Solar Streetlight Project - Phase 3 (CIP No. 8385)

Description

PUBLIC NOTICE IS HEREBY GIVEN that sealed bids will be received by the City Clerk of the chartered City of Vista (“Agency”) for furnishing all plant, labor, services, materials, tools, equipment, supplies, transportation, utilities and all other items and facilities necessary therefore, as provided in the Contract Documents, for the “Solar Streetlight Project – Phase 3 (C.I.P. No. 8385)” in strict accordance with the Project Specifications and Plans on file in the City of Vista Engineering Department. Bid Schedule Mobilization & Demobilization (5% maximum of Total Base Bid) Public Notification per Supplementary General Provisions, Section 3-11.2 Storm Water Pollution Prevention and Erosion Control Traffic Control and Construction Staging Dig Alert and Utility Potholing Receive and Store Owner(City of Vista) Supplied Solar Streetlights Furnish Ameron 2B224 concrete pole Furnish Ameron 6B126 concrete pole Install “Type A” Steel Pole Solar Streetlights per Appendix H Install “Type B” Solar Streetlights and Ameron 6B126 pole per Appendix H Install “Type C” Solar Streetlights and Ameron 2B224 pole per Appendix H Introduction Summary Background Contact Information Timeline Vendor Questionnaire Pricing Proposal Document Uploads

Published attachments
Addenda and notices
Public questions and answers
  • Will the City of Vista require 'Site Specific' traffic control plans for each streetlight location(s)?

    No, site specific traffic control plans will only be required for locations involving high-volume roadways, signalized intersections, or other conditions as determined by the City Engineer. San Diego Regional Standard Drawings(SDRSD) may be used at other locations where applicable to the work and roadway conditions.

  • Will the City of Vista require 'Engineered' traffic control plans signed and stamped by a registered traffic engineer for approval of the traffic control plans & permit?

    Reference Appendix I for the Encroachment Permit requirements. Traffic control plans must be prepared by a C31 Contractor or a licensed Traffic or Civil Engineer.

  • Given the excavation, concrete foundation, and pole installation scope, would the City accept a Class A General Engineering license as an alternative to C-10? We have previously completed solar streetlight projects under our Class A license. If accepted, would a C-10 subcontractor be required?

    The City will only accept bids from contractors holding a valid Class C-10 Electrical Contractor license, as specified in the bid documents.

  • 1.) Will the contractor be able to re-direct the Solar Pole & Equipment shipment to its own yard instead of utilizing the City of Vista Storage yard? 2.) Will the Contractor be responsible for providing all cranes and forklifts to offload the initial shipment City of Vista provided solar poles and equipment?

    1. The Contractor may arrange for delivery of the solar poles and equipment to its own storage yard, subject to prior approval by the City. The Contractor shall be responsible for all associated transportation, handling, storage, and security. 2. Yes, please reference bid item description for Bid Item 6.

  • Has the City already purchased the solar lighting systems? If not, we would appreciate the opportunity to submit an equivalent solar lighting solution that meets all project requirements for review and approval.

    The procurement of the solar lighting systems is outside the scope of this contract. Vendors interested in presenting alternative products for consideration on future projects may contact the City separately.

  • Is there an Engineers Estimate?

    Please refer to Section 6 of the Project Specifications. The Engineer’s Opinion of Probable Construction Cost is $520,000.

  • Will the City of Vista consider increasing the amount of working days for the project to 90 working days? Having to auger, pour and set over 120 poles in 40 working days in not realistic.

    Addendum No. 1 has been issued to increase the contract duration from 40 to 60 working days. The City expects the Contractor to utilize appropriate staffing, equipment, and scheduling to complete the work within the allotted time. The City will not extend the contract duration to 90 working days. Additionally, please refer to Bid Item Descriptions 9, 10, and 11, which specify that excavations shall be performed using a vacuum truck.

  • 1. Please confirm whether the City storage yard located at 2525 Lupine Hills Drive, as identified under Bid Item 6, and the Public Works Satellite Yard at 2430 Lupine Hills Drive, as referenced in Section 3-12.4.1, are separate facilities. Please confirm the designated pickup and storage location for the owner-supplied solar streetlight materials.

    2525 Lupine Hills Drive and 2430 Lupine Hills Drive are separate City of Vista facilities. 2430 Lupine Hills Drive will be the designated storage and laydown area for this project.

  • 1. Please confirm that all owner-supplied solar streetlight packages will be delivered complete with the necessary components and installation accessories. In the event that any owner-supplied materials are found to be missing, damaged, or defective upon receipt or installation, please confirm that the City will be responsible for providing replacement materials at no additional cost to the contracto

    The City will furnish the solar streetlight packages with the necessary components and manufacturer-provided installation accessories. If any City-furnished materials are found to be missing, damaged, or defective, the Contractor shall promptly notify the City for review. The City will provide replacement materials at no additional cost to the Contractor for deficiencies not caused by the Contractor's handling, storage, or installation.

  • 1. In the event that existing underground utilities, concrete structures, or other unforeseen subsurface obstructions conflict with the proposed streetlight foundations, please confirm whether any City-directed relocation, foundation modification, or additional excavation will be compensated as additional work beyond the original contract scope.

    If unforeseen subsurface obstructions, including unmarked or unidentified underground utilities, are encountered that conflict with the proposed streetlight foundations, the Contractor shall notify the City and obtain direction prior to proceeding with the affected work. Any necessary relocation, foundation modification, or additional excavation will be evaluated by the City on a case-by-case basis. Additional compensation, if warranted, will be addressed through the contract change order process in accordance with the Contract Documents.

  • 1. Please confirm the required testing and commissioning procedures for the installed solar streetlights, including battery verification, luminaire operation, controller programming, and manufacturer startup requirements. Please clarify whether commissioning assistance from Fonroche is included with the owner-supplied equipment or must be arranged and paid for by the contractor

    Please reference Appendix E for the installation procedures. For additional installation or startup information, please contact Fonroche Lighting at (339) 225-4530. Fonroche Lighting will provide commissioning assistance as part of the City-furnished equipment at no additional cost to the Contractor.