State and local · OpenGov
Request for Qualifications for Capital Building and Maintenance Program Management Services for Charleston County School District
Description
General work description: The Charleston County School District (CCSD) is soliciting sealed Qualifications for Program Management Services for its Phase VI 2029-2035 Capital Building and Maintenance Program and Long-Term Debt Projects. Enclosed is the Request for Qualifications (RFQ) for program management services. Project Details Important Instructions for Electronic Submittal The Charleston County School District is accepting electronic bid submissions. Bidders shall create a FREE account with OpenGov Procurement by signing up at https://procurement.opengov.com/signup . Once you have completed account registration, browse back to this page, click on "Submit Response", and follow the instructions to submit the electronic bid. Scope of Work or Project Details SEE ATTACHED REQUEST FOR QUALIFICATIONS. Vendor Submissions
Published attachments
Addenda and notices
Addendum #1 · 1
Please use the See What Changed link to view all the changes made by this addendum. The deadline for qualifications has been extended to December 9, 2026 @ 2:00 PM ET. A sample AIA document and draft matrix is attached to this addendum.
Public questions and answers
RFQ pp. 3 to 7 - The RFQ moves from Section 3.0 to Section 5.0. Please confirm whether a Section 4.0 (Submission Requirements) was omitted, and provide the required organization of the response, page limits, font and margin requirements, tab structure, and file format.
The organization of the response should follow the evaluation factors. You will respond in OpenGov. The response shall not exceed 200 pages.
The RFQ states online submission only but does not identify a portal, URL, registration process, or file size limit. Please identify the submission platform and confirm whether a single combined PDF is required.
The organization of the response should follow the evaluation factors. You will respond in OpenGov. The response shall not exceed 200 pages.
RFQ pp. 7, 11 - Section 7.0 refers to interviews and negotiations "per lot" and "for each lot," but no lots are defined, and Section 6.0 states award to one Offeror while reserving the right to make multiple awards. Please confirm whether the Program will be divided into lots (for example by wave, Capital Building versus Facilities Management, or Technology), how lots will be defined, and whether Offerors may pursue one or all lots.
There are no lots. Award will be made to one offeror.
RFQ pp. 2, 10, 11 - The RFQ describes approximately $1.2 billion of construction, maintenance, IT infrastructure, and security projects. Please confirm which of the following are within PMF scope: (a) the $735,000,000 funded capital project list; (b) the $383,957,451 of unfunded projects; (c) the Phase VI Capital Maintenance Program; (d) the Phase VI Technology program; and (e) Long-Term Debt Projects. Please also clarify whether the "CPM firms associated with Facilities Management projects" referenced on page 11 will be procured separately.
The awarded Program Management firm will manage all projects including Capital Maintenance.
RFQ pp. 9, 11 - Page 9 states compensation will be based on "a fixed percentage of the program budget minus the program management fee or billable hourly rates," while page 11 states "billed hourly rates." Please confirm the compensation basis, whether any fee or rate information is to be submitted with the Qualification, and whether site staff, reimbursables, and subconsultant costs are included in the fee.
This will be negotiated prior to award.
The Phase VI Capital Project Waves agenda item proposes beginning Wave 1 (2027 to 2030) early using Series 2026B Bond Anticipation Note funds, while Phase V program management contracts continue through 2028. Please confirm whether Wave 1 projects will be assigned under this contract upon award, and describe how the District intends to transition or overlap Phase V and Phase VI program management.
This will be negotiated with the highest ranked firm. Phase V projects stay with their current firms.
RFQ p. 13 - Please confirm whether the neutrality requirement on page 13 applies to the PMF's parent company, affiliates, joint venture partners, and subconsultants; whether it applies only to Phase VI Program projects or to any District work; and whether a firm with an affiliated design or construction entity may comply through a written firewall and recusal plan.
Yes, it does apply. This solicitation applies to the Phase VI Program only.
RFQ p. 9 - Phase I totals 100 points and Phase II interviews total 25 points, yet the RFQ twice states that the average score will not exceed 100. Please confirm the maximum combined score, whether Phase I scores carry into the final ranking, and whether the same committee scores both phases.
Phase I does not exceed 100. Phase I and II combined does not exceed 125 points. Phase I and II scoring will be combined. The same committee will evaluate both phases.
RFQ p. 7 - Please confirm whether both Part I and Part II of the SF 330 are required, whether a Part II is required for each firm and office on the team, and whether SF 330 pages count toward any page limit.
Part II only is required for each firm. Yes, it does count towards the page limit.
RFQ pp. 12, 13, 15 - Please describe the level of Tyler Munis access the PMF will have (for example direct entry of requisitions, purchase orders, and pay applications), what is meant by "maintaining dual financial systems," and whether the District requires a specific integration method such as automated data exchange.
You will have access to enter requisitions, purchase orders, and pay applications. The firm can also view budgets. The firm also has to have some sort of financial system.
RFQ pp. 11, 13 - Will the required single-source program dashboard be hosted by the District or provided by the PMF, will it be public-facing, and who will own the data and platform at contract end?
The Program Management Firm will provide. It will not be public facing.
RFQ p. 10 - Please clarify the PMF role for the Technology program, specifically Student and Staff Devices, network infrastructure, and physical security, and how the PMF role relates to the Project Management line in the Technology Sales Tax Phase VI Summary.
This will be negotiated later.
RFQ p. 15 - The Phase VI Capital Maintenance Program states that budgets include design costs and construction management fees. Please identify any program management fee or staffing allowance assumed in project budgets, and whether the District expects full-time site managers on each major project.
This will be negotiated later. On-site managers are required for projects over $10 million.
If the referendum is not approved on November 3, 2026, will the District cancel the solicitation, suspend it, or proceed for bond-anticipation-note and Long-Term Debt work only? Will the December 2, 2026 deadline remain in effect?
The referendum has passed.
Please provide the District's amended AIA C132-2019, required insurance types and limits, the anticipated contract term (through December 31, 2034 plus closeout), and the key personnel substitution approval process.
A previous AIA document has been attached in OpenGov. It includes requirements. Please note that the document is currently being reviewed by legal counsel and will include changes. Key personnel substitution must be approved by CCSD.
Please identify the Long-Term Debt Projects included in this solicitation, with values and funding sources.
This is not known at this time.
Which delivery methods does the District anticipate for Phase VI (design-bid-build, CM-at-Risk, design-build), and will the District follow the current Office of School Facilities guide for those methods?
Our preferred method is design-bid-build. We will follow the Office of School Facilities guide.
If any of the five unfunded projects receive funding during the contract term, will they be added to the selected PMF's scope by amendment?
Yes
Phase V program management solicitations evaluated minority business participation. Does the District have a participation goal or expectation for the Phase VI PMF team, and will participation be considered under any evaluation factor?
That is not an evaluation factor.
Please provide the anticipated interview date range, format, duration, maximum number of attendees, and whether all named key personnel must attend.
This will be provided when necessary. The expected timeframe should be mid January.
What evidence will the District accept to show an office within 30 minutes of 3999 Bridge View Drive, and is the 30 minutes measured as normal drive time?
You must provide the office address that meets the requirement or a plan to satisfy that requirement. We will measure normal drive time.
RFQ pp. 1, 5 - The cover page sets a question deadline of November 3, 2026 at 12:00 PM, while the Questions from Offerors clause references five days before opening. Please confirm that November 3 governs and the expected date of the answer amendment.
The deadline for questions is November 3rd at 12:00 PM.
May the firm's Quality Assurance Program and letters of reference be included as appendices outside any page limit?
The total page limit is 200 pages.
Is there a page limit to the response?
200 Pages.
Will the PMF be expected to office full-time from a CCSD location?
The PMF will not be located on CCSD property.
Can you provide more information on the expectation for dual financial systems? Does the PMF need to own/maintain a separate Munis system, or will they need to provide an accounting record system which supports CCSD's?
The PMF will have access to our Munis system.
Does CCSD anticipate awarding both contracts (CP2701 &CP2702) concurrently, and will the PMF be under contract before CPM firms are selected?
We anticipate them to be awarded at the same time.
Will firms be permitted to submit on both CP2701 and CP2702, and if so, are there any restrictions on holding contracts under both solicitations?
Yes.
Does CCSD currently use a project management platform (e-Builder, Kahua, Unifier, Procore, etc.), or should firms propose a solution?
Firms should propose a solution.
Please confirm the format of the response: Is it entirely based on the SF330 format, or is that only a portion of the response dependent on any subconsulting? If only a portion, can you provide an overall format requirement?
The organization of the response should follow the evaluation factors. You will respond in OpenGov. The response shall not exceed 200 pages.
The programs run 2029–2034 (PMF) vs. 2029–2035 (CPM). Are these intended to run for different lengths?
The program runs 2029-2034.
The CPM RFQ defines the onsite expectations of a full time Site Manager for projects over $10M in value. What are CCSD's expectations for the remainder of the PMF's staffing? Precon vs. Construction? Examples: One Project Manager can handle two Projects of up to $100M in value, and a Senior Project Manager can handle up to four Projects up to $200M in value with 2 PMs and 4 site managers supporting.
This will be negotiated.
Has a Master Program Schedule been developed? If so, can it be shared? If not, can you provide milestone dates for design, construction, and completion for each capital project?
This is not available at this time.
When scoring offerors, will points be awarded/considered for minority business participation or small business participation for the PMF proposal?
No
For the PMF, please explain the relationship between CCSD and the PMF regarding control and management of the project and program budget.
A matrix is attached.
Who owns and hosts the centralized dashboard: CCSD, the PMF, or each firm? What does "maintaining dual financial systems" mean in practice for the PMF?
The Program Management Firm will own and host the centralized dashboard. CCSD has Tyler Munis as the financial system. PMF will need to have their system as well.
Both RFQs skip from Section 3.0 to 5.0. Is a Section 4.0 missing? Would 4.0 include submission format, page limits, required forms, portal instructions, etc.?
The organization of the response should follow the evaluation factors. You will respond in OpenGov. The response shall not exceed 200 pages.
Please confirm that a Charleston County Business License is required and not a City of Charleston or City of North Charleston business license is based on your office location.
Any applicable license is required.
Can you provide a copy of the AIA Document C132-2019 as amended by CCSD for review?
A previous AIA document has been attached in OpenGov. Please note that the document is currently being reviewed by legal counsel and will include changes.
Is the entire Standard Form 330 Part I and Part II required?
Part II is required.