Installation of EV Chargers for the Electric Bucket Truck
Description
Alameda Municipal Power (AMP) seeks to hire a qualified C-10 contractor with experience installing EV chargers. AMP would like to install two chargers in the AMP Service Center parking lot to charge its fully electric bucket truck, a 2022 International eMV607 SBA . The two chargers, one level-3 charger and one level-2, will be installed next to each other in the yard. AMP has purchased and will supply the chargers, InCharge ICE-30 and ICE-80. Installation manuals are shown in the attachments tab. Installation of EV Chargers Contract award will be by total lump sum. Provide all materials, tax, and labor in the space provided below. Materials Tax (10.75%) Labor SCOPE OF WORK Installation of EV Chargers Scope of Work – Installation of EV Chargers for AMP’s Electric Bucket Truck Alameda Municipal Power (AMP) seeks to hire a qualified C-10 contractor with experience installing EV chargers. AMP would like to install two chargers in the AMP Service Center parking lot to charge its fully electric bucket truck, a 2022 International eMV607 SBA . The two chargers, one level-3 charger and one level-2, will be installed next to each other in the yard. AMP has purchased and will supply the chargers, InCharge ICE-30 and ICE-80. Installation manuals are shown in the attachments tab. The power sources for each charger will be coming from different locations. Power for the first charger (level 3) will be sourced from the switchgear in the Electrical Room. The scope of work for the first charger is: 1) Purchase and install a 100 Amp 3-pole, 480-volt circuit breaker. Install the breaker in the Electrical Room. 2) Purchase and install EMT conduit line of approximately 150-feet from the main panel through the ceiling. Core drill the walls and provide protection. Seal after construction. Continue installing conduit along the flashing and joist of the roofs to where the switch and EV charger will be located. 3) Purchase and install a secondary isolation switch, (1) 60-amp, 600-volt Safety Switch, Nema 3r, and mounting equipment. 4) Install ICE – 30, 30kW DC fast charger at the pole (charger will be provided by AMP). Contractor to purchase the mounting equipment. 5) Connect and program the charger. Coordinate activation with the software provider, In Charge (contact information will be provided). 6) Purchase and install (1) protective bollard. 7) The contractor will need to perform installation of all equipment before making the connection to the main panel. A power outage will be required to install the 100 Amp breaker. All conduit, wire, switch, and charger installation must be done in advance of the final tie-in. The outage will require coordination with AMP. AMP will coordinate with all other City departments. The outage is expected to take place after hours at night, possibly on the weekend. Power for the second charger (level 2) will be sourced from the panel in the warehouse. The scope-of-work for the second charger is: 1) Purchase and install a 50 Amp, 250-volt breaker in the panel located in the warehouse. 2) Purchase and install EMT conduit approximately 70 feet from the panel through the wall, to the EV charger on the post. 3) Install ICE-80, 19.2kW AC charger on the pole (charger will be provided by AMP), adjacent to the other charger. Contractor to purchase the mounting equipment. 4) Connect and program the charger. Coordinate activation with the software provider, In Charge (contact information will be provided). *Special Notes* Contractors are required to inspect the site during the solicitation of this project prior to offering a bid. All site visits must be completed before November 16, 4pm. Contact Jeff Braun at 510-748-3971 to arrange for a site visit, Monday through Thursday, 9am- 4pm. AMP will facilitate permits and inspections with the City of Alameda. If the cost of the project is greater than $25,000, performance and payment bonds will be required. The project will be registered with the Department of Industrial Relations (DIR). Prevailing wages will be required. Contractor (and subcontractor if applicable) will need to meet AMP’s insurance and provide a City of Alameda business license. Pictures demonstrating the installation of the first charger: Photos inside of the panel are posted in the attachments tab. Pictures demonstrating the installation of the second charger: NOTICE INVITING BIDS Bid Submission Alameda Municipal Power (“AMP”), a department of the City of Alameda (“City”), acting by and through the City’s Public Utilities Board (“PUB”), will accept electronically submitted bids for its Installation of EV Chargers for the Electric Bucket Truck Project (“Project”), by or before Thursday, November 19, 2026 at 12:00 pm , via OpenGov Procurement, at: https://procurement.opengov.com/portal/alamedaca/projects/321012 (“Bid Portal”). Bids that are not submitted by a registered vendor via the Bid Portal will not be accepted. Project Information Location and Description. The Project is located at AMP's service center, warehouse, and parking area. . The Scope of Work contains the full description of the Work. Time for Final Completion . The Project must be fully completed within 90 calendar days from the start date set forth in the Notice to Proceed. AMP anticipates that the Work will begin on or about December 14, 2026, but the anticipated start date is provided solely for convenience and is neither certain nor binding. License and Registration Requirements License. This Project requires a valid California contractor’s license for the following classification(s): C-10 - Electrical Contractor DIR Registration. AMP may not accept a bid from or enter into the Contract with a bidder, without proof that the bidder is registered with the California Department of Industrial Relations (“DIR”) to perform public work pursuant to Labor Code section 1725.5, subject to limited legal exceptions. Contract Documents The plans, specifications, bid forms and contract documents for the Project, and any addenda thereto (“Contract Documents”) are available for viewing or download free of charge solely via the Bid Portal, as specified above. Time for Completion The Project must be completed within 90 calendar days from the start date set forth in the Notice to Proceed. AMP anticipates that the Work will begin on or abou t December 14, 2026, but the anticipated start date is provided solely for convenience and is neither certain nor binding. Bid Security Each bidder must submit bid security equal to ten percent of the maximum bid amount, in the form of cash; a cashier’s or certified check made payable to Alameda Municipal Power; or a bid bond using the Bid Bond form included with the Contract Documents, and executed by a surety licensed to do business in the State of California if the cost of project exceeds $25,000.00. The bid security must guarantee that within fourteen days after AMP issues the Notice of Intent to Award, the successful bidder will execute the Contract and submit the insurance certificates and endorsements, valid Certificates of Reported Compliance as required under the California Air Resources Board’s In-Use Off-Road Diesel-Fueled Fleets Regulation (13 CCR § 2449 ed seq.) (“Off-Road Regulation”), if applicable and any other submittals required by the Contract Documents and as specified in the Notice of Intend to Award. Original Payment Bond and Performance Bond can be provided after the City awards and executes the Contract, however, work cannot start until these bonds are approved by the City Attorney’s Office. Prevailing Wage Requirements General. Pursuant to California Labor Code section 1720 et seq., and Alameda Municipal Code section 2-67, this Project is subject to the prevailing wage requirements applicable to the locality in which the Work is to be performed for each craft, classification or type of worker needed to perform the Work, including employer payments for health and welfare, pension, vacation, apprenticeship and similar purposes. Rates. These prevailing rates are on file with AMP and are available online at http://www.dir.ca.gov/DLSR . Each Contractor and Subcontractor must pay no less than the specified rates to all workers employed to work on the Project. The schedule of per diem wages is based upon a working day of eight hours. The rate for holiday and overtime work must be at least time and one-half. Compliance. The Contract will be subject to compliance monitoring and enforcement by the DIR, under Labor Code section 1771.4. Performance and Payment Bonds The successful bidder will be required to provide performance and payment bonds, each for 100% of the Contract Price, as further specified in the Contract Documents if the cost of project exceeds $25,000.00. Substitution of Securities Substitution of appropriate securities in lieu of retention amounts from progress payments is permitted under Public Contract Code section 22300. Subcontractor List Each Subcontractor must be registered with the DIR to perform work on public projects. Each bidder must submit a completed Subcontractor List form with its bid, including the name, location of the place of business, California contractor license number, DIR registration number, and percentage of the Work to be performed (based on the base bid price) for each Subcontractor that will perform Work or service or fabricate or install Work for the prime contractor in excess of one-half of 1% of the bid price, using the Subcontractor List form included with the Vendor Questionnaire. The Subcontractor List form must be uploaded electronically in PDF format via the Bid Portal. Instructions to Bidders All bidders should carefully review the Instructions to Bidders for more detailed information before submitting a bid. The definitions provided in the "Definitions" section of the General Conditions apply to all of the Contract Documents, as defined therein, including this Notice Inviting Bids. Retention Percentage. The percentage of retention that will be withheld from progress payments is 5 %. Pre-Bid Conference There is no pre-bid conference but each bidder is required to visit the site prior to submission of their bid. This is by appointment only with Project Manager, Jeff Braun. Contact information is provided in the Scope of Work. Submission without prior site visit will be disqualified. INSTRUCTIONS TO BIDDERS Bid Documents Included The documents below are included with this Invitation for Bid (IFB) for your review and submittal: In the Vendor Questionnaire section, Sample Construction Agreement including Insurance Requirements; optional to submit redlined agreement Statement of Qualifications Questionnaire* Non-Collusion Declaration* Subcontractor List* Bid Bond Template if the cost of project exceeds $25,000* Signed W-9* Local Business Affidavit if applicable *Must be submitted with bid. Please note, bidders must specifically note each edit or exception they may have to the attached sample construction agreement. AMP is not obligated to accept any proposed deviations from the standard contract or agreement, and may consider any deviation non-responsive at AMP’s discretion. CADIR Registration Requirements Alameda Municipal Power (AMP) hereby provides notice of California Labor Code section 1771.1(a), which reads: “A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5. It is not a violation of this section for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section 10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded.” Please note: If AMP is unable to verify that the bidder/contractor’s DIR registration is current, AMP must disqualify the bidder, as required by Labor Code section 1725.5. Bidder’s Representation and Warranties The Bidder represents and warrants: That it has not retained a person to solicit or secure an AMP contract (upon an agreement or understanding for a commission, percentage, brokerage, or contingent fee) except for retention of bona fide employee or bona fide established commercial selling agencies for the purpose of securing business; That any information submitted by the Bidder prior to the award of Contract, or thereafter, upon request, whether or not submitted under a continuing obligation by the terms of the Contract to do so, is true and correct at the time such information is submitted or made available to AMP; That the Bidder has not colluded, conspired, or agreed, directly or indirectly, with any person in regard to the terms and conditions of the Bidder's Bid, except as may be permitted by this Invitation for Bid; That the Bidder has the power and authority to enter into this Contract with AMP, that the individual(s) executing this Contract are duly authorized to do so by appropriate resolution (if applicable), and that this Contract shall be executed, delivered and performed pursuant to the power and authority conferred upon the person or persons authorized to bind the Bidder; That the Bidder has not attempted to exert undue influence with the Utility Procurement Administrator or Project Manager or any other person who has directly participated in the decision to award the Contract to the Bidder; That the Bidder has furnished and will furnish true and accurate statements, records, reports, resolutions, certifications, and other written information as may be requested of the Bidder by AMP during the term of this Contract; That the Bidder and all its subcontractors performing work on this Project are duly licensed as a contractor with the State of California as required by California Business & Professions Code Section 7028, as amended; That the Bidder has fully examined and inspected the Project site and has full knowledge of the physical conditions of the Project site; and, That there are no claims or disputes between the Bidder and AMP which would materially affect the Bidder's ability to perform under the Contract. Bidder’s Designated Contact Person of this solicitation. Addenda AMP reserves the right to issue an electronic Addendum or Addenda to the electronic solicitation prior to the bid closing date and time. During the Bid process there may be changes to the Contract Documents, which would require an issuance of an addendum or addenda AMP disclaims any and all liability for loss, or damage to any Bidder who does not receive any addendum issued by AMP in connection with this IFB. Any Bidder by submitting a Bid waives any and all claims and demands Bidder may have against AMP on account of the failure of delivery of any such Addendum to Bidder. Any and all Addenda issued by AMP shall be deemed included in this IFB, and the provisions and instructions therein contained shall be incorporated into any Bid submitted by Bidder. Request(s) for Clarification Any Bidder may submit to AMP an electronic request for the clarification of any aspect of the Specifications or any other related information, or part thereof, which is a part of the IFB. Such a request shall be submitted electronically through AMP’s electronic procurement system Q&A function. Such requests shall be submitted no later than the time and date specified in the Notice of Invitation for Bid. AMP shall electronically respond with a copy to all bidders of record at least three (3) Business Days prior to the opening of Bids. Submission of Bids Submittal. A Bid shall be submitted in AMP’s electronic procurement system as required . Any Bid which is attempted to be delivered on paper shall be deemed non- responsive and rejected. The Bidder shall have the sole and exclusive responsibility for ensuring that a Bid is submitted by the time stated by the electronic procurement system herein. Any Bid that is incomplete, unclear, or that fails to fully comply with the applicable requirements set forth herein, including, but not limited to, information requested by the City, may be rejected as nonresponsive. Bid Authorization. The electronic login authorization of the person, whether as assigned personal or representative capacity, executes the e-Bid and any other e- document which AMP requires. If the person does business under his or her own name, that person shall login under his or her own login and PIN as authorized by the electronic procurement system provider. If the person does business under a fictitious business name, that person shall login under his or her own login and PIN as authorized by the electronic procurement system provider. If the person logins for and on behalf of a partnership, the person shall do so with his or her authority to sign/login under his or her own login and PIN as authorized by the electronic procurement system provider. Responsibility of Bidder. A Bid shall be submitted at the sole cost and expense of the Bidder and, in submitting such Bid to AMP, the Bidder waives any claim or demand against AMP which the Bidder may have for any direct or indirect cost or expense of preparing and submitting such Bid. Certification of Nondiscrimination. By submitting a Bid, the Bidder certifies that they do not and in the performance of this contract they will not discriminate in employment of any person because of race, skin color, gender, age, religion, disability, national origin, ancestry, sexual orientation, housing status, marital status, familial status, weight or height of such person; and further certify that they are in compliance with all Federal, State and local laws, regulations, rules, directives and executive orders regarding nondiscrimination in employment. Bid Price. Bid prices shall state the net delivered price with all transportation charges prepaid and include all State and Federal Taxes, including the amount of any Use or Excise Tax that may be applicable to the transaction, all of which will be paid by the Bidder. If California Use Tax is applicable, Bidder shall state whether they maintain a place of business in the State of California, or are authorized by the State Board of Equalizations of said State under Section 6202 of the Revenue and Taxation Code, to collect Use Taxes. If the Bidder to whom the Contract is awarded does not maintain a place of business in the State of California, or is not authorized to collect Use Taxes, the amount of such taxes, if applicable, will be deducted from the total bid price and paid directly by AMP to the State of California. All solicited Base Bids shall be bid. If the Bidder proposes no change in the Base Bid, then the Bidder shall submit a zero (0) cost Bid on the bid line item. Alternate Bids. No alternate Bid shall be accepted or considered by AMP, unless AMP solicits an alternate Bid. Add Alternates. All solicited alternate Bids shall be bid, whether additive or deductive. If the Bidder proposes no change in the alternate Bid, then the Bidder shall submit a zero (0) cost Bid on the bid line item. Interest in More Than One Bid. Unless AMP provides otherwise, no person shall be permitted to submit or be interested in more than one Bid for the same public works project. A person may submit a price to more than one Bidder as a subcontractor or materials supplier without violating this prohibition. Withdrawal of Bid. A Bidder may withdraw its Bid by reentering the submitted electronic bid and activating the submittal at any time before the deadline for the receipt of Bids as specified in the Notice for Invitation for Bid. No
Published attachments
- IMG_9237
- IMG_9235
- IMG_9239
- IMG_9238
- IMG_9236
- IMG_9240
- IMG_9245
- IMG_9229
- IMG_9234
- IMG_9249
- IMG_9232
- IMG_9228
- IMG_9226
- IMG_9247
- IMG_9244
- IMG_9233
- IMG_9231
- IMG_9227
- IMG_9243
- IMG_9230
- IMG_9250
- InCharge-Installation-Manual-ICE-80A
- InCharge-Installation-Manual-ICE-30
- Installation_of_EV_Chargers_for_the_Electric_Bucket_Truck_(Addendum_#4_Revision).pdf
Addenda and notices
Addendum #1 · 1
Addendum #1 AMP will accept a Certificate of Exemption under Labor Code 3352 in lieu of a workers' compensation policy for corporate officers/owners performing the work, provided the following requirements are met: -The bidder must submit a Certificate of Exemption on company letterhead. -The certificate should clearly state that the company has no employees and therefore is exempt from carrying workers' compensation insurance. -There is no required template. The bidder may prepare the certificate in their preferred format, as long as the intent and exemption status are clearly explained on company letterhead. -The certificate can be uploaded with the Sample Construction Agreement. If the bidder has any additional edits or exceptions to the agreement, those should also be uploaded along with the certificate for review.
Official Notice #1: Reminder of Site Visit Deadline - 11/16/2026 before 4pm · 1
Contractors are required to inspect the site during the solicitation of this project prior to offering a bid. All site visits must be completed before November 16, 4pm. Contact Jeff Braun at 510-748-3971
Addendum #2 · 2
Addendum #2 - Specification Changes For the ICE-30 charger installation, the changes are: the 100A breaker changed to 60A, the 60A isolation-switch changed to 50A fused, conduit can be installed along or under the overhang, and wire specifications have been added. For the ICE-80 charger installation, the changes are the 50A breaker changed to 60A and wire specifications have been added. Changes are shown bolded below: Power for the first charger (level 3) ICE-30 will be sourced from the switchgear in the Electrical Room. The scope of work for the first charger is: 1) Purchase and install a 60 Amp 3-pole, 480-volt circuit breaker. Install the breaker in the Electrical Room. 2) Purchase and install EMT conduit line of approximately 150-feet from the main panel through the ceiling. Core drill the walls and provide protection. Seal after construction. Continue installing conduit along or under overhang to where the switch and EV charger will be located. Use #6 AWG copper conductors for the ICE-30, and the EMT conduit should be sized in accordance with the CEC. 3) Purchase and install a secondary isolation switch, (1) 50-amp fused , 600-volt Safety Switch, Nema 3r, and mounting equipment. 4) Install ICE – 30, 30kW DC fast charger at the pole (charger will be provided by AMP). Contractor to purchase the mounting equipment. 5) Connect and program the charger. Coordinate activation with the software provider, In Charge (contact information will be provided). 6) Purchase and install (1) protective bollard. 7) The contractor will need to perform installation of all equipment before making the connection to the main panel. A power outage will be required to install the 60A breaker. All conduit, wire, switch, and charger installation must be done in advance of the final tie-in. The outage will require coordination with AMP. AMP will coordinate with all other City departments. The outage is expected to take place after hours at night, possibly on the weekend. Power for the second charger (level 2) ICE 80 will be sourced from the panel in the warehouse. The scope-of-work for the second charger is: 1) Purchase and install a 60 Amp , 250-volt breaker in the panel located in the warehouse. 2) Purchase and install EMT conduit approximately 70 feet from the panel through the wall, to the EV charger on the post. Use #2 AWG copper conductor and EMT conduits size per CEC. 3) Install ICE-80, 19.2kW AC charger on the pole (charger will be provided by AMP), adjacent to the o
Official Notice #2: Reminder of Bid Due - 11/19/2026 at 12:00pm PST · 2
This is a friendly reminder that deadline to submit a bid is at noon tomorrow Thursday 11/19/2026 PST. We strongly suggest that interested bidders start submission early since the Bid Portal will close at specified time/date and AMP does not accept any bid submitted outside the Bid Portal. We look forward to receiving complete bids soon.
Addendum #3 · 3
Picture of the nameplates for each panel.
Addendum #4 · 4
Addendum #4 - The sign in sheet has been uploaded here.
Public questions and answers
Two questions about the insurance requirements in Section 8: 1. Workers' Compensation. Will AMP accept a Certificate of Exemption under Labor Code 3352 for corporate officers/owners performing the work, in lieu of a workers' compensation policy? 2. Professional Liability ($2,000,000). The scope is installation only, with no design or professional services by the contractor. Can the Professional Liability requirement be waived for this project? Thank you.
1. Yes, AMP will accept a Certificate of Exemption under Labor Code 3352 in lieu of a workers' compensation policy for corporate officers/owners performing the work, provided the following requirements are met: -The bidder must submit a Certificate of Exemption on company letterhead. -The certificate should clearly state that the company has no employees and therefore is exempt from carrying workers' compensation insurance. -There is no required template. The bidder may prepare the certificate in their preferred format, as long as the intent and exemption status are clearly explained on company letterhead. -The certificate can be uploaded with the Sample Construction Agreement. If the bidder has any additional edits or exceptions to the agreement, those should also be uploaded along with the certificate for review. 2. Even though the engineering was done by AMP, modifications may be required during installation, and we may rely on the expertise of the contractor. $2,000,000 is the standard limit and will not be waived.
What are liquidated damages for the project? We will need to request a bid bond.
There are no liquidated damages for this project.
Will the EVSE units require data lines connected? Thanks.
No data lines will be connected.
1. After calling the vendor to purchase the pole mount for the L2 unit, the vendor does not have the mount for the L2 unit. What options are available to mount this unit? Thanks.
The installer will need to determine how to mount the unit.
Are you required to have contractors Professional Liability and Cyber and Technology Liability
We are requiring Professional Liability of $2,000,000. Cyber and Technology Liability is not required.
can you clarify what City-owned electronic data or information "property" would be in the contractors care, custody, or control?
Electronic data will not be shared with the contractor.
Is AMP looking for coverage if a cyberattack damages that data, or for property damage resulting from an installation error?
Professional Liability is required for professional acts, errors and omissions of Provider’s profession and work. Cyber and Technology Liability is not required.
Where do I find the bid bond form?
Bid bond form is attached under Section 11. Vendor Questionnaire.
We had a converastion with Incharge rep Randy Everman, the ICE 80 unit is disconnected and they have a replacement for it. You may want to reach out to Randy.
Thank you for your comments. AMP has purchased the unit and needs a contractor to install it.
These chargers generally require a on-site InCharge tech to program and activate/commission. Is this cost included in AMP's purchase of the chargers or payed by the contractor awarded the project?
The selected contractor will be required to connect, program, and activate the chargers, as specified in the scope of work.
In the project specifications the 100AMP circuit for the ICE-30 specifies a 60A disconnect, this seems incorrect based on the fact this is fed by a 100AMP breaker? Does the ICE-80 require a disconnect?
Specification for the 100A breaker has been changed to a 60A breaker with a 60A fused disconnect. A disconnect is not required for the ICE-80. Please see Addendum #2.
Business license timing: The spec requires a City of Alameda business license before bid submittal. If a bidder does not currently hold one, is obtaining it before the Nov 19, 2026 bid deadline sufficient, and what proof must be included with the bid?
The business license is not required for bid submittal and can be attained during contract preparation.
Bollard count: Please confirm the number of bollards required and their locations for each charger (ICE-80 and ICE-30).
The existing structure provides one bollard. One additional bollard is required to be installed that protects both chargers as specified in the scope of work.
Site visit confirmation: How will completion of the mandatory site visit be recorded and verified for bid responsiveness, and will AMP confirm a bidder's visit in writing or through the OpenGov portal?
The sign-in sheet for site visits will be posted as an addendum.
Bid security and bonds: The spec requires 10 percent bid security and, if the bid is over $25,000, 100 percent performance and payment bonds. Please confirm the bid security form or format required with the OpenGov submittal.
Bid bond form is attached under Section 11 of the Vendor Questionnaire and is required with the submittal in OpenGov.
Conduit routing: The conduit runs (about 115 ft to each charger) are shown above ground routed through landscaping. Please confirm whether any trenching, boring, or landscape restoration is in scope, and if so, the extent.
Conduit will be installed in ceilings, and along or under overhangs. Boring through walls and sealing after construction will be required. No landscape restoration or trenching is necessary.
Switchboard feeder: Please confirm the brand and model of the existing 1200A main switchboard and the size and type of feeder breaker to be used for the new 480V 200A panel, and whether that breaker is existing to be reused, existing spare, or contractor-furnished new.
Pictures of the existing panels' nameplates have been posted in addendum #3. Contractor to furnish new breakers.