Description

The City of Pembroke Pines is seeking bids from qualified firms, hereinafter referred to as the Contractor, to renovate the existing soccer field and associated park facilities at Silver Lakes North Park, 2300 NW 172nd Avenue, Pembroke Pines, Florida. , in accordance with the terms, conditions, and specifications contained in this solicitation. Work includes regrading and re-sodding of the existing soccer field; irrigation modifications; construction of new concrete player seating pads and associated concrete improvements; demolition and replacement of the existing pavilion; modifications to existing field lighting; renovation of the existing restroom building; and all associated site restoration. The Contractor shall provide all labor, supervision, materials, equipment, tools, transportation, temporary facilities, protection, permits, testing, disposal and incidentals necessary to provide a complete and fully operational project in accordance with the Construction Documents and applicable codes. All work shown or reasonably required to provide complete installations shall be included whether or not every incidental item is specifically identified within this Scope of Work. SCOPE OF WORK General Project Scope The project consists of renovations to the existing soccer field and associated park facilities at Silver Lakes North Park, located at 2300 NW 172nd Avenue, Pembroke Pines, Florida. The work includes regrading and re-sodding of the existing soccer field; irrigation modifications; construction of new concrete player seating pads and associated concrete improvements; demolition and replacement of the existing pavilion; sports field lighting improvements; renovation of the existing restroom building, including associated architectural, plumbing, mechanical and electrical work; and restoration of areas affected by construction. The Contractor shall provide all labor, supervision, materials, equipment, tools, transportation, permits, testing, disposal and incidentals necessary to provide a complete and fully operational project in accordance with the Construction Documents and applicable codes. The Scope of Work is intended to summarize the major components of the project and shall not limit the requirements of the Construction Documents. Work shown or reasonably required for complete and functional installations shall be included whether or not every incidental item is specifically identified herein. Soccer Field Regrading and Re-Sodding The Contractor shall renovate the existing soccer field in accordance with the Civil and Landscape Construction Documents. Work shall include: Survey and verify existing field elevations, grades, drainage conditions, utilities, irrigation components, light poles, sidewalks and other improvements that may be affected by the work. Remove existing sod and prepare the field for grading operations. Perform all excavation, cut, fill, soil redistribution, compaction and fine grading necessary to achieve the proposed elevations, slopes and drainage patterns shown on the Construction Documents. Furnish and place suitable imported fill where necessary to achieve the required grades. Imported material shall be suitable for its intended application and free of debris, vegetation and deleterious materials. Provide a smooth and uniform finished playing surface free of depressions, abrupt grade changes, exposed debris and other irregularities. Establish and maintain positive drainage throughout the renovated field. Finished grading shall not create areas of ponding or adversely affect existing or proposed buildings, sidewalks, pavilion improvements, concrete pads or other adjacent facilities. Coordinate finished grades with existing and proposed concrete improvements, pavilion construction, light poles, irrigation components and surrounding site improvements. Furnish and install Bermuda grass sod throughout the areas indicated on the Landscape Construction Documents. The Landscape Plan identifies approximately 132,902 square feet of Bermuda grass sod. Prepare the finished soil surface and furnish, install, roll and water new sod as required to provide a smooth and uniform finished playing surface. Maintain newly installed sod as required for establishment and replace areas that fail to establish, settle, wash out or otherwise become unacceptable prior to final acceptance. Provide, maintain and remove all required erosion and sediment control measures throughout construction in accordance with the Civil Construction Documents. The Civil set includes a Pollution Prevention Control Plan for the work. Repair any settlement, erosion, rutting, ponding or other deficiencies resulting from the work prior to final acceptance. Restore all areas disturbed by grading, construction access, equipment, material storage or staging to a condition equal to or better than that existing prior to construction. Irrigation Modifications The Contractor shall perform all irrigation modifications required to accommodate the soccer field regrading, new sod, concrete improvements, pavilion work and other construction activities. The completed irrigation system shall provide proper coverage of all affected turf areas and shall be fully operational prior to acceptance by the City. Work shall include: Locate, identify and protect existing irrigation mains, laterals, valves, wiring, rotors, controllers, pump equipment and related components prior to grading or other construction activities. Verify the condition and operation of the existing irrigation system prior to commencement of work. Document and notify the City of any existing deficiencies prior to performing work that may affect the system. Coordinate irrigation modifications with proposed field grading, concrete work, pavilion construction and other site improvements. Adjust, relocate, reset or replace irrigation heads and related components affected by the new field elevations or construction. Set irrigation heads flush with final grade and adjust spray patterns to provide proper coverage and prevent overspray onto concrete walks, slabs, buildings and other non-landscape areas. Preserve existing irrigation valve zones identified on the Construction Documents. Irrigation valve zones 12 through 20 shall remain and be protected throughout construction. Preserve existing irrigation rotors unless otherwise indicated and modify the system as necessary to provide complete coverage. Protect the existing irrigation pump and associated equipment. The existing 15 HP, 120 GPM, 65 PSI irrigation pump shall remain, and the Contractor shall confirm that the irrigation system is operational. Test all affected irrigation zones following completion of the modifications and adjust the system as required to provide proper coverage. Repair or replace irrigation piping, wiring, valves, heads, rotors or other irrigation infrastructure damaged as a result of construction operations at no additional cost to the City. Maintain the irrigation system as required to support establishment of newly installed sod. Prior to final acceptance, demonstrate operation of the affected irrigation system to the City and correct any deficiencies identified. Concrete Improvements and Pavilion Replacement The Contractor shall provide all demolition, concrete improvements and pavilion replacement work shown on the Architectural and Site Construction Documents. Work shall include: Construct new 4-inch concrete player seating pads at the locations and dimensions indicated on the Construction Documents. Construct new concrete walkways and other concrete improvements indicated on the Construction Documents. Coordinate finished concrete elevations with the renovated soccer field, existing sidewalks, pavilion and surrounding grades and maintain required accessible transitions. Demolish, remove and legally dispose of the existing pavilion structure and associated components designated for removal. Protect the existing pavilion slab and other improvements indicated to remain. Repair any damage resulting from construction operations at no additional cost to the City. Furnish and install the new approximately 15-foot by 24-foot aluminum pavilion, including the structure, roofing, columns, foundations and associated components shown on the Construction Documents. The Construction Documents identify Perfection Architectural Systems, LLC, or approved equal, as the basis of design. Provide perforated gable-end panels for future signage as indicated on the Construction Documents. Provide signed and sealed engineered pavilion shop drawings prepared by a Florida-licensed professional engineer. Deferred submittals shall be reviewed and approved as required prior to fabrication and installation. Restore all sod, irrigation, concrete and other site improvements disturbed by the pavilion and concrete work. Sports Field Lighting Improvements The Contractor shall perform the sports field lighting improvements shown on the Electrical Construction Documents. Work shall include: Protect existing sports lighting poles and associated electrical infrastructure designated to remain. Verify existing electrical conditions serving the affected field lighting prior to commencement of work and notify the City of identified deficiencies. Existing light poles shall remain unless otherwise indicated on the Construction Documents. Replace existing field lighting fixtures as indicated on the Electrical Construction Documents, including associated electrical modifications and connections required for complete operation. The Architectural Site Plan identifies the existing light poles to remain and directs fixture replacement to the Electrical Construction Documents. Repair or replace electrical infrastructure damaged as a result of construction operations at no additional cost to the City. Test the completed field lighting improvements and demonstrate proper operation to the City prior to final acceptance. Restroom Building Renovation The Contractor shall provide a complete interior renovation of the existing restroom building in accordance with the Architectural, Plumbing, Mechanical and Electrical Construction Documents. Work shall include: Remove existing floor and wall finishes, toilet partitions, plumbing fixtures, drinking fountain, hand dryers, lighting fixtures and other components designated for removal. Protect all existing building components, utilities and equipment designated to remain, including the existing electrical panel and ice maker. Patch and repair walls, floors, ceilings and other surfaces affected by demolition and installation of the new work. Patch, repair and paint the existing gypsum-board ceiling as indicated. Furnish and install new floor and wall finishes, restroom partitions, doors, hardware, grab bars, mirrors, dispensers and restroom accessories as indicated on the Construction Documents. Furnish and install new plumbing fixtures and perform all associated domestic water, sanitary and vent piping modifications required for the new work. Perform all mechanical and ventilation modifications indicated on the Construction Documents. Furnish and install new lighting fixtures, hand dryers, receptacles, electrical devices and associated electrical modifications indicated on the Construction Documents. Maintain required accessibility clearances and mounting requirements throughout the renovated facilities. The Construction Documents provide accessible mounting requirements for the restroom fixtures and accessories. Test all plumbing, mechanical and electrical systems affected by the work and correct any deficiencies prior to acceptance. Repair any existing building components, utilities or equipment damaged as a result of construction operations at no additional cost to the City. Provide final cleaning of the renovated restroom facilities prior to acceptance. City General Requirements The following requirements shall apply to all Work included in the project: The Contractor shall visit the project site prior to bidding and verify existing conditions, dimensions, elevations, utilities, site access and other conditions affecting the work. The Contractor shall provide all labor, supervision, materials, equipment, tools, transportation, permits, testing, disposal and incidentals necessary for a complete turnkey project in accordance with the Construction Documents. The Contractor shall coordinate the work of all trades and sequence the work to avoid conflicts between civil, architectural, landscape, irrigation, plumbing, mechanical and electrical improvements. Any discrepancies, conflicts or unforeseen conditions encountered in the Construction Documents or field shall be brought to the attention of the City and Architect/Engineer prior to proceeding with the affected work. The Contractor shall obtain and maintain all required permits, sub-permits, inspections and approvals necessary to complete the work. All work shall comply with applicable federal, state and local codes, regulations, ordinances and accessibility requirements and all authorities having jurisdiction. The restroom plans identify the applicable 2023 Florida Building Code, Eighth Edition, and Florida Fire Prevention Code requirements. The Contractor shall locate and protect existing utilities, buildings, sidewalks, concrete, fencing, light poles, landscaping, trees, turf, irrigation systems, equipment and other improvements designated to remain. Any existing facility, utility, equipment or improvement damaged as a result of construction operations shall be repaired or replaced by the Contractor at no additional cost to the City and restored to a condition equal to or better than that existing prior to construction. The Contractor shall provide and maintain construction fencing, barricades, warning signs and other measures necessary to secure the construction area and protect City staff, park users and the public. The Contractor shall coordinate construction access, staging areas, material storage and any required temporary facility or utility shutdowns with the City. Portions of the park outside the approved construction limits shall remain accessible unless otherwise authorized by the City. The Contractor shall maintain the project site in a clean, safe and orderly condition throughout construction and regularly remove construction debris, waste and surplus materials. Prior to commencement of construction, the Contractor shall provide a detailed construction schedule and schedule of values and participate in a pre-construction meeting with the City and project team. Updated schedules shall be provided as requested throughout construction. The Construction Documents require a pre-construction conference and project coordination meetings. The Contractor shall provide all required shop drawings, product data, samples, signed and sealed engineering and other required submittals sufficiently in advance of the work to allow for review and approval without delaying the project. Materials or equipment requiring approval shall not be ordered, fabricated or installed prior to receipt of the required approvals. The Contractor shall perform all testing required by the Construction Documents and authorities having jurisdiction and shall correct and retest deficient work as required. The Contractor shall maintain current record drawings throughout construction documenting field modifications and deviations from the Construction Documents. Upon completion of the work, the Contractor shall restore all areas affected by construction, including sod, irrigation, concrete, landscaping, utilities and other site improvements. The Contractor shall complete all punch-list items and correct all deficiencies prior to final acceptance. Prior to final payment, the Contractor shall provide all required closeout documentation, including record/as-built drawings, warranties, operation and maintenance information, test reports, inspection approvals, permit closeouts and other documentation required by the City. The Construction Documents likewise require record drawings, warranties, maintenance information and final closeout documentation. Final acceptance shall not occur until the work is complete, systems are fully operational, affected areas have been restored, required inspections and permits have been closed, punch-list items have been completed and required closeout documentation has been submitted. NOTICE Notice is hereby given that the City Commission of the City of Pembroke Pines is seeking sealed proposals for: IFB # RE-26-04 Soccer Field and Structural Renovations at Silver Lakes North Park Solicitations may be found on the City of Pembroke Pines website under the Procurement Department at http://www.ppines.com/index.aspx?NID=667 , and may be downloaded directly from the OpenGov platform at https://procurement.opengov.com/portal/pembrokepines . For Technical Support , proposers can reach the OpenGov Service Desk between 7:00 am to 10:00 pm from Monday through Friday via the following methods: Chat (preferred method): Click the button in the lower right-hand corner of the portal. E-mail: procurement-support@opengov.com Phone: 1 (650) 336-7167 If additional help is needed with downloading the solicitation package please contact the Procurement Department at (954) 518-9020 or by email at purchasing@ppines.com . The Procurement Department hours are between 7:00 am to 6:00 pm on Monday through Thursday and is located at 8300 South Palm Drive , Pembroke Pines , FL 33025 . Bidders shall submit all questions regarding this bid via the City's e-Procurement Portal, located at https://procurement.opengov.com/portal/pembrokepines . Please note the deadline for submitting questions. All answers will be posted on the City's e-Procurement Portal. Bidders may also click “Follow” on this bid to receive an email notification when answers are posted. It is the bidder's responsibility to check the portal for updates. Only written responses issued through the OpenGov platform will be considered official for interpretations or clarifications. Proposals will be accepted until 2:00 pm on Tuesday, December 1, 2026 , electronically at https://procurement.opengov.com/portal/pembrokepines/projects/297429 . Bid Opening: The sealed electronic proposals will be publicly opened at 2:30 pm, on the bid due date, by the City Clerk’s Office, in the City Clerk’s Office Conference Room located on the 4 th Floor in the Charles F. Dodge City Center/ City Hall Administration Building, located at 601 City Center Way, Pembroke Pines, Florida, 33025. Virtual Bid Opening: In light of public health concerns and to ensure accessibility for all, the City encourages interested parties and the public to participate virtually via live streaming instead of attending the meeting in person. As a result, meetings may be a combination of in-person and virtual, all as provided by law. To virtually attend the bid opening, please use the Cisco Webex Meetings platform. Virtual Meeting Details: WebEx Meeting Link: https://ppines.webex.com/meet/purchasing Cisco Webex Meeting Number: 717 019 586 Join by Phone Number: +1-408-418-9388 The public may download the Cisco Webex Meetings app from https://www.webex.com/downloads.html/. To ensure an efficient meeting process, participants are requested to mute their audio and camera during the meeting. While the public is welcome to attend the virtual bid opening, please note that active participation and commenting will not be allowed during the proceedings. For further information about the bid opening or assistance in accessing the virtual meeting, please contact: Ivan Ospinal or other Procurement Staff in the Procurement Department City of Pembroke Pines 8300 South Palm Drive, Pembroke Pines, FL 33025 (954) 518-9020 or 954-518-9020 purchasing@ppines.com GENERAL PROJECT INFORMATION & TIMELINE Project Timeline The work shall be completed within 90 days calendar days from issuance

Published attachments
Addenda and notices
  • Addendum #1 · 1

  • Addendum #2 · 2

    MANDATORY SITE VISIT A second mandatory site visit is scheduled for Tuesday, October 6, 2026, at 10:00 AM . Vendors who attended the first mandatory site visit are not required to attend the second site visit. Location: Silver Lakes North Park, located at 2300 NW 172nd Avenue, Pembroke Pines, Florida

  • Addendum #3 · 3

    Mandatory Site Visit

  • Addendum #4 · 4

    Please use the See What Changed link to view all the changes made by this addendum. Please be advised that the solicitation schedule has been revised as follows: Deadline for Questions: October 8, 2026 Bid Submission Deadline: October 27, 2026

  • Addendum #5 · 5

    Please use the See What Changed link to view all the changes made by this addendum. Please be advised that the project Bid Submission Deadline has been extended to November 3, 2026 .

  • Addendum #6 · 6

    Please use the See What Changed link to view all the changes made by this addendum. Please be advised that the solicitation schedule has been revised as follows: Bid Submission Deadline: November 17, 2026

  • Addendum #7 · 7

    Please use the See What Changed link to view all the changes made by this addendum. Please be advised that the project Bid Submission Deadline has been extended to December 1, 2026.

Public questions and answers
  • What is the budget for this project?

    The estimated project cost is $480,000.

  • 1. - What is the budget for this project? 2.- Is Bid Bond and/or P&P bond required?

    1. The estimated project cost is $480,000. 2. Please refer to Sections 2.8 and 2.9

  • Sheet C-2 (paving, grading, and drainage) does not show any drainage system within the soccer field. Could you indicate on the plan any existing drainage system (catch basin, yard drain) that would be affected by the new elevations within the soccer field?

    There are not any existing structures affected by the grading effort to drain the field properly. No impact to any existing structures

  • What type of fill material will be required for the application intended in this project to achieve the required levels? Could you provide the material specifications?

    98% compacted clean fill material

  • According to plan C-2, the new sod area to be installed on the soccer field is approximately 62,960 square feet; added to this is the new sod in the east area, which covers about 79,650 square feet according to plan L-1.0, resulting in a total of 140,610 square feet of new sod. Could you verify the quantity of new sod? There is a discrepancy between plans C-2, L-1.0, and SP-101.

    Follow plan C-2 for sodded area for west field. Follow plan L-1.0 for sodded area for east field.

  • We have to export material from this site after leveling the soccer field to the proposed elevations, which means we are using portion of the existing material to level the soccer field. Question: Are any specific materials required to be placed under the new sod for this project? Or can we level the soccer field using the existing material, as planned?

    Existing materials can be used as long as they are clean soils with no muck, clays, or silt. Clean sandy soil compacted to 98%.

  • Will it be necessary to install a temporary fence on both fields (East and West)? If so, please indicate its location on the plans.

    No temporary fence is required at this time. Silt fence is required for west field only per sheet C-3.

  • The sections of sheet A-101 do not match the elevations of sheet A-201.

    Subtract -1 from the elevation tags on sheet A-101 to find the correct matching elevation on sheet A-201.

  • Sheet 201 the scale is incorrect, it should be 1/4" = 1'.

    That is correct.

  • There is a contradiction in the labels WT-01 and WP-01 identified on sheets A-101 and A-201, which do not match each other.

    Follow Sheet A-101, all restroom walls to receive finish WT-01 up to 60” AFF, remainder of wall above to be finished with WP-01. Transition from WT-01 to WP-01 per detail 6 / A-201.

  • What type of finish will the walls of the women's stalls, the walls of the men's urinal area, and the stall walls (WT-01, WP-01) have? This information is not indicated on sheet A-201 (elevations).

    Follow Sheet A-101, all restroom walls to receive finish WT-01 up to 60” AFF, remainder of wall above to be finished with WP-01. Transition from WT-01 to WP-01 per detail 6 / A-201.

  • The bathroom baseboard material has not been specified. Could you provide the baseboard specifications?

    Refer to detail 4 / A-201 for cove transition detail at wall / floor transition.

Plain text

OpenGov categories

  • 15540 · Gazebos, Kiosks (Including Informational Type), and Pavilions
  • 79002 · Athletic Field Compositions (Baseball Infields, etc.)
  • 90775 · Site Assessment and Site Field Observation
  • 92538 · Field Engineering
  • 92935 · Earth Handling, Grading, Moving, and Packing Equipment Maintenance and Repair
  • 98832 · Grading (Of Parking Lots, etc. - Not Road Building)