Polk Street Community Center Parking Lot Renovation Project

Description

The City of Bartow plans to renovate and improve the parking lot and surrounding landscape at the Polk Street Community Center. The project is intended to address deteriorating parking lot conditions, improve functionality and accessibility, and create a more attractive and welcoming environment for residents and visitors. Work is anticipated to include removal of existing trees that are contributing to pavement and infrastructure damage, repair or replacement of affected parking surfaces, and improvements to the overall parking lot layout and appearance. In addition to the parking lot improvements, the project will refresh the surrounding landscaping with an emphasis on attractive, durable, and low-maintenance plantings appropriate for a high-use public facility. The completed project should improve vehicle and pedestrian circulation, enhance safety and usability, reduce future maintenance concerns, and provide a positive first impression that reflects the Community Center's importance as a public gathering and recreation space. SCOPE OF WORK Overview The City of Bartow plans to renovate and improve the parking lot and surrounding landscape at the Polk Street Community Center. The project is intended to address deteriorating parking lot conditions, improve functionality and accessibility, and create a more attractive and welcoming environment for residents and visitors. Work is anticipated to include removal of existing trees that are contributing to pavement and infrastructure damage, repair or replacement of affected parking surfaces, and improvements to the overall parking lot layout and appearance. In addition to the parking lot improvements, the project will refresh the surrounding landscaping with an emphasis on attractive, durable, and low-maintenance plantings appropriate for a high-use public facility. The completed project should improve vehicle and pedestrian circulation, enhance safety and usability, reduce future maintenance concerns, and provide a positive first impression that reflects the Community Center's importance as a public gathering and recreation space. Project Timeline The Contract Time is as follows: 45 CALENDAR DAYS The contract time for this project is 45 calendar days from Notice to Proceed to reach Substantial Completion and 15 calendar days from Substantial Completion for Final Completion. Completion of the contract will have been achieved once Final Completion has been reached and all final documentation, including the final application for payment, has been received and processed. Scope of Work The Contractor shall furnish all labor, materials, equipment, supervision, and professional services necessary to complete the Polk Street Community Center site improvements at 1255 Polk Street, Bartow, Florida, in accordance with the civil engineering and landscape architecture construction plans, specifications, and all applicable addenda. Work includes demolition and site preparation; erosion and sediment control; earthwork, grading, and stormwater management improvements; asphalt paving and pavement rehabilitation; curbing, sidewalks, accessible parking and pedestrian improvements; pavement markings, signage, and site furnishings; landscaping, sod, and irrigation; and associated restoration, testing, and project closeout. The Contractor shall retain and pay for a Florida-licensed geotechnical engineer to provide construction oversight, materials testing, recommendations, and the required letter of conformance, and a Florida-licensed professional surveyor and mapper to provide construction layout, verification of grades and elevations, and certified record survey/as-built documentation in strict accordance with the plan specifications. All associated costs shall be included in the Contract Price. Qualifications The Contractor shall demonstrate successful completion of projects comparable in scope and complexity to this Work, including site grading, stormwater management, asphalt paving, concrete curbing and sidewalks, accessible site improvements, landscaping, and irrigation. The Contractor shall submit supporting qualifications identifying comparable completed projects, owner references, proposed supervisory personnel, and any subcontractors anticipated for specialized work. The Contractor and applicable subcontractors shall hold current licenses appropriate to their respective work and demonstrate adequate personnel, equipment, financial capacity, bonding, and insurance capability to complete the Work within the Contract Time. The Contractor shall retain qualified, Florida-licensed geotechnical engineering and surveying professionals for the services required by the Contract Documents. A. Bidders must meet the following minimum qualifications to be considered responsive and responsible: The Contractor must have been in business under the same name and TIN/FEIN for the past two (2) years. The Contractor shall be appropriately licensed to perform the services offered and shall possess, at the time of bid opening, all required licenses and certifications. Copies of all licenses and certifications must be submitted with the response. The Contractor shall hold a valid Florida Certified General Contractor license. Businesses located within the City of Bartow must submit a copy of their current City of Bartow Business/Occupational License. Businesses located within Polk County but outside City limits, or located outside Polk County, must submit a copy of their current Polk County Business/Occupational License. B. The Contractor shall provide three (3) references for similar projects successfully completed within the last five (5) years. At least one (1) reference must be from another government municipality. Project summaries must clearly indicate where the Contractor served as the Prime Contractor. Please refer to the Reference Form provided under the Vendor Submittal Forms. C. The Contractor shall not use alternative materials or supplies unless expressly authorized in writing by the Project Manager. D. Subcontracting Requirements: The Contractor shall not subcontract any portion of the Work without the prior written approval of the Project Manager. Subcontractor qualifications will be reviewed and approved after award as part of the contract administration process. E. Bonding Requirements: There are no bonding requirements for this project unless Section 2: Instructions to Bidders, subsection 2.30. Bonds are met. If said conditions are met, please follow the conditions set forth under Section 5. Standard Terms and General Conditions, subsection 5.5. Bonds, Insurance, Indemnification. Contractors must demonstrate the financial capacity and bonding ability necessary to support the Project. Note: Contractors must complete and upload the Qualifications Statement included in the Bid Documents as it relates to this section. Detailed Scope of Services The detailed Scope of Work is provided in the Attachments section and includes the following documents: Appendix A - Construction Documentation. Appendix B - Civil Engineering Construction Plans Appendix C - Landscaping Architecture Construction Documents Pricing - Contingency Funds A Contingency Funds is included in the Pricing Table as a separate lump‑sum line item to cover unforeseen conditions or additional work that may reasonably arise during construction of the Polk Street Community Center Parking Lot Renovation Project. The allowance is not intended to cover known scope items or work that is already included under other bid items. Use of the Contingency Allowance must be pre‑approved in writing by the City Project Manager before any work is performed. The Contractor shall submit a cost proposal for each requested contingency activity, including labor, materials, equipment, and supporting documentation. Only City‑approved contingency work performed under a written Work Authorization will be eligible for payment from this allowance. Any unused portion of the Contingency Allowance will remain with the City and shall not be invoiced by the Contractor. INTRODUCTION AND BACKGROUND INFORMATION Purpose of Solicitation The City of Bartow plans to renovate and improve the parking lot and surrounding landscape at the Polk Street Community Center. The project is intended to address deteriorating parking lot conditions, improve functionality and accessibility, and create a more attractive and welcoming environment for residents and visitors. Work is anticipated to include removal of existing trees that are contributing to pavement and infrastructure damage, repair or replacement of affected parking surfaces, and improvements to the overall parking lot layout and appearance. In addition to the parking lot improvements, the project will refresh the surrounding landscaping with an emphasis on attractive, durable, and low-maintenance plantings appropriate for a high-use public facility. The completed project should improve vehicle and pedestrian circulation, enhance safety and usability, reduce future maintenance concerns, and provide a positive first impression that reflects the Community Center's importance as a public gathering and recreation space. City Background Information The City of Bartow, through its Parks, Recreation & Cultural Arts Department and other municipal operations, is committed to enhancing community facilities, infrastructure, and public spaces. As a growing municipality focused on improving quality of life, the City of Bartow invests in projects that support safety, accessibility, recreation, and long‑term sustainability for residents and visitors. The Polk Street Community Center and its surrounding amenities play a vital role as a public gathering and recreational destination, and the City of Bartow remains dedicated to maintaining and upgrading these facilities to ensure they continue to meet community needs and reflect Bartow’s high standards for public service. INSTRUCTIONS TO BIDDERS - CONSTRUCTION Bid Schedule ITB-CON Solicitation Issued: October 23, 2026 Question Submission Deadline: November 10, 2026, 4:00pm Bids Due: November 25, 2026, 2:00pm Bid Opening It is the responsibility of the bidder to assure that their bid is delivered or submitted at the proper time and place prior to the bid opening. All bid openings shall be public, following 2:00 pm , on the date specified in the solicitation. Bids which for any reason are not so delivered or submitted electronically through the City’s e-procurement system, will not be considered. Bid Submittals Using Facsimile or Email Will Not Be Accepted. Note: In accordance with Florida Statute 119.071, a listing of vendors that provided a bid submittal shall be posted to the City’s e-procurement platform OpenGov. All bids shall remain exempt from disclosure, including bid amounts, until recommendation of award or 30 days after bid opening, whichever event occurs first. Should the City reject all bids, before the recommendation of award or 30 days after bid opening, and concurrently provide notice of the City’s intent to reissue the bid, the rejected bids will remain exempt from Florida Statute 119.07 until such time as the City provides notice of recommendation of award of the reissued bid or until the City withdraws the reissued bid. The bid is not exempt for longer than 12 months after the notice of rejection of all bids. Execution of Bid Bid must contain an original signature of an authorized representative in the space provided on the signature page. Bid must be typed or printed in black ink. Erasable ink is not permitted. Corrections made by the bidder to any bid entry must be initialed by the person who signs the bid. Bid Submittals Submittal may be withdrawn by notifying the City, in writing, at any time prior to the deadline for bid submittal. After the deadline, the bids become a record of the City and will not be returned to the Contractor unless the bid is cancelled. It is the responsibility of the Contractor to make a written request for return of the Bid Submittal after notification of cancellation. Absent this written request, the City shall destroy the submittal. Negligence on the part of the Contractor in preparing their Bid Submittal confers no right of withdrawal or modification of their Bid Submittal after such Bid Submittal has been opened by City Staff at the appointed time and place. Bid Submittals and any bid security shall be in force for a period of not less than ninety (90) calendar days after the bid opening time. At the time and place specified for the opening of Bid Submittals (see above), every Bid Submittal properly delivered within the time specified for receiving Bid Submittals will be opened and publicly read aloud, irrespective of any irregularities found therein. Bidders and other people interested may be present or represented. Bid Submittal -Exhibits & Forms Supplementary Conditions, Special Conditions, Plans, Drawings, Instructions to Bidders, the Conditions of the Contract, Exhibits, the Bid Submittal, Technical Specifications, any resulting addenda issued, and the Contract together therein identified constitute the entire “bid package” and upon award shall constitute the Contract Documents concerning this present bid matter. The following documents, collectively, comprise the “Bid Submittal” which, when tendered, on or before the Bid due date and time, must include: Bid Sheet(s) Bid pricing must be submitted through the City’s e-procurement system, OpenGov. A printed copy may also be included with the physical bid submission, if applicable. Contractors shall not deviate from the Pricing Table unless expressly authorized by the City of Bartow Procurement Contact. Any unauthorized deviation from the provided Pricing Table may result in the bid being deemed non-responsive. With th e signature of an authorized representative of the company or their designee, all information requested below shall be uploaded and submitted with your bid in accordance with the requirements of this bid/project (Contractors are to Refer to Section 8: Vendor Submittal Forms): Bidder Incorporation Information Reference Form Acknowledgement Form Exhibit I – Bid Bond, when applicable Exhibit IV – Non-Collusion Affidavit of Prime Bidder. Exhibit VI – Affidavit of Percentage of Work (this requirement does not include Exhibit VI-A – Subcontractor List Exhibit VI-B – Good Faith Effort Documentation). Exhibit VII – Trench Safety Act Compliance Exhibit VIII – Equal Employment Opportunity Exhibit IX – Drug-Free Workplace Form Exhibit X – Safety Requirements/Regulations Exhibit XVIII – Certificate of Compliance Exhibit XIX – Affidavit Certification Immigration Laws Exhibit XX – Contractor Certification regarding Scrutinized Companies List Exhibit XXI – Certification Regarding Debarment, Suspension, Proposed Debarment, and other Responsibility Matters Exhibit XXII – Appendix A, 44 C.F.R. Part 18 – Certification Regarding Lobbying Exhibit XXIII – Employment Eligibility Verification (E-Verify) Certification Exhibit XXIV – Sworn Statement of Public Entity Crimes Exhibit XXV – Affidavit Regarding the Use of Coercion for Labor or Services All additional information requested as a “must” item in any Addendum. All corrections made by the Bidder to the Bid Sheets and Acknowledgement Form should be acknowledged by written initials of the authorized representative signing the Bid Submittal or their designee. Should a price correction not be acknowledged, the lowest price will prevail. Requested Information by the City (Post Submittal/ Pre-Award) All additional requested information and Exhibits must be submitted within a reasonable period of time if chosen as the apparent low, responsive and responsible bidder during the Bid Analysis phase. These items include: Exhibit II, Public Performance Bond Exhibit III, Payment of Bond Exhibit V, Non-Collusion Affidavit of Subcontractor Upon Execution of a Contract (Post Notice to Proceed Forms, when or if applicable): Exhibit XI, Application for Payment Exhibit XII, Contractor Certification of Disbursement Exhibit XIII, Certification of Substantial Completion Exhibit XIV, Certification of Final Completion Exhibit XV, Materials & Equipment Stored On-site Exhibit XVI, Allowance Authorization Release (AAR) Exhibit XVII, Change Order Sales Tax Saving Form Recommendation of Award A bid may be recommended for award by the Financial Services Manager to the lowest responsive and responsible Bidder , provided that the bid submittal is considered reasonable, in the best interest of the City, and no bid protest has been filed. The basis of the recommendation will be the Base Bid, the Base Bid plus all alternates, or any combination thereof, depending on the availability of funds and the best interest of the City. If the award includes selected alternates, the priority of those alternates will be set forth in the Supplementary Conditions, if applicable. As the best interest of the City may require, the right is reserved to: Make awards by individual item or group of items. Reject all bids. Waive any minor irregularities or technicalities in bids received. In determining the lowest responsive and responsible bidder, the following criteria may be considered in addition to price: Performance Quality: Vendor’s evaluation and quality of performance on previous projects. Capability: The ability, capacity, equipment, and skill of the bidder to fulfill the contract. Timeliness: Whether the bidder can fulfill the contract within the time specified without delay or interference. Reputation: The character, integrity, reputation, judgment, experience, and efficiency of the bidder. Compliance: The previous and existing compliance by the bidder with laws and ordinances relating to the contract. Financial Resources: The sufficiency of the financial resources to fulfill the contract. Suitability: The quality, availability, and adaptability of the suppliers or contractual services to the particular use required. Future Support: The ability of the bidder to provide future maintenance and service. Bid Conditions: The number and scope of conditions attached to the bid. The successful Bidder to whom a bid is recommended for award will be so notified by City staff. The Financial Services Manager, however, at their sole discretion, reserves the right to reject any and all bid submittals or to waive any informality concerning the bid submittal whenever such rejection or waiver is in the best interest of the City. The Financial Services Manager, likewise, reserves the right to reject the bid submittal of any Bidder who has previously failed to perform properly or to complete on time, contracts of a similar nature; or who is not in a position to perform the contract; or who has habitually and without just cause neglected the payment of bills or otherwise disregarded its obligations to subcontractors, materialmen or employees. F.O.B Destination All prices covered by this bid/contract will be inclusive of all cost to the jobsite within the City of Bartow, Florida. Packaging All containers shall be suitable for storage or shipment, and all prices should include standard commercial packaging. Taxes No taxes shall be included in any bid price. The City of Bartow is exempt from state and federal sales use and excise tax. If sales taxes are applicable due to third party purchasing, nothing herein shall prohibit the City from deleting line items and purchasing said items directly from a supplier if it is determined that there are sufficient sales tax savings to make purchasing by the City practical. Prices Unless otherwise specified, all prices and/or discounts shall be firm for the duration of the original contract/purchase order. In the event of price decreases the City of Bartow shall be given full proportionate benefits

Published attachments
Addenda and notices
  • Addendum #1 · 1

    Please use the See What Changed link to view all the changes made by this addendum.

  • Addendum #2 · 2

    Please use the See What Changed link to view all the changes made by this addendum.

  • Addendum #3 · 3

    Revised Price Schedule. Please use the See What Changed link to view all the changes made by this addendum.

Public questions and answers
  • The solicitation documents do not reference a Pre-Bid Conference or Site Visit. Will the City conduct an official Pre-Bid Meeting and/or Site Visit for prospective bidders?

    No, the City will not conduct an official Pre-Bid Meeting or Site Visit for this solicitation. However, prospective bidders are encouraged to visit and inspect the project site independently and familiarize themselves with existing conditions before submitting a bid. Any such site visits shall be conducted at the bidder's convenience.

  • Sheet C3.0 indicates that the existing pavement is to be "mill and resurface or replace (see Pavement Evaluation Notes)." The Pavement Evaluation Notes further state that the Contractor is to provide pricing for milling and resurfacing the existing pavement and, as an alternative, for full-depth removal and replacement. Please confirm that the Base Bid shall include milling and resurfacing of all applicable pavement areas. Additionally, please clarify who will be responsible for obtaining pavement cores for the Geotechnical Engineer's evaluation and, if the Contractor is responsible, whether the Owner/Engineer will provide core locations. Finally, because the current Bid Schedule does not include a line item or alternate bid for full-depth pavement replacement, please confirm whether an alternate pricing request will be issued after the pavement evaluation is complete.

    As indicated on Sheet C3.0 and further detailed in the Pavement Evaluation Notes, the Base Bid shall be based on the Milling and Resurfacing option for all applicable existing pavement areas. The Contractor shall be responsible for providing all required geotechnical services, including pavement coring, necessary for completion of the project. The number and locations of pavement cores shall be determined by the City following contract award. All costs associated with these services, including pavement coring and testing, shall be included in the Contractor's bid price. Additionally, bidders shall be required to provide alternative pricing for the full-depth removal and replacement of the existing pavement, as referenced on Sheet C3.0 and in the Pavement Evaluation Notes. The City will issue a formal addendum to the solicitation to update the Price Schedule in OpenGov with a separate table for this alternative pricing.

  • Section 4, Scope of Work (Page 14), states that the Contractor shall have forty-five (45) calendar days from the issuance of the Notice to Proceed (NTP) to achieve Substantial Completion of the Work. Please clarify whether the Contractor will be permitted a period prior to NTP to perform necessary pre-construction activities, including the preparation and submission of shop drawings, resolution of design and construction inquiries, coordination with the Geotechnical Engineer, electrical utilities, and other third-party stakeholders, as well as permitting, material procurement, and other project startup requirements. If these activities are expected to occur before NTP, please identify the anticipated duration of this period and clarify which activities may be completed before the start of the 45-calendar-day contract time.

    The Notice to Proceed (NTP) will be issued following contract award and completion of the pre-construction meeting with the awarded Contractor. During the pre-construction meeting, the project start date will be established. The 45-calendar-day period for Substantial Completion shall commence on the established start date, as specified in the NTP.

  • Sheet C3.0 of the Bid Documents includes notes stating that the Contractor is responsible for coordinating with an electrical engineer/contractor and the local power utility to ensure adequate power is provided to the site, and that the Contractor shall coordinate with the local power company for the parking lot lighting design. Based on the information provided, please clarify whether the Contractor is expected to include pricing for the power service and parking lot lighting design, materials, and installation in this bid submission. If so, please identify the appropriate utility company and any other entities the Contractor should coordinate with during bidding. Also, please provide the required lighting criteria and acceptable illumination levels for the parking and loading areas, as well as any applicable City standards, specifications, or approved material requirements to be incorporated into the Contractor's pricing.

    The Contractor shall be responsible for coordinating all work with the City of Bartow Electric Department, including any necessary arrangements for power service and related electrical requirements. The Contractor's bid shall include all costs associated with any additional power service, lighting design, materials, equipment, labor, and installation necessary to complete the project in accordance with the solicitation documents. No additional compensation will be provided for these requirements.

  • Please clarify whether the Community Center will remain open and operational during construction. If the facility will remain open, please provide any requirements regarding phased construction, maintaining access for staff and the public, allowable work hours, noise restrictions, temporary utilities, safety and security measures, and any other operational constraints to consider in the Contractor’s bid and construction schedule.

    The facility is expected to remain open and operational throughout construction. The building has three (3) separate entrances on the north, east, and west sides, which the Contractor may use to facilitate construction activities while maintaining facility operations. All construction work shall be performed between the hours of 8:00 a.m. and 5:00 p.m., Monday through Friday. No weekend work shall be permitted without prior written approval from the City of Bartow. The Contractor shall be responsible for securing all active construction and work areas by providing temporary, lockable fencing or equivalent barriers to restrict unauthorized access. The Contractor shall also be responsible for securing all tools, materials, equipment, and other construction-related items at all times to ensure the safety of facility occupants, visitors, staff, and the general public.

Plain text

OpenGov categories

  • 90900 · Building Construction Services, New (Incl. Maintenance And Repair Services)
  • 90924 · Building Construction, Commercial and Institutional
  • 90925 · Building Construction, Prefabricated (All Types)
  • 90930 · Building Construction (Not Otherwise Classified)
  • 91117 · C.I.P., Construction, Roads
  • 91200 · Construction Services, General (Incl. Maintenance And Repair Services)
  • 91336 · Construction, Parking Lot and Alley
  • 91347 · Construction, Sidewalk and Driveway (Includes Pedestrian and Handicap Ramps)
  • 91357 · Construction, Vaulted Sidewalk
  • 91382 · Maintenance and Repair, Sidewalk and Driveway (Including Removal)
  • 98863 · Park Area Construction/Renovation