Transportation Facilities Master Plan (TCDI Project Category 5 – Transportation and Infrastructure Planning)

Description

The Delaware Valley Regional Planning Commission (DVRPC) is seeking proposals from qualified vendors for: TCDI Project Number: 27-67-105 TCDI Project Category: Category 5 – Transportation and Infrastructure Planning Project Title: Transportation Facilities Master Plan Project Sponsor: City of Philadelphia (Streets) TCDI Prequalified Consultants DVRPC REQUIRES ALL CONSULTANTS TO BE PREQUALIFIED TO COMPETE TO WORK ON TCDI-FUNDED PROJECTS. ONLY CONSULTANTS WHO HAVE MET DVRPC’S PREQUALIFICATION REQUIREMENTS ARE ELIGIBLE TO WORK ON TCDI PROJECTS. PLEASE DO NOT SUBMIT A PROPOSAL IF YOU ARE NOT A PREQUALIFIED CONSULTANT UNDER TCDI CATEGORY 5: TRANSPORTATION AND INFRASTRUCTURE PLANNING. REFER TO ATTACHMENT B TO CONFIRM YOUR APPROVED CATEGORIES. Project Background Background The City of Philadelphia is seeking proposals from qualified consulting firms to prepare a Transportation Facilities Master Plan (“Master Plan”) to guide capital investments in City-owned transportation operations, maintenance, storage, and support facilities over the next decade. The City of Philadelphia Streets Department either owns or operates a network of facilities that support roadway, bridge, traffic operations, street lighting, maintenance, materials storage, surveying, training, and other transportation functions throughout the city. These facilities provide critical infrastructure for maintaining Philadelphia's transportation system and supporting the employees responsible for its operation. The City currently has approximately 18 transportation-related sites that house a variety of operational functions. Many facilities have been constructed or adapted over several decades and serve multiple purposes. As operational needs have evolved, facilities have often been modified incrementally rather than through comprehensive modernization or replacement programs. For more than two decades, limited capital funding has resulted in deferred maintenance and investment at many transportation facilities. The City's capital resources have generally been directed toward other critical transportation needs, including structurally deficient bridges, roadway paving and rehabilitation, ADA improvements, and transportation safety projects. As a result, many transportation buildings, maintenance yards, storage facilities, and associated site infrastructure require significant investment to restore them to a state of good repair and to accommodate current and future operational needs. The City seeks to undertake a coordinated assessment of its transportation facilities to establish a long-term strategy for capital investment. The resulting Master Plan will identify existing facility deficiencies, operational needs, potential improvements, and opportunities for modernization, reduced resource consumption, consolidation, relocation, or other strategic changes where appropriate. The Master Plan is intended to provide the City with a practical framework for identifying and prioritizing capital investments over the next ten years. The plan will also support the development of future capital budget requests by identifying the level and timing of investment necessary to maintain safe, functional, and efficient transportation facilities. The project is consistent with the City's comprehensive planning framework, including Phila2035 , which identifies objectives related to maintaining municipal support facilities in an utility-efficient state of good repair and co-locating, consolidating, and modernizing municipal support facilities. The Master Plan will also consider the relationship between transportation facilities and their surrounding communities. Several facilities are located within established industrial, residential, and mixed-use areas and may present opportunities to improve site functionality, neighborhood compatibility, and the efficient use of City-owned property. Project Objectives The primary objectives of the Transportation Facilities Master Plan are to: Establish a comprehensive understanding of the physical condition and functional characteristics of the City's transportation facilities; Identify building, site, infrastructure, and systems deficiencies and deferred capital needs; Evaluate the ability of existing facilities to support current and anticipated operational requirements; Identify opportunities for facility modernization, rehabilitation, utility efficiency, consolidation, relocation, or other strategic improvements and extend the life of the facility for 5, 10 and 20 years; Develop planning-level cost estimates for identified capital improvements and facility strategies; Establish a framework for prioritizing capital investments; Develop a phased, approximately ten-year implementation strategy for transportation facility investments; and Provide the City with a practical decision-making tool to support future capital planning, budgeting, grant / funding applications, and facility investments. Project Description (Scope of Work) The consultant team shall provide all professional, technical, analytical, planning, and facilitation services necessary to complete the Transportation Facilities Master Plan. The consultant team should include a cross-functional set of subject matter experts, including, but not limited to: Facility Planning / Space Planning Architectural Structural Engineering Mechanical, Electrical, and Plumbing Engineering Fire protection and life safety Environmental / health compliance Telecom, networking, security, and AV Sustainability Operations & Maintenance Landscape and Stormwater management Site Planning for circulation, parking, loading, storage The consultant team must have expertise in facility evaluation of building and sites in Philadelphia and have advanced experience related to building, zoning, mechanical, electrical, plumbing, stormwater and other permits specific to the City of Philadelphia. Consultant team familiarity with Philadelphia Building Code and associated Permitting Requirements, including PWD Stormwater requirements, is desired. The consultant shall coordinate closely with the City of Philadelphia Streets Department and other relevant City departments and agencies throughout the project. The following tasks represent the anticipated minimum scope of services. Respondents may propose additional activities that they believe are necessary to accomplish the project objectives. The Technical proposal should provide a timeline for all deliverables and the Budget proposal should include a cost estimate by task. Task 1 – Project Management and Coordination, and TCDI Administration The consultant team shall provide overall project management and coordination throughout the duration of the project. At a minimum, the consultant team shall: Prepare a detailed project schedule identifying major tasks, milestones, deliverables, meetings, and review periods; Conduct a project kickoff meeting with the Streets Department and other designated City representatives; Establish a project management and communication protocol; Coordinate regularly with the City's project management team; Conduct periodic progress meetings to review project status, findings, issues, and upcoming activities; Prepare meeting agendas, presentation materials, and meeting summaries as appropriate; Maintain a current project issues and decisions log; Submit periodic progress reports documenting completed work, upcoming activities, schedule status, and issues requiring City direction; Coordinate logistics with site and building visits; Attend two project status meetings with DVRPC and the project sponsors; and Draft and submit progress reports and invoices with a confirmation letter from the City to DVRPC as required (at least quarterly, but no more than monthly) for TCDI administration. The consultant team shall identify information and documentation required from the City at the beginning of the project and coordinate requests for available plans, reports, maintenance records, capital project information, facility data, and other relevant materials. Deliverables Project Work Plan and Schedule Project Management and Communication Protocol Meeting Agendas and Summaries Progress Reports Project Issues and Decisions Log Task 2 – Facility Inventory and Existing Conditions Assessment The consultant team shall develop a comprehensive inventory and planning-level existing conditions assessment of the City's transportation facilities. The assessment shall address the facilities identified by the Streets Department, including transportation maintenance yards, garages, salt storage facilities, shops, operations centers, training facilities, survey facilities, and other transportation-related properties. The current facility portfolio includes, but is not limited to: 1st Highway District Field Office, Maintenance Yard, and Salt Dome at 4806-4840 Parkside Avenue; 2nd Highway District Maintenance Yard at 3030 S. 63rd Street; 2nd Highway District Salt Dome at 3140 S. 61st Street; 2nd Highway District Residential Trailers and Survey District 2 at 1100 Wharton Avenue; 3rd Highway District Maintenance Yard and Salt Dome at 2121 W. York Street; 3 rd Highway District Highway Field Office at 667 N. Broad Street; 4th Highway District Maintenance Yard and Salt Dome at 4521 Stenton Avenue; 4 th Highway District Field Office at 6249 Wissahickon Avenue; 4 th Highway Salt Dome and Brine Hut at 5201 Umbria Street; Streets Complex at 4000-40 Whitaker Avenue; Highway District 5 Field Office, Maintenance Yard, Salt Dome Central Maintenance Unit (CMU) Field Office Asphalt Yard Line Striping Building Bridge Maintenance Unit (BMU) Field Office Highway Storeroom 6th Highway District Field Office and Survey District 4 at 1701 Bowler Street; Streets Training Center, 6 th Highway District Maintenance Yard, Salt Dome and Brine Hut at 8401 State Road; Street Lighting Shop at 701 Ramona Avenue; Traffic District 3, Traffic Signal & Sign Shop Field Office and Traffic Operations Center (TOC) at 4501 G Street; Employee Assistance Program facility at 5027 Grays Avenue; Survey District 5 at 6601 Rising Sun Av; Survey District 7 at 6448 Woodland Av; and Survey District 9 at 4000 N American St. The consultant team shall confirm the facility inventory with the Streets Department . The existing conditions assessment shall include, to the extent information is reasonably available: Building Conditions General condition and age of buildings; Building envelope and roof conditions; Interior conditions and functionality; Americans with Disabilities Act (ADA) considerations; Office, shop, warehouse, and storage space; Adequacy of existing spaces for current operations; and Major building deficiencies and deferred maintenance needs. Building Systems Conditions HVAC systems; Electrical systems; Mechanical systems; Plumbing systems; Environmental Assessments Exterior Retaining Walls, Stairs, Railings, Landscaping Lighting (interior & exterior); Fire protection and TCDI Timeline TCDI Timeline Posting of Request for Proposal: Monday, October 19, 2026 Submission of Inquiries: Thursday, October 29, 2026 , 5:00 pm Posting of Responses to Inquiries: Monday, November 9, 2026 , 5:00 pm Proposal Deadline: Wednesday, December 2, 2026 , no later than 4:59 pm Anticipated Award of Project: January 8, 2027 Inquiries All inquiries related to this RFP should be submitted through the OpenGov portal and submitted no later than 5:00 pm on Thursday, October 29, 2026 . Inquiries may not be considered if not received by then. DVRPC will respond to questions it considers appropriate to the RFP and of interest to all Proposers, but reserves the right, at its discretion, to amend or not respond to any question. Responses posted on DVRPC’s procurement portal become part of the RFP upon posting. DVRPC reserves the right, in its discretion, to revise questions and responses to questions after posting, by posting the modified response. No oral response to any Proposer question by any DVRPC employee or agent shall be binding on DVRPC or in any way considered to be a commitment by DVRPC. DVRPC considers any information submitted directly to DVRPC through a solicitation announcement to be confidential and proprietary. DVRPC’s Access to Records Policy may be viewed at www.dvrpc.org/Policies . Submission Information DVRPC will receive all proposals on behalf of the Project Sponsor. DVRPC will release all technical proposals to the Project Sponsor for their review and scoring following the submission deadline. The Proposer shall submit the following RFP proposal documents (Technical Proposal and Administrative "Budget" Proposal) in PDF format , as indicated below. Technical Proposal Submissions All elements of the Technical Proposal must be submitted in the OpenGov portal to their corresponding upload field (e.g., Cover Letter, Lead Consultant Staff, Project Teams, Project Schedule, etc). Administrative (Budget) Proposal Submissions The Administrative (Budget) Proposal must be submitted separately in the OpenGov portal to its respective upload field. The Administrative (Budget) Proposal shall remain separate and sealed until such time as the qualitative evaluation of all technical proposals is completed. In accordance with the Brooks Act, cost is not a factor of evaluation. Both the Technical and Administrative Proposal submissions are due no later than 4:59 pm EDT, Wednesday, December 2, 2026 . Technical and Administrative Proposals submitted after the submission deadline or that are non-responsive to any of the requirements of this RFP may be deemed disqualified and will therefore be ineligible for award. DVRPC assumes no responsibility for delays causing any proposal submission to be received after the above-referenced due dates and times. The Proposer bears all costs related to the preparation and submittal of its proposal(s). DVRPC reserves the right to award all or only part of the solicitation to one or more Proposers, and the right to cancel the RFP and make no award. Proposal Requirements Evaluation Criteria Negotiations for the award of the contract will be with the Proposer that best meets the evaluation criteria. DVRPC reserves the right to award in part or as a whole. DVRPC may reject all proposals. DVRPC further reserves the right to negotiate cost and scope elements with the leading Proposer(s). An evaluation committee consisting of representatives from the project sponsor will evaluate each responsive proposal and, at its discretion, recommend an awardee to the DVRPC Board. Criteria have been established to guide the evaluation of each responsive proposal. The following scoring criteria will be used to evaluate and rank proposals: Disadvantaged Business Enterprises The DBE subcontracting goal has been removed from the project. Therefore, there is no subcontracting goal on the contract. Digital Accessibility DVRPC requires that all final deliverables funded through TCDI be in compliance with any relevant federal, state, and/or local digital accessibility laws at the time of publication.

Published attachments
Addenda and notices
Public questions and answers
  • What degree of building and building system assessment will be expected in facilities that are shared with other city departments? (e.g. the 2nd Highway & Survey Districts, 6th Highway & 4th Survey, 7th Survey, etc.)

    For facilities that have a shared use with other departments, the scope of work will first assess whether the needs for StreetsDOT are being met in the existing facility.

  • Will the City provide existing facility drawings, building inventory records, prior condition assessments, utility data, maintenance records, and capital plans for all facilities? If not available, does the City wish to create them as part of this project and future use?

    StreetDOT will provide existing facility drawings and prior documentation about the building, if available. Site visits and interviews with maintenance staff will be a part of the consultant team's scope in order to collect additional information.

  • Has any facility-condition assessment work been completed within the last ten years that can be reviewed to establish the level of effort required and confirm the disciplines of required subject matter experts?

    StreetsDOT will provide building assessment documentation, if available.

  • How frequently does the City expect coordination meetings beyond the required DVRPC status meetings?

    StreetsDOT will establish a standing bi-weekly project management meeting between City staff and the consulting team.

  • Is the City currently using a Maintenance Management System for maintaining assets?

    No.

  • Will the City facilitate access to all facilities, including operationally sensitive sites such as the Traffic Operations Center and maintenance facilities?

    Yes, StreetsDOT will coordinate access to all facilities for the purpose of site visits for consultant team.

  • Is the consultant expected to perform ADA compliance evaluations at a planning level only, or develop detailed ADA deficiency inventories?

    No, this scope does not require detailed ADA deficiency inventories at each facility. Rather, the Master Plan will identify future actions/recommendations for each facility, which should note planning-level ADA accessibility issues.

  • Are there any facilities currently planned for closure, replacement, redevelopment, or relocation that should be considered baseline assumptions?

    There are some high level ideas about facility efficiencies that can be shared at the onset of the project, but they should not be considered as absolute requirements.

  • Will staffing projections, fleet replacement plans, and operational growth forecasts be available for analysis?

    Detailed growth forecasts will be not available at the start of this Master Plan; however, through stakeholder interviews and Leadership input, assumptions about future needs will be developed, which should be used to inform high level recommendations.

  • Is there an existing fleet electrification strategy or EV transition plan that should be incorporated into facility recommendations?

    The City has a Municipal Clean Fleet Plan (https://www.phila.gov/media/20211006130414/Philadelphia-Municipal-Clean-Fleet-Plan-202110.pdf). This Master Plan process will help identify the needs for EV parking at priority facilities.

  • To what level of analysis are consolidation and co-location alternatives expected to be developed?

    Consolidation and co-location alternatives can be considered following the initial evaluation of all facilities.

  • Does the City have space standards or workplace guidelines that should be used when evaluating administrative and operational space needs?

    There are some high level workplace guidelines, along with work space policies, that can be shared at the onset of the process; however, details will be developed as part of the Master Plan process.

  • What planning horizon assumptions should be used for the required 5-, 10-, and 20-year facility life-extension evaluations?

    This plan will provide the initial understanding of each facility structure and initiate future improvements by the City. The plan will identify structures that need immediate systems repair, partial facility replacement, and/or complete replacement that will contribute to the framework of an implementation plan.

  • What level of detail is expected in the ROI analysis for resilience, sustainability, and consolidation initiatives?

    High-level ROI analysis is expected to determine the monetary benefits from capital investment due to reduced maintenance costs for each facility.

  • Is there a specific tool that the City uses for its capital planning or can the consultant suggest a tool for use?

    The consultant team may make a recommendation for a capital planning tool that is specific for facilities.

  • What specific climate hazards should be evaluated as part of the resilience assessment (flooding, heat, severe storms, etc.)?

    Yes, the Master Plan should look at specific climate hazards, including, but not limited to the facility's flood risk and how severe weather can impact facility energy reliability, which could affect operations.

  • Are greenhouse gas reduction goals or energy-use reduction targets available that should be considered?

    The greenhouse gas reduction goals and municipal energy-use reduction targets are associated with the City's Climate Action Playbook: https://www.phila.gov/media/20210113125627/Philadelphia-Climate-Action-Playbook.pdf

  • Given the operational nature of most facilities, what level of public outreach participation is anticipated?

    Given the operational nature of the facilities, we anticipate that public engagement will be focused on understanding the relationship between facility operations and the surrounding communities, rather than soliciting public input on the technical or operational requirements of the facilities themselves. The intent is to identify opportunities to ensure that facility improvements and operations minimize adverse impacts and, where possible, provide benefits to surrounding communities. We recognize that the appropriate level and format of engagement may vary depending on the facility and its context. We encourage consultants to propose an approach that they believe will meaningfully engage nearby residents and other relevant stakeholders, inform the planning process, and satisfy TCDI's public engagement requirements. Proposals should identify anticipated engagement activities and associated level of effort.

  • Should we be assuming that the two required public engagement meetings be in person?

    We are open to considering different formats for public engagement, including virtual or hybrid options, depending on the proposed engagement approach and the needs of the communities being engaged. Consultants should propose the format they believe will be most effective in providing meaningful opportunities for public participation.

  • Are existing environmental reports (Phase I/II ESAs, asbestos surveys, lead-based paint surveys, etc.) available for review?

    StreetsDOT will provide existing reports, if available.

  • Will the City be organizing the locations for the public meetings as well as the logistics for set up and clean up?

    StreetsDOT will organize the location for public meetings, and will support in the set up and clean up for public meetings.

  • Are multilingual/ADA outreach materials anticipated as part of the engagement process, will the City provide these resources or should the consultant account for them in the proposal?

    Depending on the resulting public engagement plan, multilingual and ADA outreach materials may be required, however, StreetsDOT will provide that support.

  • Is the City expecting a GIS-based facility database and mapping deliverable, or are static maps sufficient? If GIS, what system does the City use?

    The consultant team will not be responsible for a GIS-facility database, static maps will be sufficient.

  • What format is preferred for the Facility Profiles and Capital Needs Database/Matrix (Excel, GIS, Power BI, etc.)?

    The Facility Profiles and Capital Needs Matrix is to be in Excel format.

  • Are editable CAD, GIS, or BIM files expected as part of the final delivery package?

    Editable CAD, GIS, or BIM files are not expected for this project.

  • Does the City have document accessibility standards beyond standard ADA and TCDI digital accessibility requirements?

    There are no other known digital accessibility requirements.

  • Are there budget limitations or specific times of day that should guide the level of effort associated with site assessments and access to the facilities?

    StreetsDOT will coordinate with its staff and consultant team to schedule site visits/assessments. Typical hours would be 8AM to 4PM, during weekdays.

  • Please confirm whether the consultant and/or subconsultants selected to prepare the Transportation Facilities Master Plan will remain eligible to compete for subsequent architectural, engineering, programming, design, or implementation assignments associated with the facilities or improvements identified in the Master Plan, whether implemented by the City, another City department or agency, a public authority, or other public entity. Please also confirm whether participation in this study would preclude or otherwise restrict participation in any such future assignments.

    Award of this contract does not, in and of itself, preclude the selected consultant or its subconsultants from competing for future architectural, engineering, design, or implementation assignments related to facilities or improvements identified in the Master Plan. However, DVRPC cannot make any representation regarding eligibility for future procurements. Eligibility for any future assignment will be determined by the subsequent procuring entity (whether the City of Philadelphia, another City department or agency, a public authority, or other public entity) in accordance with its own procurement policies and applicable federal, state, and local requirements, including those governing organizational conflicts of interest. In particular, under 2 CFR 200.319(b), “contractors that develop or draft specifications, requirements, statements of work, or invitations for bids must be excluded from competing on those procurements.” Proposers should consider these requirements when assembling their teams, as they may affect eligibility for future procurements related to the facilities or improvements identified in the Master Plan.

  • Given the $200,000 project budget and approximately 18 facilities included in the scope, would the City accept the scope to focus on delivering a high-level planning document that identifies major facility and operational needs, establishes overall improvement priorities, develops planning-level costs, and provides a phased capital strategy? Or is the expectation a more detailed facility-by-facility, informed by a multidisciplinary assessment that identifies specific deficiencies and operational needs, evaluates facility-specific improvement alternatives, develops recommended improvement strategies and packages, establishes planning-level costs, and defines projects sufficiently to support prioritization and the City's capital program? Please clarify the intended level of development within the stated project budget.

    The scope of work is to deliver a high-level planning document that identifies priority operational and facility needs for each building, along with planning level costs for priority needs. (Note, for facilities that have a shared use with other departments, the scope of work will first assess whether the needs for the StreetsDOT are being met in the existing facility.) Multi-disciplinary input should inform the operational and facility needs.