Northside Park Site Improvements
Description
The County of Greenville is seeking proposals from qualified general contractors to complete park renovations at Northside Park - 101 West Darby Road, Taylors, SC 29687. Project renovations include the parking lot, access routes such as sidewalks and stairs, and expansion of the athletic courts to include shaded plaza and additional pickleball courts. Construction documents are included and all details referenced within are part of the bid package. Details include demolition, site work, grading, paving, stormwater treatment, and landscaping. Table 1 Mobilization, administration, staking, traffic control Erosion control Existing concrete pavement to be sawcut and removed Existing asphalt pavement to be sawcut and removed Existing curb and gutter to be removed Existing tree to be removed Existing chain link fence to be removed; including all gates, posts & footings Existing concrete extruded curb to be removed Existing drinking fountain to be removed including entire masonry base Existing handicap parking sign to be removed Existing concrete wheelstop to be removed Existing bench to be removed Manual removal of existing curb by pond Removal of tree stumps Removal of gravel at shelter drive Removal of gate post at entrance Remove existing sand volleyball court & all related nets, poles, borders Stair/Ramp Handrail Square Receptacle by UltraSite; model #TRSQ-32; Green recycled plastic slats &lid Extra Heavy-Duty Rectangular Table by UltraSite; Model #238-UltraCoat;8' length; surface mount; Black seat & frame color; perforated pattern+ Hamilton Bench with Back by UltraSite;6' length; black color; surface mount Bi-Level Outdoor Drinking Fountain with Water Bottle Filling Station by Murdock; Model #GYQ85; color: Textured Fairway Green Asphalt paving; mill & overlay existing Asphalt recreation court (includes paving and paving) Recreation court netting Asphalt paving; standard duty Tennis court resurfacing Concrete walk Heavy-duty concrete paving Concrete Curb and gutter Rolled concrete curb 6" concrete curb Concrete wheel stop; 6' long Detectable Warning Plates; Cast-In-Place Painted pavement marking; 4" solid white line Painted pavement marking; 8" wide crosswalk striping Painted pavement marking; 4" solid blue line Chain link fence; 4' black vinyl Chain link fence; 10' black vinyl 6" Schedule 40 PVC sleeve Table 2 Mobilization, administration, staking, traffic control Erosion control Existing concrete pavement to be sawcut and removed Existing asphalt pavement to be sawcut and removed Existing curb and gutter to be removed Existing tree to be removed Existing chain link fence to be removed; including all gates, posts & footings Existing concrete extruded curb to be removed Existing drinking fountain to be removed including entire masonry base Existing handicap parking sign to be removed Existing concrete wheelstop to be removed Existing bench to be removed Removal of tree stumps Remove existing sand volleyball court & all related nets, poles, borders Stair/Ramp Handrail Square Receptacle by UltraSite; model #TRSQ-32; Green recycled plastic slats &lid Extra Heavy-Duty Rectangular Table by UltraSite; Model #238-UltraCoat;8' length; surface mount; Black seat & frame color; perforated pattern+ Hamilton Bench with Back by UltraSite;6' length; black color; surface mount Wall Mounted Bottle Filler with Angled Bi-Level Drinking Fountain by Murdock; model GYE25-R; Green color; install per manufacturer's instructions Asphalt paving; mill & overlay existing Asphalt recreation court Asphalt paving; standard duty Concrete walk Heavy-duty concrete paving Concrete Curb and gutter Rolled concrete curb 6" concrete curb Concrete wheel stop; 6' long Detectable Warning Plates; Cast-In-Place Painted pavement marking; 4" solid white line Painted pavement marking; 8" wide crosswalk striping Painted pavement marking; 4" solid blue line Chain link fence; 5' Chain link fence; 10' black vinyl 6" Schedule 40 PVC sleeve Handicap parking and raised crosswalk sign Painted handicap symbol Tree protection fencing Shade Structure Level Spreader poured concrete Table 3 Mobilization, administration, staking, traffic control Erosion control Asphalt repaving in waterpark lot; mill & overlay existing Painted pavement marking; 4" solid white line Painted handicap symbol Painted pavement marking; 4" solid blue line Scope of Work General The awarded Bidder(s) is expected to fulfill all of the requirements and duties contained in this solicitation as directed by the County's representative. A proposal shall consist of details for the provision and management of the services envisioned in the Specifications, in accordance with the requirements described in this solicitation. The detailed Specifications are provided in a later section. Greenville County Parks, Recreation & Tourism manages 43 county parks, 22 miles of trails, 7 community centers, and several special recreation facilities in Greenville County, South Carolina. Bidder(s) can gain more information on the Greenville County Parks and its standards by entering the County's website at www.greenvillerec.com . The scope of work includes, but is not limited to, the responsibilities listed in this RFP and any future authorized, amended documents related to this solicitation. If the Bidder takes any exceptions to any part of the solicitation, include the exceptions with the proposal on a separate page titled “Exceptions to Proposal Criteria.” Project Location Northside Park is located at 101 West Darby Road, Taylors, SC 29687. The park includes Otter Creek Waterpark, tennis courts, pickleball courts, basketball court, picnic shelter, playground and two athletic fields. Project Schedule It is the desire of the County for all work to be completed by May 15th, 2027. Anticipated notice to proceed to selected vendor - December 28, 2026. Anticipated construction start date - January 1, 2027 Anticipated project completion date - May 15, 2027 Please include a written proposed project timeline and approach to maintaining schedule. Project Details The project shall follow the construction documents attached to this solicitation as the scope of work. The project is spilt into three distinct phases - Phase 1, Phase 2, and Alternate. The goal is for all three phases to be completed at the same time, however due to available resources, the bid sheet is split in case one or more phases are not feasible at this time. Phase 1 - East Side of Park - Entrance road, associated parking lots, and athletic courts Phase 2 - West Side of Park - Park Road, parking lots and athletic fields Alternate - Repaving the waterpark parking lot The County reserves the right to award Phase 1, Phase 2, and the Alternate individually or in any combination, depending on available funding and resources. The County is not obligated to award all components of the project. Bidders shall provide separate pricing for Phase 1, Phase 2, and the Alternate on the bid sheet. Pricing shall include all labor, materials, equipment, and other costs necessary to complete the applicable work in accordance with the construction documents. Public Notice Greenville County is soliciting sealed proposals in response to Northside Park Site Improvements , subject to the conditions and all provisions set forth herein and attached. Sealed proposals will be received through the County’s online procurement portal located at https://procurement.opengov.com/portal/greenvillecounty until Monday, November 30, 2026 , 3:30 pm , then publicly opened. The goods and/or services must be furnished as described and specified herein and submitted to Greenville County. All inquiries regarding this proposal shall be submitted no later than Wednesday, November 18, 2026 , 12:00 pm via the County’s online procurement Portal, located at https://procurement.opengov.com/portal/greenvillecounty . Please note the deadline for submitting inquiries. All answers to inquiries will be posted on the County’s online procurement Portal. Offerors may also click “Follow” on this proposal to receive an email notification when answers are posted. It is the responsibility of the Offeror to check the website for answers to inquiries. Introduction Summary Background Contact Information Timeline Instructions to Offerors Pre-Proposal Meeting A Non-Mandatory Pre-Proposal meeting will be held at the date and time specified in the Timeline. A site visit will follow. Vendors are encouraged to RSVP for the meeting through the OpenGov portal. The RSVP link is in the header of the solicitation. Pricing Pricing must be based upon payment in thirty (30) days. Discounts for payment in less than thirty (30) days will not be considered in making award. Discounts shall be stated in proposals as a percentage. Time in connection with discount offered will be computed from date of delivery of commodities to carrier, when inspecting and acceptance is at point of origin; or date of delivery at destination; or if laboratory inspection is made part of bid, from date of laboratory report. Unit pricing will govern over extended pricing, unless stated otherwise. Pricing shall include packing. Unless indicated by County, pricing must be firm. Vendors shall enter pricing in the Pricing proposal section. Bonding Bonding will be required for this project. See Bonds section for the requirements. Statement of Qualifications Vendor shall include the following with their response: Company Information - Basic company details, years in business, location Relevant Experience - Similar projects completed References - Contact information for recent clients Licensing/Certifications - Required trade licenses, certifications Bid Bond Requirements: Submit ONE of the following prior to bid opening: Original hard copy delivered to Procurement Services, OR Surety 2000 electronic version submitted through the OpenGov system. Deviations from these requirements may result in bid rejection. Submission Procedures and Requirements All submissions must be received by Monday, November 30, 2026 at 3:30 pm . Submissions will not be accepted after the deadline. There will be no exceptions. Responders submitting proposals shall be responsible for all cost of preparing such proposals. Information requested and not received at the time of submission may disqualify the submitted proposal. Responders to this solicitation shall closely examine the specific requirements noted herein and the attached Terms and Conditions. Facsimile transmittals, hard copies, emails or offers communicated by telephone will not be accepted or considered. Proposals shall be organized in the following manner with the subject headings and sequence indicated. Introduction - Include the Company Information requirements identified in SOQ Item 1. Experience and Past Performance - Include the Relevant Experience and References requirements identified in SOQ Items 2 and 3. Organization and Personnel Proposed Solution(s) Proposed construction methods and approach. Project timeline, including anticipated start and completion dates and major milestones. Approach to scheduling, sequencing, and coordinating the work. Strategies for maintaining the proposed schedule and addressing potential delays. Pricing Proposal section completed Other Information Requested License and Permits – The Contractor shall obtain all applicable licenses, and promptly pay all taxes required by the State of South Carolina, and/or Greenville County. SAM.gov registration required for all contractors/sub-contractors. Confirm that you have submitted documentation with proposal. Inquiries and Addenda Offerors shall submit all inquiries regarding this RFP via the County’s online procurement Portal, located at https://procurement.opengov.com/portal/greenvillecounty . Please note the deadline for submitting inquiries. All answers to inquiries will be posted on the County’s online procurement Portal. Offerors may also click “Follow” on this bid to receive an email notification when answers are posted. It is the responsibility of the bidder to check the website for answers to inquiries. The County will not be responsible for or bound by any oral instructions made by any employee(s) of the County in regard to this RFP. Addenda Notification: This RFP represents the most definite statement Greenville County will make concerning information upon which proposals are to be based. Offerors are required to register for an account via the County’s online procurement Portal hosted by OpenGov. Once you have completed the registration, you will receive addenda notifications to your email by clicking “Follow” on this project. Ultimately, it is sole responsibility of each proposer to periodically check the site for any addenda at https://procurement.opengov.com/portal/greenvillecounty . No addenda will be issued later than five (5) working days prior to the date for receipt for proposals except an addendum which, if necessary, postpones the date for receipt of proposals or cancels this RFP. Vendors shall acknowledge receipt of all addenda. General Information Proprietary Information – The County of Greenville is a public body and governed by the South Carolina Freedom of Information Act. Documents submitted to the County relating to this Solicitation are subject to requirements of the Freedom of Information Act and may be deemed public records. Errors and Omissions – The Responder will not be allowed to take advantage of any errors or omissions in the Request for Proposals. Where errors or omissions appear in the RFP, the Responder shall promptly notify the County of Greenville in writing of such error or omission it discovers. Any significant error, omission and/or inconsistency in the specifications are to be reported as soon as possible but no later than five (5) days before such time the response is to be submitted. Withdrawal of Proposal – An official representative of a Responder may withdraw a Responder’s response at any time prior to the proposal submission deadline. Acceptable proof establishing that he/she is the representative of the Responder must be provided. Non-Endorsement – If the County awards a contract, the successful Responder shall not issue any news release or other statement relating to the award or servicing of the agreement which state or imply the County of Greenville’s endorsement of the successful Responder’s services. Insurance Insurance Requirements The contractor is responsible for and must have all required insurance listed below and shall not commence work under the associated contract until it has obtained all insurance required, and the County has approved such insurance in writing, nor shall the Contractor allow any subcontractor to commence work on its subcontract until all similar insurance required of the subcontractor has been obtained. All insurance policies shall be maintained for the life of the contract. THE COUNTY SHALL BE NAMED AS “ADDITIONAL INSURED” FOR ITS INTEREST on all policies of insurance except Worker’s Compensation, Automobile Liability, and Professional Errors and Omissions, as regards ongoing operations, products and completed operations, and this shall be noted on the face of the Certificate of Insurance. As a part of the certificate of insurance requirement the contractor shall also include acknowledgement and acceptance of the wavier of subrogation provision granted to Greenville County. This acknowledgement and acceptance should be included in the same section of the Certificate of Insurance that evidences the “Additional Insured” provision. Certificates for all such policies of insurance shall be provided by the Contractor's insurance agent or broker to the County within 10 working days from the date of Notice of Award. All Certificates of Insurance submitted shall provide on the face of the certificate reference to County's RFP # RFP #27032 . Contractor will provide County a minimum of 30 days advance notice in the event the insurance policies (or an insurance policy) are canceled. Subcontractors approved to perform work on this project are subject to all of the requirements in this Section. Contractor agrees to maintain and keep in force during the life of this Agreement, with a company or companies authorized to do business in South Carolina, the following insurance policies: Comprehensive General Liability: $1,000,000 per occurrence - combined single limit / $2,000,000 general aggregate, to include products and completed operations. Automobile Liability: $1,000,000 per occurrence - combined single limit (Coverage shall include bodily injury and property damage and cover all vehicles including owned, non-owned and hired) Statutory Worker's Compensation: Coverage A - State of SC Coverage B - Employers liability $1,000,000 Each Accident $1,000,000 Disease, Per Employee $1,000,000 Disease, Policy Limit Policies shall contain a waiver of subrogation in favor of and/or that applies to Greenville County, its departments, agencies, boards, employees, and commissions for losses from work performed by or on behalf of the contractor. No deviation from this coverage’s will be accepted unless, in the County’s sole discretion, it is more advantageous to the County, i.e., $1,000,000 - a $2,000,000 or $5,000,000 limit would be acceptable. Evaluation Phases The proposals will be evaluated on the following criteria. Greenville County reserves the right to interview responders or have demonstrations to this RFP at its discretion. Greenville County will not be responsible for any costs associated with interviews of responders or demonstrations. If interviews or demonstrations are needed, a second phase of the evaluation process may be implemented at the County's discretion. Point values are described below. 5 = High 4 = Medium High 3 = Average 2 = Medium Low 1 = Low 0 = Non-Responsive Bonds Bid Bond: This project requires a Bid Bond and a Performance/Payment Bond. Proposers shall submit with their proposal, a Bid Bond in the amount of 5% of the bid price. This bond may be in the form of Bid Bond from the American Institute of Architects (AIA), electronically through Surety 2000, Certified Check, Cashier’s or Bank Money Order of any national or state bank and shall be made payable to Greenville County. Proposals submitted without being accompanied by any of the foregoing as required, may be considered informal and may be rejected. Any proposal accompanied by a bid bond not properly executed in the opinion of the County Attorney, may be rejected. The bond will be forfeited to the County by the successful bidder as liquidated damages in case a proposal award is made to that bidder and the contract and bond are not promptly and properly executed. 1. Instructions for Bond through AIA or similar bond document: The Original (hard- copy) Signed-Bid Bond must be delivered to the Procurement Services Office by the Bid Due Date/Time specified . The Bid Bond must be submitted in a sealed-envelope to: Greenville County Procurement Services Division; 301 University Ridge, Suite N-2400; Greenville, SC, 29601. The following information must be included, on the outside of the envelope: A. “Bid Bond” (labeled) B. Bid Number C. Company Name 2. Instructions for Surety2000: The County has an account with an online Bid Security program called Surety2000. This is a fee-based program that bidders can use to obtain an electronically issued, verified and legal bid bond which can be used for bidding purposes. No bid bond can be created by the bonding agent on the site without the Surety being fully aware of that bond. Only agents appointed directly by the Surety can issue bid bonds on the site. If your company chooses to use Surety2000 to obtain the bid bond, please access Surety2000 at www.surety2000.com. Complete the necessary steps to log in to
Published attachments
- COG Sub W9
- Sample Construction Agreement
- Northside_Park_Bid_Sheets
- Bid Sheet - Phase 1 - Northside Park Improvements
- Bid Sheet - Phase 2 - Northside Park Improvements
- Bid Sheet - Phase ALT - Northside Park Improvements
- 260904 NORTHSIDE PARK - PLANS
- 260904 NORTHSIDE PARK PLANS - Rev 11-9 - smaller file
- Rectangle Hip Shade
- Pickleball Net
- Northside_Park_Site_Improvements_(Addendum_#3_Revision).pdf
Addenda and notices
Official Notice #1: Sign in sheet · 1
Addendum #1 · 1
This addendum is issued to provide additional information in response to a vendor question. The following documents are added to the solicitation and incorporated into the solicitation documents: Attachment I: Rectangle Hip Shade Attachment J: Pickleball Net Proposers are also reminded to review the Questions and Answers section. All other terms and conditions remain unchanged. Proposers must acknowledge receipt of this addendum with their proposal submission. Please use the See What Changed link to view all the changes made by this addendum.
Addendum #2 · 2
This addendum is issued to correct a quantity in the Electronic Pricing Proposal, identified in response to a vendor question. Electronic Pricing Proposal, Item 89: 5' Fence (Sheet C204) The quantity for item 89 is revised from 1,376 LF to 1,290 LF. The Electronic Pricing Proposal has been updated to reflect this change. Proposers who have already begun entering pricing should review Item 89 and update their pricing accordingly. Proposers are also reminded to review the Questions and Answers section. All other terms and conditions remain unchanged. Proposers must acknowledge receipt of this addendum with their proposal submission. Please use the See What Changed link to view all the changes made by this addendum.
Addendum #3 · 3
Proposal Due Date Extended to November 30, 2026, 3:30pm The irrigation, topsoil, and maintenance requirements in the "General Landscape Notes," on Page 27, of the Northside Park plans document do not apply. THESE ITEMS ARE NOT ON THE BID SHEET. DO NOT INCLUDE COSTS FOR THEM. All other terms and conditions remain unchanged. Proposers must acknowledge receipt of this addendum with their proposal submission. Please use the See What Changed link to view all the changes made by this addendum.
Public questions and answers
I am having trouble getting the plans to open on my end. I can open the specs and bid forms however the plan file says it is corrupt. Is there any way the plans can be re uploaded?
11/9 - 10:38am - Please try the updated attachment, file “H”. Thank you for letting us know. The file isn’t corrupt. It’s very large (about 520 MB), so it needs a strong connection.. It took us about 10 minutes on a desktop computer. Please try again ensuring you're using Wi-Fi rather than cellular data, or use a desktop or laptop if you can, and allow several minutes for the file to load. If you still have trouble, please let us know.
I also have had problems opening plans. Downloaded three times on wifi and waited 30-60 minutes and nothing opens.
Thank you. 11/9 - 10:38am - Please try the updated attachment, file “H”.
What is the expected completion date or time allowed for this project?
Thank you. Please see section 3.3 of the scope of work.
What are the LD's on this project?
Thank you. If LD's refers to Liquidated Damages, they are not included in this project.
Do you have a detail/spec for the Recreation court net? Do you have a detail/spec for the pavilion shade structure? Are all of the structures on the project type 9's? What size pipe should we price? Can you provide more specs on the following bid tab items (aside from the detail provided on C-220) : 1 Asphalt paving: mill and overlay 2 Asphalt Rec Court 3 Asphalt Paving standard duty 4 Tennis court resurfacing (mainly need depths of each item, asphalt type like SCDOT Surface C, and depths of stone below if needed)
Do you have a detail/spec for the Recreation court net? --Pickleball nets are to be 36" at the sides and 34" at the center. (attachment "J") Do you have a detail/spec for the pavilion shade structure? --Attachment "I". Superior Shade Rectangle Hip Shade 10’ Eave Height – or approved equivalent. Are all of the structures on the project type 9's? --Structure details can be found on page C-130. All structures labeled CB will be Type 9, and structures labeled CI will be Neenah R-3246 Combo Inlet Frame/Grate/Curb Box. What size pipe should we price? --All pipe sizes can be found on sheet C-120. Can you provide more specs on the following bid tab items (aside from the detail provided on C-220) ? (mainly need depths of each item, asphalt type like SCDOT Surface C, and depths of stone below if needed): 1 Asphalt paving: mill and overlay --Surface course to be milled, typically 2 inches. Surface course to be replaced with Hot Mix Asphalt (HMA) Surface Course Type C - SCDOT (Standard Specification 403) of same depth. 2 Asphalt Rec Court --See page C-221 for the court edge detail. This detail includes the surface specifications for all courts. 3 Asphalt Paving standard duty --See page C-220 for site paving details. 4 Tennis court resurfacing --See page C-221 for the court edge detail. This detail includes the surface specifications for the courts.
Can you explain what you expect to be included in the LS Erosion Control Item?
Thank you. Matting, tracking, silt fence for perimeter and stockpile, sediment tubes, inlet protection, construction entrance, debris enclosure, concrete washout, porta-john, skimmer, and baffles. All items can be found on plan sheets C-100 - C-103 and detail sheets C-110 - C-111.
Could we please get clarification of Phase 1 line 7 of sitework. Asphalt recreation court ( incudes paving and paving)
Includes pavement base, asphalt paving, and liquid applied acrylic surface system.
There is a discrepancy with the 5’ fence on page C204; we are measuring 1,270 LF. This is less than what they call for on the bid tab, can you clarify?
Thank you. The correct quantity for the 5' fence would be 1290 LF.
Item 32-31-05 5' Fence calls for 1,736lf On page C 204 We see aprx 1290lf of 5' fence Could you please clarify where the additional fencing in located
Thank you. The correct quantity for 5’ fencing is 1290 LF.
Is there a separate erosion control bid sheet I may have missed, or should I use the site plans to prepare a bid?
An erosion control cost estimate can be found under Overall Project Costs line 2. Please see sheets C-101 through C-103 for the erosion control plans.
Could you please provide details for the: Level Spreader Poured Concrete
Thank you. These details can be found on sheet C-222.
Is HP acceptable in lieu of RCP?
Thank you. HP is acceptable. HDPE is not acceptable.
Who will be installing the lighting and will that require coordination from the contractor?
Thank you. Musco Sports Lighting will install the court lighting. The County will coordinate timing and installation of lighting and concrete plaza with selected vendor and Musco.
OpenGov categories
- 91339 · Construction, Pipe Culvert
- 91340 · Construction, Pipeline
- 91345 · Construction, Sewer and Storm Drain
- 91347 · Construction, Sidewalk and Driveway (Includes Pedestrian and Handicap Ramps)
- 91350 · Construction, Street (Major and Residential)(Includes Reconstruction)
- 91357 · Construction, Vaulted Sidewalk
- 91377 · Maintenance and Repair, Pipe Culvert
- 91378 · Maintenance and Repair, Pipeline (Includes Removal and Relocation)
- 91382 · Maintenance and Repair, Sidewalk and Driveway (Including Removal)
- 91384 · Maintenance and Repair, Street (Major and Residential)
- 91395 · Paving/Resurfacing, Highway and Road