Skip to content
← Back to search

State and local · OpenGov

Opportunityopen

SOQUEL SAN JOSE RD PM 5.55 STORM DAMAGE REPAIR PROJECT, FEDERAL PROJECT No. ER-15J2 (004)

Description

The County of Santa Cruz, Department of Community Development & Infrastructure is accepting sealed bids for the SOQUEL SAN JOSE RD PM 5.55 STORM DAMAGE REPAIR PROJECT, FEDERAL PROJECT No. ER-15J2 (004) Bid opening will occur on Thursday, February 4, 2027 no later than 2:00 pm and soon thereafter, will be publicly opened and read. Soquel San Jose Rd PM 5.55 CONSTRUCTION AREA SIGNS TRAFFIC CONTROL SYSTEM PORTABLE SIGNAL SYSTEMS (EA) TEMPORARY TRAFFIC STRIPE (PAINT) TEMPORARY RAILING (TYPE K) CHANNELIZER (SURFACE MOUNTED) TEMPORARY CRASH CUSHION MODULE WATER POLLUTION CONTROL PROGRAM TEMPORARY REINFORCED SILT FENCE CONTRACTOR-SUPPLIED BIOLOGIST (LS) CLEARING AND GRUBBING (LS) ROADWAY EXCAVATION STRUCTURE EXCAVATION (SOLDIER PILE WALL) STRUCTURE BACKFILL (SOLDIER PILE WALL) CONCRETE BACKFILL (SOLDIER PILE WALL) LEAN CONCRETE BACKFILL STEEL SOLDIER PILE (W14x90) 30" DRILLED HOLE TIMBER LAGGING GEOCOMPOSITE DRAIN CLEAN AND PAINT STEEL SOLDIER PILING GUARD RAILING DELINEATOR MIDWEST GUARDRAIL SYSTEM (STEEL POST) ALTERNATIVE IN-LINE TERMINAL SYSTEM (TL-2) ROLLED EROSION CONTROL PRODUCT (JUTE MESH) FIBER ROLLS HYDROSEED COLD PLANE ASPHALT CONCRETE PAVEMENT HOT MIX ASPHALT (TYPE A) PLACE HOT MIX ASPHALT DIKE (TYPE F) PLACE HOT MIX ASPHALT DIKE (TYPE C) GABION ROCK SLOPE PROTECTION FABRIC (CLASS 8) THERMOPLASTIC TRAFFIC STRIPE VEGETATION CONTROL MAT (RUBBER OR FIBER) MOBILIZATION Project Details Proposal Instructions Bidders shall create a free of charge account via the online procurement portal, OpenGov Procurement by signing up at https://procurement.opengov.com/signup . For additional information on account registration, see https://opengov.my.site.com/support/s/ Once account registration is completed, browse back to this page, https://procurement.opengov.com/portal/santacruzcounty , click on the “ SOQUEL SAN JOSE RD PM 5.55 STORM DAMAGE REPAIR PROJECT, FEDERAL PROJECT No. ER-15J2 (004) ”, "Submit Response", and follow the instructions to submit the electronic bid. Only electronic proposals will be accepted. Proposal forms for this work must be uploaded via the online procurement portal, OpenGov Procurement. Copies of the forms are included in a separate book entitled: Book 1 of 2 Bid Book For Construction of SOQUEL SAN JOSE RD PM 5.55 STORM DAMAGE REPAIR PROJECT, FEDERAL PROJECT No. ER-15J2 (004) Cashier's check or certified check, payable to the order of the County of Santa Cruz, of not less ten percent (10%) of the bid submitted, payable to the County of Santa Cruz and signed by the bidder as well as a corporate surety, shall accompany the bid. Bidder’s bonds shall be issued by a corporate surety duly admitted and authorized to issue bonds and undertakings by the State of California. Scan and upload a copy of your bid bond/cashier's check via the online procurement portal, OpenGov. No later than 4 p.m. on the 5th business day after bid opening, please mail the original Proposal forms, remaining Proposal forms due as stated in Section 2, and the bid bond/cashier's or certified check to the Contract Analyst , Rosa Ortiz ; Attn: Rosa Ortiz County of Santa Cruz, Department of Community Development & Infrastructure, Public Works Bid Proposal for SOQUEL SAN JOSE RD PM 5.55 STORM DAMAGE REPAIR PROJECT, FEDERAL PROJECT No. ER-15J2 (004) 701 Ocean Street, Room 410 Santa Cruz, CA 95060 Any questions concerning the bid process, required submittals, evaluation criteria, bid schedule, and selection process should be sent through OpenGov. General Work Description The project location in the County of Santa Cruz is as follows: In the unincorporated area of the County of Santa Cruz, along Soquel San Jose Road at Post Mile 5.55. Work includes construction of retaining walls to repair storm damage. Major work includes, but is not limited to: Soldier pile retaining wall with timber lagging Midwest guardrail, Asphalt concrete overlay, Erosion control and re-vegetation Traffic Control For the Federal training program, the number of trainees or apprentices is 0 . Federal-aid project No.: ER-15J2 (004) . Complete the work within 40 working days. Do not include plant establishment working days in your bid. The estimated cost of the project is $507,000 . Contract Documents A digital copy of the Contract documents is available free of charge and can be downloaded, see Attachments . A hard copy of the Contract documents is available for purchase for $60.00 at the County of Santa Cruz, Department of Community Development & Infrastructure, Public Works, Room 410, 701 Ocean Street, Santa Cruz, California. No partial sets will be issued. Introduction Summary Background Contact Information Timeline Vendor Submissions Pricing Proposal Attachments

Published attachments
Addenda and notices
  • Official Notice #1: Official Notice #1: Delayed Bid Opening · 1

    The bid opening for this project has been delayed and is tentatively scheduled for February 2027. An addendum will be released shortly stating the revised bid opening day and time.

  • Addendum #1 · 1

Public questions and answers
  • What is the anticipated start date for this project?

    Please refer to the special notice in Book 2. There is Delayed Start language.

  • If the contractor can only start between 4/1/2027 and 6/15/2027, does section 8-1.04C require the contractor to immediately procure and store the piles and lagging until the window starts?

    Yes, jobsite activities are delayed until April 1 - June 15 as requested by the contractor. The contractor must include the submittals noted with the requested start date, within 30 days and submit a written statement for the piles and lagging after 60 days. The purpose of this section is to ensure the contractor has ordered long lead time items and has the material on hand when job site activities begin.

  • Does form 9-L need to be submitted with the bid package? Please provide timeframe for when you need this form submitted.

    Yes. See Project Documents -- Vendor Submissions. Question 3. The Bid Form Submittal Schedule (Book 2) is another place you can view what is required at time of bid. Although it is missing the 9-L form currently. An addendum will be issued next week incorporating the E9-L into the Book 2 table.

Plain text