? Or must all clearing and sediment removal be performed by hand along the entire approximately 1,700 linear feet?
Mechanical equipment is permitted and encouraged wherever access allows. However, due to the limited access throughout much of the ditch, we anticipate that a significant portion of the work will need to be completed by hand. Additionally, in certain sections, existing tree roots are contributing to the drainage restrictions. These roots will need to be removed to reestablish the proper flowline and improve drainage.
Is an online RSVP required for the mandatory November 16 pre-bid walkthrough, or may vendors sign in on site?
There isn't an online RSVP. Vendors will sign on on site.
Is there a bond requirement for this project?
No.
Has the accumulated sediment been tested or characterized for disposal?
The accumulated sediment has not been tested. However, the project is not located near any known contaminated sites, so we do not need testing.
Is there an approved disposal facility designated by the County, or will the contractor be responsible for identifying an acceptable facility? What disposal facility is currently being used?
If needed, the County can provide a designated disposal location for the excavated material clean dirt only no trash or debris accepted.
Can the County clarify the extent of restoration required following sediment removal? Will restoration include grading, sod installation, erosion control measures, or other improvements?
Regarding restoration, we would typically require sod installation following excavation. However, due to the conditions at this location, we believe sod would have a low chance of successfully establishing. For this project, we are only requiring the contractor to restore the drainage swale to its proper grade and elevations. Once grading is complete, the area can be left as bare soil without sod installation.
If additional sediment quantities, buried obstructions, or unforeseen conditions are encountered, will the County allow for additional compensation through an approved change order?
No, we will have to stay with the quoted amounts from this QQ
Will Sarasota County provide the existing and proposed ditch-bottom elevations, benchmarks, or an approved drainage profile? Is the contractor responsible for obtaining a survey, or will the County provide the necessary elevation information to establish and verify the required drainage grades?
Sarasota County requires the ditch to be restored to its original elevation to ensure proper water flow. The contractor is not required to provide a licensed surveyor. Upon completion, the County will inspect and survey the ditch to verify that all high spots have been removed, and proper drainage flow has been restored.
During the site walkthrough, we observed several large trees within or immediately adjacent to the drainage ditch that appear to obstruct the required drainage flowline. Does Sarasota County intend to remove these trees separately, or is the contractor expected to include removal of large trees, including their root systems, within the quoted scope of work?
Sarasota County does not intend to remove the trees, nor is the contractor required to include tree removal within the quoted scope of work. Only roots located within the drainage flowline may be removed with prior County approval, provided their removal does not compromise the health or stability of the trees.
Can Sarasota County provide documentation or a survey identifying the boundaries of the existing drainage easements along the approximately 1,700-foot project area, so the contractor can determine the limits within which work and equipment access are permitted?
A survey done in 2016 will be provided to the winning bidder.
has a decision been made concerning the trees in question? one being removing the roots possibly killing the trees. and concerning the large tree in particular, removing the whole root system will not only kill that tree but weaken its stability considerably. are trees to be removed in house or will that be the contractors responsibility?
Sarasota County does not intend to remove the trees, nor is the contractor required to include tree removal within the quoted scope of work. Only roots located within the drainage flowline may be removed with prior County approval, provided their removal does not compromise the health or stability of the trees.
OpenGov categories
- 02059 · Land Levelers
- 91141 · C.I.P., Landscaping
- 91187 · Storm Drainage
- 91219 · Clearing and Grubbing Services
- 91223 · Construction, General (Backfill Services, Digging, Ditching, Road Grading, Rock Stabilization, etc.)
- 91244 · Excavation Services
- 91368 · Maintenance and Repair, Canal
- 96833 · Ditch Maintenance
- 96834 · Dredging Services
- 96873 · Storm Drain Cleaning, Repair, and Sludge Removal Services