Transit Hub Elevator Additions
Description
Scope will include the addition of a new passenger elevator at the exterior to provide accessibility to all building levels and demolition of an exterior loading area. Project Details Important Instructions for Electronic Submittal TARTA is accepting electronic bid submissions. Bidders shall create a FREE account with OpenGov Procurement by signing up at https://procurement.opengov.com/signup . Once you have completed account registration, browse back to this page, click on "Submit Response", and follow the instructions to submit the electronic bid. Scope of Work or Project Details Please reference the document labeled "Put document title here" for the full scope of work. Introduction Summary Background Contact Information Timeline Evaluation Criteria Vendor Submissions Attachments
Published attachments
- TARTA TASK8C - Transit Hub Elevator Addition - Project Manual
- TARTA TASK8C - Transit Hub Elevator Addition - Dwgs
- FederalClauses 10.6.2026
- Declaration of Non-Collusion SH
- Lobbying Certifcation
- Insurance Requirements 11.3.2026
- Section 5525.16 Contract performance bond and payment bond
- TARTA TASK8C-Transit Hub Elev Addition-Bid Addendum 2-Drawings
- TARTA TASK8C-Transit Hub Elev Addition-Bid Addendum 2-Narrative
- TARTA TASK8C-Transit Hub Elev Addition-Bid Addendum 2-Project Manual
- Transit_Hub_Elevator_Additions_(Addendum_#2_Revision).pdf
Addenda and notices
Addendum #1 · 1
Added payment bond, performance bond, and insurance clauses as attachments. Please review. Please use the See What Changed link to view all the changes made by this addendum.
Addendum #2 · 2
Please use the See What Changed link to view all the changes made by this addendum.
Public questions and answers
Confirm that building permit fees are paid by Owner.
Contractor will be responsible for paying for and obtaining all permits, licenses, and inspections required by the AHJ.
Confirm that testing fees are paid by Owner.
Contractor will be responsible for testing fees
Suggest an integral poured in place concrete sump basin would be more leak proof than a precast sump caulked in place.
Foundations have been modified to allow for cast-in-place prefabricated sump liner. Fully formed cast-in-place sump pit may also be acceptable. Information will be include in forthcoming Addendum.
Clarify underdrains diameter, locations, and tie-in invert at catch basin as no details found.
Refer to forthcoming Addendum.
It appears that the existing catch basins are full of debris and the invert could not be verified nor details found on drawings.
Refer to forthcoming Addendum.
Confirm that LG wall bears on concrete stub wall as shown on the structural drawings.
Correct. At foundation level, light gauge wall will bear on new concrete grade wall along the face of existing foundation wall.
Confirm that new CMU wall braced by LG framing is 8” as shown on structural drawings and not 12” as shown on the architectural drawings.
8” CMU wall is correct
Provide bearing details for the new overhead door lintel at the existing concrete column as details not found.
Refer to forthcoming Addendum.
Confirm that all the new bollards are 6” schedule 40 prime painted (not galvanized) with HDPE-1 covers. Bollards are mounted on steel plates bolted to concrete (not galvanized).
Bollards and its components including but not limited to the base plate and bolts to be hot-dipped galvanized.