State and local · OpenGov
Manhole and Sewer Lateral Rehabilitation, As Needed
Description
The Vendor/Contractor shall provide all labor, equipment, and materials for manhole and sewer lateral rehabilitation to include but not limited to pre-inspections, leak proofing, surface preparation, repair and coating, casting adjustment, chimney reconstruction, and flow control. This is an indefinite quantity contract with no guarantee of the use of services or guarantee of a minimum or maximum dollar amount to be expended. All work shall be in strict compliance with the latest codes, standards, and practices, and in accordance with Hernando County Utilities Specifications Section 9, Detail S-02, and Federal, State, and Local laws. SCOPE AND SPECIFICATIONS Manhole & Sewer Lateral Rehabilitation The purpose of this solicitation is to award a contract to one vendor to provide all labor and supplies, equipment, and any incidental items for the completion of each project. Request for services will be based on annual County inspections and/or as needed. The County will notify the vendor/contractor with an approved purchase order to complete each project. No work shall commence without County approval and/or an approved purchase order. This is an indefinite quantity contract with no guarantee of the use of services or guarantee of a minimum or maximum dollar amount to be expended. All work shall be in strict compliance with the latest codes, standards, and practices, and in accordance with Hernando County Utilities Specifications Section 9, Detail S-02, Federal, State, and Local laws. Actual annual expenditures are unknown and County purchases from this contract will be based upon the department available budget, actual work identified, and as required. 7.2 MANHOLE REHABILITATION SERVICES Project Overview The Contractor shall provide all labor, equipment, and materials for the following services. Assignment: Work is on an as-needed basis. Compliance: All work must adhere to applicable ASTM standards, industry best practices, and FDOT-specified traffic control requirements for right-of-way areas. Pre-Inspections: Comprehensive assessment of manhole conditions prior to work. Leak Proofing: Elimination of active infiltration and structural leaks. Surface Preparation: Cleaning and sandblasting (required), removal of existing coatings or linings, and patching to restore damaged or removed base material. Repair & Coating: Application of repairs and protective coatings as deemed appropriate by the Owner. Casting Adjustment: Replacement or adjustment of manhole rings and covers. Chimney Reconstruction: Replacement of brick chimneys with Precast concrete risers. Flow Control: Implementation of flow control as required to perform assessment or rehabilitation. Product and Material Specifications: All furnished materials shall be designed and manufactured for sewer manhole rehabilitation. Materials must have a proven history of performance in sewer environments, be delivered in original unopened packaging, and be stored/handled according to manufacturer recommendations. Leak Mitigation and Patching Active Leaks: Use chemical grout or a premixed, fast-setting, waterproof cement plug (hydraulic cement with graded silica aggregates). Must be chloride-free with a set time of approximately 1 minute and a 10-minute compressive strength of approximately 500 psi. Non-Leaking Repairs: Use premixed, non-shrink cement-based patching material for cracks and spalls. Must have a set time (ASTM C-191) under 30 minutes and a minimum ultimate compressive strength (ASTM C-882-Modified) of 1,700 psi. Lining Systems Cementitious Lining: Spray-applied or centrifugally cast structural reinforced calcium aluminate blend. 28-Day Minimums: Compressive Strength (ASTM C-579B): 3,000 psi; Tensile Strength (ASTM C-496): 300 psi; Flexural Strength (ASTM C-293): 600 psi. Epoxy/Polymeric Systems: Multi-component stress skin panel liner or spray-applied epoxy formulated for sanitary sewer environments and hydrogen sulfide resistance. Minimum Cured Standards: Tensile Stress (ASTM D-638): 7,000 psi Flexural Stress (ASTM D-790): 13,000 psi Flexural Modulus (ASTM D-790): 500,000 psi Compressive Strength (ASTM D-695): 13,000 psi 7.2. SEWER LATERAL CLEANING, REPAIR, AND LINING Project Overview The Contractor shall provide all labor, materials, equipment, and supervision necessary to clean, inspect, assess, and rehabilitate sanitary sewer laterals and main-to-lateral connections. Assignment: Work is on an as-needed basis. Compliance: All work must adhere to applicable ASTM standards, industry best practices, and FDOT-specified traffic control requirements for right-of-way areas. Sanitary Sewer Cleaning The Contractor may utilize hydro-jetting, rodding or mechanical cutting, provided the method does not damage infrastructure or private property. Scope: Remove roots, grease, and debris ranging from light deposits to heavy obstructions to allow for accurate inspection. Sequence: Upstream cleaning must be completed first. Any downstream cleaning performed out of sequence will be re-cleaned at the Contractor's expense. Disposal: All debris must be removed and disposed of legally off-site. Sewer Condition Assessment (CCTV) Standards: Inspections must follow NASSCO PACP, LACP, and MACP standards. Data Capture: Provide digital video and defect coding to support Hernando County asset management. Camera Operations: Analog: Max speed 30 ft/min; must be centered with clear video. HD (1080p+): Max speed 50 ft/min. Requirements: Cameras must stop and pan 360° at every defect, joint separation, lateral connection, or previous repair. 7.3. LATERAL REHABILITATION SERVICES Technical Requirements Methodology: Trenchless technologies, specifically CIPP (Cured-in-Place Pipe) using UV, ambient cure, steam, or water cure. Conform to applicable ASTM standards (e.g., ASTM F1216, F2019, F2599, F2561, F1743, and other pertinent ASTM standards). Interface Seal: Must provide a watertight, seamless, full-circle structural seal extending at least 12 inches into both the main and the lateral. Design Life: Minimum 50-year service life, designed for "fully deteriorated" conditions and external groundwater pressure. Post-Inspection: Post-rehabilitation CCTV is required to verify full coverage and water tightness. Reporting & Accountability: Documentation: Provide individual electronic inspection reports for each lateral via email. Data Integrity: Automated Defect Recognition (ADR) tools are permitted but must be verified by qualified personnel. Restoration: All work deficiencies or damage to residential/commercial property must be corrected at the Contractor's expense. 7.4. CONTRACTOR QUALIFICATIONS Licensing: Must hold appropriate state/local licenses in Undergrou SOLICITATION ISSUED BY: BOARD OF COUNTY COMMISSIONERS HERNANDO COUNTY, FLORIDA Jerry Campbell, Chairman Ryan Amsler, Vice Chairman Steve Champion, Second Vice Chairman John Mitten John Allocco SUBMIT BID OFFER TO: HERNANDO COUNTY PROCUREMENT DEPARTMENT via Hernando County's eProcurement Portal Carla Rossiter-Smith Director of Procurement and Strategic Initiatives SEALED BIDS FOR FURNISHING THE SERVICES, SUPPLIES OR EQUIPMENT DESCRIBED HEREIN WILL BE RECEIVED BY THE OFFICE OF PROCUREMENT, VIA THE COUNTY'S eProcurement Portal UNTIL 10:00 a.m., LOCAL TIME ON Monday, November 30, 2026 . NO BIDS WILL BE ACCEPTED AFTER THE BID SUBMISSION DEADLINE. THIS IS AN ADVERTISED SOLICITATION AND THE RESPONDING BIDDERS WILL BE PUBLICLY READ AT 15470 FLIGHT PATH DRIVE BROOKSVILLE, FL 34604 IN THE ADMINISTRATIVE CONFERENCE ROOM AT 10:00 a.m. ON Monday, November 30, 2026 . PURSUANT TO FS 119.071 SEALED BIDS, PROPOSALS, OR REPLIES RECEIVED BY AN AGENCY PURSUANT TO A COMPETITIVE SOLICITATION ARE EXEMPT FROM INSPECTION UNTIL SUCH TIME AS THE AGENCY PROVIDES NOTICE OF AN INTENDED DECISION OR UNTIL THIRTY DAYS AFTER OPENING THE BIDS, PROPOSALS, OR FINAL REPLIES, WHICHEVER IS EARLIER. Procurement Contact Information: Gretchen Bechtel , Contract Agent II 352-754-4020 gbechtel@co.hernando.fl.us INTRODUCTION ADVERTISEMENT OF BID INVITATION TO BID NOTICE IS HEREBY GIVEN that the Board of County Commissioners of Hernando County, Florida, is accepting Bids for: TERM CONTRACT ITB NO. SOLICITATION # 26-T01400 FOR Manhole and Sewer Lateral Rehabilitation, As Needed Hernando County Board of County Commissioners is soliciting providers that are active in Manhole and Sewer Lateral Rehabilitation services. Bids for furnishing the above will be received and accepted up to 10:00 a.m. (local time), Monday, November 30, 2026 , via Hernando County's eProcurement Portal . Only electronic submittals through the eProcurement Portal shall be accepted by the County. The Hernando County Board of County Commissioners reserves the right to accept or reject any or all bids and waive informalities and minor irregularities in bids received in accordance with this solicitation and the Hernando County Procurement Ordinance. Providers interested in submitting a bid may obtain all information, forms, documents, plans, and drawings pertaining to this solicitation by visiting the County's eProcurement Portal. For additional information, please visit the Hernando County Board of County Commissioners Procurement Department at www.hernandocounty.us or by by submitting a question via the Q&A tab in the County's eProcurement Portal . Ex Parte Communication: Please note that to ensure the proper and fair evaluation of all bids, the County prohibits ex parte (i.e., unsolicited) communication initiated by any bidder to any County official or employee evaluating or considering the bids prior to the time a decision has been made. Communication between any bidder and the County will be initiated by the appropriate County official or employee in order to obtain information or clarification needed to develop a proper and accurate evaluation of the bid. Ex Parte communication may be grounds for disqualifying the offending bidder from consideration or award of the solicitation or any future solicitation. The Procurement Department will post addenda on the eProcurement Portal in response to all questions in accordance with these solicitation instructions. It is your responsibility to visit the County’s eProcurement portal to ensure that you are aware of all such addenda. Pursuant to sec. 119.071, F.S., sealed bids, proposals or replies received by an agency pursuant to a competitive solicitation are exempt from inspection until such time as the agency provides notice of an intended decision or until thirty (30) days after opening the bids, proposals, or final replies whichever is earlier. NOTICE TO BIDDERS To ensure that your bid is responsive, you are urged to request clarification or guidance on any issues involving this solicitation before submission of your bid. Your method of contact for this solicitation is the Q&A Tab in the County's eProcurement Portal . AWARD UPON AWARD, PLEASE SUBMIT INVOICES TO: Hernando County Utilities 15365 Cortez Blvd. Brooksville, FL 34613 DEFINITIONS AND SOLICITATION INSTRUCTIONS DEFINITION OF TERMS Where the following terms, or their pronouns, occur herein, the intent and meaning shall be as follows: BID DOCUMENTS: The forms and documents pertaining to this solicitation that must be filled out, completed or signed, as applicable, by the bidder. BIDDER: Any person, joint venture, or business organization submitting a bid to the County in response to this solicitation. Sometimes referred to as “proposer” or “respondent”. BOARD: The Board of County Commissioners for Hernando County, Florida; the governing body of Hernando County, Florida. CHANGE ORDER: A document that details and authorizes an addition, deletion, or revision in the contracted work or an adjustment in the contract price or times, issued on or after the effective date of the Contract, and which requires the recommendation of the Engineer and the authorized signatures of the Vendor/Contractor and the County and any other applicable agency. CONTRACT or THE CONTRACT (uppercase C): The written agreement, and any amendments, extensions and renewals thereof, resulting from this solicitation, that is executed by the County and Vendor/Contractor and that includes the Contract Documents listed in the Contract including, but not limited to the Solicitation-Offer-Award, plans, specifications, notices to the Vendor/Contractor, proposal, surety bonds, addenda, bid documents and other documents, and other incorporated or referenced documents in the solicitation or the Contract, whether attached thereto or not. COUNTY: Hernando County, Florida, a political subdivision of the State of Florida; sometimes referred to as "the Owner". F.S.: Florida Statutes; the version in effect on the effective date of the Contract, unless otherwise indicated. PUBLIC OPENING : The opening of the bids or proposals received in response to this solicitation, and the announcing of the bidders that submitted the bids received in response to this solicitation, in the presence of the public, that occurs immediately after the bid submission deadline. SOLICITATION: This Invitation to Bid (“ITB”), Request for Proposals (“RFP”) or Request for Quotes (“RFQ”), whichever applies. VENDOR/CONTRACTOR: The entity with whom the County has entered into the Contract as a result of this solicitation. Sometimes referred to as the "Contractor". WORK or THE WORK: The services and supplies without limitation, or any portion or quantity thereof, required by the solicitation prior to the Contract’s effective date; or those of the Contract beginning on the Contract’s effective date. YOU/YOUR: The bidder, whether singularly or on behalf of an entity or a joint venture, its business entities, successors, assigns, employees and representatives, that intends to submit, or does submit, a bid in response to this solicitation. If you and the Vendor/Contractor are one and the same, then any reference to you/your also refers to the Vendor/Contractor and vice-versa. AVAILABILITY OF BIDDING DOCUMENTS You may obtain all information, bid documents, plans, drawings, site locations, and other documents pertaining to this solicitation by visiting Hernando County's eProcurement Portal . For additional information please contact the County's Procurement Department via the County's eProcurement Portal Q&A Tab. PREPARATION OF BID To ensure acceptance of your bid, please follow these instructions: To submit a bid, you must register via the County's eProcurement Portal . Once registered, to submit a response please click on the "DRAFT RESPONSE" button and provide an answer to all of the prompts and questions. You must respond to all required questions and acknowledge all addenda so that your bid may be considered responsive by the County. Submitting more than one bid with different pricing will result in your bid(s) being rejected. Bids that do not comply with these conditions may be subject to rejection. You may submit your bid only through the Hernando County's eProcurement Portal . You are solely and strictly responsible for submitting your bid on or before the bid submission deadline; no bid will be accepted after the bid submission deadline. The County bears no responsibility for delays caused by wi-fi connection or speed, power outage or any other occurrence. Submitting your bid by any means other than electronically via the County's eProcurement Portal will result in your bid being rejected. You must complete and submit all bid documents using the instructions herein. The County will not honor any explanation or change in the bid documents unless the County has issued a written addendum authorizing such change through the eProcurement Portal. The County reserves the right to reject any or all bids and to waive any informalities thereof. Your bid shall be firm for a period of ninety (90) days after the time set for public opening. Upon award, prices quoted in your bid will be in effect for the term of the Contract. Unless otherwise expressly stated herein, the County will furnish no material, labor, or facilities. You must properly fill in all blank spaces in the bid documents. You may not change any phraseology in, nor make any additions to, the bid documents; such changes or additions shall render your bid irregular, and your bid will be rejected. You shall make all investigations necessary to thoroughly inform yourself regarding all drawings, specifications, delivery requirements, performance requirements, site locations and all solicitation instructions to satisfy yourself of conditions affecting submission of your bid and the terms and cost of performing the Contract. The County will not accept your or the Vendor/Contractor’s pleas of ignorance regarding conditions that exist or may hereafter exist as a result of your failure or omission to make the necessary investigations, or your failure to fulfill in every detail the requirements of the Contract, as a basis for varying the County's requirements or the compensation under the Contract. The submittal or your bid is prima facie evidence you have conducted such investigations. Communications: All technical, scope, and project related questions shall be submitted through the Q&A Tab before the question submission deadline and according to these specifications. Any and all other bidding communications shall only be to the County's Procurement representative using the contact information herein. Communicating with any other County official or employee regarding this solicitation will subject you to disqualification. PUBLIC OPENING: Bids received through the eProcurement Portal by the bid submission deadline will be publicly opened immediately after the bid submission deadline and will remain binding upon the respective bidders for a period of ninety (90) days thereafter. Pursuant to sec. 119.071(1)(b), F.S., sealed bids, proposals, or replies received by an agency pursuant to a competitive solicitation are exempt from inspection until such time as the agency provides notice of an intended decision or until thirty (30) days after public opening of the bids, proposals, or final replies, whichever is earlier. QUESTIONS REGARDING SPECIFICATIONS OR BIDDING PROCESS To ensure fair consideration for all bidders, the County prohibits communication to or with any department, division or employee during the bid process, except as provided below: All questions regarding interpretation of the specifications or the bidding process shall be addressed in writing via the County's eProcurement Portal Q&A Tab , prior to the question submission deadline. The County’s interpretation or clarification made in response to questions will be expressed in the form of an addendum which will be posted on the County's eProcurement Portal Q&A tab . Oral answers will not be authoritative. It is your responsibility to visit https://secure.procurenow.com/portal/hernandocounty to ensure you are aware of all addenda issued for this solicitation. Questions will only be accepted until the question submission deadline: Monday, November 9, 2026 at 5:00 pm You must acknowledge all addenda via the County's eProcurement Portal. Your failure to acknowledge any addendum may result in your bid being rejected as non-responsive. PROHIBITED COMMUNICATION Except for technical, scope, and project-related questions, and questions regarding interpretation of the specifications or the bid process, which shall be submitted through the eProcurement Portal as directed above, your communications with the County shall be through the Procurement Department. Any attempt to communicate with any County employee outside the Procurement Department will be considered a violation of section 19 of the Hernando County Procurement Manual and may result in the rejection of your bid. WITHDRAWAL OF BIDS: You may withdraw your bid only through the County’s eProcurement Portal prior to the bid submission deadline. Attempted
Published attachments
Addenda and notices
Addendum #1 · 1
Addendum No. 1
Official Notice #1: Notice Issued in error · 1
Notice issued in error
Addendum #2 · 2
Addendum No. 2
Public questions and answers
Please consider Sherwin Williams DuraPlate 6100 as a Polyurea Substitution .https://industrial.sherwin-williams.com/na/us/en/protective-marine/catalog/product/products-by-industry.11543396/dura-plate-6100.9752910.html
Thank you for your interest in doing business with Hernando County. Your question is received and will be answered via Addendum.
Please consider Loctite Geospray for cementitious coating. https://www.cs-nri.com/product/geospray-geopolymer/
Thank you for your interest in doing business with Hernando County. Your question is received and will be answered via Addendum.
Please consider Sherwin Williams DuraPlate 6100 for epoxy coating. https://industrial.sherwin-williams.com/na/us/en/protective-marine/catalog/product/products-by-industry.11543396/dura-plate-6100.9752910.html
Thank you for your interest in doing business with Hernando County. Your question is received and will be answered via Addendum.
Can you please provide an estimated annual quantity of manholes and sewer laterals requiring rehabilitation?
Thank you for your interest in doing business with Hernando County. Your question is received and will be answered via Addendum.
Please provide the historical quantities or expenditures from the existing contract be provided?
Thank you for your interest in doing business with Hernando County. Your question is received and will be answered via Addendum.
Will the County establish a minimum quantity of work per purchase order or allow for a separate mobilization charge when only a small number of structures require rehabilitation?
Thank you for your interest in doing business with Hernando County. Your question is received and will be answered via Addendum.
Please provide anticipated manhole depths, diameters, and general conditions?
Thank you for your interest in doing business with Hernando County. Your question is received and will be answered via Addendum.
Are the structures primarily located in roadways, easements, or off-road areas?
Thank you for your interest in doing business with Hernando County. Your question is received and will be answered via Addendum.
What is the expected annual spend on the contract?
Thank you for your interest in doing business with Hernando County. Your question is received and will be answered via Addendum.
Section 7.6 D [Specs p.43] specifies a ten (10) year labor and materials warranty. Standard industry warranties for spray-applied coatings and CIPP lateral liners are typically 1 to 5 years. Will the County clarify if manufacturer standard warranties apply, or confirm if the 10-year requirement applies strictly to all manhole lining systems?
Thank you for your interest in doing business with Hernando County. Your question is received and will be answered via Addendum.
Section 7.5 F [Specs p.42] states that TTC items will be reimbursed at 110% of supplied invoices. Can contractors submit internal cost accounting logs if MOT/TTC is self-performed by contractor in-house certified MOT personnel, or are third-party subcontractor invoices required for reimbursement?
Thank you for your interest in doing business with Hernando County. Your question is received and will be answered via Addendum.
OpenGov categories
- 81522 · Gaskets: Flange, Handhole and Manhole, All Types
- 89030 · Manholes, and Manhole Covers, Frames, Grates, Rings, Yokes, etc.
- 91063 · Public Utilities: Water, Sewer and Gas Maintenance and Repair
- 91381 · Maintenance and Repair, Sewer and Storm Drain (Including Removal)