FACILITIES MANAGEMENT ON-CALL GENERAL CONTRACTOR SERVICES

Description

T he purpose of this Invitation to Bid is for Pierce County to secure the services of a qualified general contractor with expertise of all phases of construction to perform a variety of facility modification projects, repairs and other construction projects in court facilities, general office buildings, and correctional facilities throughout Pierce County, including jail facilities. The General Construction Services include, but are not limited to, labor, carpentry, millwork, framing, drywall, doors, windows, caulking, hardware, demolition, excavation, ceilings, masonry, etc. Project Details Important Instructions for Electronic Submittal Pierce County is accepting electronic bid submissions. Bidders shall create a FREE account with OpenGov Procurement by signing up at https://procurement.opengov.com/signup . Once you have completed account registration, browse back to this page, click on "Draft Response", and follow the instructions to submit the electronic bid. Scope of Work or Project Details Please refer to attached bid packet and supporting document for detailed scopes of work. Introduction Summary Background Contact Information Timeline Vendor Submissions Attachments

Published attachments
Addenda and notices
Public questions and answers
  • 1. What convictions or circumstances disqualify someone from moderate, CJIS, and detention clearance, respectively? 2. Are decisions individualized based on the offense, time elapsed, sentence completion, and rehabilitation? 3. Is there a reconsideration or waiver process? 4. Can workers who do not qualify for secure areas perform other assignments, including exterior work? Are escorted-access arrangements available? 5. Must the awarded contractor serve every security level, or can a team accept only assignments its personnel can access? 6. Can prospective workers receive a confidential preliminary eligibility review before award, and how long does clearance take?

    1. Disqualification for any of the clearances involve violations / convictions / circumstances against law. 2. Unless Federal / State / County / City records are explicitly expunged, decisions are not individualized; 3. There are no reconsideration / waiver processes; 4. No; 5. Escorted access is not normally provided; however, & upon advanced request to & approval by County officials, the County may subjectively accommodate; 6. The County does not provide "..confidential preliminary eligibility review..' before award (i.e., it'll be incumbent on prospective bidders to coordinate with the jurisdictive FBI and Police entities)

  • The Unit Item Descriptions in the Scope of Work (item 1, Straight Time Hourly Rate) state: "The Contractor shall specify the normal straight time working hours on the bid form." Bid Form 00 41 00.01 has no field for these hours. Where should bidders state their normal straight-time working hours, and will a typed line on the bid form stating them be accepted without the bid being considered non-responsive?

    Contractors shall specify the normal straight-time working hours on the bid form, and a typed line on the bid form stating them will be accepted without the bid being considered non-responsive

  • General Conditions 00 72 00.01, 8.01 C, provides that "repeated failure to provide timely and complete Work Order Bid Proposals" may subject the Contractor to a determination of default. May the Contractor decline to submit a Work Order Bid Proposal for a particular Work Order Request, and if so, would a request the Contractor declines in writing count toward that provision?

    Yes, contractors may explicitly decline work, provided they also furnish an accompanying explanation re: their limited expertise / resource capabilities / subcontracting. Declinations will be admonished if the County does not receive / explicitly sanction the contractor's explanation.

  • Would project accept a 10% retainage hold in lieu of providing a 5% bid bond

    No, a 5% bid bond must accompany all bids.

  • The Bid Form states that subcontractor rates are capped at the prime contractor’s allowable rates. For a specialty labor classification that is not listed in the bid form, how does this cap interact with Bid Item 25? Specifically, may the prime bill the required prevailing wage rate plus the awarded Item 25 markup, or does a different cap apply to subcontracted specialty labor?

    The prime contractor's labor rate structure shall be bid item 25; the subcontractor's labor rate structure must not exceed the prime contractor's labor rate structure; and the aggregate total may be the sum of the prime contractor's itemized rate structure + the subcontractor's lumpsum costs + the %markup of the subcontractor's lumpsum costs ...