Description

We are seeking one contractor for the full scope of work which generally consists of the following: Northeast Advanced Pollution Control Facility Generator Docking Station - Sand Filter Building. The Project consists of installation of new generator docking stations. All associated electrical work shall be provided for the removal of designated equipment and the installation of new equipment as described herein and on the project drawings. Northeast Advanced Pollution Control Facility Generator Docking Station - Reclaim Building. The project consists of installation of new generator docking stations. All associated electrical work shall be provided for the removal of designated equipment and the installation of new equipment as described herein and on the project drawings. Northeast Advanced Pollution Control Facility Install Generator Docking Station at Reclaim Building General Conditions 8" reinforced Equipment Pad 4" Housekeeping Pad ADD Alternate #1 Canopy FDN Earthwork 6" Pipe Bollard/ Conc Filled ADD Alternate #1 8'x12'x9' ht - Alum Canopy Electrical Gear Feeder and control Circuits Trenching/Compacting/Backfill GPR Radar NEMA-3R SS Pullboxes Generator Rental/Fuel Contingency 10% of Base Bid 10% of Base Bid Northeast Advanced Pollution Control Facility Install Generator Docking Station at Sand Filter Building General Conditions 8" reinforced Equipment Pad 4" Housekeeping Pad ADD Alternate #1 Canopy FDN Earthwork 6" Pipe Bollard/ Conc Filled ADD Alternate #1 8'x12'x9' ht - Alum Canopy Electrical Gear Feeder and control Circuits Trenching/Compacting/Backfill GPR Radar NEMA-3R SS Pullboxes Handhole (4'x4') Traffic Road Handhole (2'x3') Generator Rental/Fuel Contingency 10% of Base Bid SUPPLEMENTAL TECHNICAL SPECIFICATIONS - Section IVA Add Technical Specifications - Section IVA here Northeast Advanced Pollution Control Facility Install Generator Docking Station at Sand Filter and Reclaim Buildings 4. SUPPLEMENTAL TECHNICAL SPECIFICATIONS - Section IVA 4.1. Technical Specifications Reference Attachments: 21-0019-UT_NE Generator Docking Station_Sand Filter 100% Tech Sepcs 21-0019-UT_NE Generator Docking Station_Reclaim 100% Tech Sepcs INSTRUCTIONS TO BIDDERS SECTION II INSTRUCTIONS TO BIDDERS 1. COPIES OF BIDDING DOCUMENTS 1.1. Bid Documents, any attachments and addenda are available for download at: https://procurement.opengov.com/portal/myclearwater/projects/310477 . Bidding Documents may include, but are not limited to, plans, specifications, bond forms, contract form, affidavits, bid/proposal form, and addendums. 1.2. Complete sets of Bidding Documents must be used in preparing bids. Neither the City nor the Engineer shall be liable for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents, by Bidders, sub-bidders, or others. 2. QUALIFICATION OF BIDDERS 2. 1 Each prospective Bidder must pre-qualify to demonstrate, to the complete satisfaction of the City of Clearwater, that the Bidder has the necessary facilities, equipment, ability, financial resources and experience to perform the work in a satisfactory manner. An application package for pre-qualification may be obtained by contacting the City of Clearwater, Engineering Division by phone at (727) 562-4750. Pre-qualification requirement information is also available on the City of Clearwater Website at address: www.myclearwater.com/government/city-departments/engineering/construction-management . Contractors wanting to pre-qualify to bid on a project as a General Contractor must do so two weeks (ten workdays) prior to the bid opening date. Bidders currently pre-qualified by the City do not have to make reapplication. It is the Contractor’s responsibility to confirm pre-qualification status before a Bid Opening. The Contractor shall include copies of their current license/registration with the State of Florida and Pinellas County (if applicable) with their bid response. 3. EXAMINATION OF CONTRACT DOCUMENTS AND SITE 3.1.It is the responsibility of each Bidder, before submitting a Bid, to (a) examine the Contract Documents thoroughly; (b) visit the site to become familiar with local conditions that may in any manner affect cost, progress, performance or furnishing of the work; (c) consider and abide by all applicable federal, state and local laws, ordinances, rules and regulations; and (d) study and carefully correlate Bidder's observations with the Contract Documents, and notify Engineer in writing of all conflicts, errors or discrepancies in the Contract Documents. 3.2.For the purposes of bidding or construction, bidder may rely upon the accuracy of the technical data contained in reports of explorations and tests of subsurface conditions at the site which have been utilized by the Engineer in the preparation of the Contract Documents, but not upon non‑technical data, interpretations or opinions contained therein or for the completeness thereof. Drawings relating to physical conditions of existing surface and subsurface conditions (except Underground Facilities) which are at or contiguous to the site and which have been utilized by the Engineer in preparation of the Contract Documents, may be relied upon by Bidder for accuracy of the technical data contained in such drawings but not upon the completeness thereof for the purposes of bidding or construction. 3.3.Information and data reflected in the Contract Documents with respect to Underground Facilities at or contiguous to the site are based upon information and data furnished to the City and Engineer by owners of such Underground Facilities or others, and the City does not assume responsibility for the accuracy or completeness thereof unless expressly provided in the Contract Documents. 3.4.Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders on subsurface conditions, Underground Facilities, other physical conditions, possible conditions, and possible changes in the Contract Documents due to differing conditions appear in the General Conditions. 3.5. Before submitting a Bid, each Bidder shall, at Bidder's own expense, make or obtain any additional examinations, investigations, explorations, tests and studies and obtain any additional information and data which pertain to the physical conditions (surface, subsurface and Underground Facilities) at or contiguous to the site or otherwise which may affect cost, progress, performance or furnishing the work in accordance with the time, price and other terms and conditions of the Contract Documents. 3.6. On request in advance, City will provide each Bidder access to the site to conduct such explorations and tests at Bidder's own expense as each Bidder deems necessary for submission of a Bid. Bidder shall fill all holes and clean up and restore the site to its former condition upon completion of such explorations and tests. 3.7. The lands upon which the Work is to be performed, rights-of-way and easements for access thereto and other lands designated for use by the Contractor in performing the Work are identified in the Contract Documents. All additional lands and access thereto required for temporary construction facilities or storage of materials and equipment are to be provided by the Contractor. Easements for permanent structures or permanent changes in existing structures are to be obtained and paid for by the City unless otherwise provided in the Contract Documents. 3.8. The submission of a Bid will constitute an unequivocal representation by the Bidder that the Bidder has complied with every requirement of these Instructions to Bidders and that, without exception, the Bid is premised upon performing and furnishing the Work required by the Contract Documents by such means, methods, techniques, sequences or procedures of construction as may be indicated in or required by the Contract Documents, and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions of performance and furnishing of the work. 4. INTERPRETATIONS AND ADDENDA 4.1. All questions as to the meaning or intent of the Contract Documents are to be directed in writing to the Engineer. Interpretations or clar GENERAL CONDITIONS Section III - General Conditions can be found on the City's website at: https://www.myclearwater.com/Business-Development/Doing-Business-with-the-City/Engineering-Construction-Bid-Information/Contract-Specifications TECHNICAL SPECIFICATIONS SCOPE OF WORK Project Name: Northeast Advanced Pollution Control Facility Install Generator Docking Station at Sand Filter and Reclaim Buildings Project Number: 21-0019-UT Scope of Work: We are seeking one contractor for the full scope of work which generally consists of the following: Northeast Advanced Pollution Control Facility Generator Docking Station - Sand Filter Building. The Project consists of installation of new generator docking stations. All associated electrical work shall be provided for the removal of designated equipment and the installation of new equipment as described herein and on the project drawings. Northeast Advanced Pollution Control Facility Generator Docking Station - Reclaim Building. The project consists of installation of new generator docking stations. All associated electrical work shall be provided for the removal of designated equipment and the installation of new equipment as described herein and on the project drawings. Section IV - Technical Specifications Section IV - Technical Specifications can be found on the City's website at: https://www.myclearwater.com/Business-Development/Doing-Business-with-the-City/Engineering-Construction-Bid-Information/Contract-Specifications Section V - Contract Documents Section V - Contract Documents can be found on the City's website at: https://www.myclearwater.com/Business-Development/Doing-Business-with-the-City/Engineering-Construction-Bid-Information/Contract-Specifications PRICING SHEET: The City intends to make a single award to the lowest responsive and responsible bidder. Bidders shall provide pricing for both the Reclaim Building and Sand Filter Building. The City intends to make a single award to the lowest responsive and responsible bidder based on the combined bid total for both buildings. SUBMITTAL REQUIREMENTS

Published attachments
Public questions and answers
  • We are currently prequalified by the City of Clearwater with a maximum bid limit of $1.5 million under the following categories: Commercial Buildings (New), Commercial Buildings (Renovation/Repairs), Concrete Flatwork, Construction Management Services, Demolition, Excavation/Sitework, and Landscape/Irrigation. Can you please let us know if we still need to obtain prequalification for the Electrical category in order to bid this project? Thank you. We appreciate your guidance.

    Yes, you must be pre-qualified in the Electrical category to bid on this project.

  • Are there any drawings available for this project? If so, please send them over at your convenience.

    Drawings have been uploaded as attachments C & D

  • Cannot open the plans. Getting a msg says "the destination path is too long. Rename the compressed zip folder and try again."

    Thank you so much for letting us know.

  • I went into my downloads, renamed the zip folder to a shorter name, and it then allowed me to open the plans.

    Thank you so much for letting us know.

  • Are there drawings available for this project?

    Drawings have been uploaded as attachments C & D

  • Is the re-sod to be completed under the electrical contractor?

    Re-sodding is required by the contract documents and should be included in the bid. The contractor responsible for the overall scope must ensure the re-sodding is completed. Whether that contractor performs the work with its own crews or assigns it to a landscaping subcontractor is a matter of the contractor’s means and methods.