Skip to content
← Back to search

State and local · OpenGov

Opportunityevaluation

Santa Fe Regional Airport Airfield Preservation Rehabilitation, Maintenance and Design

Description

The Santa Fe Regional Airport (Airport) is soliciting qualification-based proposals from qualified architectural and engineering (A&E) firms to provide professional design services for multiple airfield preservation, rehabilitation, and maintenance projects. Runway 02/20 is the Airport's primary runway and serves as the designated runway for commercial airline arrivals and departures, including regional jet operations. During the Federal Aviation Administration's (FAA) most recent annual inspection, deficiencies and areas requiring corrective action were identified on both Runway 02/20 and the secondary Runway 15/33. These findings, along with the Airport's ongoing infrastructure preservation needs, have established the need for professional A&E services to evaluate existing conditions, develop appropriate design solutions, and prepare plans and specifications for the required improvements. The projects requiring attention include, but are not limited to, the following: Runway Safety Area (RSA) Grading Improvements: Evaluate and develop corrective grading improvements to address deficiencies within the RSAs for Runways 02/20 and 15/33. Runway Pavement Preservation: Evaluate pavement conditions and develop preservation and rehabilitation improvements for Runways 02/20 and 15/33. Runway 02/20 Improvements: Evaluate alternatives and develop design plans for improvements to Runway 02/20, which may include runway extension, rehabilitation, or reconstruction. Pavement Maintenance Plan (PMP): Develop a comprehensive pavement maintenance plan to support the ongoing assessment, preservation, and management of airport pavement infrastructure. Airfield Marking Maintenance Plan: Develop a maintenance plan for airfield pavement markings to ensure continued visibility, compliance, and operational safety. Airfield Rubber Removal: Evaluate existing rubber accumulation and develop appropriate removal and maintenance strategies to maintain runway surface conditions and operational safety. The selected A&E firm will be expected to provide the professional expertise necessary to evaluate existing conditions, assess alternatives, develop recommendations, and prepare the required engineering designs, plans, specifications, and related deliverables for these projects. The overall objective is to maintain and improve the safety, operational efficiency, and long-term reliability of the Airport's airfield infrastructure. SCOPE OF WORK SOW Santa Fe Regional Airport Airfield Preservation Rehabilitation, Maintenance and Design The Santa Fe Regional Airport consists of three (3) runways: Runway 02/20, the primary runway; Runway 15/33, the secondary runway; and Runway 10/28, which primarily serves General Aviation (GA) operations. The airfield also includes multiple taxiways, identified as Alpha, Delta, Delta 1, Foxtrot, Foxtrot 1, Foxtrot 2, Foxtrot 3, Golf, and Juliet. The selected Firm shall furnish all labor, qualified personnel, supervision, equipment, software, transportation, and professional expertise necessary to perform the services required under this RFQ. Specific assignments and project requirements will be established and authorized through individual task orders issued by the Airport. Each task order will identify the applicable scope of work, required deliverables, schedule, and other project-specific requirements. Projects will be designated on priority per the airport's directive include, but are not limited to: Grading and Slant Surveying on Runway Safety Areas (RSA) of 02/20 and 15/33 Runway Safety Area (RSA) Improvements of 02/20 and 15/33 Pavement Rehab of Runway 02/20 and 15/33 Pavement Preservation on Runway 02/20 and 15/33 Airfield Lighting Improvements and Electrical Vault Rubber Removal on Runway 02/20 and 15/33 Services may include, but are not limited to, the following: 1. Professional Planning Services Review existing conditions, facilities, infrastructure, and available project information Meet with Airport staff to identify project needs, goals, and priorities Develop preliminary project concepts and recommendations Assist with project scope development and identification of required design and construction services Prepare preliminary project cost estimates and budget recommendations Develop preliminary project schedules and identify major project milestones Identify potential permitting, environmental, regulatory, FAA, or other project requirements Coordinate with Airport staff, stakeholders, utilities, agencies, and other parties as needed Identify potential project risks, challenges, and construction impacts Provide recommendations regarding project phasing and implementation Assist the Airport with determining project priorities and funding needs Prepare planning documents, reports, exhibits, and other materials necessary to support project development and decision-making Airport Layout Plan (ALP) Updates 2. Architectural and Services Airfield rehab and improvements design Building code analysis and compliance, per State and Local Regulations Preparation of construction drawings and specifications Regulatory Compliances per FAA Advisory Circulars (AC's) Preparation of Construction Safety and Phasing Plan (CSPP) 3. Civil and Airfield Engineering Runway, taxiway, apron, and safety area improvements Pavement rehabilitation and reconstruction Drainage and stormwater system design Utility infrastructure improvements Grading and erosion control Airfield marking and signage improvements 4. Geotechnical and Materials Geotechnical investigations Soil borings Pavement cores Subgrade evaluation Materials testing Asphalt testing Concrete testing Pavement strength evaluation FWD testing, if appropriate Aggregate testing Compaction testing Construction materials inspection 5. Electrical Engineering Electrical distribution and lighting systems Emergency power and backup systems 6. Construction Administration and Support Bid phase assistance and responses to Request for Information (RFI) Review of contractor submittals and shop drawings Construction observation and inspection Project scheduling and coordination Change order review and recommendations Preparation of punch lists and closeout documentation Coordination with airport staff, tenants, contractors, and regulatory agencies 7. Emergency and Miscellaneous Services Rapid-response engineering evaluations Emergency repair design services Airfield condition assessments Grant support documentation As-built documentation and record drawings Other related professional services as required by the Airport All work shall be performed in accordance with applicable FAA Advisory Circulars 14 CFR Part 139, TSA requirements 49 CRF Chapter XII, New Mexico state regulations, local codes, and Airport standards. The Consultant shall coordinate closely with Airport staff to minimize operational disruptions and maintain safe airport operations throughout all phases of work. For any and all work conducted, hard copy and digital copies of as-built plans are required to be given to the Airport. The Consultant shall provide professional recommendations and planning information that will allow the Airport to make informed decisions before proceeding with Architect, Engineering, bidding, and construction services. Planning services may be requested on an as-needed basis for individual projects throughout the term of the agreement. INTRODUCTION PURPOSE OF THIS RFQ The Santa Fe Regional Airport (Airport) is soliciting qualification-based proposals from qualified architectural and engineering (A&E) firms to provide professional design services for multiple airfield preservation, rehabilitation, and maintenance projects. This Solicitation is in adherence to Advisory Circular 150/5100-14E. Runway 02/20 is the Airport's primary runway and serves as the designated runway for commercial airline arrivals and departures, including regional jet operations. During the Federal Aviation Administration's (FAA) most recent annual inspection, deficiencies and areas requiring corrective action were identified on both Runway 02/20 and the secondary Runway 15/33. These findings, along with the Airport's ongoing infrastructure preservation needs, have established the need for professional A&E services to evaluate existing conditions, develop appropriate design solutions, and prepare plans and specifications for the required improvements. The projects requiring attention include, but are not limited to, the following: Runway Safety Area (RSA) Grading Improvements: Evaluate and develop corrective grading improvements to address deficiencies within the RSAs for Runways 02/20 and 15/33. Runway Pavement Preservation: Evaluate pavement conditions and develop preservation and rehabilitation improvements for Runways 02/20 and 15/33. Runway 02/20 Improvements: Evaluate alternatives and develop design plans for improvements to Runway 02/20, which may include runway extension, rehabilitation, or reconstruction. Pavement Maintenance Plan (PMP): Develop a comprehensive pavement maintenance plan to support the ongoing assessment, preservation, and management of airport pavement infrastructure. Airfield Marking Maintenance Plan: Develop a maintenance plan for airfield pavement markings to ensure continued visibility, compliance, and operational safety. Airfield Rubber Removal: Evaluate existing rubber accumulation and develop appropriate removal and maintenance strategies to maintain runway surface conditions and operational safety. The selected A&E firm will be expected to provide the professional expertise necessary to evaluate existing conditions, assess alternatives, develop recommendations, and prepare the required engineering designs, plans, specifications, and related deliverables for these projects. The overall objective is to maintain and improve the safety, operational efficiency, and long-term reliability of the Airport's airfield infrastructure. BACKGROUND INFORMATION The Santa Fe Regional Airport was originally constructed in 1945 and has served as a primary source of commercial air transportation for Santa Fe and Northern New Mexico. As commercial aviation activity and passenger demand have grown, the need for continued infrastructure maintenance, rehabilitation, and expansion has become increasingly important to accommodate current operations and future growth. The airport's original development included approximately five miles of combined runway length and infrastructure designed to accommodate some of the military's heaviest aircraft. In 1957, a major airport expansion was completed through a joint effort between the City of Santa Fe and Santa Fe County, establishing what was then known as the Santa Fe Municipal Airport. This expansion included significant improvements to the airfield, particularly the runways, taxiways, and airline terminal apron. The first major runway rehabilitation, which included resurfacing, took place in 1972 to support the airport's continued operational needs and anticipated growth. Subsequent rehabilitation of Runway 02/20 included resurfacing in 2005 and milling and overlay work in 2017. The airport currently operates two primary runways: Runway 02/20: 8,366 feet long and 150 feet wide. Runway 15/33: 6,316 feet long and 100 feet wide. Given the airport's continued growth and the ongoing demands placed on its infrastructure, maintaining, modernizing, and expanding airport facilities is essential to ensuring the continued safety, efficiency, and reliability of airport operations. FAA Mandatory Contract Provisions I. ACCESS TO RECORDS AND REPORTS The Contractor must maintain an acceptable cost accounting system. The Contractor agrees to provide the Owner, the Federal Aviation Administration and the Comptroller General of the United States or any of their duly authorized representatives access to any books, documents, papers and records of the Contractor which are directly pertinent to the specific contract for the purpose of making audit, examination, excerpts and transcriptions. The Contractor agrees to maintain all books, records and reports required under this contract for a period of not less than three years after final payment is made and all pending matters are closed. II. BREACH OF CONTRACT TERMS Any violation or breach of terms of this contract on the part of the Consultant or its subcontractors may result in the suspension or termination of this contract or such other action that may be necessary to enforce the rights of the parties of this agreement. Owner will provide Consultant written notice that describes the nature of the breach and corrective actions the Consultant must undertake in order to avoid termination of the contract. Owner reserves the right to withhold payments to Contractor until such time the Contractor corrects the breach or the Owner elects to terminate the contract. The Owner’s notice will identify a specific date by which the Consultant must correct the breach. Owner may proceed with termination of the contract if the Consultant fails to correct the breach by the deadline indicated in the Owner’s notice. The duties and obligations imposed by the Contract Documents and the rights and remedies available thereunder are in addition to, and not a limitation of, any duties, obligations, rights and remedies otherwise imposed or available by law. III. GENERAL CIVIL RIGHTS PROVISION In all its activities within the scope of its airport program, the Contractor agrees to comply with pertinent statutes, Executive Orders, and such rules as identified in Title VI List of Pertinent Nondiscrimination Acts and Authorities to ensure that no person shall, on the grounds of race, color, national origin, creed, sex, age, or disability be excluded from participating in any activity conducted with or benefiting from Federal assistance. This provision is in addition to that required by Title VI of the Civil Rights Act of 1964. IV. CIVIL RIGHTS – TITLE IV ASSURANCE – SOLICITATION NOTICE As a condition of a grant award, the Sponsor shall demonstrate that it complies with the provisions of Title VI of the Civil Rights Act of 1964 (42 U.S.C. §§ 2000d et seq) and implementing regulations (49 CFR part 21) including amendments thereto, the Airport and Airway Improvement Act of 1982 (49 U.S.C. § 47123), the Age Discrimination Act of 1975 (42 U.S.C. 6101 et seq.), Section 504 of the Rehabilitation Act of 1973 (29 U.S.C. § 794 et seq.), the Americans with Disabilities Act of 1990 (42 U.S.C. § 12101, et seq.), U.S. Department of Transportation and Federal Aviation Administration (FAA) Assurances, and other relevant civil rights statutes, regulations, or authorities, including any amendments or updates thereto. This may include, as applicable, providing a current Title VI Program Plan to the FAA for approval, in the format and according to the timeline required by the FAA, and other information about the communities that will be benefited and impacted by the project. A completed FAA Title VI Pre-Grant Award Checklist is required for every grant application, unless excused by the FAA. The Sponsor shall affirmatively ensure that when carrying out any project supported by this grant that it complies with all federal nondiscrimination and civil rights laws based on race, color, national origin, sex, creed, age, disability, genetic information, in consideration for federal financial assistance. The Department’s and FAA’s Office of Civil Rights may provide resources and technical assistance to recipients to ensure full and sustainable compliance with Federal civil rights requirements. Failure to comply with civil rights requirements will be considered a violation of the agreement or contract and be subject to any enforcement action as authorized by law. V. TITLE VI – LIST OF PERTINENT NON DISCRIMINATION ACTS AND AUTHORITIES During the performance of this contract, the Contractor, for itself, its assignees, and successors in interest (hereinafter referred to as the “Contractor”) agrees to comply with the following non-discrimination statutes and authorities; including but not limited to: • Title VI of the Civil Rights Act of 1964 (42 U.S.C. § 2000d et seq., 78 stat. 252) (prohibits discrimination on the basis of race, color, national origin); • 49 CFR Part 21 (Non-discrimination in Federally-Assisted programs of the Department of Transportation—Effectuation of Title VI of the Civil Rights Act of 1964) including amendments thereto; • The Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, (42 U.S.C. § 4601) (prohibits unfair treatment of persons displaced or whose property has been acquired because of Federal or Federal-aid programs and projects); • Section 504 of the Rehabilitation Act of 1973 (29 U.S.C. § 794 et seq.), as amended (prohibits discrimination on the basis of disability); and 49 CFR part 27 (Nondiscrimination on the Basis of Disability in Programs or Activities Receiving Federal Financial Assistance); • The Age Discrimination Act of 1975, as amended (42 .U.S.C. § 6101 et seq.) (prohibits discrimination on the basis of age); • Airport and Airway Improvement Act of 1982 (49 U.S.C. § 47123), as amended (prohibits discrimination based on race, creed, color, national origin, or sex); • The Civil Rights Restoration Act of 1987 (P.L. 100-259) (broadened the scope, coverage and applicability of Title VI of the Civil Rights Act of SCOPE OF PROCUREMENT The resulting contract will result in a professional services contract with an initial term of four (4) years with the option to renew up to eight (8) years. PROCUREMENT MANAGER The Santa Fe Regional Airport has assigned a Procurement Manager who is responsible for the conduct of this procurement whose name, address, telephone number, and email address are listed below: Name Sebastian Gallegos, Airport Project Manager Telephone Number 505-695-3538 Email sfgallegos@santafenm.gov Any inquiries or requests regarding this procurement should be submitted via the OpenGov Procurement Portal at https://procurement.opengov.com/portal/santafenm/projects/299974 . DEFINITION OF TERMINOLOGY This section contains definitions of terms used throughout this procurement document, including appropriate abbreviations: “ Addendum ” means a written or electronic document issued by the City to modify, clarify, or supplement the information in the original RFQ prior to the proposal due date. This may also be called Amendment or RFQ Amendment. “ Amended Proposal ” means a revised and complete version of a proposal submitted by an Offeror prior to the proposal due date, clearly labeled as superseding the original submission. “ Authorized Purchaser ” means an individual authorized by a Participating Entity to place orders against this contract. “ Award ” means the point at which the contract document has been fully executed. See also “Contract” and “Final Award”. “ Evaluation ” means an evaluation process in which identifying information is removed from proposals to ensure objective scoring by the Evaluation Committee. “ Business Hours ” means the normal business hours of the Requesting department; 8:00 AM through 5:00 PM Mountain Standard or Daylight Time, whichever is in effect on the date given. “ Central Purchasing Division ” or “ CPD ” means the City office responsible for overseeing and managing the procurement of tangible personal property, services, and construction, including ensuring compliance with applicable procurement laws, policies, and procedures. “ Chief Procurement Officer ” or “ CPO ” means that person within the CPD who is responsible for the control of procurement of items of tangible personal property, services, or construction. “

Published attachments
Addenda and notices
Public questions and answers
  • Items (a) and (b) under Organizational Experience on page 20 appear to overlap with items (g) and (h) under Mandatory Specifications on page 22. Does the City want the requested information provided in full in both sections?

    Yes. Required in both sections.

  • OpenGov provides separate upload fields for Financial Stability and the Technical Proposal. We are privately held and consider our audited financial statements confidential. We understand that the technical proposal will be made available to the public in accordance with the City’s procurement process. Will our audited financial statements also be made available to the public?

    No, the City will not make your financial statements public. Please mark the upload as "Confidential".

  • The FAA mandatory and model solicitation provisions appear to be absent from the RFQ, and the corresponding FAA professional services contract provisions appear to be absent from the proposed agreement. Does the City anticipate using FAA Airport Improvement Program (AIP) funds for any projects under this contract? If so, please clarify which FAA provisions will apply.

    An amendment has been created for the contract that does have the correct language per AC150/5100-14

Plain text