Description

GRAVITY SEWER: Construction of approximately 4,900 LF of 8-inch diameter SDR-26 PVC and 400 LF of DIP gravity sewers with 18 4-feet diameter manholes, 87 6-inch diameter SDR-26 PVC service laterals with cleanouts. POTABLE WATER: Placing an aged water distribution system out of service, replaced by approximately 6,000 linear feet of 8-inch diameter C900 PVC with ductile iron fittings, maintenance valves, five (5) fire hydrants, 40 linear feet of 4-inch diameter C900 PVC, and 101 water services, relocating each existing meter to the front property line. SCOPE OF WORK/SERVICES Project Description GRAVITY SEWER: Construction of approximately 4,900 LF of 8-inch diameter SDR-26 PVC and 400 LF of DIP gravity sewers with 18 4-feet diameter manholes, 87 6-inch diameter SDR-26 PVC service laterals with cleanouts, associated improvements via open trench construction and full restoration in the unsewered areas between N. 72nd Ave. to N. 70th Ter. and Fillmore St. to Johnson St. The new gravity sewer system discharges into an existing sanitary sewer manhole located on Fillmore St. at the intersection with NW 70th Ter. POTABLE WATER: Placing an aged water distribution system out of service, replaced by approximately 6,000 linear feet of 8-inch diameter C900 PVC with ductile iron fittings, maintenance valves, five (5) fire hydrants, 40 linear feet of 4-inch diameter C900 PVC, and 101 water services, relocating each existing meter to the front property line. 12 bacteriological sample points are included for water quality verification and connecting the relocated water meters to the water system entering each home. Add language for this titled section or revise/remove as needed. If this is a sole source, a brief description should suffice, feel free to remove the remaining sections below. Technical Specifications Refer to Attachment D - Technical Specifications Contractor Qualifications Minimum of three (3) similar projects performed within the last seven (7) years. The projects must be similar in nature with equal or greater linear feet of pipe installed within public right of way. Resumes of individuals (especially Superintendent) performing the work must be provided. The Bidder must also state their proposed project manager by name and list a minimum of two (2) similar projects managed by him/her with references listed on his/her resume. Must have a Certified Underground Utility and Excavation Contractor. Staff must be licensed and have a minimum of 5 years' work experience installing gravity sanitary sewers and potable water mains. Any one of the following causes, among others, may be considered as sufficient justification to disqualify a bidder and reject his or her bid: A. Submission of more than one bid for the same work by an individual, firm, partnership or corporation under the same or different names. B. Evidence of collusion. C. Previous participation in collusive bidding on work for the City of Hollywood, Florida. D. Submission of an unbalanced bid in which the prices bid for some items are out of proportion to the prices bid for other items. E. Lack of competency. The Bidder shall provide proof that their past experience can demonstrate similar complexity and size compared to this contract. The Engineer may declare any bidder ineligible, at any time during the process or receiving bids or awarding the contract, if developments arise which, in his opinion, adversely affects the bidder's responsibility. The Bidder will be given an opportunity, by the engineer, to present additional evidence before final action is taken. F. Lack of responsibility as shown by past work judged by the Engineer from the standpoint of workmanship and progress. G. Non-compliance with the City’s Local Preference (when applicable). H. Uncompleted work for which the Bidder is committed by Contract, which is in the judgment of the Engineer, might hinder or prevent the prompt completion of work under this Contract. I. Being in arrears on any existing Contracts with the City, or any taxes, licenses or other monies due the City; in litigation with the City or having defaulted on a previous contract with the City. Deliverable and Objectives Refer to Attachment B - General Conditions, Attachment C - Supplementary General Conditions, Attachment D - Technical Specifications and Attachment E - Drawings. Project Schedule / Timeline Refer to Attachment C, Supplementary conditions, Section 1, Project Schedule. Questions Refer to Form 15, “Information Required from Bidders,” provided in IFB Section 5, “Bid Submissions.” SUMMARY Summary Background Contact Information Timeline INTRODUCTION Purpose The City of Hollywood, Florida (City) is seeking bids from qualified and experienced contractors, hereinafter referred to as the Contractor or Bidder, to furnish all tools, equipment, materials, supplies, and manufactured articles and for furnishing all transportation and services, including fuel, power, water, and essential communications, and for the performance of all labor, work, or other operations required for the fulfillment of the Contract for the City, in accordance with the terms, conditions, and specifications contained in this solicitation. Responses to this solicitation are due by Wednesday, December 9, 2026 , by 3:00 pm , and will be opened in a virtual public setting on December 9, 2026, at 3:00 PM . Submittals shall be received electronically through OpenGov, the City's eProcurement Portal ("Portal"). Submittals shall be considered a bid on the part of the bidder, which bid shall be deemed accepted upon approval of the City, and in case of default, the City reserves the right to accept or reject any or all bids, to waive irregularities and technicalities, and request new bids The City also reserves the right to award any resulting agreement as it deems will best serve the interests of the city. Submission of a bid shall serve as prima facie evidence that the Bidder has examined this solicitation and is fully aware of all conditions affecting the provision of services and the evaluation criteria and scoring methodology as set forth in this solicitation document. Pre-bid Conference and/or Site Visit (Non-Mandatory) There will be a non- mandatory pre-bid co nference and/or site visit scheduled for this solicitation. It is strongly suggested that all Contractors attend the non-mandatory pre-bid conference and/or site visit to receive information that may be critical to their understanding of this solicitation. Please keep in mind that site visits at other times might not be available. It is the sole responsibility of the Contractor to become familiar with the scope of the City’s requirements prior to submitting a bid. No variation in price or conditions shall be permitted based upon a claim of ignorance. Submission of a bid will be considered evidence that the Bidder has familiarized themselves with the nature and extent of the work, equipment, materials, and labor required. OpenGov ("Portal") The City of Hollywood uses OpenGov, the e-Procurement Portal (“Portal”) ( https://procurement.opengov.com/portal/hollywoodfl ) to administer the competitive solicitation process, including but not limited to soliciting bids/proposals, issuing addenda, posting results and issuing notification of an intended decision. The City shall not be responsible for a Bidder's/Proposer’s inability to submit a bid/proposal by the bid/proposal end date and time for any reason, including issues arising from the use of the Portal. Point of Contact For information concerning procedures for responding to this solicitation, contact the Point of Contact within the Office of Procurement Services, Julissa Marcano , Senior Purchasing Agent at jmarcano@hollywoodfl.org or by phone at (954) 710-9956 , or Jean Joinville, Procurement Manager, at jjoinville@hollywoodfl.org or by phone at 954-921-3290. Such contact is to be for clarification purposes only. All questions must be submitted in writing via the Portal by Monday, November 23, 2026 , by 5:00 pm , in order to receive a timely response. Project Manager: Roger Bezerra , Project Manager , Public Utilities , email: rbezerra@hollywoodfl.org , or by phone: (954) 921-3930 . For information concerning technical specifications, please utilize the question / answer feature provided by OpenGov at https://procurement.opengov.com/portal/hollywoodfl . Questions of a material nature must be received prior to the cut-off date specified in the solicitation schedule. Material changes, if any, to the scope of services or bidding procedures will only be transmitted by written addendum. (See addendum section of the OpenGov site). Bidders please note: No part of your bid can be submitted via FAX. No variation in price or conditions shall be permitted based upon a claim of ignorance. Submission of a bid will be considered evidence that the Bidder has familiarized themselves with the nature and extent of the work, and the equipment, materials, and labor required. The entire bid response must be submitted in accordance with all specifications contained in this solicitation. The questions and answers submitted in OpenGov shall become part of any contract that is created from this solicitation. It is the sole responsibility of the Bidder to ensure that their bid is submitted electronically through the Portal at https://procurement.opengov.com/portal/hollywoodfl Cone of Silence The City of Hollywood City Commission adopted Ordinance No. O-2007-05, which created Section 30.15(F) imposing a Cone of Silence for certain City purchases of goods and Services. The Cone of Silence refers to limits on communications held between vendors and vendor’s representatives and City elected officials, management and staff during the period in which a Formal Solicitation is open. The Ordinance does allow potential vendors or vendor’s representatives to communicate with designated employees for the limited purpose of seeking clarification or additional information. The names and contact information of those employees that may be contacted for clarification or additional information are included in the solicitation. The Cone of Silence does not prohibit a vendor or vendor’s representative from communicating verbally, or in writing with the City Manager, the City Manager’s designee, the City Attorney or the City Attorney’s designee on those procurement items to be considered by the City Commission. The Cone of Silence does not prohibit a vendor or vendor’s representative from making public presentations at a duly noticed pre-bid conference or duly noticed evaluation committee meeting or from communicating with the City Commission during a duly noticed public meeting. The Cone of Silence shall be imposed when a formal competitive solicitation has been issued and shall remain in effect until an award is made, a contract is approved, or the City Commission takes any other action which ends the solicitation. To view the Cone of Silence, go to the City of Hollywood Code of Ordinance online, and view Section 30.15F All communications regarding this bid should be sent in writing to the Procurement and Performance Management Division as identified in this bid. SPECIAL TERM AND CONDITIONS Addenda, Changes, and Interpretations It is the sole responsibility of each contractor to notify the Point of Contact utilizing the question / answer feature provided by OpenGov and request modification or clarification of any ambiguity, conflict, discrepancy, omission or other error discovered in this competitive solicitation. Requests for clarification, modification, interpretation, or changes must be received prior to the Question and Answer (Q & A) Deadline. Requests received after this date may not be addressed. Questions and requests for information that would not materially affect the scope of services to be performed, or the solicitation process will be answered within the question / answer feature provided by OpenGov and shall be for clarification purposes only. Material changes, if any, to the scope of services or the solicitation process will only be transmitted by official written addendum issued by the City and uploaded to OpenGov as a separate addendum to the solicitation. Under no circumstances shall an oral explanation given by any City official, officer, staff, or agent be binding upon the City and should be disregarded. All addenda are a part of the competitive solicitation documents and each firm will be bound by such addenda. It is the responsibility of each to read and comprehend all addenda issued. Dimensions, Quantities and Subsurface Information Dimensions, quantities, and subsurface information supplied by the City are in no way warranted to indicate true amounts or conditions. Bidders/Contractors shall neither plead misunderstanding or deception nor make claims against the City if the actual amounts, conditions, or dimensions do not conform to those stated. Any "Outside" reports made available by the Engineer are neither guaranteed as to accuracy or completeness, nor a part of the Contract Documents. Trench Safety Form The Trench Safety Form included in the Bid Documents must be completed and signed. Noncompliance with this requirement may invalidate the bid. Changes and Alterations Bidder may change or withdraw a Bid at any time prior to Bid submission deadline; however, no oral modifications will be allowed. Modifications shall not be allowed following the Bid deadline. Bidder’s Costs The City shall not be liable for any costs incurred by Bidders in responding to this solicitation. Pricing/Delivery All pricing must include delivery and installation and be quoted FOB: Destination, unless specified otherwise in the #SCOPE OF WORK/SERVICES section. Price Validity Prices provided in this solicitation shall be valid for at least One-Hundred and Twenty (120) days from time of solicitation opening unless otherwise extended and agreed upon by the City and Bidder. No Exclusive Contract Bidder agrees and understands that the contract shall not be construed as an exclusive arrangement and further agrees that the City may, at any time, secure similar or identical services from another vendor at the City’s sole option. Responsive In order to be considered responsive to the solicitation, the contractor’s bid shall fully conform in all material respects to the solicitation and all of its requirements, including all form and substance. Responsible In order to be considered as a responsible bidder, bidder shall be fully capable to meet all of the requirements of the solicitation and subsequent contract, must possess the full capability, including financial and technical, to perform as contractually required, and must be able to fully document the ability to provide good faith performance. Minimum Qualifications To be eligible for award of a contract in response to this solicitation, the Bidder must demonstrate that they have successfully completed services, as specified in the #SCOPE OF WORK/SERVICES section of this solicitation, are normally and routinely engaged in performing such services, and are properly and legally licensed (if required) to perform such work. Bidder must possess and be able to provide the City with any and all required Federal, State, County and/or municipal licenses, and occupational licenses. Bidder must be able to provide proof of valid licensing for all subcontractors and/or material suppliers hired by the contractor, if requested. In addition, the Bidder must have no conflict of interest with regard to any other work performed by the Bidder for the City. Award of Contract Award may be in the aggregate, or by line Item, or by group, whichever is determined to be in the best interest of the City. Award will be made to the responsive and responsible bidder, quoting the lowest price, for that product/service that will best serve the needs of the City. The Contract will be awarded only to a Bidder, who in the opinion of the Engineer, is fully qualified to undertake the work, quoting the lowest price, for that product/service that will best serve the needs of the City. The City reserves the right before awarding the Contract to require a Bidder to submit such evidence of his qualifications as it may deem necessary and may consider any available evidence of his financial status, technical qualifications, and other qualifications and abilities. The City also reserves the right to accept or reject any or all bids, part of bids, and to waive minor irregularities or variations to specifications contained in bids, and minor irregularities in the bidding process. The City also reserves the right to award the contract on a split order basis, lump sum basis, individual item basis, or such combination as shall best serve the interest of the City. As applicable, the City shall comply with Section 287.05701, Florida Statutes, in not considering or giving preference for an award based on a vendor’s social, political, or ideological interest. The City, in all solicitations or advertisements for purchasing of goods, supplies, materials, equipment and services, will receive consideration from qualified businesses without regard to race, color, religion, sex, sexual orientation, gender identity, or national origin. Execution Of Contract The Bidder awarded the Contract shall, within ten days from the date of award, execute all required documents and submit them electronically, complete with valid signatures and seals. A. The Contract B. Performance and Payment Bond C. Evidence of required Insurance D. Proof of authority to execute the Contract E. Proof of authority to execute the Bond on behalf of the Awardee F. List of Subcontractors, estimated Contract Value for each and proof that such subcontractors possess all required Federal, State, County and/or municipality licenses, including but not limited to certified of competency and occupational license The above documents must be furnished, executed and delivered before the Contract will be executed by the City. The Contract shall not be binding upon the City until it has been executed by the City and a copy of such fully executed Contract is delivered to the Contractor. Failure To Execute Contract, Bid Guaranty Forfeited Should the Bidder to whom the Contract has been awarded refuse or fail to complete the requirements of Section 2.13 above within ten (10) days after Notice of Award, the additional time in days (including weekends) required to CORRECTLY complete the documents will be deducted, in equal amount, from the Contract Time, or the City may elect to revoke the Award. The Bid Guaranty of any Bidder failing to execute the awarded Contract shall be retained by the City and the Contract awarded as the Commission desires. Manufacturer/Brand/Model Specific Request In the event of a manufacturer/brand/model specification. No substitutions will be allowed unless specified in Section: SCOPE OF WORK/SERVICES . Permits and Fees The Contractor and Subcontractors must obtain Building Permits required for all work covered under this contract as well as any other permit required by any other regulatory agency. The Master Building Permit required by the City shall be obtained by the Contractor but paid for by the City. Any and all other permits required by the City, County, State of Florida, or other regulatory agency shall be obtained and paid for by the Contractor. The Contractor or Subcontractors shall also be responsible to call for all inspections as required in Section 110 (Inspections) of the latest edition of the Florida Building Code. Refer to the Technical Specifications (Section 01025 Basis of Payment) Contract Security When the awarded bidder delivers the executed contract to the City, it must be accompanied by the required bonds. Contract Period The initial contract term shall commence upon date of award by the City for a duration o

Published attachments
Addenda and notices
Public questions and answers
  • What is the budget/engineers estimate?

    $8,426,630.00

  • Is there an engineer's estimate for the project?

    $8,426,630.00

  • Please provide the Engineer's estimate for this project.

    $8,426,630.00

  • What will be the liquidated damages amount?

    Liquidated damages are included on page 00800-4 of “Attachment C – Supplementary General Conditions.”

  • Are there any existing Asbestos pipes within the work area of this project

    The City water atlas shows AC pipe for the existing water mains along Fillmore Street and the dead-end run to the existing fire hydrant on N 70th Way; said water main on Fillmore Street was relocated around the south side of Lift Station A-10 using 6-inch diameter ductile iron pipe per City as-builts. AC pipes may be present in other areas of the project. Per Sections 01025 and 01530, exploratory excavations are included in the scope of work and shall be performed by the Contractor as soon as practicable after award of the Contract and in sufficient time, at least 200 feet in advance of the construction work area, to avoid delays. Said atlases (3 images total) and as-built drawing are included in Addendum No. 1.

  • What is the EXPECTED / PLANNED date of award for this project?

    We expect to award the project between spring and summer 2027.

  • What is the EXPECTED / PLANNED date for construction to commence?

    Expected to start between the Spring and Summer of 2027.

  • Is there any known construction with other contractors within this project that may impact the work on this contract? If so: a. Where is the work involved? b. What type of work is it? c. What are the dates anticipated?

    No other foreseeable construction with other contractor.

  • Is there any tree removal required in this project?

    Tree (and palm) removal and/or replacement may be required at certain properties where existing trees conflict with the proposed lateral/service location. The Contractor should make every effort to select routes for each lateral and service that avoids impacts to existing trees and palms. Bid Item 51 of Form 3 and Section 01025 is the allowance task for performing such work. See also the Landscape Notes on Sheet G-002 of the Drawings for additional requirements and allowance/work approval process.

  • Is there any Owner or Utility companies work planned in the project boundaries.

    Refer to Answer 8. Additionally, the Contractor should coordinate with property owners and utility companies, as applicable, throughout construction.

  • What is the procedure for obtaining water for testing and construction use? – If required to pay for water what are the fees?

    Contractor will need to submit a temporary water meter application to the City per the website. The temporary water meter deposit is $2,500. Water consumption fees are per the City’s rates.

  • Will you be providing payment for stored materials?

    Partial payment for properly stored materials will be provided with proper backup.

  • Are there any materials to be furnished by the City?

    Contractor shall relocate existing water meters at each property. No other materials will be furnished by the City. The Contractor shall be responsible for furnishing all materials and equipment necessary to complete the work, including testing.

  • Any vibration Monitoring requirements in specs?

    Yes. Vibration monitoring is required in accordance with Sections 01100, 02160, and 02200. Monitoring is incidental to minimizing damage to adjacent public or private property.

  • Are there any fees/bonds DUE from BWD Traffic Engineering?

    The Contractor shall be responsible for any applicable fees and/or bonds required by Broward County Traffic Engineering Division. Refer to BCTED Ref. No. 230913060 for applicable requirements.

  • Are there any schools within the within or impacting this project?

    No. There is a school located near the project area at the northwest corner of Johnson Street and N 72nd Avenue. The Contractor should anticipate typical school-related traffic, including school buses and pedestrian and vehicular traffic associated with students, parents, and school personnel traveling to and from school. The Contractor should also be aware of posted 15-mph school zone speed limit during the designated hours before and after school.

  • Provide Webex/teams/zoom link for viewing of bid opening?

    Preliminary bid results will be available automatically in OpenGov on the bid due date.

  • TESTING LAB. Please confirm that testing such as densities, conc cylinders, proctors, etc. will be provided by the City.

    All testing shall be provided by the Contractor. The City reserves the right to perform their own testing at their discretion for verification, which shall in no way relieve the Contractor from performing the required testing under the Contract Documents.

  • No pay item for flat concrete work, please provide

    Refer to Pay Item 49 for concrete sidewalks and driveways. “Should the Contractor feel that the cost of any item of work has not been established by the Proposal or Basis of Payment, he shall include the cost for that work in the last Bid Item for each construction package so that his proposal for the project does reflect his total price for completing the work in its entirety.” – Section 01025-1.01E.

  • No allowance provided for off duty police

    Off-duty police is captured under Pay Item 52 – Maintenance of Traffic. Refer to Section 01025.

  • Line items #51, 54 & 55 which are allowance items don't have a dollar amount, please provide dollar amount of each allowance

    Addendum No. 1 revised IFB Section 6 – PRICING (BID FORM) to include dollar amounts for all allowances.

  • We would like to request that the City provide dollar values each contractor is to carry for the allowance items so that every bidder treats these pay items equally.

    Refer to Answer 21.

  • Please confirm that all private property sanitary sewer service work after the clean out including the abandonment of any septic systems will be handled by the property owner or under a separate contract.

    Correct. The sewer lateral on private property is not included in this project.

  • The pay item for the installation of the water services on private property reads as a per each, we would like to ask that the city provide the location of the existing connection to each house on the plans or provide a footage of pipe to be used so each bidder is able to price this work accordingly as we currently dont know where the connection point on the house is.

    Pay Item 29 includes locating existing utilities, coordinating access, scheduling, and installation activities with the property owner; performing all excavation, trenching, shoring, installation, backfilling, and compaction necessary to complete the service line. Bidders shall include locating the water line into each structure in this pay item. Refer to the WR sheets for water meter locations.

  • ATTACHMENT D TECH SPECS PG PDF189 mentions Uniformed Officers, please provide an allowance account for Off-duty Police. If not, please provide the rate of pay, fees and any other charges associated with police. Also, the locations where they will be required at, how many officers per location, the minimum hours that have to be paid, and the number of hours required at each location so that the appropriate cost can be included in the bid.

    Pay Item 52 includes police. The quantity, locations, and hours needed for police officers will depend on the bidder’s MOT plan. No separate allowance is provided.

  • Does this project require sod replacement? There is no pay item provided. Please provide quantity and types.

    Sod replacement and restoration is included under Pay Item 51 – Landscaping and Tree Trimming. Refer to Specification 01025 - Basis of Payment and Detail C-33 on Sheet P-505.

  • TECH SPECS PDF PG 172 MENTIONS A FIELD OFICE, IS a field office mandatory?

    No, a field office is not mandatory.

  • ATTACHMENT D TECH SPECS: S. and T. PDF 189. States: “Polyethylene encasement of cast/ductile iron pipe and fittings, riser pipe and valves, if required by the City,” Please advise if this is required, we are assuming it is not a requirement.

    Polyethylene encasement is required per Section 15997.

  • ATTACHMENT D TECH SPECS: PDF PG 38. States: “Night work and/or weekend work may be required for various areas within the project limits. The Contractor is responsible for costs associated with all night work including but not limited to, inspector costs, police or flagmen costs, signage and MOT costs and all other costs associated with night or weekend work.” Is this required on this project? If so, in order to provide accurate pricing, please a. listing the locations of the night work b. foreseeable number of night(s) anticipated c. any expressed requisites the City is considering

    Night work is not anticipated for this project. Weekend work may occur with City approval. Refer to the updated Page 01030-3 dated 111326, attached.

  • Unmarked utilities, marked after NTP/Construction. Since the quantity of utilities not shown on plans and marked after the bid cannot be calculated. How will the Owner recompensate the Contractor for the additional exploration of such utilities? We suggest creating a unit pay item for such an occurrence.

    Per Sections 01025 and 01530, exploratory excavations are included in the scope of work and shall be performed by the Contractor as soon as practicable after award of the Contract and in sufficient time, at least 200 feet in advance of the construction work area, to avoid delays.

  • Please advise where 3,000 lf of 8" dip is being installed in the project?

    Per Specification 01025 – Basis of Payment, “Only where PVC pipe cannot be used due to installation constraints, regulatory requirements, utility conflicts, or site conditions, the Contractor shall submit an RFI to the Engineer and obtain approval before furnishing and installing the ductile iron pipe (DIP) of the same nominal diameter.”

  • Section 4.3 states that the Bidder must be a Certified Underground Utility and Excavation Contractor. Section 5.10 says that the Bidder must hold a Florida General Contractor License. Please verify if either license is acceptable.

    The Bidder shall hold a valid Florida Certified General Contractor license (Section 5.10). The Florida Certified Underground Utility and Excavation Contractor (Section 4.3) may be held by the Bidder or by a subcontractor performing the applicable underground utility work.

  • Based on the measurement and payment descriptive, are we to assume all of the water main in the project limits to be ac?

    No. Refer to Answer 5.

  • On Fillmore St, the proposed sanitary main crosses under an existing sanitary main. What is the composition of the existing sanitary main? Are there any other sanitary mains within the project limits and if so, their composition?

    Per the City’s GIS, said pipe is Vitrified Clay Pipe (VCP). Contractor to field verify. Yes, there are other sanitary mains within the project: an 8-inch diameter VCP crossing Fillmore Street at LS 10 and an 8-inch diameter VCP crossing Buchanan east of N 70th Way.

  • Will a $5 Million Umbrella Liability policy satisfy the General Liability requirement for $2 Million each occurrence if the bidder only has $1 Million?

    Yes. The bidder’s $1 million General Liability policy may be combined with its $5 million Umbrella Liability policy to satisfy the $2 million each-occurrence requirement, provided the umbrella policy extends coverage over the General Liability policy.

  • Please confirm where the payment is to be made for the connections from the right of way to the existing septic tanks (it appears this is to be included in the sanitary lateral installations per the measurement and payment section)? 59 of the septic tanks have been shown on the survey or proposed plans (some with a horizontal location and no invert, others include an invert), what happens if the homeowner does not want to connect? (could a separate pay item be used to avoid any confusion?)

    Refer to Answer 23.

  • Bid schedule item 61 has listed a 5 cy excavator and is not likely to be used due to its' size, item 63 lists a loader with no size classification, please advise. Will these alternate items be included in the tabulation for the base bid?

    Payment under these items applies to additional work not defined in this contract and shall only be used when authorized in advance by the City in writing. Bidders shall estimate equipment of the type and size relating to the scope of work. These items shall be included in the Bid Schedule at the unit prices provided but will not be included in the Base Bid tabulation.

  • There are multiple bid items that list "allowances" (11, 12, 32, 51, 54, 55). Should monetary values be provided by the City for these items?

    Addendum No. 1 revised IFB Section 6 – PRICING (BID FORM) to include dollar amounts for all allowances.

  • ATTACHMENT D TECH SPECS PDF pg 38, STATES: “Night work and/or weekend work may be required for various areas within the project limits. The Contractor is responsible for costs associated with all night work including but not limited to, inspector costs, police or flagmen costs, signage and MOT costs and all other costs associated with night or weekend work.” In order for contractors to include these costs in the bids, please provide the costs associated with “inspectors”, “police” as well as expected location where this may be required.

    Refer to Answers 25 and 29.

  • ATTACHMENT D TECH SPECS PDF pg 75 MENTIONS: “Engineer's review will be for compliance with the Contract Documents, and his comments will be transmitted to the Contractor with reasonable promptness.” Please provide the week days involved in the “reasonable promptness”

    - 7 calendar days for RFIs - 14 calendar days for submittals

  • ATTACHMENT D TECH SPECS PDF pg 109: “The CONTRACTOR shall make all repairs to adjacent facilities which may be damaged as a result of the CONTRACTOR's efforts in abandoning, salvaging or otherwise removing existing facilities, at no additional cost to the CITY.” In order to include such costs in the bid, please provide: i. The item(s) TYPES to be salvaged? ii. The item(s) SIZES to be salvaged? iii. The quantity of each TYPE and SIZE? iv. The location of such items? v. And the destination of deliveries? vi. Also, if the delivery is to be made after all items selected are ready for delivery, or are items to be delivered on the day of salvage?

    Any items to be salvaged will be discussed during construction and picked up by the City.

  • PDF pg 110 States: “Certain areas of existing structures, piping, conduits, and the like will be affected by work necessary to complete modifications under this Contract. The CONTRACTOR shall be responsible to rehabilitate those areas affected by its construction activities.” Could you please elaborate where such circumstances are situated and manner of conflict to be encountered, in order to appropriately comprise the necessitous efforts and pricing?

    Rehabilitation of the existing sanitary sewer structure at the intersection of Fillmore Street and N 70th Terrace shall be completed post connection of the west invert pipe.

  • PDF pg 116 STATES: “It is the CONTRACTOR'S responsibility to arrange through the City Underground Utilities Division for a 2-inch fire hydrant water meter. A deposit to be paid by the CONTRACTOR is required for meter rental and all water shall be purchased at the prevailing rate.” Please provide the prevailing rate applied in the future of award and NTP price.

    Refer to Answer 11.

  • PDF pg 121, STATES: “Contractor shall pay for the charges for all overtime work”. In order to include such costs please provide the Inspector normal hours and overtime hours, as well as any and all fees applicable?

    Tetra Tech will supplement the City’s inspections at no cost to the Contractor.

  • PDF pg 141, Please clarify the City’s position and procedure on “gravity main low-air pressure test”.

    Testing of the gravity system will need to be by exfiltration and infiltration. The gravity main low-air pressure test is not anticipated. Refer to the updated Page 01700-2 dated 111326, attached.

  • Item 50 (Mobilization) states 10% if the total of Items 1 thru 48, shouldn’t that be items 1 thru 49? Also, if the necessary cost for mobilization requires more than the 10%, in which item(s) should such necessary costs be placed?

    Concur. Refer to the updated page 01025-18, included in Addendum No. 1.

  • PDF pg 189 STATES: “Polyethylene encasement of cast/ductile iron pipe and fittings, riser pipe and valves, if required by the City, “ and also “valves and ductile iron riser pipes”. Please confirm if this is a requirement.

    Refer to Answer 28.

  • will the city require a mailed original of the bid bond? if yes, when does the mailed original bid bond need to be submitted by?

    No. Only an electronic copy of the bid bond is required with the bid. Once the City Commission approves the resolution, administrative staff will contact the awarded contractor to request the required bonds. The contractor will have 10 days from the date of the request to submit the bonds to the City. Refer to IFB Section 3.32 and Section 5, Item 18, for bond requirements.

Plain text

OpenGov categories

  • 65860 · Pipe, PVC (Polyvinyl Chloride)
  • 89000 · Water Supply, Groundwater, Sewage Treatment, And Related Equipment (Not For Air Conditioning, Steam Boiler, Or Laboratory Reagent Water)
  • 91200 · Construction Services, General (Incl. Maintenance And Repair Services)
  • 91400 · Construction Services, Trade (New Construction)
  • 96800 · Public Works And Related Services
  • 98800 · Roadside, Grounds, Recreational And Park Area Services