Lift Station W- 27 Upgrades and Force Main Replacement (Project No. 23- 8073)
Description
A. Lift Station Improvements: 1. Replacement of 3 existing pumps and extended shaft motors with 4 dry pit submersible pumps and motors. 2. Construction of a new electrical room on the ground floor, complete with air-conditioning and lighting. 3. Addition of variable frequency drives (VFDs). 4. Replacement of all station piping and valves 5. Replacement od sump pumps. 6. Addition of flow meter, vault and accessories on the discharge force main. 7. Replacement of emergency generator with a skid-mounted generator in a sound attenuated enclosure with subbase, dual wall, diesel fuel storage tank. 8. Demolition of existing bulk diesel fuel storage tank and associated structure. 9. Replacement of all electrical gear, controls, and instruments. 10. Replacement of all interior and exterior lighting. 11. Removal of existing ventilation systems, and installation of new ventilation system including ductwork, stack, wet well ventilator and exhaust/supply fans. 12. Replacement of station roofing, exterior doors, and louvers. 13. Replacement of station monorail system. 14. Rehabilitation and specialty coating of wet well. 15. Interior and exterior painting of pump station structure. 16. Site work, including site restoration, perimeter fencing, access driveway, sidewalk installation, and landscaping. B. Force Main: 1. Installation of 20-inch epoxy lined, ductile iron force main from Lift Station W-27 to the existing 48-inch ductile iron force main on Taft Street. 2. Abandon-in-place existing 10-inch and 12-inch cast iron discharge force mains from Lift Station W-27 to the existing 48-inch ductile iron force main on Taft Street. C. Stormwater Improvements: 1. Installation of approximately 300 linear feet of exfiltration trench on Roosevelt Street;. 2. Installation of approximately 450 linear feet of 24-inch high performance polypropylene pipe in North 31st Road, extending from Roosevelt Street to Taft Street, then extending east on Taft Street until the alley directly west of Rotary Park. 3. Installation of approximately 350 linear feet of 15-inch high performance polypropylene pipe in the alley directly west of Rotary Park to Arthur Street. 4. Installation of a 48-inch inline check valve and access structure on the existing 48-inch reinforced concrete pipe that discharges to the C-10 canal on Arthur Street. SCOPE OF WORK/SERVICES Project Description 1. Lift Station W-27 Improvements: a. Replacement of three existing pumps and extended shaft motors with four dry pit submersible pumps and motors b. Construction of a new electrical room on the ground floor, complete with air-conditioning and lighting as required c. Addition of variable frequency drives (VFDs) d. Replacement of all station piping and valves e. Replacement of sump pumps f. Addition of flow meter, vault and accessories on the discharge force main g. Replacement of emergency generator with a skid-mounted generator in a sound attenuated enclosure with subbase, dual wall, diesel fuel storage tank h. Demolition of existing bulk diesel fuel storage tank and associated structure i. Replacement of all electrical gear, controls, and instruments j. Replacement of all interior and exterior lighting k. Removal of existing ventilation systems, and installation of new ventilation system including ductwork, stack, wet well ventilator and exhaust/supply fans l. Replacement of station roofing, exterior doors, and louvers m. Replacement of station monorail system n. Rehabilitation and specialty coating of wet well o. Interior and exterior painting of pump station structure p. Site work, including site restoration, perimeter fencing, access driveway, sidewalk installation, and landscaping 2. Force Main: a. Installation of 20-inch epoxy lined, ductile iron force main from Lift Station W-27 to the existing 48-inch ductile iron force main on Taft Street b. Abandon-in-place existing 10-inch and 12-inch cast iron discharge force mains from Lift Station W-27 to the existing 48-inch ductile iron force main on Taft Street. 3. Stormwater Improvements: a. Installation of approximately 300 linear feet of exfiltration trench on Roosevelt Street b. Installation of approximately 450 linear feet of 24-inch high performance polypropylene pipe in North 31st Road, extending from Roosevelt Street to Taft Street, then extending east on Taft Street until the alley directly west of Rotary Park c. Installation of approximately 350 linear feet of 15-inch high performance polypropylene pipe in the alley directly west of Rotary Park to Arthur Street d. Installation of a 48-inch inline check valve and access structure on the existing 48-inch reinforced concrete pipe that discharges to the C-10 canal on Arthur Street Technical Specifications See Attachment D - Technical Specifications Contractor Qualifications General Contractor’s License: List at least three (3) similar projects completed within the last seven (7) years by the bidder that include pump station and mechanical piping systems with pumps larger than 60 HP. At least two (2) of the three (3) projects should include bypass pumping of an active pump station while maintaining service. Additionally, list at least three (3) similar projects completed within the last seven (7) years by the bidder (or the bidder’s subcontractor) that include force main installation of pipe diameters 16-inch or larger with a minimum length of 1,000 linear feet via the open cut / direct bury method. Include owner, project value, completion date, reference contact information and brief project description. Any one of the following causes, among others, may be considered as sufficient justification to disqualify a bidder and reject his or her bid: A. Submission of more than one bid for the same work by an individual, firm, partnership or corporation under the same or different names. B. Evidence of collusion. C. Previous participation in collusive bidding on work for the City of Hollywood, Florida. D. Submission of an unbalanced bid in which the prices bid for some items are out of proportion to the prices bid for other items. E. Lack of competency. The Bidder shall provide proof that their past experience can demonstrate similar complexity and size compared to this contract. The Engineer may declare any bidder ineligible, at any time during the process or receiving bids or awarding the contract, if developments arise which, in his opinion, adversely affects the bidder's responsibility. The Bidder will be given an opportunity, by the engineer, to present additional evidence before final action is taken. F. Lack of responsibility as shown by past work judged by the Engineer from the standpoint of workmanship and progress. G. Non-compliance with the City’s Local Preference (when applicable). H. Uncompleted work for which the Bidder is committed by Contract, which is in the judgment of the Engineer, might hinder or prevent the prompt completion of work under this Contract. I. Being in arrears on any existing Contracts with the City, or any taxes, licenses or other monies due the City; in litigation with the City or having defaulted on a previous contract with the City. Project Schedule / Timeline Substantial Completion: 720 days Final Completion: 780 days See Attachment C - Supplementary General Conditions SUMMARY Summary Background Contact Information Timeline INTRODUCTION Purpose The City of Hollywood, Florida (City) is seeking bids from qualified and experienced contractors, hereinafter referred to as the Contractor or Bidder, to construction services related to Lift Station W-27, the force main, and stormwater improvements for the City, in accordance with the terms, conditions, and specifications contained in this solicitation. Responses to this solicitation are due by Wednesday, December 9, 2026 , by 3:00 pm , and will be opened in a virtual public setting on December 9, 2026, at 3:00 PM . Submittals shall be received electronically through OpenGov, the City's eProcurement Portal ("Portal"). Submittals shall be considered a bid on the part of the bidder, which bid shall be deemed accepted upon approval of the City, and in case of default, the City reserves the right to accept or reject any or all bids, to waive irregularities and technicalities, and request new bids The City also reserves the right to award any resulting agreement as it deems will best serve the interests of the city. Submission of a bid shall serve as prima facie evidence that the Bidder has examined this solicitation and is fully aware of all conditions affecting the provision of services and the evaluation criteria and scoring methodology as set forth in this solicitation document. Pre-bid Conference and/or Site Visit (Non-Mandatory) There will be a non- mandatory pre-bid co nference and/or site visit scheduled for this solicitation. It is strongly suggested that all Contractors attend the non-mandatory pre-bid conference and/or site visit to receive information that may be critical to their understanding of this solicitation. Please keep in mind that site visits at other times might not be available. It is the sole responsibility of the Contractor to become familiar with the scope of the City’s requirements prior to submitting a bid. No variation in price or conditions shall be permitted based upon a claim of ignorance. Submission of a bid will be considered evidence that the Bidder has familiarized themselves with the nature and extent of the work, equipment, materials, and labor required. OpenGov ("Portal") The City of Hollywood uses OpenGov, the e-Procurement Portal (“Portal”) ( https://procurement.opengov.com/portal/hollywoodfl ) to administer the competitive solicitation process, including but not limited to soliciting bids/proposals, issuing addenda, posting results and issuing notification of an intended decision. The City shall not be responsible for a Bidder's/Proposer’s inability to submit a bid/proposal by the bid/proposal end date and time for any reason, including issues arising from the use of the Portal. Point of Contact For information concerning procedures for responding to this solicitation, contact the Point of Contact within the Office of Procurement Services, Julissa Marcano , Senior Purchasing Agent at jmarcano@hollywoodfl.org or by phone at (954) 710-9956 , or Jean Joinville, Procurement Manager, at jjoinville@hollywoodfl.org or by phone at 954-921-3290. Such contact is to be for clarification purposes only. All questions must be submitted in writing via the Portal by Monday, November 23, 2026 , by 5:00 pm , in order to receive a timely response. Project Manager: Roger Bezerra , Project Manager , Public Utilities , email: rbezerra@hollywoodfl.org , or by phone: (954) 921-3930 . For information concerning technical specifications, please utilize the question / answer feature provided by OpenGov at https://procurement.opengov.com/portal/hollywoodfl . Questions of a material nature must be received prior to the cut-off date specified in the solicitation schedule. Material changes, if any, to the scope of services or bidding procedures will only be transmitted by written addendum. (See addendum section of the OpenGov site). Bidders please note: No part of your bid can be submitted via FAX. No variation in price or conditions shall be permitted based upon a claim of ignorance. Submission of a bid will be considered evidence that the Bidder has familiarized themselves with the nature and extent of the work, and the equipment, materials, and labor required. The entire bid response must be submitted in accordance with all specifications contained in this solicitation. The questions and answers submitted in OpenGov shall become part of any contract that is created from this solicitation. It is the sole responsibility of the Bidder to ensure that their bid is submitted electronically through the Portal at https://procurement.opengov.com/portal/hollywoodfl Cone of Silence The City of Hollywood City Commission adopted Ordinance No. O-2007-05, which created Section 30.15(F) imposing a Cone of Silence for certain City purchases of goods and Services. The Cone of Silence refers to limits on communications held between vendors and vendor’s representatives and City elected officials, management and staff during the period in which a Formal Solicitation is open. The Ordinance does allow potential vendors or vendor’s representatives to communicate with designated employees for the limited purpose of seeking clarification or additional information. The names and contact information of those employees that may be contacted for clarification or additional information are included in the solicitation. The Cone of Silence does not prohibit a vendor or vendor’s representative from communicating verbally, or in writing with the City Manager, the City Manager’s designee, the City Attorney or the City Attorney’s designee on those procurement items to be considered by the City Commission. The Cone of Silence does not prohibit a vendor or vendor’s representative from making public presentations at a duly noticed pre-bid conference or duly noticed evaluation committee meeting or from communicating with the City Commission during a duly noticed public meeting. The Cone of Silence shall be imposed when a formal competitive solicitation has been issued and shall remain in effect until an award is made, a contract is approved, or the City Commission takes any other action which ends the solicitation. To view the Cone of Silence, go to the City of Hollywood Code of Ordinance online, and view Section 30.15F All communications regarding this bid should be sent in writing to the Procurement and Performance Management Division as identified in this bid. SPECIAL TERM AND CONDITIONS Addenda, Changes, and Interpretations It is the sole responsibility of each contractor to notify the Point of Contact utilizing the question / answer feature provided by OpenGov and request modification or clarification of any ambiguity, conflict, discrepancy, omission or other error discovered in this competitive solicitation. Requests for clarification, modification, interpretation, or changes must be received prior to the Question and Answer (Q & A) Deadline. Requests received after this date may not be addressed. Questions and requests for information that would not materially affect the scope of services to be performed, or the solicitation process will be answered within the question / answer feature provided by OpenGov and shall be for clarification purposes only. Material changes, if any, to the scope of services or the solicitation process will only be transmitted by official written addendum issued by the City and uploaded to OpenGov as a separate addendum to the solicitation. Under no circumstances shall an oral explanation given by any City official, officer, staff, or agent be binding upon the City and should be disregarded. All addenda are a part of the competitive solicitation documents and each firm will be bound by such addenda. It is the responsibility of each to read and comprehend all addenda issued. Dimensions, Quantities and Subsurface Information Dimensions, quantities, and subsurface information supplied by the City are in no way warranted to indicate true amounts or conditions. Bidders/Contractors shall neither plead misunderstanding or deception nor make claims against the City if the actual amounts, conditions, or dimensions do not conform to those stated. Any "Outside" reports made available by the Engineer are neither guaranteed as to accuracy or completeness, nor a part of the Contract Documents. Trench Safety Form The Trench Safety Form included in the Bid Documents must be completed and signed. Noncompliance with this requirement may invalidate the bid. Changes and Alterations Bidder may change or withdraw a Bid at any time prior to Bid submission deadline; however, no oral modifications will be allowed. Modifications shall not be allowed following the Bid deadline. Bidder’s Costs The City shall not be liable for any costs incurred by Bidders in responding to this solicitation. Pricing/Delivery All pricing must include delivery and installation and be quoted FOB: Destination, unless specified otherwise in the #SCOPE OF WORK/SERVICES section. Price Validity Prices provided in this solicitation shall be valid for at least One-Hundred and Twenty (120) days from time of solicitation opening unless otherwise extended and agreed upon by the City and Bidder. No Exclusive Contract Bidder agrees and understands that the contract shall not be construed as an exclusive arrangement and further agrees that the City may, at any time, secure similar or identical services from another vendor at the City’s sole option. Responsive In order to be considered responsive to the solicitation, the contractor’s bid shall fully conform in all material respects to the solicitation and all of its requirements, including all form and substance. Responsible In order to be considered as a responsible bidder, bidder shall be fully capable to meet all of the requirements of the solicitation and subsequent contract, must possess the full capability, including financial and technical, to perform as contractually required, and must be able to fully document the ability to provide good faith performance. Minimum Qualifications To be eligible for award of a contract in response to this solicitation, the Bidder must demonstrate that they have successfully completed services, as specified in the #SCOPE OF WORK/SERVICES section of this solicitation, are normally and routinely engaged in performing such services, and are properly and legally licensed (if required) to perform such work. Bidder must possess and be able to provide the City with any and all required Federal, State, County and/or municipal licenses, and occupational licenses. Bidder must be able to provide proof of valid licensing for all subcontractors and/or material suppliers hired by the contractor, if requested. In addition, the Bidder must have no conflict of interest with regard to any other work performed by the Bidder for the City. Award of Contract Award may be in the aggregate, or by line Item, or by group, whichever is determined to be in the best interest of the City. Award will be made to the responsive and responsible bidder, quoting the lowest price, for that product/service that will best serve the needs of the City. The Contract will be awarded only to a Bidder, who in the opinion of the Engineer, is fully qualified to undertake the work, quoting the lowest price, for that product/service that will best serve the needs of the City. The City reserves the right before awarding the Contract to require a Bidder to submit such evidence of his qualifications as it may deem necessary and may consider any available evidence of his financial status, technical qualifications, and other qualifications and abilities. The City also reserves the right to accept or reject any or all bids, part of bids, and to waive minor irregularities or variations to specifications contained in bids, and minor irregularities in the bidding process. The City also reserves the right to award the contract on a split order basis, lump sum basis, individual item basis, or such combination as shall best serve the interest of the City. As applicable, the City shall comply with Section 287.05701, Florida Statutes, in not considering or giving preference for an award based on a vendor’s social, political, or ideological interest. The City, in all solicitations or advertisements for purchasing of goods, supplies, materials, equipment and services, will receive consideration from qualified businesses without regard to race, color, religion, sex, sexual orientation, gender identity, or national origin. Execution Of Contract The Bidder awarded the Contract shall, within ten days from the date of award, execute all required do
Published attachments
- Attachment A - Contract and P&P Bonds
- Attachment_B_-_General_Conditions_Public_Utilities
- Attachment_C_-_Supplementary_General_Conditions
- Attachment D - Technical Specifications_Addendum 1
- Attachment E - Drawings File 1 of 2_Addendum 1
- Attachment E - Drawings File 2 of 2_Addendum 1
- Lift_Station_W-27_Upgrades_and_Force_Main_Replacement_(Project_No._23-8073)_(Addendum_#2_Revision).pdf
Addenda and notices
Official Notice #1: Notice of a Public Meeting (Virtual) · 1
Addendum #1 · 1
Addendum No. 1 includes the following: Revised attachment: Attachment D - Technical Specifications_Addendum 1 Revised attachment: Attachment E - Drawings File 1 of 2_Addendum 1 Revised attachment: Attachment E - Drawings File 2 of 2_Addendum 1 Please use the See What Changed link to view all the changes made by this addendum.
Addendum #2 · 2
Addendum No. 2 includes the following: Item 1: Technical Specifications A. SECTION 01 20 00 Measurement and Payment 1. On page 01 20 00-12, paragraph 1.19, K(29), delete the words “Furnish and Place Asphalt: Measurement for payment of asphalt pavement will be based upon the number of square yards of such asphalt pavement constructed, as detailed in the Drawings, all in accordance with the requirements of the Contract Documents. Payment for placement of asphalt pavement will be made at the unit price per square yard for such placement as named and at the thickness indicated in the bid Schedule which price will constitute full compensation for applying a tack coat and furnishing, placing and compacting the asphalt surface, complete in place to the cross section and thicknesses show on the Drawings; including restoration of traffic loop detectors, adjustment of finished grades of valve boxes, manholes, and catch basins, and all cleanup of the area disturbed by the construction. Payment for maintenance and protecting of traffic, including but not limited to temporary striping between lifts of asphalt, as required, shall be made under the maintenance and protection of traffic item named in the Bid Schedule.” and replace them with “Mill and Resurface Asphalt: Measurement for payment for milling existing asphalt and resurfacing will be based upon the number of square yards of such materials actually milled and resurfaced in accordance with the requirements of the Contract Documents. Payment for milling and resurfacing existing asphalt will be made at the unit price per square yard up to 1-inch depth, which price shall constitute full compensation for milling, hauling off and disposing of the milled material, resurfacing, and for any other appurtenant items needed for milling and resurfacing asphalt for which separate payment is not specifically included in the Bid Schedule. Payment shall include milling up to 1-inch of depth and a minimum of 1-inch thick to a maximum of 1.5-inches thick Type SP-9.5 or milling up to 1-inch of depth and application of up to 3-inches thick Type SP-12.5 leveling course and a 1-inch thick Type SP-9.5 surface course.” Item 2: Technical Drawings A. Volume 3, Drawing C-1 1. Delete Sheet C-1, Revision 6 and replace with Sheet C-1, Revision 7. B. Volume 3, Drawing C-9 1. Delete Sheet C-9, Revision 5 and replace with Sheet C-9, Revision 7. C. Volume 3, Drawing C-10 1. Delete Sheet C-10, Revision 5 and replace with Sh
Public questions and answers
Is there an engineer's estimate for the project?
$11,929,000
What is the budget/engineers estimate?
$11,929,000
Please provide the Engineer's estimate for this project.
$11,929,000
Could you please let us know if Sewpercoat can be approved for the corrosion protection coatings inside the existing structure surfaces where you currently have Epoxytec specified. Sewpercoat has been successfully used and spec’d in the City of Hollywood for decades?
'Refer to Specification Section 01 25 00 for subsitution procedures. Any proposed product substitution must comply with all requirements of Section 09 96 59.
The price for the restoration of the trench pipe in the Force Main and the Drainage, in which items should we include it?
Refer to Specification Section 01 20 00. Item 14 (force main) and Item 24 (stormwater pipe) include all associated restoration work for each trench. In addition, refer to Items 1A and 3C and revised IFB Section 6 – PRICING (BID FORM), included in Addendum No. 2.
The 1" Milling Item is missing. Please advise.
Provide milling in accordance with the Contract Documents. Refer to Items 1A and 3C and revised IFB Section 6 – PRICING (BID FORM), included in Addendum No. 2. No separate payment will be made for milling.
What type of asphalt is required ( SP- FC ,etc)?
Provide asphalt in accordance with the Contract Documents. Refer to Volume 3, Drawing C-17. For asphalt related to work at Lift Station W-27, refer to Volume 2, Drawings CD-01 and CD-02.
According with the item # 18, the Contractor would have to restore the road in many places to install 500 LF of restrains on 48" Force Main. That means that the milling and resurfacing on Taft Street should be more. Please advise.
Refer to Item 3C and revised IFB Section 6 – PRICING (BID FORM), included in Addendum No. 2.
Please confirm that the 2 Plug Valves are to be installed in a precast structure.
Refer to Item 3A and revised IFB Section 6 – PRICING (BID FORM), included in Addendum No. 2. Refer to Volume 3, Drawing C-3, Station 0+17.5 and refer to Drawing C-15.
The plans and specifications state that the pumps may be Flygt or approved equals. Our suppliers are asking whether the City accepts approved pumps other than Flygt?
Refer to Section 43 25 13.20, Paragraph 2.02.
The Drainage system does not Baffles; is this correct?
No baffles are required per the Contract Documents.
Should the Catch Basins have a Concrete or Asphalt Aprons?
No concrete or asphalt aprons are required per the Contract Documents.
Please review the drainage design from Station 40 to 100 along Taft Street. As you can see, the center of the pipeline runs through the middle of the sidewalk in that section; this means that half of the excavator ( regardless of how small it may be ) encroaches onto private property, damaging some landscaping and PVC Fence. Furthermore, since the ground consists of sand and the use of the Trench Box there is a risk of additional damage to the private property. Please advise.
Refer to revised Technical Drawings included in Addendum No. 2.
Under which item do we include the price for the 3" DIP Force Main ?
'Refer to Specification Section 01 20 00, Item 13.
Please review the quantity for Milling & Resurfacing. The bid items indicate 1,100 SY, whereas our measurement is close to 7,000 SY.
Refer to Item 3C and revised IFB Section 6 – PRICING (BID FORM), included in Addendum No. 2.
OpenGov categories
- 89000 · Water Supply, Groundwater, Sewage Treatment, And Related Equipment (Not For Air Conditioning, Steam Boiler, Or Laboratory Reagent Water)
- 89065 · Sewage and Waste Treating Equipment and Supplies
- 89066 · Sewer Lift Stations and Parts
- 91300 · Construction Services, Heavy (Incl. Maintenance And Repair Services)
- 91400 · Construction Services, Trade (New Construction)
- 96800 · Public Works And Related Services
- 96895 · Wastewater Treatment Plant, Operations, and Testing
- 96896 · Water and Wastewater Treatment Services