Description
The City of Santa Cruz (City) is issuing this Request for Qualifications (RFQ) dated Nov. 16, 2026 for an Engineer (Engineer) to prepare concept and final engineering plans and specifications for the construction of the Santa Cruz Wharf South Landing. Introduction Summary Background Contact Information Timeline Attachments Vendor Questionnaire
Published attachments
- 20250912 Santa Cruz Wharf Phase II Assessment Report Final 12Sept2025
- Submittal 013R1 - Pile Logs MN NET
- Submittal 015R1 - Pile Driving Logs MN NET
- Submittal 016 - Pile Driving Logs MN NET
- Submittal 018 -Pile Driving Record Sheets WE24JAN2026_MN NET
- Submittal 019 -Pile Driving Record Sheets WE31JAN2026_MN NET
- Submittal 028 -Pile Driving Record Sheet WE14FEB2026_MN NET
- Submittal 029 -Pile Driving Record Sheet WE28FEB2026_MN NET
- SC Wharf South Landing Engineering RFQ FINAL 16Nov2026
Public questions and answers
Is there any geotechnical information available for the wharf related to the project?
There is no geotechnical information in the City's possession related to the Wharf or the South Landing Project.
Considering the job walk is two weeks before the bid responses are due, would the city consider moving the submission due date back two weeks to allow for more detailed preparation after the job walk on Nov 30th.
In the interest of moving the Project forward as expeditiously as possible, the City will maintain December 15, 2026 at 1:30 PM as the submittal date and time.
Construction Schedule: The RFQ indicates that construction is to be completed no later than 2034 but does not identify an anticipated construction start date. What is the City’s anticipated timeframe for bidding and commencing construction of the South Landing, and what construction duration should proposers assume when developing the fee for Task 8 – Engineering Support During Construction?
The City desires to move forward with the project as expeditiously as possible. Dates for releasing the project for competitive bidding, start of construction, and duration of construction were designated in the RFQ as "to be determined" and will be refined as the process unfolds. Early unofficial projections have the project being released for bid in Spring/Summer 2027 with start of construction early 2028. The RFQ, Section B, Task 6.1 requires the Engineer to provide an estimated construction schedule. Engineers should use their projected schedule for developing the fee for Task 8.
Design and Permitting Schedule: The RFQ anticipates issuance of the 50% design package on March 15, 2027 for environmental review and regulatory permitting, followed by 100% design on March 31, 2027. Given the potential for agency review to extend beyond this period and result in changes to the project footprint, structural configuration, or mitigation requirements, is there flexibility in the 50% and 100% design milestones to allow substantive regulatory comments to be incorporated before completion of final design? If 100% design is to be completed before regulatory comments are received, should subsequent permit-driven revisions be considered additional services?
The City has a reasonable expectation that the physical design of the project will not require extensive review by the permitting authorities as it is likely covered under the existing SC Wharf Five-Year Maintenance Plan. Environmental review will require more extensive interaction with the permitting authorities but should not significantly alter the physical design of the project. The City could exercise flexibility with respect to the 100% plan set delivery date if necessitated by the environment review process.
Project Funding: Is the South Landing project currently funded in full or in part through federal, state, local, grant, or other restricted funding sources? If so, are there funding-related milestones, obligation dates, expenditure deadlines, or other requirements driving the design schedule identified in the RFQ?
The project is fully funded through a federal appropriation. The City is responsible for ensuring compliance with all milestones related to the funding source. The Anticipated Project Schedule is expected to allow the City to do so.
Design Schedule Flexibility: Please clarify whether the February 15, March 15, March 31, and April 15, 2027 milestones are fixed contractual requirements or anticipated target dates. If conditions identified during design, City review, or regulatory coordination require additional time, does the City have flexibility to modify these milestones?
The dates in RFQ Section C "Anticipated Project Schedule" are, as indicated, anticipatory. The City will exercise flexibility with respect to these dates at its discretion.
Knowing that the Santa Cruz Wharf South Landing uses federal funding, and given the applicability of federal procurement requirements, including 2 CFR Part 200, can you please confirm whether firms that previously participated in the development of the Wharf Master Plan, engineering studies, structural assessments, or subsequent design work for the Wharf are eligible to compete for this contract? Specifically, we would appreciate clarification as to whether any prior consultant involvement is considered to create an organizational conflict of interest or otherwise preclude participation in the current procurement.
The City is consulting with HUD to formulate a response to this question. In order to better inform our discussion with HUD please provide the section of 2 CFR Part 200 that you're citing.
Can the city make available the 2014 Engineering Report, including appendices and calculations generated by Moffatt & Nichol’s
THe 2014 Engineering Report Parts 1 and 2 can be accessed online at https://www.santacruzca.gov/files/assets/city/v/1/edh/edh-iam/documents/wharf/reference-documents/santa-cruz-wharf-engineering-report-part-1.pdf and https://www.santacruzca.gov/files/assets/city/v/1/edh/edh-iam/documents/wharf/reference-documents/santa-cruz-wharf-engineering-report-part-2.pdf.
Can the City provide any of the original or recent wharf construction drawings and pile-driving records?
The SC Wharf was originally constructed in 1914, the City is not aware of any original construction drawings from that time period. The City does have construction drawings and pile driving records from recent projects, but if you could be more specific as to what records you're interested in we can best respond. For instance, there have been some recently completed projects near the proposed South Landing project that may be germane to your request.
Can the city supply any records of replacement piles, including pile lengths, tip elevations, refusal criteria, driving logs, and installation dates?
Please see answer to Question 9 above and Question 13 below.
Can the City provide any prior geotechnical investigation or data reports for the wharf, Municipal Wharf entrance, nearby seawalls, Beach Street, Cowell Beach, or Santa Cruz Harbor projects?
Researching this question now. Will update when information becomes available.
Can the city provide any bathymetric survey files near the South Landing location?
Please see the Phase II Assessment Report, Section 5.3, located in the Attachments tab of this project.
Can the city provide construction drawings and pile driving records from any recent project that was completed near the proposed South Landing project?
The construction drawings for the 2025 SC Wharf End Interim Repair Project are available online at https://www.santacruzca.gov/files/assets/city/v/1/pr/documents/santa-cruz-wharf/wharf-end-interim-repair-project-drawings.pdf. See the Attachment tab in this project for pile logs for that project.
OpenGov categories
- 91107 · C.I.P., Architectural/Engineering Services
- 91842 · Engineering Consulting
- 92500 · Engineering Services, Professional
- 92517 · Civil Engineering
- 92533 · Engineer Services, Professional
- 92536 · Engineering Services (Not Otherwise Classified)
- 92548 · Harbors; Jetties; Piers; Ship Terminal Facilities - Engineering
- 92570 · Municipal Engineering
- 92588 · Structural Engineering