Trail Design and Construction Services
Description
Greenville County is requesting proposals for providing professional trail design and construction services for development of a soft surface trail at Southside Park, 417 Baldwin Rd, Simpsonville, SC, as identified in the attached map. The specific description and components are listed under the General Requirements section. Table 1 Trail Design Trail Construction Scope of Work General Requirements The intent of these requirements is not to give all technical specifications, but instead to give general requirements such that the prospective vendor will be able to make a proposal. It is expected the successful vendor must professionally perform a quality job in accordance with Greenville County Parks, Recreation and Tourism direction/standards. The vendor must furnish all labor and transportation necessary to perform the work specified in this request. Any additional work required to complete the following tasks and not specified below is considered incidental and no additional payment will be made. 1. Provide complete construction of approximately 1.5 miles of single track trail, following US Forest Service Trail Class 3 Design Parameters, suitable for mountain biking and hiking. Any wet drainage crossings shall consist of native rock armoring. 2. This section of trail shall follow the natural contours of the land, which is rolling and wooded. It is anticipated that only minimal, if any, non-native dirt will be required to supplement native materials ( 10 tons of clay soil). 3. Technical bike trails and features must be designed and constructed in accordance with best practices established by recognized trail organizations. 4. Finished tread width will be a minimum of 42 inches wide. Vegetation cleared outside of trailway, 5’ wide minimum, 8, high minimum. 5. Basic trails and trail structures must be designed and constructed in accordance with the STANDARD SPECIFICATIONS FOR CONSTRUCTION OF TRAILS AND TRAIL BRIDGES ON FOREST SERVICE PROJECTS (2014 Edition). The following link is provided for reference: https://www.fs.usda.gov/sites/default/files/trail-specifications.pdf Firm Requirements Proven experience in design in the natural environment and recreational areas. Proposal Submittals The proposals must include the following related to the scope of work: Required Proposal Submittals (Items 1–3: One-Page Limit) 1) Cover letter, signed by a person authorized to bind the firm) 2) Resume that outlines: design-build team, experience, and references 3) Examples of past work (photos and narratives) 4) Proposed costs (per Pricing Proposal ) Inspection and Acceptance The County’s representative may inspect the work at any time and will conduct required inspections at (1) route flagging, before construction begins, and (2) substantial completion. Work must conform to the Scope of Work, the Class 3 Design Parameters, and the referenced standards. The Contractor shall correct deficiencies on the County’s written punch list within [14] days. Final acceptance will be issued in writing by the County after all corrections are complete and the Contractor has delivered a GPS track of the completed trail. Final payment is due after acceptance. Public Notice Greenville County is soliciting sealed proposals in response to Trail Design and Construction Services , subject to the conditions and all provisions set forth herein and attached. Sealed proposals will be received through the County’s online procurement portal located at https://procurement.opengov.com/portal/greenvillecounty until Tuesday, November 24, 2026 , 3:00 pm , then publicly opened. The goods and/or services must be furnished as described and specified herein and submitted to Greenville County. All inquiries regarding this proposal shall be submitted no later than Tuesday, November 17, 2026 , 2:00 pm via the County’s online procurement Portal, located at https://procurement.opengov.com/portal/greenvillecounty . Please note the deadline for submitting inquiries. All answers to inquiries will be posted on the County’s online procurement Portal. Offerors may also click “Follow” on this proposal to receive an email notification when answers are posted. It is the responsibility of the Offeror to check the website for answers to inquiries. Introduction Summary Background Contact Information Timeline Instructions to Offerors Pre-Proposal Meeting A Non-Mandatory Pre-Proposal meeting will be held at the date and time specified in the Timeline. A site visit will follow. Vendors are encouraged to RSVP for the meeting through the OpenGov portal. The RSVP link is in the header of the solicitation. Pricing Pricing must be based upon payment in thirty (30) days. Discounts for payment in less than thirty (30) days will not be considered in making award. Discounts shall be stated in proposals as a percentage. Time in connection with discount offered will be computed from date of delivery of commodities to carrier, when inspecting and acceptance is at point of origin; or date of delivery at destination; or if laboratory inspection is made part of bid, from date of laboratory report. Unit pricing will govern over extended pricing, unless stated otherwise. Pricing shall include packing. Unless indicated by County, pricing must be firm. Vendors shall enter pricing in the Pricing Proposal section. Bonding Bonding will be required for this project. See Bonds section for the requirements. Statement of Qualifications Vendor shall include the following with their response: Company overview and background Corporate/individual qualifications and experience, including certifications Project references: at least three (3) completed trail projects, including any South Carolina governmental entity references. For each, provide: - Completion date (month/year) - Trail length (miles) and design standard (if known) - Your role: Design / Construction / Both - Who did the work: Own forces / Subcontractor - Reference contact (name, phone, email) Subcontractors: Identify any subcontractor who will perform design or trail construction and the portion of work they will perform. Experience will be evaluated based on the firms that will perform the work. Submission Procedures and Requirements All submissions must be received by Tuesday, November 24, 2026 at 3:00 pm . Submissions will not be accepted after the deadline. There will be no exceptions. Responders submitting proposals shall be responsible for all cost of preparing such proposals. Information requested and not received at the time of submission may disqualify the submitted proposal. Responders to this solicitation shall closely examine the specific requirements noted herein and the attached Terms and Conditions. Facsimile transmittals, hard copies, emails or offers communicated by telephone will not be accepted or considered. Proposals shall be organized in the following manner with the subject headings and sequence indicated. Section 1: Statement of Qualifications Company overview and background Corporate qualifications, experience, and certifications Minimum 3 project references (include SC governmental entities if applicable) -Project name and location: -Completion date (month/year): -Trail length (miles) and design standard (if known): -Your role: Design / Construction / Both -Who did the work: Own forces / Subcontractor -Reference contact (name, phone, email) Subcontractors: Identify any subcontractor who will perform design or trail construction on this project and the portion of work they will perform. Experience will be evaluated based on the firms that will perform the work. Section 2: Technical Approach Brief description of the contractor's approach to the design and construction of approximately 1.5 miles of single-track trail, including wet drainage crossings. Section 3: Business Documentation Business licenses and certifications Insurance certificates Acknowledgment that the selected contractor shall obtain all applicable licenses and permits, and promptly pay all applicable taxes required by the State of South Carolina and/or Greenville County Section 4: Pricing Completed Pricing Proposal Form (provided electronically) License and Permits – The Contractor shall obtain all applicable licenses and permits, and promptly pay all taxes required by the State of South Carolina, and/or Greenville County. Proposals must include the Required Proposal Submittals listed in the Scope of Work (Items 1-4) SAM.gov registration required for all contractors/sub-contractors. Confirm that you have submitted documentation with proposal. Inquiries and Addenda Offerors shall submit all inquiries regarding this RFP via the County’s online procurement Portal, located at https://procurement.opengov.com/portal/greenvillecounty . Please note the deadline for submitting inquiries. All answers to inquiries will be posted on the County’s online procurement Portal. Offerors may also click “Follow” on this bid to receive an email notification when answers are posted. It is the responsibility of the bidder to check the website for answers to inquiries. The County will not be responsible for or bound by any oral instructions made by any employee(s) of the County in regard to this RFP. Addenda Notification: This RFP represents the most definite statement Greenville County will make concerning information upon which proposals are to be based. Offerors are required to register for an account via the County’s online procurement Portal hosted by OpenGov. Once you have completed the registration, you will receive addenda notifications to your email by clicking “Follow” on this project. Ultimately, it is sole responsibility of each proposer to periodically check the site for any addenda at https://procurement.opengov.com/portal/greenvillecounty . No addenda will be issued later than five (5) working days prior to the date for receipt for proposals except an addendum which, if necessary, postpones the date for receipt of proposals or cancels this RFP. Vendors shall acknowledge receipt of all addenda. General Information Proprietary Information – The County of Greenville is a public body and governed by the South Carolina Freedom of Information Act. Documents submitted to the County relating to this Solicitation are subject to requirements of the Freedom of Information Act and may be deemed public records. Errors and Omissions – The Responder will not be allowed to take advantage of any errors or omissions in the Request for Proposals. Where errors or omissions appear in the RFP, the Responder shall promptly notify the County of Greenville in writing of such error or omission it discovers. Any significant error, omission and/or inconsistency in the specifications are to be reported as soon as possible but no later than five (5) days before such time the response is to be submitted. Withdrawal of Proposal – An official representative of a Responder may withdraw a Responder’s response at any time prior to the proposal submission deadline. Acceptable proof establishing that he/she is the representative of the Responder must be provided. Non-Endorsement – If the County awards a contract, the successful Responder shall not issue any news release or other statement relating to the award or servicing of the agreement which state or imply the County of Greenville’s endorsement of the successful Responder’s services. Insurance Insurance Requirements The contractor is responsible for and must have all required insurance listed below and shall not commence work under the associated contract until it has obtained all insurance required, and the County has approved such insurance in writing, nor shall the Contractor allow any subcontractor to commence work on its subcontract until all similar insurance required of the subcontractor has been obtained. All insurance policies shall be maintained for the life of the contract. THE COUNTY SHALL BE NAMED AS “ADDITIONAL INSURED” FOR ITS INTEREST on all policies of insurance except Worker’s Compensation, Automobile Liability, and Professional Errors and Omissions, as regards ongoing operations, products and completed operations, and this shall be noted on the face of the Certificate of Insurance. As a part of the certificate of insurance requirement the contractor shall also include acknowledgement and acceptance of the wavier of subrogation provision granted to Greenville County. This acknowledgement and acceptance should be included in the same section of the Certificate of Insurance that evidences the “Additional Insured” provision. Certificates for all such policies of insurance shall be provided by the Contractor's insurance agent or broker to the County within 10 working days from the date of Notice of Award. All Certificates of Insurance submitted shall provide on the face of the certificate reference to County's RFP # RFP #27031 . Contractor will provide County a minimum of 30 days advance notice in the event the insurance policies (or an insurance policy) are canceled. Subcontractors approved to perform work on this project are subject to all of the requirements in this Section. Contractor agrees to maintain and keep in force during the life of this Agreement, with a company or companies authorized to do business in South Carolina, the following insurance policies: Comprehensive General Liability: $1,000,000 per occurrence - combined single limit / $2,000,000 general aggregate, to include products and completed operations. Automobile Liability: $1,000,000 per occurrence - combined single limit (Coverage shall include bodily injury and property damage and cover all vehicles including owned, non-owned and hired) Statutory Worker's Compensation: Coverage A - State of SC Coverage B - Employers liability $1,000,000 Each Accident $1,000,000 Disease, Per Employee $1,000,000 Disease, Policy Limit Policies shall contain a waiver of subrogation in favor of and/or that applies to Greenville County, its departments, agencies, boards, employees, and commissions for losses from work performed by or on behalf of the contractor. No deviation from this coverage’s will be accepted unless, in the County’s sole discretion, it is more advantageous to the County, i.e., $1,000,000 - a $2,000,000 or $5,000,000 limit would be acceptable. Evaluation Phases The proposals will be evaluated on the following criteria. Greenville County reserves the right to interview responders or have demonstrations to this RFP at its discretion. Greenville County will not be responsible for any costs associated with interviews of responders or demonstrations. If interviews or demonstrations are needed, a second phase of the evaluation process may be implemented at the County's discretion. Point values are described below. 5 = High 4 = Medium High 3 = Average 2 = Medium Low 1 = Low 0 = Non-Responsive Bonds Bid Bond: This project requires a Bid Bond and a Performance/Payment Bond. Proposers shall submit with their proposal, a Bid Bond in the amount of 5% of the bid price. This bond may be in the form of Bid Bond from the American Institute of Architects (AIA), electronically through Surety 2000, Certified Check, Cashier’s or Bank Money Order of any national or state bank and shall be made payable to Greenville County. Proposals submitted without being accompanied by any of the foregoing as required, may be considered informal and may be rejected. Any proposal accompanied by a bid bond not properly executed in the opinion of the County Attorney, may be rejected. The bond will be forfeited to the County by the successful bidder as liquidated damages in case a proposal award is made to that bidder and the contract and bond are not promptly and properly executed. 1. Instructions for Bond through AIA or similar bond document: The Original (hard- copy) Signed-Bid Bond must be delivered to the Procurement Services Office by the Bid Due Date/Time specified . The Bid Bond must be submitted in a sealed-envelope to: Greenville County Procurement Services Division; 301 University Ridge, Suite N-2400; Greenville, SC, 29601. The following information must be included, on the outside of the envelope: A. “Bid Bond” (labeled) B. Bid Number C. Company Name 2. Instructions for Surety2000: The County has an account with an online Bid Security program called Surety2000. This is a fee-based program that bidders can use to obtain an electronically issued, verified and legal bid bond which can be used for bidding purposes. No bid bond can be created by the bonding agent on the site without the Surety being fully aware of that bond. Only agents appointed directly by the Surety can issue bid bonds on the site. If your company chooses to use Surety2000 to obtain the bid bond, please access Surety2000 at www.surety2000.com. Complete the necessary steps to log in to the site and obtain the bid bond. Bond Identifier: RFP #27031 USE THIS CODE WHEN ACCESSING SURETY2000 Once an official bid bond is issued, use the space below to input your company's E-Bond Serial Number. The number will look something like this: SNJ5185268 This number will then be used at the bid opening to verify your company's bid bond. If you are not using this method for Bid Security submission please write "N/A" in the field provided. Please note that the County is not responsible for late submissions and no consideration will be made for bid security received after the date and time stipulated in the Notice to Bidders even if you have electronically submitted your bid on time. If the original bid security is not able to be verified by the date and time stipulated in the Notice to Bidders, your submission will be rejected. If required per solicitation and after proposals are awarded, the Procurement Services Division will return immediately all checks, except that of the successful bidder. The check of the successful bidder will be returned upon compliance with the performance and payment bond requirements. If required per solicitation, the successful bidder, within fifteen (15) working days after acceptance of the bidder’s offer by the County, shall furnish a satisfactory performance and payment bonds in the amount of the total bid price. The performance and payment bonds must be received by the county prior to issuance of an executed contract and Notice to Proceed. The fifteen (15) working days may be extended upon written approval by the Procurement Director. A copy of the written approval shall be transmitted to the successful bidder stating the terms of any extension. In the event that the bidder fails to deliver to the County Procurement Services Division the performance and payment bonds in said period of fifteen (15) working days after acceptance of the bidder’s offer by the County, then the bid bond of the bidder shall be retained by the County in its entirety and the award will be withdrawn from the bidder. The successful bidder shall have as surety a corporate surety authorized to act as surety in South Carolina. The Performance and Payment Bonds will insure that the successful bidder will promptly make payments to all persons supplying labor or materials to the bidder; and shall guarantee to indemnify and save the County, its officers, divisions, and employees harmless from all costs, damages, and expenses growing out of or by reason of the successful bidder’s failure to comply and perform the work and complete the contract in accordance with the specifications in the matter of making, furnishing and/or delivering said work or supplies. The Performance and Payment Bonds will be in effect for one year after completion of the contract. If bonding is required per the solicitation, the bonding company must have an agent available to meet with County officials to clarify and explain the County’s responsibility in maintai
Published attachments
Addenda and notices
Official Notice #1: Sign in sheet · 1
Official Notice #2: Proposal Tabulation · 2
Public questions and answers
The scope of work did not mention a trailhead map/kiosk or any trailside signage. Should contractors include such items as part of the scope of their trail construction, or are these items being handled separately by the County?
Thank you. These items are not included in the scope of work.
The RFP instructs vendors to include at least three references in the body of their response, and then there is a separate area asking respondents to attach three references using a slightly different format. We wanted to confirm that we should include references in both places using both formats.
Edited - 3:12pm - Yes, both are required: project references per Section 4.5 in the Statement of Qualifications, and references in the Section 10.1 format for the County’s reference questionnaire. The same references may be used for both sections, but each must be completed separately.
Good morning, why do I have to provide a bid bond for a project that doesn't require any materials or proprietary equipment to be acquired and installed on a project of this nature? I have built trails at gateway park, pleasant ridge park, country club park, david jackson park, shoeless joe park and northside park without requiring bonding. The job will pay out in progression payments so wouldn't that be sufficient enough leverage for the client to be able to manage their risk? I do believe that requiring bonding will deter trail contractors from being inclined to participate and leave the door open for general grading contractors who's machinery is by and far too wide to be able to abide by NFS standards for trail corridor size and environmental disturbances? I also am aware of the well established NNIS on the property, predominently kudzu. Is there any requirements to mitigate them so that once the understory gets opened up the kudzu won't just flock to the newly sundressed forest floor. Take a look at sliding rock 2. YOU CAN"T EVEN FIND THE TRAIL UNDER THE KUDZU. I would be very interested in putting in a proposal for this project but only IF my scope is to also include NNIS mitigation. This means having the kudzu tubers removed from the ground prior to trail construction. GLYPHOSATE IS NOT A MEANS OF MITIGATING ANYTHING. thanks for your time.
Due to the County's estimated costs and per the procurement ordinance, bonding will be required for this project.
Section 3.3 (Proposal Submittals) lists four items which correspond to the submission guidelines found later in the RFP (4.5 Submission Procedures). In Section 3.3 it mentions a 1-page limit for items 1-3, but this page limit is not mentioned in the later sections. Does the page limit apply? If so, does the 1-page limit apply to all three items cumulatively, or is it a 1-page limit for each of the three items individually?
Thank you. Yes, the page limit in Section 3.3 applies. Each of Items 1 through 3 (cover letter, resume, and examples of past work) is limited to one page each.