State and local · OpenGov
SCDPH Building Renovation & Parking Improvements
Description
Beaufort County is soliciting sealed bids from qualified and licensed contractors for the South Carolina Department of Public Health (SCDPH) Building Renovation project located at 247 Robert Smalls Parkway, Beaufort, South Carolina. The project consists of the interior and exterior renovation of an approximately 13,958-square-foot, single-story pre-engineered metal building to accommodate the operations and services of the South Carolina Department of Public Health. The work includes demolition and interior build-out, new office and patient care spaces, architectural finishes, mechanical, electrical, plumbing, fire protection, and low-voltage systems, along with associated exterior site improvements. Site improvements include clearing, grading, construction of a new parking area, stormwater infrastructure, drainage improvements, utility work, landscaping, and related paving and concrete improvements. The project also includes modifications to the existing building systems and site infrastructure necessary to accommodate the proposed change of occupancy and provide a complete, code-compliant, and operational facility. The selected contractor shall provide all labor, materials, equipment, supervision, permits, testing, and coordination necessary to complete the work in accordance with the issued construction drawings, specifications, and contract documents. SCDPH Building Renovation & Parking Improvements - Base Bid General Conditions, Mobilization, Insurance, Bonds, Temporary Facilities, etc. Permits, Fees, and Required Inspections (Permits, Application Fees, Utility Fees, and Permit-Related Inspections) Existing Conditions and Demolition (Existing Conditions Documentation, Building and Site Demolition, Removal and Disposal, and Protection of Existing Improvements to Remain) Interior Framing, Partitions, and Drywall (Metal Stud Framing, Gypsum Board, Interior Walls, Soffits, and Related Work) Interior Finishes (Painting, Flooring, Base, Wall Finishes, Ceiling Finishes, and Related Work) Doors, Frames, and Hardware (Interior Doors, Frames, Hardware, and Related Components & Work) Casework, Millwork, Countertops, and Architectural Specialties Mechanical / HVAC Systems (Equipment, Ductwork, Controls, Distribution, Connections, Testing, and Balancing) Plumbing and Gas Systems (Interior Piping, Fixtures, Water Heating Equipment, Gas Piping, and Building Connections) Electrical, Lighting, and Power Distribution (Panels, Wiring, Conduit, Devices, Lighting, Controls, and Equipment Connections) Low-Voltage and Data Infrastructure (Conduit, Cabling, Boxes, Outlets, and Related Infrastructure) Fire Protection and Life Safety Systems (Fire Sprinkler Modifications, Fire Alarm Devices and Connections, Life Safety Devices, and Related Work) Site Preparation, Clearing, Grading, Earthwork, and Erosion Control Parking, Paving, Concrete, Sidewalks, Striping, Signage, Fencing, Bollards, and Site Improvements Stormwater Management and Drainage (Piping, Structures, Ponds, BMPs, and Related Work) Site Utilities and Sanitary Sewer Infrastructure (Removal and Disposal of Existing Septic Tank and Drainfield; Sewer Pump Station, Force Main Piping, Directional Drilling, Valves, Connection to Existing Force Main, Testing, Backfill, and Restoration as Required by the Contract Documents) Landscaping, Site Restoration, and Stabilization Testing, Commissioning, Special Inspections, Record Drawings, O&M Documents, Warranties, Final Cleaning, and Project Closeout Add Alternate 01 – Existing Asphalt Parking Lot Resurfacing Provide a separate lump-sum price to mill and overlay the designated existing asphalt parking area within the Beaufort County portion of the front parking lot, as identified in the contract documents. This alternate is limited to resurfacing the existing asphalt area and shall not include any paving, asphalt repairs, or other pavement work required by the construction documents for the Base Bid. All paving and related improvements specifically required by the construction documents shall be included in the Base Bid. Existing Asphalt Parking Lot Resurfacing (Mill and Overlay the Designated Existing Asphalt Parking Area, shown as Bid Alternate, within the Beaufort County Portion of the Front Parking Lot, Including Associated Preparation and Work) Add Alternate 02 – Exterior Canopies Provide a separate lump-sum price for the installation of exterior canopies at the two designated employee entrances, including all required supports, connections, materials, labor, and associated work necessary for a complete installation. This work shall be included only as an Add Alternate and shall not be included in the Base Bid. Exterior Canopies (Furnish and Install Canopies at the Two Designated Employee Entrances, Including Supports, Connections, and Associated Work) Add Alternate 03 – Additional Exterior Building Painting Provide a separate lump-sum price to paint the remaining exterior surfaces of the existing building that are not specifically identified as requiring painting in the Base Bid construction documents. This alternate is for additional exterior building painting beyond the painting and coating work expressly required by the construction documents. All exterior painting, coatings, surface preparation, and related work specifically required by the construction documents shall be included in the Base Bid and shall not be included in this alternate. Exterior Building Painting (Prepare and Paint the Remainder of the Existing Building Exterior) SCOPE OF WORK Scope of Work South Carolina Department of Public Health (SCDPH) Building Renovation & Parking Improvements The Contractor shall provide all labor, materials, equipment, supervision, subcontractors, permits, testing, and services necessary to complete the South Carolina Department of Public Health (SCDPH) Building Renovation project in accordance with the issued construction drawings, project specifications, and contract documents. The project generally consists of the interior and exterior renovation of the existing approximately 13,958-square-foot, single-story pre-engineered metal building, including construction of new interior spaces, modifications to existing building systems, and associated site improvements. The project includes a change of occupancy from Mercantile to Business and the associated improvements necessary to bring the existing facility into compliance with applicable building code requirements. The following identifies the general categories of work and is intended to provide an overview of the project. It is not intended to identify every individual component or construction activity. The Contractor shall review and comply with the complete construction documents, including all drawings, details, schedules, notes, and specifications, which collectively define the full extent of the work. 1. General Requirements and Demolition Provide project management, supervision, coordination, mobilization, temporary facilities, and all associated services necessary to complete the project. Perform demolition and removal of existing building components, finishes, equipment, and designated site improvements as indicated in the construction documents. Protect existing building components, utilities, and improvements designated to remain. The existing building is unoccupied and will remain unoccupied for the duration of construction. The Contractor shall coordinate and perform the work accordingly. 2. Building Renovations and Interior Construction Renovate and build out the existing building to accommodate SCDPH operations, including ambulatory patient care and administrative services. Spaces include patient restrooms, staff restrooms, a unisex laboratory restroom, exam rooms, a break room, offices, meeting and training spaces, storage, and open office areas. Work includes metal stud and gypsum board partitions, solid-core wood doors in hollow-metal frames, flooring, suspended acoustical tile and gypsum board ceilings, plastic laminate cabinetry with solid-surface countertops, and other architectural improvements indicated in the construction documents. Include modifications to existing exterior building components and openings where required. 3. Mechanical, Plumbing, Electrical, and Fire Protection Systems Modify, extend, replace, and install mechanical, plumbing, electrical, low-voltage, and fire protection systems as required to serve the renovated facility. Work includes new split-system heat pumps, ductwork and air distribution devices; new electrical panels, lighting, service outlets, and equipment connections; and plumbing fixtures and floor drains serving restrooms, exam rooms, and the break room. Domestic water work shall utilize existing on-site service lines as indicated in the construction documents. The existing fire sprinkler system shall be modified as necessary to accommodate the new building layout and occupancy. Include all associated equipment, distribution systems, controls, wiring, piping, and connections necessary for a complete and operational facility. 4. Sitework, Parking, and Stormwater Improvements Perform the site preparation and improvements necessary to support the renovated facility. Work generally includes clearing, demolition, grading, earthwork, improvements to the existing parking lot, construction of a new parking lot, gravel, asphalt and concrete paving, sidewalks, accessible routes, drainage, stormwater piping and structures, a rain garden, a stormwater retention pond, landscaping, erosion control, and site restoration as indicated in the construction documents. 5. Site Utilities and Sewer Infrastructure Remove and properly dispose of the existing septic tank and drainfield as indicated in the construction documents. Provide the sanitary sewer infrastructure, including a new pump station and associated piping and appurtenances, connected to the existing sewer force main. Domestic water and other utility work shall utilize or connect to existing on-site service lines as indicated in the construction documents. Include associated excavation, connections, valves, equipment, testing, backfill, and restoration necessary to provide complete and operational utility systems. 6. Testing, Inspections, and Project Closeout Provide all required permits, inspections, testing, adjustments, and commissioning necessary for completion and operation of the building and site improvements. Provide required closeout documentation, record drawings, warranties, operation and maintenance information, final cleaning, and correction of deficiencies. Turn over a complete, safe, clean, and operational facility. 7. Owner-Furnished Equipment and Materials Coordinate with the Owner regarding furniture, equipment, appliances, and other items identified as Owner-furnished in the construction documents. Provide the coordination, rough-ins, connections, blocking, supports, and other associated work required of the Contractor. Procurement and furnishing of Owner-furnished items shall be excluded from the Contractor's base bid unless specifically identified otherwise in the contract documents. The Contractor shall be responsible for reviewing the complete construction documents and including all work necessary for a complete project, whether or not every individual item or activity is specifically identified in this general Scope of Work. IMPORTANT ELECTRONIC SUBMITTAL REQUIREMENTS Response submittals for this Invitation For Bid will ONLY be received electronically and must be submitted ONLINE, through the Procurement Portal, no later than 3:00 pm on Friday, December 18, 2026 . All responses must adhere to the following guidelines: Suppliers are encouraged to submit responses as soon as possible. Responses are received through our secure Procurement Portal and cannot be opened prior to the due date and time. The time and date of receipt as recorded by the server will serve as the official time of receipt. The County is not responsible for late submissions, regardless of the reason. All requested information and forms MUST be uploaded as indicated in the PROPOSAL SUBMITTAL Section. If you have a problem with your submittal, you may contact Support through the Procurement Portal. TITLE VI STATEMENT COUNTY COUNCIL OF BEAUFORT COUNTY Title VI Statement to Prime Contractors, Subcontractors, Architects, Engineers, and Consultants It is the policy of the County Council of Beaufort County, South Carolina, hereafter referred to as “Beaufort County” or “the County”, to comply with Title VI of the 1964 Civil Rights Act (Title VI) and its related statutes. To this end, Beaufort County assures that no person shall be excluded from participation in, denied the benefit of, or subjected to discrimination under any of its programs or activities on the basis of race, color, national origin, age, sex, disability, religion, or language regardless of whether those programs and activities are Federally funded or not. The County is also committed to assuring every effort will be made to prevent the discrimination of low-income and minority populations as a result of any impact of its programs or activities. Beaufort County also assures that every effort will be made to prevent discrimination through the impacts of its programs, policies, and activities on minority and low-income populations. Additionally, the County will take reasonable steps to provide meaningful access to services for persons with limited English proficiency. In addition, Beaufort County will not retaliate against any person who complains of discrimination or who participates in an investigation of discrimination. Beaufort County will, where necessary and appropriate, revise, update, and incorporate nondiscrimination requirements into appropriate documents, directives, and regulations. Pursuant to Title VI requirements, any entity that enters into a contract with Beaufort County including, but not limited to Prime Contractors, Subcontractors, Architects, Engineers, and Consultants, may not discriminate on the basis of race, color, national origin, age, sex, disability, religion, or language in their selection and retention of first-tier subcontractors, and first-tier subcontractors may not discriminate in their election and retention of second-tier subcontractors, including those who supply materials and/or lease equipment. Further, Contractors may not discriminate in their employment practices in connection with highway construction projects or other projects assisted by the U.S. Department of Transportation (USDOT) and/or the Federal Highway Administration (FHWA). In all solicitations either by competitive bidding or negotiation made by the Contractor for work to Beaufort County to be performed under a subcontract, including procurements of materials or leases of equipment, each potential subcontractor or supplier shall be notified by the Contractor of the Contractor's obligations under the contract and the Title VI regulations relative to nondiscrimination on the basis of race, color, national origin, age, sex, disability, religion, or language by providing such a statement in its bidding and contract documents. Upon request, the Contractor shall provide all information and reports required by Title VI requirements issued pursuant thereto, and shall permit access to its books, records, accounts and other sources of information, and its facilities as may be determined by Beaufort County, USDOT, and/or FHWA to be pertinent to ascertain compliance with such regulations, orders, and instructions. Where any information required of a Contractor is in the exclusive possession of another who fails or refuses to furnish this information, the Contractor shall so certify to USDOT or FHWA, as appropriate and via Beaufort County, and shall set forth what efforts it has made to obtain the information. In the event of the Contractor's non-compliance with nondiscrimination provisions of this contract, USDOT may impose such contract sanctions as it or FHWA may determine to be appropriate, including, but not limited to: Withholding of payments to the Contractor under the contract until the Contractor complies, and/or Cancellation, termination, or suspension of the contract, in whole or in part. In the event a Contractor becomes involved in, or is threatened with, litigation with a subcontractor or supplier as a result of this direction to comply with Title VI, the Contractor may request USDOT to enter into such litigation to protect the interests of USDOT and FHWA. Additionally, the Contractor may request the United States to enter into such litigation to protect the interests of the United States. Any person or Subcontractor who believes that they have been subjected to an unlawful discriminatory practice under Title VI has a right to file a formal complaint within one hundred eighty (180) days following the alleged discriminatory action. Any such complaint must be filed in writing or in person: Beaufort County Government Post Office Drawer 1228 | Beaufort, SC 29901-1228 843-255-2304 Telephone | E-mail: dthomas@bcgov.net INVITATION FOR BID Dates Advertised: 11182026 This is a Formal Sealed Bid We require Bids to be Electronically submitted through the Procurement Portal. Please go to https://procurement.opengov.com/portal/bcgov and sign up to submit your bid. BIDS WILL BE RECEIVED UNTIL 3:00 pm LOCAL TIME ON Friday, December 18, 2026 . Bid Title: SCDPH Building Renovation & Parking Improvements Bid No: IFB121826 PREBID CONFERENCE: A Pre-Bid conference will be held on Wednesday, December 2, 2026 at 2:00 pm p.m. virtually through Teams. This is a Mandatory meeting; all interested bidders and subcontractors are required to attend. WebEx: Meeting will be held at 247 Robert Smalls Parkway, Beaufort, South Carolina. . All questions must be submitted through the Procurement Portal no later than 5:00 pm on Friday, December 11, 2026 . A Bid Tabulation Will Be Posted On The Procurement Portal After Bid Opening. BID ACCEPTANCE AND DELIVERY (Prices bid must be firm for a minimum of 90 Days ). In compliance with the Invitation, and subject to all conditions thereof, the Offeror agrees, if this bid is accepted within (90) days from date of opening, to furnish any or all items quoted on at prices as set forth after the item and to make delivery within NA after receipt of order with transportation cost included and prepaid. Unless otherwise stated and accepted herein, the Offeror agrees to complete this proposed contract in less than thirty (30) calendar days after issue date of purchase order. I M P O R T A N T IF YOU CONSIDER THESE SPECIFICATIONS AS RESTRICTIVE, SEE GENERAL PROVISIONS, PARAGRAPH #20, DISCREPANCIES. Bids received after the time specified for opening cannot be considered. BID INVITATION SCDPH Building Renovation & Parking Improvements IFB121826 Sealed bids submitted through the Procurement Portal will be received electronically until 3:00 pm on Friday, December 18, 2026 at which time responses to this request will be recorded in the presence of one or more witnesses in the Procurement Services Department. A Bid Tab will be posted on the Procurement Portal for: SCDPH Building Renovation & Parking Improvements A PRE-BID conference will be held on Wednesday, December 2, 2026 at 2:00 pm p.m. virtually through Teams. This is a Mandatory meeting; all interested bidders are required to attend. WebEx: Meeting will be held at 247 Robert Smalls Parkway, Beaufort, South Carolina. . Bid documents are available through the Procurement Portal at https://procurement.opengov.com/portal/bcgov . Beaufort County reserves the right to reject all proposals and to waive minor informalities and irregularities. All Bids shall be accompanied by a Bid Bond drawn in favor of the Beaufort County Treasurer of Beaufort County, Beaufort, South Carolina, in the amount of at least five percent (5%) of the bid for the complete work: such Bid Bond repre
Published attachments
Public questions and answers
in the bid-packet the pre-bid is non-mandatory. On the portal it states that the pre-bid is mandatory. Please confirm Release Project Date:November 17, 2026 Pre-Bid Meeting (Mandatory):December 2, 2026, 2:00pm Meeting will be held at 247 Robert Smalls Parkway, Beaufort, South Carolina.
Thank you for bringing this to our attention! It has been corrected. This will be a mandatory meeting, located at 247 Robert Smalls Parkway, Beaufort, South Carolina.
Will you be requiring third party Commissioning fr this project?
No. Third-party commissioning by an independent commissioning agent is not required for this project. The Contractor is responsible for completing all specified equipment startup, testing, adjusting, and verification activities, including confirming proper operation of equipment, controls, and safety devices, in accordance with the Contract Documents and manufacturers’ requirements. This is consistent with the Project Manual, which requires the Contractor to start and adjust equipment and test each piece of equipment to verify proper operation (Section 01 70 00, Paragraph 3.4).
The Bid Invitation states: "County permits shall be required as applicable, but the fee shall be waived. This waiver shall apply to the Beaufort County permit fee only and not to any "City or Town" permit fee and/or licenses, when applicable." Is this project in the City or does it fall under county jurisdiction?
This project is within the City of Beaufort and any Permit Fees will need to be paid accordingly.
Is the mandatory Pre-Bid meeting in person at the site or on Teams?
The pre-bid meeting is in-person and on-site at 247 Robert Smalls Pkwy.
OpenGov categories
- 90900 · Building Construction Services, New (Incl. Maintenance And Repair Services)
- 90921 · Building Construction, Industrial (Warehouse, etc.)
- 90922 · Building Construction, Non-Residential (Office Bldg., etc.)
- 90924 · Building Construction, Commercial and Institutional
- 90928 · Building Construction, Medical
- 90930 · Building Construction (Not Otherwise Classified)