Eureka Canyon Road PM 8.11 and 8.39 Storm Damage Repair Projects

Description

The County of Santa Cruz, Department of Community Development & Infrastructure is accepting sealed bids for the Eureka Canyon Road PM 8.11 and 8.39 Storm Damage Repair Projects Bid opening will occur on Thursday, February 4, 2027 no later than 2:00 pm and soon thereafter, will be publicly opened and read. Eureka Canyon Road PM 8.11 Storm Damage Repair Project CONSTRUCTION AREA SIGNS TRAFFIC CONTROL SYSTEM TEMPORARY RAILING (TYPE K) TEMPORARY CRASH CUSION JOB SITE MANAGEMENT PREPARE WATER POLLUTION CONTROL PLAN TEMPORARY HIGH-VISIBILITY FENCE INVASIVE SPECIES CONTROL CLEARING AND GRUBBING ROADWAY EXCAVATION STRUCTURE EXCAVATION (SOLDIER PILE WALL) STRUCTURE BACKFILL (SOLDIER PILE WALL) CONCRETE BACKFILL (SOLDIER PILE WALL) LEAN CONCRETE BACKFILL DEBRIS REMOVAL/CLEAN DITCH FIBER ROLLS HYDROSEED CLASS 2 AGGREGATE BASE HOT MIX ASPHALT (TYPE A) COLD PLANE ASPHALT CONCRETE PAVEMENT PLACE HOT MIX ASPHALT DIKE (TYPE C) PLACE HOT MIX ASPHALT DIKE (TYPE F) EARTH RETAINING STRUCTURE (GUARDRAILING) STEEL SOLDIER PILE (HP 12 X 84) 30" DRILLED HOLE TIMBER LAGGING CLEAN AND PAINT STEEL SOLDIER PILING & STRUCTURAL STEEL MIDWEST GUARDRAIL SYSTEM (STEEL POST) ALTERNATIVE IN-LINE TERMINAL SYSTEM (TL-2) FILTER FABRIC MOBILIZATION Eureka Canyon Road PM 8.39 Storm Damage Repair Project CONSTRUCTION AREA SIGNS TRAFFIC CONTROL SYSTEM TEMPORARY PAVEMENT MARKING (PAINT) PORTABLE DELINEATOR PORTABLE SIGNAL SYSTEMS (EA) TEMPORARY RAILING (TYPE K) TEMPORARY CRASH CUSHION JOB SITE MANAGEMENT PREPARE WATER POLLUTION CONTROL PROGRAM INVASIVE SPECIES CONTROL TEMPORARY HIGH-VISIBILITY FENCE CLEARING AND GRUBBING (LS) ROADWAY EXCAVATION STRUCTURE EXCAVATION (SOLDIER PILE WALL) STRUCTURE BACKFILL (SOLDIER PILE WALL) CONCRETE BACKFILL (SOLDIER PILE WALL) LEAN CONCRETE BACKFILL DEBRIS REMOVAL/CLEAN DITCH FIBER ROLLS HYDROSEED CLASS 2 AGGREGATE BASE (CY) HOT MIX ASPHALT (TYPE A) COLD PLANE ASPHALT CONCRETE PAVEMENT TIEBACK ANCHOR ASSEMBLY (COMPLETE-IN-PLACE) STEEL SOLDIER PILE (HP 12X84) 24" DRILLED HOLE STEEL WALER (COMPLETE-IN-PLACE) TIMBER LAGGING CLEAN AND PAINT STEEL SOLDIER PILING AND WALERS GABION MIDWEST GUARDRAIL SYSTEM (8' POST) ALTERNATIVE IN-LINE TERMINAL SYSTEM (TL-2) MOBILIZATION Project Details Proposal Instructions Bidders shall create a free of charge account via the online procurement portal, OpenGov Procurement by signing up at https://procurement.opengov.com/signup . For additional information on account registration, see https://opengov.my.site.com/support/s/ Once account registration is completed, browse back to this page, https://procurement.opengov.com/portal/santacruzcounty , click on the “ Eureka Canyon Road PM 8.11 and 8.39 Storm Damage Repair Projects ”, "Submit Response", and follow the instructions to submit the electronic bid. Only electronic proposals will be accepted. Proposal forms for this work must be uploaded via the online procurement portal, OpenGov Procurement. Copies of the forms are included in a separate book entitled: Book 1 of 2 Bid Book For Construction of Eureka Canyon Road PM 8.11 and 8.39 Storm Damage Repair Projects Cashier's check or certified check, payable to the order of the County of Santa Cruz, of not less ten percent (10%) of the bid submitted, payable to the County of Santa Cruz and signed by the bidder as well as a corporate surety, shall accompany the bid. Bidder’s bonds shall be issued by a corporate surety duly admitted and authorized to issue bonds and undertakings by the State of California. Scan and upload a copy of your bid bond/cashier's check via the online procurement portal, OpenGov. No later than 4 p.m. on the 5th business day after bid opening, please mail the original Proposal forms, remaining Proposal forms due as stated in Section 2, and the bid bond/cashier's or certified check to the Contract Analyst , Rosa Ortiz ; Attn: Rosa Ortiz County of Santa Cruz, Department of Community Development & Infrastructure, Public Works Bid Proposal for Eureka Canyon Road PM 8.11 and 8.39 Storm Damage Repair Projects 701 Ocean Street, Room 410 Santa Cruz, CA 95060 Any questions concerning the bid process, required submittals, evaluation criteria, bid schedule, and selection process should be sent through OpenGov. General Work Description The project is located in the County of Santa Cruz as follows: In the unincorporated area of the County of Santa Cruz, along Eureka Canyon Road at Post Mile (P.M.) 8.11 and 8.39 Work includes storm damage repair. Major work includes, but is not limited to: Construction of soldier pile retaining walls with tiebacks Backfill wall and compact Reconstruct Roadway Drainage Improvements Install Midwest Guardrail System Erosion control and re-vegetation Traffic Control with Temporary Signals For the Federal training program, the number of trainees or apprentices is 0 . Federal-aid project No.: ER-15J2(001) and ER-32L0(260) . Complete the work within 80 working days. Do not include plant establishment working days in your bid. The estimated cost of the project is $918,017.00 . Contract Documents A digital copy of the Contract documents is available free of charge and can be downloaded, see Attachments . A hard copy of the Contract documents is available for purchase for $60.00 at the County of Santa Cruz, Department of Community Development & Infrastructure, Public Works, Room 410, 701 Ocean Street, Santa Cruz, California. No partial sets will be issued. Introduction Summary Background Contact Information Timeline Vendor Submissions Pricing Proposal Attachments

Published attachments
Addenda and notices
  • Official Notice #1: Notice No. 1 - Delayed Bid Opening · 1

    The bid opening for this project has been delayed and is tentatively scheduled for February 2027. An addendum will be released shortly stating the revised bid opening day and time.

  • Addendum #1 · 1

    Addendum No.1 has been issued for this project.

Public questions and answers
  • What is the anticipated start date for this project?

    The Contractor shall begin work per section 8-1.04 Start of Job Site Activities. Contract Execution typically occurs withing 5-7 weeks after bid opening. Section 8-1.06 and 8-1.07 Provides standard language on Suspensions and Delays. In the event that weather is unfavorable to complete work you may coordinate with the Resident Engineer to suspend job site activities until weather allows work to be completed.

  • The County has 3 Storm Damage Repair Projects all bidding same day with the optional pre-bid meetings scheduled the same day and time, will all three project be covered in one call/Zoom/Teams?

    Bid openings have been delayed, see Addendum No.1 issued 11/04/26.

  • Sheet 11 has a front view of a circular bearing plate, please confirm that the bearing plate is not circular. Also, please confirm that the 10" x 10" bearing plate does not need to be welded on the backside to the inside edge of the walers.

    See Addendum No.1 issued 11/04/26.

  • Is it possible to move the bid dates of 2 of the 3 County Slide Jobs bidding on the same date - currently they all bid on November 5 and that is a lot for a small business contractor to handle all 3 bid closings on same date

    Bid openings have been delayed, see Addendum No.1 issued 11/04/26.

  • Will this project include thermoplastic striping and if yes, how many LF at 8.11 & 8.39?

    No.

  • Is the TC plan on sheet 4 for 8.39 sufficient for the contractor to use or do we need to provide something else for 8.39?

    A similar traffic control plan will need to be provided for PM 8.11.

  • Steel mill is already saying major delays on H piles due to data centers ordering so many, are there any alternate piles that the engineer would consider?

    The contractor can submit alternative steel pile shapes for the engineer’s review. Possible alternatives must meet the wall design demands.

  • The contract specs permit full closures for upto 30 minutes at a time for certain operations, such as drilling. Is there any provision for longer full road closures for both 8.11 and 8.39?

    Please refer to Book 2 of 2, Special Provisions and Notice to Bidders, Section 12-4.01. Contractor may continue work exceeding 30 minutes if no traffic is accumulating within the project limits. Accumulated traffic within the project limits must be able to pass through the work zone and must not accumulate for more than 30 minutes at a time. Flaggers must be present to monitor traffic conditions.

  • Both specification books list Federal project numbers ER-15J2 (001) and ER-32LO (260). On the Notice to Bidders on page 2, spec book has page 7 on the bottom, it says Federal project numbers ER-15J2 (001) and ER-32LO (013). Please clarify the last project number.

    ER-15J2 (001) and ER-32LO (260)

  • We were tabbing through OpenGov and do not see a place to upload our bid. Can you please direct us as to where we attach our proposal?

    The Vendor Submissions has been corrected, see "3. Proposal - Required Forms Due at Bid Opening**" to upload proposals.

  • We will need to send you CARB certificates within 10 days after the bid opening. How would you like us to get those to you? Email, hand delivery, fax?

    Please email all certificates to both the Project Contact and Procurement Contact. Their names and email addresses are listed in the Introduction section.

  • Does form 9-L need to be submitted with the bid package? Please provide timeframe for when you need this form submitted.

    Yes, the LAPM Exhibit 9-L: Bidder's/Proposer's List will need to be submitted at time of bid.

  • Does the same seed mixture and application rates from PM 8.39 apply to PM 8.11?

    Yes.