The Seattle Public Library (Central) Level 2 Remodel

Description

Project Description: The Project renovates interior space on Level 2 of the Central Branch to office and mixed-use workspaces to support the shelving and operations team (SHO). On Levels 1 and 3, the work will infill openings in the existing structural concrete floors where the book conveyor system was previously removed. Scope includes but is not limited to modification of existing electrical, mechanical, fire alarm and fire sprinkler systems; construction of new framed walls; installation of suspended ceiling systems; interior finishes; casework modification and fabrication; and supporting work as indicated in the Contract Documents. Engineer's Estimate: $225,000 base bid Project Location: The Seattle Public Library (Central) 1000 Fourth Ave Seattle, WA 98104 Attachments

Published attachments
Addenda and notices
Public questions and answers
  • Painting limits and existing finishes “Please confirm the rooms and surfaces included in the painting scope. A2.01 Note 8 calls for all interior walls to receive new paint, and A2.40 Note 3 calls for all exposed existing finishes in the work area to be painted, while the finish schedule identifies several existing finishes as ‘E.’ Please confirm the limits of repainting and identify any existing surfaces or rooms that are excluded.” Exposed ceilings and overheads “Please identify the areas where dry-fall painting is required. A2.31 identifies existing ceiling/structure for painting, and Section 099000 includes overheads such as structure, ductwork, piping, conduit, fireproofing, and suspension devices. Should painting cover all exposed overheads in the Level 2 work area, including above or around the new suspended ceiling/clouds, or only specifically exposed areas?” P-2 doors and frames “A5.01 labels existing hollow metal doors and frames P-2; A2.70 identifies P-1 as the typical door color, and Section 099000 calls for both sides when a room is repainted. Please confirm whether the P-2 designation applies to both sides of each labeled door and frame, including the faces toward rooms scheduled to remain existing.”

    Please direct all your questions to the Architect via e-mail jessechapman@millerhayashi.com. All questions and responses will then be posted on OpenGov 11-12-26 by 5:00pm due to the holiday.

  • The instructions to bidders says to submit the bid pricing in open gov. I do not see the documents to submit bid pricing in the bid forms or in open gov

    Please direct all your questions to the Architect via e-mail jessechapman@millerhayashi.com as instructed in the bid advertisement. All questions and responses will then be posted on OpenGov 11-12-26 by 5:00pm due to the holiday. I will respond to bid submittal and advise you to please go to the bid manual and review BID SUBMITTAL CHECKLIST SECTION 00 43 93 CENTRAL L2 REMODEL on Page 1 1.01 GENERAL A. Bid Submittal: 1. Electronic Bid Submittal: Submit Bids through both the OpenGov portal: https://procurement.opengov.com/portal/seattle and email to buyer.bid@spl.org.

  • Section 00 41 00 states to submit the bid on the form via openGov We are unable to locate the bid form there.

    I have advised in the previous question that you need to read the Bid Manual or project manual as all required documents and complete instructions are in the Bid /Project manual this document is located in the attachment section of OpenGov. Please open the attachment section and go to the bid manual and review look for BID SUBMITTAL CHECKLIST SECTION under 00 43 93 CENTRAL L2 REMODEL on Page 1 1.01 GENERAL A. Bid Submittal: 1. Electronic Bid Submittal: Submit Bids through both the OpenGov portal: https://procurement.opengov.com/portal/seattle and email to buyer.bid@spl.org as well. We are asking that you submit to both OpenGov and the Buyer.Bid@spl.org e-mail address to ensure prompt delivery of your response and in case there is an issue then we know we have your bid. Please OPEN and review all the documents that have been made available to you in the attachment section of OpenGov. Lastly, direct all your questions to the Architect via e-mail jessechapman@millerhayashi.com as instructed in the bid advertisement. All questions and responses will then be posted on OpenGov 11-12-26 by 5:00pm due to the holiday. Thank you

  • The response to OpenGov Questions #1-3 states that questions and responses will be posted by November 12, 2026, at 5:00 p.m., which coincides with the current bid deadline. With the Veterans Day holiday on November 11, please confirm when responses to outstanding questions and any associated addenda will be issued. Responses may affect subcontractor scope and pricing, and issuance at the bid deadline would leave no time to incorporate that information. We respectfully request extending the bid deadline to allow at least three business days after issuance of the final responses and associated addenda for subcontractors and prime contractors to review the clarifications, update pricing, and submit complete bids. Please confirm the bid date and time.

    I will redirect this to the A & E as the bid indicated that all question be sent directly to the A & E via e-mail jessechapman@millerhayashi.com and for whatever reason they are still being sent to OpenGov. Please look for a response from the A & E regarding your question and a addendum to support findings. Thank you

  • Will the pre-bid meeting attendance list be posted with the project? Thanks.

    See addendum # 2

  • The work under 260573 requires the use of an electrical one line diagram. Could you please provide a one line diagram? Also, What is the location of panel L2D?

    Please direct all your questions to the Architect via e-mail jessechapman@millerhayashi.com as instructed in the bid advertisement