Description
The Kenton County Airport Board (“KCAB”) will receive proposals for Server Equipment Relocation . Questions are due at 11:59 pm on Monday, November 30, 2026 and answers will be posted no later than Thursday, December 3, 2026 at 11:59 pm . Proposals must be received by Thursday, December 10, 2026 at 2:00 pm . No proposals will be accepted after that time unless such date or time is extended pursuant to an addendum issued by KCAB. Server Equipment Relocation SCOPE OF SERVICES Scope of Services The Kenton County Airport Board (KCAB) is seeking bids from qualified vendors for the relocation of server equipment from three locations at CVG to a new server room. The successful bidder ("Contractor") must provide the comprehensive plan for the relocation of server equipment listed in the Attachment 1 Equipment List which include but not limited to: A. Assessment and Planning: Conduct a thorough assessment of the current server environment, including inventory of all equipment, configurations, and dependencies. Develop a detailed relocation plan that outlines the timeline, resources required, and risk management strategies. Coordinate with CVG IT staff to ensure alignment with operational needs and schedules. B. Equipment Preparation: Ensure all server equipment is properly labeled and documented prior to relocation. Implement necessary backup procedures to safeguard data integrity during the move. Prepare equipment for transport, including disconnection, packing, and securing of all components. C. Transportation: Provide secure transportation for all server equipment to the new location within the data center. Ensure compliance with all applicable safety and transportation regulations. D. Installation and Configuration: Reinstall all server equipment in the designated location, ensuring proper placement and connectivity. Perform necessary configurations to restore functionality, including network settings, power connections, and peripheral devices. Conduct thorough testing to verify that all systems are operational and meet performance standards. NOTICE TO BIDDERS NOTICE TO BIDDERS Pursuant to KRS 424.260 and KRS 183.142, the Kenton County Airport Board (“KCAB”) will receive bids for Server Equipment Relocation at the Cincinnati/Northern Kentucky Int’l Airport (“CVG”). Bids will be received no later than Thursday, December 10, 2026 , at 2:00 pm . No bids will be accepted after that time unless such date or time is extended pursuant to an addendum issued by KCAB. KCAB reserves the right to waive any informality or irregularity in any proposal or bid guaranty, to reject any or all bids, to award or refrain from awarding a contract for the work, and to negotiate with the apparent qualified responsible proposer to such extent as may be beneficial to KCAB. Preference for Kentucky resident bidders will be applied in accordance with Kentucky law. Further information and copies of the Invitation to Bid (ITB) may be downloaded from our website www.cvgairport.com/bids - KCAB's e-Procurement Portal. KENTON COUNTY AIRPORT BOARD Lawrence J. Krauter, Chief Executive Officer CINCINNATI /NORTHERN KENTUCKY INTERNATIONAL AIRPORT Hebron , KY 41048 GENERAL INFORMATION & BID INSTRUCTIONS SCHEDULE OF EVENTS Release Project Date: November 19, 2026 Deadline For Questions To Be Submitted: November 30, 2026, 11:59pm Answers To Questions Issued: December 3, 2026, 11:59pm Proposals Due: December 10, 2026, 2:00pm KCAB reserves the right to modify or alter the schedule of events to such extent as may be beneficial to KCAB. AUTHORITY TO RELEASE KCAB is the sole entity with the authority to issue and/or distribute any solicitation documents and/or related information. All solicitation documents obtained from any source other than KCAB may be incomplete or incorrect. KCAB assumes no responsibility for any error, omission or misinterpretation resulting from the reliance or use of any Solicitation Documents not issued and distributed by KCAB. All solicitation documents are posted on KCAB’s e-procurement portal at: https://procurement.opengov.com/portal/cvgairport BACKGROUND KCAB relies on its server infrastructure to support critical information technology and operational technology (IT/OT) applications, integrations, and services used across the CVG campus. This infrastructure enables essential airport business and operational functions and must remain secure, available, and properly connected throughout the relocation. The equipment is currently distributed among existing CVG facilities, including active server rooms within the Airport Police Department and on the Concourse A ramp level, and will be consolidated into the new server room at the CVG Centre. Because the work involves production equipment and interconnected systems, the relocation must be carefully planned and coordinated to minimize service interruptions, protect data and hardware, maintain system dependencies, and restore full functionality within KCAB-approved operational windows. KCAB is therefore seeking an experienced contractor capable of developing and executing a comprehensive relocation plan that addresses equipment inventory, sequencing, labeling, backup and recovery, secure transport, reinstallation, configuration, testing, documentation, and contingency measures. SUBMISSION OF BIDS Responses to this ITB must be submitted electronically through KCAB’s online bidding system which can be accessed at https://procurement.opengov.com/portal/cvgairport . Select the project titled Server Equipment Relocation (Invitation # 26-062-ITB ) and follow the instructions for submittal. The completed and signed bid (together with all required attachments) must be transmitted and received through OpenGov no later than Thursday, December 10, 2026 at 2:00 pm Eastern Time (ET). Bidders should allow for sufficient time to upload and transmit all required information. Proposer is solely responsible to ensure its submission is transmitted prior to the due date and time. KCAB will not accept submissions after the due date and time and is not responsible for any error in transmission including but not limited to power outage, internet connectivity, unauthorized access, etc. BID QUESTIONS KCAB is not bound by, and bidders may not request or rely on any oral interpretation or clarification of this RFP. Therefore any questions regarding this ITB are encouraged and must be submitted electronically using the Question and Answer tab of this ITB on KCAB’s online bidding system, which can be accessed at https://procurement.opengov.com/portal/cvgairport . Questions received on or before the Deadline to Submit Questions in the Schedule of Events will be posted on the Question and Answer tab of this ITB on the bidding system per the Schedule of Events. Answers to questions from any bidder will be available to all proposers. All communications regarding this solicitation must only be through the Questions and Answers section of the ITB or through the Contract and Procurement Administration Department. No communication is to be directed to any other KCAB personnel unless otherwise instructed by the Contract and Procurement Administration Department. Failure to comply may result in the disqualification of proposer’s submittal. ADDENDA In the event it becomes necessary to revise, change, modify or cancel this ITB or to provide additional information, addenda will be issued to all recipients of this ITB. KENTUCKY OPEN RECORDS ACT Each bidder must specifically identify any portion of its bid which it deems confidential, or which contains proprietary information, patents, copyrights or trade secrets. Bidder should provide justification of what material should not be disclosed, upon request, by KCAB to a third party. All documents received by KCAB are subject to general inspection under the provisions of Kentucky Revised Statutes Chapter 61.870 et seq, the “Kentucky Open Records Act”, subject to very narrow exceptions. These statutes may require disclosure of documents a bidder deems confidential. KCAB may otherwise use or disclose the data submitted by each bidder for any purpose, unless such data is so identified as confidential or proprietary by the bidder. The bidder's opinion of proprietary information is not binding upon KCAB. ACCEPTANCE PERIOD Bids in response to this ITB must indicate it is valid for a period no less than one hundred twenty (120) days from the closing date. AWARD KCAB intends to award a contract or contracts resulting from this solicitation to the responsible bidder(s) whose bid represents the best value after evaluation. KCAB reserves the right to waive any informality or irregularity in any bid guaranty, to reject any or all bids, to award or refrain from awarding a contract for the work, and to negotiate with the apparent qualified responsible bidder to such extent as may be beneficial to KCAB. KCAB intends to evaluate bids and may award a contract without discussions with bidders. Therefore, the bidder's initial bid should contain the bidder's best terms from a cost or price and technical standpoint. KCAB reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered. KCAB reserves the right to make multiple awards if, after considering the bids submitted, it is in KCAB’s best interest to do so. The successful bidder will be required to enter into a contract substantially in the form of the contract included under the ATTACHMENTS Tab and incorporated by reference. All proposers are required to note any exception(s) to the Invitation to Bid or the attached contract and are required to specifically state the exception(s) and the reason(s) for the exception(s). No exceptions will be recognized to the Government Clauses section of the proposed contract. If no exceptions to the contract are included in the bidder's response, the bidder is expected to execute the contract in the form set forth herein. Final acceptance of a bid and contract is contingent upon reaching a mutually satisfactory agreement regarding noted exceptions. If an acceptable and timely agreement is not reached, KCAB reserves the right to disqualify the bidder and to reevaluate the remaining bids. KCAB reserves the right to refuse to negotiate with a successful bidder on any item not specifically excepted in its submittal. KCAB will have the right, at its sole election, to alter the specifications and/or frequencies of services required and tailor the contract price to said change (increase or decrease). The term of the agreement will be will continue until completion and acceptance of the services. PERFORMANCE AND PAYMENT The successful bidder shall issue an invoice on a monthly basis for work performed along with supporting data. KCAB will pay submitted invoices on a net 30 basis subject to the terms of the attached agreement. BADGES AND KEYS Contractor shall badge a sufficient number of employees to satisfactorily complete its obligations under this contract regardless of circumstances. This will require a background check made through a fingerprint process. When determining the number of employees to badge, Contractor must consider absent employees due to illness, vacation, employment termination, or other reasons, emergency/on call situations, and supervisors who need access for inspection/supervision visits. Contractor is responsible for the cost of badging. The current fee for identification badges is $44.00 per badge for the badge, security threat assessment, and for fingerprinting. Contractor shall return all badges upon expiration or termination of the contract whichever is earlier. Additionally, Contractor shall immediately return an employee’s badge when that employee is no longer employed by Contractor. Contractor shall pay $100.00 per badge for each badge not returned within ninety (90) days from the date the Contractor is required to return the badge(s). Contractor is responsible for all keys or badges issued to Contractor’s employees. Such keys or badges may not be duplicated. Contractor shall return any or all keys or access cards to KCAB when requested by KCAB. If the loss of keys or access cards requires changing the combination of locks or changing other access equipment, the cost of such labor and material may be charged to Contractor at the discretion of KCAB. Replacement of lost or damaged keys or badges will be provided at Contractor’s expense. Any fines or civil penalties assessed to KCAB caused by Contractor negligence is the responsibility of Contractor. Badge replacement is at the sole discretion of KCAB. A $100.00 fee will be assessed per lost badge. In the event a Contractor’s employee loses a second badge, the Contractor shall pay $200.00. If a third badge is lost, the badge will only be renewed with permission of the Airport Security Coordinator and the Contractor shall pay $300.00. If necessary, KCAB will provide initial supply of keys after receipt of a $500.00 deposit from Contractor. In the event Contractor loses or duplicates a key(s), KCAB will charge the cost of rekeying the lock(s) of the corresponding area against the $500.00 deposit. Contractor shall be responsible for the full cost of rekeying if Contractor loses or duplicates a key. Any funds remaining of this $500.00 deposit upon termination of the contract will be returned to contractor upon KCAB’s receipt of all keys. All personnel assigned to perform services at the CVG Police Department are required to obtain security clearance for access to the CVG Police Department by completing the Criminal Justice Information System (CJIS) in the State of Kentucky and Federal Bureau of Investigation Criminal Justice Information Services Security Addendum. Please review and sign the Addendum in the Exhibit C attached. RECORDS/FINANCIALS In submitting bids on any item to be purchased by KCAB, the bidder hereby agrees to make available any and all records, books of account, correspondence, or other information reasonably necessary to enable KCAB or its designated agents to investigate the responsibility of the bidder in terms of its financial status, capacity to produce, sources of supply, performance record in the business or industry, and any other matter reasonably related to the proposer’s probable ability to perform adequately under a contract if it is awarded to the bidder. GRATUITIES AND KICKBACKS It is a breach of ethical standards for any person to offer, give, or agree to give any employee or former employee, or for any employee or former employee to solicit, demand, accept, or agree to accept from another person, a gratuity or an offer of employment in connection with any decision, approval, disapproval, recommendation, preparation of any part of a program requirement or a purchase request, influencing the content of any specification or procurement standard, rendering of advice, investigation, auditing, or in any other advisory capacity in any proceeding of application, request for ruling, determination, claim or controversy, or other particular matter, pertaining to any program requirement or a contract or subcontract, or to any solicitation or proposal therefore. It is a breach of ethical standards for any payment, gratuity, or offer of employment to be made by or on behalf of a subcontractor under a contract to the prime vendor or higher tier subcontractor or any person associated therewith, as an inducement for the award of a subcontract or order. In the event that any gratuities or kickbacks are offered or tendered to any KCAB employee, the proposal shall be disqualified and shall not be reinstated. NON-COLLUSIVE VENDOR CERTIFICATION By the submission of this proposal, the proposer certifies that: The proposal has been arrived at by the proposer independently and has been submitted without collusion with any other vendor. The contents of the proposal have not been communicated by the proposer, or, to its best knowledge and belief, by any of its employees or agents, to any person not an employee or agent of the proposer or its surety on any bond furnished herewith and will not be communicated to any such person prior to the official opening of the proposal. No proposer may submit more than one proposal for this purchase. It shall be the responsibility of each proposer to obtain the prior written permission of KCAB before proposal opening in every situation in which the proposer, due to corporate association or other affiliation, may be found to be impermissibly associated with another vendor. Failure to observe this requirement could result in all such affiliated proposals being rejected. BID CONDITIONS AND PROVISIONS The terms and conditions of this Invitation to Bid (ITB) include all general and special conditions as enumerated herein. All participating proposers agree to comply with all of the conditions, requirements and instructions of this ITB as stated or implied herein. Any alteration, erasure or interlineation by the proposer in this proposal constitutes cause for rejection by KCAB. Should KCAB omit anything from this ITB which is necessary to a clear understanding of the work, or should it appear that various instructions are in conflict, then the proposer shall notify the Contract and Procurement Administration Department prior to the deadline for question submissions as per the time and date shown in the Schedule of Events. Typographical errors in entering quotations on this proposal may result in the disqualification of this proposal. All proposers are required to complete all information requested in this proposal. Failure to do so may result in the disqualification of proposal. Unit price for each item must be shown for the unit of measurement indicated. In case of error in extension of prices, the unit price governs. Each proposer shall fully acquaint and familiarize themselves with the conditions as they exist and the character of the operations to be carried on under the proposed contract and make such investigations as the proposer may see fit so that the proposer shall fully understand the facilities, physical conditions and restrictions associated with the services. The successful proposer shall comply with all of the specifications, terms and conditions of this ITB. KCAB is not liable for any costs incurred by proposer in the preparation of proposals or for any work performed in connection therein. PRICING PROPOSAL PRICING PROPOSAL Pricing must be all-inclusive, firm fixed for will continue until completion and acceptance of the services. , and delivered to the address specified inclusive of all transportation charges FOB Cincinnati/Northern Kentucky International Airport. Bids must be submitted electronically using the Line Items tab on KCAB’s electronic bidding system. Submittals must be confirmed by a duly authorized official of the bidding company. VENDOR QUESTIONNAIRE VENDOR QUESTIONNAIRE Each bid must include the following written information: ATTACHMENTS
Published attachments
Addenda and notices
Addendum #1 · 1
Please use the See What Changed link to view all the changes made by this addendum.
Addendum #2 · 2
Please use the See What Changed link to view all the changes made by this addendum. KCAB staff will be providing the escort; the contractors personnel do not have to go through the CJIS process. Section 4.2. ATTACHMENTS: Changed: "Attachments included C - CJIS Security Addendum - Exhibit C " To: "Attachments no longer include C - CJIS Security Addendum - Exhibit C "
Public questions and answers
For this project, does the testing include Certification or Qualification of the network cable links? If so, I would like to submit an entry as a vendor/subcontractor with test equipment that is less than half price of the popular brand and faster, saving immense cost in CAPEX and through test time reduction.
All network/cable links in the new room will be patched into a local switch. Certification is not necessary.
The ITB background states that one source room is “on the Concourse A ramp level.” Draft Contract Section 7.C.2–3 requires commercial general liability and automobile liability of not less than $10,000,000 each occurrence or accident if the contractor performs work or services “on the aircraft ramps, taxiways, or runways,” or operates motor vehicles or mobile equipment unescorted on those areas. Otherwise the limits are $2,000,000. Does physical work inside the Concourse A ramp-level server room, including moving equipment by an approved path from that room to the CVG Centre, constitute work “on the aircraft ramps, taxiways, or runways” for purposes of the $10,000,000 requirement? If movement must cross a ramp, taxiway, or runway, will KCAB provide an escort, and may the contractor remain on the $2,000,000 limits if all such movement is escorted and the contractor does not operate vehicles unescorted on those areas?
Yes, moving equipment from Concourse A to the CVG Centre constitutes work on the ramp. Proposer may wish to consider noting an exception per section 2.10(F) of the ITB, however KCAB will not agree to any exception during this solicitation stage and proposer’s pricing should be reflective of the specifications as stated in the sample contract.
Draft Contract Section 7.C.4 requires a Kentucky workers’ compensation policy, and Section 7.H requires evidence of Kentucky workers’ compensation prior to contract execution. The bidder is an Ohio employer holding an active Ohio Bureau of Workers’ Compensation policy. If that Ohio policy is endorsed with other-states or all-states coverage that includes Kentucky, will KCAB accept it as satisfying Section 7.C.4 and 7.H? If not, please confirm that a separate Kentucky workers’ compensation policy will be required before contract execution.
Provided Kentucky is a covered state under any such endorsed policy that is sufficient. Ohio Bureau of Workers’ Compensation coverage alone is not sufficient as there is no reciprocity between Ohio and Kentucky. Note also the employer's liability coverage under section 7.C.4.
No pre-bid conference or site walk is listed in the Schedule of Events. May an escorted walkthrough of the three source rooms (Concourse A, NARFF, and the Police Department) and the CVG Centre destination room be arranged for prospective bidders before the December 10, 2026 bid due date? If yes, what is the request process, lead time, and any badging or escort requirement for a pre-bid visit?
Due to the clearance requirements for access to these rooms an estimated walkthrough is not being scheduled. The selected bidder will receive as many escorted walkthroughs as required.
All relocation work will be performed in KCAB-approved off-hours windows. Please confirm: - Typical start and end times for an approved window, and whether an eight-hour night is a reasonable planning assumption. - How many windows KCAB can make available, and whether they may be scheduled on consecutive nights or must be spaced. - Any blackout dates (holidays, peak travel periods, or operational events) between award and mid-winter 2026–2027. - Whether assessment, inventory, and labeling may be performed during normal business hours under escort.
1. The typical maintenance window is 00:00-06:00. An eight-hour night is reasonable for planning. 2. As many as are required to complete the work. They can be scheduled on consecutive nights, depending on KCAB staff availability. 3. The weeks of December 21st and 28th are not ideal, but not out of the question. 4. Yes.
Attachment 1 includes network and security appliances (including ARUBA-MD02, CVG_CONTROLLER_2, Forcepoint NGFW units, Nokia SAS units, PD-MX-01, and DIGI) that may terminate carrier, fiber, or other circuits. Who is responsible for disconnecting and reconnecting telco, carrier, or other third-party circuits — KCAB, the carrier, or the relocation contractor? If the contractor is responsible, will KCAB provide circuit identifiers, demarcation points, and carrier contacts, and will those cutovers be scheduled inside the same approved windows?
We'll coordinate those moves with the carrier. However, ARUBA-MD02 and PD-MX-01 can be moved in this project. The firewalls are dependent on the circuit at the source location and will be coordinated with the carrier as well.
Will KCAB provide, before the first move window and at no cost to the contractor, the destination rack positions, reserved rack-unit elevations, PDU or power-whip assignments (including receptacle type and rating), and network patch-panel or switch port assignments for all Attachment 1 devices at the CVG Centre? Will the cabinets, PDUs, and structured cabling already be installed and energized, or is any of that work part of this contract? If elevations will not be issued before bidding, when will they be issued after award?
1. Destination racks are in Attachment 1 page 3. PDU assignments have not yet been made but can be prior to the move window. 2. Yes, and we'll have copper and fiber patch and power cables available. 3. Attachment 1 page 3.
Several systems appear to require application-owner or vendor procedures before power can be removed, including Honeywell hardware and storage, Oracle (ORACLEPROD2 and ORACLETEST), the MVR video recorders (MVR1-F through MVR11-F), virtualization hosts (VMH2 and VMH4), backup and storage appliances (BACKUP, Tape Library, HPE StoreOnce, PD-SAN01), and network security appliances. Will KCAB staff or KCAB’s existing vendors perform operating-system and application shutdown and startup for those systems, with the relocation contractor responsible for physical disconnect, transport, racking, and power and network reconnection? Or must the contractor perform shutdown and startup? If the latter, will KCAB provide procedures, credentials or supervised access, and vendor support on the call for Honeywell, Oracle, and the MVR environment?
KCAB will perform shutdown and startup for all systems being relocated.
Please confirm that Attachment 1 is the complete list of devices to be moved. In particular: - Should rails, cable-management hardware, transceivers, SFPs, tape media, and other modules that are installed in or dedicated to a listed device be moved with that device? - Are cabinet PDUs, patch panels, KVMs, or other shared cabinet infrastructure included, or are they staying in place? - The Perfect Turn Server is listed with cabinet “N/A.” Where is that device located, and how should it be handled? - How should the contractor treat any device found in a source cabinet that is not on Attachment 1?
1. Yes. 2. Nothing but the server equipment is being moved. 3. It's sitting on a table in Concourse A due to insufficient power. We will have everything needed to rack it at CVG Centre. 4. It should be left in place if not moving. If it needs to move, we'll add it to the scope via contract amendment.
What is the approved physical path from each source room (Concourse A ramp-level room, NARFF, and the Police Department) to the CVG Centre? Please identify whether movement is landside or airside, whether a vehicle is permitted or equipment must be hand-carted, whether elevators or docks will be available during off-hours, and whether KCAB will provide escorts for each window. Are there weight, size, or weather constraints we should plan for on the heavier chassis (for example Honeywell storage, PD-SAN01, HPE StoreOnce, Alletra, and the Tape Library)?
1. Every source room is landside except Concourse A. 2. Vehicles are permitted and required to be under escort for Concourse A. 3. Elevators are available and a lift gate will be helpful. 4. Escorts will be provided. 5. Fair weather preferred.
Are there systems that must not be taken down in the same window, or that must remain in service until a counterpart is restored? We are particularly interested in the Forcepoint NGFW pair, the Nokia SAS pair, the wireless controllers (ARUBA-MD02 and CVG_CONTROLLER_2), Oracle production versus test, the VMware hosts, and backup appliances versus the systems that still write to them. Please also identify any maximum allowable downtime by system or room.
The firewalls, CVG_CONTROLLER_2 and Nokia will be coordinated with the carrier. ARUBA-MD02 is redundant and can be moved with KCAB IT action. Oracle only needs to be scheduled ahead of time. VMware hosts might require two trips depending on available capacity during the window. CAD is the biggest question currently. We're still waiting for approval and will need to coordinate with Police. Backup appliances can be moved with IT coordination.
What is the current lead time to obtain an airport identification badge, including fingerprinting and the security threat assessment, and how should the successful contractor schedule those appointments? For Police Department room access, is the Exhibit C certification uploaded with the bid sufficient for the company representative, and when must each on-site employee complete Kentucky CJIS clearance and sign the addendum — with the bid, after award, or before the first Police Department window? Will KCAB or the Police Department schedule the CJIS process, and is an escort required in that room even after clearance?
1. Once the company has been approved by the Sr. Manager Airport Security for badging, the authorized signatory will complete the process first, then other employees can be badged. The process will take from start of company to receiving a badge to about 10 days. 2. CVG escort will be provided.
The scope requires backup procedures to safeguard data integrity. Will CVG IT (or the named system owner) be responsible for taking and certifying restorable backups before each window, with the contractor witnessing that confirmation and not taking a device down until it is given? What are KCAB’s acceptance criteria at the end of each window (for example, power and link status, owner confirmation of application health, or a formal sign-off sheet), and who is authorized to accept the work?
1. KCAB IT is responsible for backups. 2. KCAB confirmation of application health. 3. KCAB IT staff are authorized to access the work. Named individuals will be identified at project kickoff.
For approved off-hours windows, will KCAB provide parking, restroom access, a staging area at or near the CVG Centre, carts or pallet jacks, and a point of contact with after-hours authority? May the contractor bring its own lifts, carts, and packing materials airside if needed, and are there screening rules for those tools?
1. Yes, but the contractor should provide their carts and pallet jacks. 2. Yes.
ITB Section 2.12.6 refers to a $500 key deposit if keys are issued. Is a key deposit expected for this engagement, or will access be by badge and escort only? Will KCAB provide existing cabinet elevations, cable matrices, or network diagrams under the Protected Information rules to the awarded contractor, or should the contractor build documentation solely from the on-site assessment?
1. A key deposit is not expected. Badge and escort only. 2. KCAB will provide the documentation that's available. We would expect contractor documentation to result from that and the on-site assessment.
What are the anticipated project start and required completion dates? Is 00:00–06:00 the actual outage window, with the eight-hour planning allowance covering preparation and closeout?
1. No dates, the destination room is not yet complete. Anticipate early 2027. 2. This is our window for system outages. KCAB expect most moves to be done during the day (07:00-16:00) with minimal after-hours required.
Since there won’t be a prebid walkthrough, can CVG provide equipment models, weights, mounting requirements and a breakdown of the components grouped under “Honeywell Hardware” in Attachment 1? Is Attachment 1 the complete inventory list?
1.KCAB can provide these details to the successful bidder. The largest items are likely the HPE Alletra storage units at approximately 174lbs. 2. Yes.
Will KCAB provide operational racks, power/PDUs, cooling, switches and uplinks? What materials should we include, such as rails, power cords, patch cables and optics if any?
1. Yes. 2. None.
Will KCAB handle network and storage configuration changes, or should we include that work? Are there any peripheral or field-device connections that need to move or be extended?
1. Yes, KCAB will handle. 2. No.
Do any services need to remain available while equipment moves? If so, who provides and configures any temporary equipment or redundancy?
1. Everything being moved is either redundant or can be failed over with sufficient planning. 2. KCAB will handle service availability.
Can KCAB provide approximate distances, loading locations, vehicle restrictions and any stairs, elevator limits or special handling requirements? Will temporary equipment storage be needed?
1. All work will be done at the CVG Airport. Equipment can be loaded next to each building in scope. Typical personnel elevators will be available but only likely required at North ARFF, with stairs being the alternative. 2. No temporary equipment storage will be needed.
Beyond airport badging, what CJIS screening, training and individual forms must our team and subcontractors complete? Who signs Exhibit C with the bid, and who coordinates personnel clearance after award?
1. CJIS trained personnel will be available to provide escort. Contractor will need to provide driver's license for background check at Police. 2. N/A , See Addendum #1
Beyond installation, power and connectivity checks, what contractor testing is required? Will KCAB document acceptance after each move window, and what post-move support should we include?
1. None. 2. KCAB will document acceptance after project completion. Informal verification of relocated system functionality will be provided immediately.
How will pre-existing or age-related hardware failures be distinguished from relocation damage? Who handles troubleshooting, replacement parts, vendor support and restoration if equipment fails to restart?
We will negotiate appropriate language with the selected contractor.
How will additional equipment, missing hardware, destination delays or CVG-requested rescheduling be handled under the fixed price? Will changes to scope, cost or schedule be approved in writing before that work proceeds?
1. For the additional equipment or the scope changes the Contract amendment will be executed. 2. Yes, changes will be approved in writing before the work proceeds.
OpenGov categories
- 334 · Computer and Electronic Product Manufacturing
- 334118 · Computer Terminal and Other Computer Peripheral Equipment Manufacturing
- 423430 · Computer and Computer Peripheral Equipment and Software Merchant Wholesalers