Washington County is seeking a contractor to remove trees and shrubs in the Right-of-Way at 3 different upcoming project sites. Work must be complete by February 28, 2027, unless otherwise specified. Quote Form Quotes will include a $5000 extra work contingency. Quotes for each site will be a lump sum for the site as a whole, not a per-tree quote. Extra Work Contingency Removal of all trees, NW Thompson Road Removal of all trees, SW Denney Road Removal of all trees, SW Kinnaman Road Project Details DESCRIPTION OF WORK Remove all trees as shown on the attached plan sheets. There are 251 trees in total, at 3 different locations. Size and number of trees to be verified in the field by the Contractor. Trees shown on the plans sheets are 6” diameter and larger trees. Contractor work includes cutting, removal and clearance of ALL trees and shrubs within the designated road Right-of-Way and easements (including smaller diameter trees). All stumps to be cut approximately 6 inches above existing ground level, unless otherwise noted on the plan sheets. Note: road Right-of-Way/easement lines are shown on plan sheets. All removal work (falling, cutting, access for vegetation removal shall occur within the designated easements. No access onto or within private property is authorized by the County. No work is allowed in-water. Remove all debris on a daily basis. All debris will be removed from the project site by the Contractor for appropriate disposal. All exposed soil must have ground cover protection measures daily (within provided road Right-of-Way/easements), as needed. Perform extra work as directed by the County. Work shall include temporary removal and reinstallation of existing fences (within provided road Right-of-Way/easements), as needed. GENERAL PROVISIONS Work must be complete by February 28, 2027 (including all clean-up work), unless otherwise directed, assuming: A contract is signed by all parties A traffic control plan has been submitted to and approved by the County Perform no construction activity on Saturday, Sunday or between the hours of 7:00 pm and 7:00 am on other days, without the approval of the Engineer. Contractor shall provide adequate lag time for anticipated winter weather conditions (i.e. snow or high water conditions). No time extensions of work beyond the designated completion date will be considered. Quotes shall include $5,000.00 for extra work. All extra work must be authorized by the Project Manager (listed below). This amount is not guaranteed to be utilized by the County, but is available for additional work, if required. The contractor will invoice the County for work performed when all the tasks are completed. The County will issue payment no later than one month from approval of invoice. TRAFFIC CONTROL Road Closures are not authorized for the above work. Single lane closures are allowed Monday-Friday 9:00 am to 3:30 pm on arterial roads. Monday-Friday 8:30 am to 4:00 pm on collector roads. During any lane closure, access priority shall be given to school buses, TriMet buses and emergency vehicles. Maintain access to businesses and residences at all times. Coordinate with property owner and/or resident if access is to be temporarily restricted. Contractor will provide all required traffic control per MUTCD Contractor will provide traffic control plans for County approval prior to start of work. Traffic control plans shall be consistent with Oregon Standard Drawing TM-850 (2 lanes, 2-way roadway, 1 lane closure). Implementation of the traffic control plan will be part of the lump sum bid and shall include Temporary Protection and Direction of Traffic (TP&DT) devices as required. BOLI WAGE RATES This Project is subject to BOLI Wage Rates: https://www.oregon.gov/boli/WHD/PWR/Pages/pwr_book.aspx The applicable publications are: October 5, 2024 - Definitions of Covered Occupations for Public Works Contracts in Oregon July 5, 2026 - Prevailing Wage Rates for Public Works Contracts in Oregon October 5, 2026 - PWR Apprenticeship Rates October 5, 2026 - PWR Amendment A copy of these rules may be requested by calling the Bureau of Labor and Industries directly. Bureau of Labor and Industries – (971) 673-0838 SITE DETAILS For NW Thompson Road: The Project Manager is Ben Lively - 503-846-7828 Thompson Road is an Arterial Road There are 197 trees to be removed on this site. For SW Denney Road: The Project Manager is Naomi Vogel - 503-846-7914 Denney Road is a Collector Road There are 41 trees to be removed on this site. Work at this site cannot begin before December 15, 2026. Work at this site must be completed before January 15, 2026 For SW Kinnaman Road: The Project Manager is Ryan Kruger - 503-846-7827 Kinnaman Road is a Collector Road There are 13 trees to be removed on this site. See tree protection notes. Coordinate with project manager prior to removal. QUESTIONS Submit all questions through this OpenGov solicitation. Quotes will only be accepted via the OpenGov solicitation. Quotes are due no later than November 6, 2026 . Introduction Summary General work description Background Contact Information Timeline Washington County reserves the right to modify this timeline at the County’s discretion without notice. Legal Advertisement Legal Ad WASHINGTON COUNTY, OREGON REQUEST FOR QUOTE No. 2026.099-ITQ Early Tree Removal for Capital Project Services The Quote documents will be available at www.WashCoPurch.com/biz Respondents are responsible for checking the site for any addenda to the quote documents before submitting their quotes to the site. Quotes are due no later than 2:00 pm on Friday, November 6, 2026 ; the system does not allow for late submissions. Quotes must contain a statement as to whether the bidder is a resident bidder, as defined in ORS 279A.120(1)(b). The County may reject any quote not in compliance with all prescribed public bidding procedures and requirements, and may reject for good cause any or all quotes upon a finding of the County it is in the public interest to do so. Washington County reserves the right to reject any and all responses and to waive any and all informalities in the best interest of the County. Respondents are solely responsible for ensuring receipt of their quote by the Procurement Division. Respondents must conform to the requirements of these quote documents and all related, applicable laws. The County does not intend to pre-qualify any respondents for this project. All quotes submitted for this project will be considered provided that they meet the criteria set forth in the quote documents with respect to submission in a timely manner, bonding, and all other applicable requirements. Dated this Monday, October 26, 2026 Kiersten Vanderhoof Senior Procurement Analyst (503) 846-3585 Pricing Table The hourly rates specified by the responder shall include labor, consumable materials and supplies, necessary or incidental costs and all direct and indirect administrative costs. These incidental supplies and materials include such items as fasteners, adhesives, hardware and other small expense items which are difficult to track or bill through any other process. All items must have a price or percentage in order to be seen as responsive. The County considers a line marked as $0 to be the price quoted for that line item. If there is a NO BID column then choosing that option is acceptable. Instructions to Bidders DEADLINE DISCLAIMER It is the responsibility of the bidder to upload and submit electronic bids before the deadline date and time approaches as posted on the County's Procurement Portal. Allow for a sufficient amount of time for the bid entry/document upload process in order to ensure timely submission. Some people are experiencing problems with the Internet, so make sure that all documents are uploaded as soon as possible well in advance of the deadline. The County's Procurement Portal system will close promptly at the deadline date and time…no exceptions are allowed. PUBLIC BID OPENING A Public Bid Opening is not required for purchases under $250,000. RIGHTS OF THE COUNTY The County expressly reserves the following rights: To waive any irregularities in the quotes submitted. To base awards with due regard to price, delivery, compliance with specifications, and other such factors as may be necessary and in the public interest in the circumstances. To make awards to any respondent whose quote, in the opinion of management and the Board, is the lowest responsible quote. To cancel the procurement or reject any or all quotes, or selected portions thereof, in accordance with ORS 279B.100. Under no circumstances shall the County be responsible for, nor shall it reimburse, any costs associated providing a bid for this solicitation. To negotiate final contract terms and conditions to the fullest extent allowed by the law and as in the best interests of the County. Acceptance of an offer is subject to budget approval and budgetary constraints as determined by the County. EXPECTATIONS OF RESPONDER 1 If this solicitation requires response on all items, failure to do so will disqualify the quote. If quoting on all items is not required, responders should check the No Bid box for any item on which no price is submitted. 2 To examine all specifications, instructions, terms and conditions thoroughly. 3 To provide for appropriate insurance as required. 4 To comply with all Federal, State and County laws, ordinances, and rules. 5 Responder will comply fully with specifications as attached for the agreed quote and/or resulting contract, especially where materials and work are involved. 6 To clean up all debris and remove from the site as specified. 7 Upon completion of the resulting contract and/or delivery and installation, to pass a good, free and clear title for goods and services rendered to the County. Such goods and services shall be free of all claims, mechanic’s liens, subcontractor judgments and other encumbrances which might cloud the County’s title to said goods and services. 8 That they have met any and all registration or license requirements where required for contractors as set forth in the Oregon Revised Statutes. 9 To accept any claims, liens and demands to indemnify the County and preserve harmless the County or the property the entire time of equipment installation and/or resulting contract duration. 10 To meet the highest standards prevalent in the industry or business most closely related to the goods or services of this bid. 11. To understand that the successful bidder will be held to all County policies and procedures. CHANGES The County, by written order, may make changes in the following areas: 1 Drawings, design, and/or specifications where the product or service is a special order or separate project for the County. 2 The method of shipment or packaging. 3 The place of delivery and installation (if required). 4 If said change(s) increases or decreases the net cost of the product/service, the County and the responder agree to negotiate an equitable adjustment. 5 The contractor shall not make any changes in the specifications or other requirements without the express prior written consent of the County. Any proposed changes shall be presented in writing to County management not less than fourteen (14) calendar days prior to the proposed effective date of said change. 6 The additions of similar or related work or materials or unidentified needs. LUMP SUM QUOTES This contract uses lump sum quotes for each site. Each line item in the Pricing Table shall be a lump sum cost for the removal of all trees and other labor at the site, as necessary and specified. The lump sum quotes specified by the responder shall include labor, consumable materials and supplies, necessary or incidental costs and all direct and indirect administrative costs. These incidental supplies and materials include such items as fasteners, adhesives, hardware and other small expense items which are difficult to track or bill through any other process. LOW TIE QUOTES 1 Low tie quotes are subject to the Oregon preference contained in ORS 279A.120: “For purposes of awarding a public contract, a contracting agency shall give preference to goods or services that have been manufactured or produced in this state if price, fitness, availability and quality are otherwise equal.” 2 Low tie quotes that remain after application of the statutory Oregon preference shall be awarded according to the following sequence: A Preference shall be given to the responder whose principal offices or headquarters are located in Oregon. B. If a tie still remains after applying (A) above, award shall be made by drawing lots among any tied Oregon responders. Such responders shall be given notice and an opportunity to be present when lots are drawn. C. If none of the tied responders is located in Oregon, award of the contract shall be made by drawing lots among the tied responders. GUARANTEE and DAMAGE CLAUSE 1 Contractor agrees to repair any failures due to inferior workmanship and/or materials without additional expense to the County. 2 Contractor shall be responsible for redecorating, restoring, or otherwise repairing any portion of the County's premises, facilities, or any County owned properties or right-of-ways which are damaged by the contractor and its agents in the case of any work related to its obligation under this contract. 3 Contractor agrees to repair any avoidable damage to existing materials, surfaces and equipment caused during the execution of the work, without additional expense to the County. PUBLIC CONTRACTING STATUTES 1 This solicitation and the resulting contract are governed by Oregon Law and Washington County Procurement Rules. The provisions of Oregon Revised Statutes 279B.220 through 279B.235, Public Contracts, as applicable are incorporated herein by reference. Any Contractor accepting a purchase order from the County and/or executing a contract with the County for the delivery of materials and/or services agrees to comply with said provisions. 2 Oregon Revised Statutes can be obtained from: Legislative Counsel Committee, S101 State Capitol, Salem, OR 97310-0630. Phone (503) 378-8146 or on line at: http://www.leg.state.or.us/ors/home.html 3 Washington County Procurement Rules can be obtained from: Washington County Procurement Division, 180 East Main St., Ste 226, Hillsboro, OR 97123, phone (503) 846-8737 or email wcpurchasing@co.washington.or.us. QUESTIONS, INTERPRETATIONS, and ADDENDA 1. If necessary, interpretations or clarifications in response to questions will be issued by addenda. Questions received after the deadline to submit questions may not be answered unless the County determines, in its sole discretion that it is in its best interests to do so. Oral and other interpretations or clarifications will be without legal effect. 2. Any amendment(s) to or error(s) in the document called to the attention of the County will be added to or corrected by written addendum and posted to the County's Procurement Portal. The County may also issue addenda to modify the proposal documents, as it deems advisable. 3. Receipt of addenda must be acknowledged. 4. Proposers shall be solely responsible to check for and download all addenda, if any, from the County's Procurement Portal prior to submitting their proposals. AWARD OF CONTRACT The County intends to award the quote to the lowest responsible responder who has met all the requirements of the specifications, and who is not disqualified or debarred under Washington County Rules of Procurement or Oregon State Statutes. The County reserves the right to reject any and/or all quotes in whole or in part and to not contract for any individual categories. County reserves the right to award contracts by lump sum, individual line items, groups of items, or categories whichever is determined solely by the County to be in the best interest of the County. Determination of lowest quote will be based on Award will be to the lowest responsive, responsible responder based on a total lump sum basis., One contract will be awarded for all items. Responder must quote all items listed on the quote table to be considered responsive. Determination of lowest quote will be based on the Total Quote Price. . CONTRACT Initial contract term will be one year, with the option to renew for up to a total of five years. The term of the contract resulting from this quote shall not exceed five years. The contract that will be executed for this solicitation will be a standard Washington County Contract, which may incorporate terms and conditions from this solicitation document, as well as from the responder’s response. A sample contract is attached. Potential responders should review this contract to ensure they can meet the terms and conditions of this contract prior to submitting a quote. Form of Contract A copy of the County's contract that the County expects the successful firm or individual to execute is attached. The contract will incorporate the terms and conditions from this RFP document, attachments provided, and the successful proposer's response documents. Firms taking exception to any of the contract terms should indicate the same by uploading in the Vendor Submission or their exceptions will be deemed waived Payment Payment shall be made upon submission of invoice and any required supporting documentation after final acceptance of each phase and/or monthly progress payments. Contractor shall invoice the County no later than thirty (30) days following completion of work. The County will pay the invoice within 30 days after approval of the invoice by the contract administrator. INSURANCE REQUIREMENTS The insurance requirements for this contract are outlined in the attached Insurance Requirements Summary Form. Oregon Corporate Activity Tax ("CAT") In 2019 Oregon adopted a Corporate Activity Tax (“CAT”) applicable to all types of business entities. The legislation accomplishes the following: a. Establishes a "Fund for Student Success" that is separate and distinct from the state's general fund b. Adopts a new Corporate Activity Tax (CAT) imposed on all types of business entities The CAT is in addition to the state's current corporate income tax. The CAT is imposed on businesses for the privilege of doing business in this state. It is measured on a business's commercial activity, which is the total amount a business realizes from transactions and activity in Oregon. The CAT is applied to taxable Oregon commercial activity in excess of $1 million. Any costs relating to Oregon’s Corporate Activity Tax will not be reimbursable under Cost of the Work. Attachments Vendor Questionnaire Please note the system will accept Google Docs or Google Pages, but they are not readable by the County. DO NOT upload your response using a Google product.
Published attachments
Addenda and notices
Addendum #1 · 1
Please use the See What Changed link to view all the changes made by this addendum. The revised plan sheet is attached.
Official Notice #1: Notice of Intent to Award · 1
See Attached.
Public questions and answers
Where is the exact location of the 3 sites
The "ETR" plan sets located under Attachments will display the locations of the sites as well as the exact locations of the trees to be removed.
Are the trees marked with "X" but not highlighted part of this bid?
Correct. The number of trees highlighted on each sheet should correspond to the number called out in the text box on each sheet.
Do you have a main document for the RFQ? All I see are attachments on the OpenGov website.
See the "Project Documents" tab on this OpenGov solicitation.
Specifically on the Thompson rd portion. Will clearing all brush and trees to the ROW other than the highlighted ones be required in the bid. no survey stakes designate that line. This mostly concerns the eastern portion from Permian westward to 138+00
Only trees marked in the provided plans for removal should be removed.
Is there any material from the trees that can be left onsite after removal. For example: wood chips, logs, grindings, etc.
Debris must be removed from the project site. However, there is a chance that that can be negotiated after contract award.
Has each site gone through minimum approach distance inspection by the appropriate utility companies? Will the power lines and other utilities be in the current set up during the project window, or should we expect better/worse access when it comes time to execute on the contract?
On Kinnaman and Thompson Roads, utility relocations will occur after tree removal. No changes are anticipated at these sites prior to tree removal. For Denney, the utilities (PGE) will remove their required trees in December and relocations will occur in January. This is subject to change, however.
Are the sidewalks on Thompson usable for machinery?
No representation is made regarding the load-carrying capacity of the existing sidewalks. Contractors shall determine the suitability of the sidewalks for their proposed means and methods and shall be responsible for any damage caused by their operations.
Will the trees be flagged at anytime before or after the contract is award at any of the locations? Having the plans in the field didn't help for some of the locations, the correct trees were still hard to confirm.
Trees can be marked prior to removal. The selected contractor should coordinate with the project manager for each site.
Have the residents along the project sites been notified of this project and aware of the disturbance? If we're able to community with homeowner's and gain their direct permission to access their property for any of the work is that acceptable?
Residents along the roadway at each site will be sufficiently notified before the start of on-site activities. All work performed under this contract will occur in the public Right-of-Way or temporary construction easement. Generally, it is not acceptable to contact private property owners or gain access to the property without first contacting the Project Manager. The contractor should contact the PM prior to any engagement with the property owners. On Kinnaman Road, there is one property that will require coordination with the property owner and the involvement of the County’s ROW staff. This property has a radio tower and fence that may be impacted by the tree removal occurring in the ROW. That location is called out in the plans.