Underground Utility District 38 Overhead-to-Underground Service Conversions

Description

AMP is completing the conversion of overhead electric facilities within UUD-38 to underground service. Underground service lateral conduits have already been installed to the affected properties. The Work under this Contract consists primarily of site assessment and owner coordination; preparation of a location-specific Conversion Strategy Plan; furnishing, pulling, installing and terminating service conductors; modifying the existing service entrance as required to convert from overhead to underground; minor restoration; and associated closeout documentation. SCOPE OF WORK General The Contractor shall furnish all labor, supervision, tools, equipment, materials, incidental items, coordination, documentation, and other work necessary to complete 195 residential overhead-to-underground service conversions, except work expressly identified as being performed or furnished by AMP or others. The Contractor shall verify field conditions and shall not rely solely on photographs, record drawings, preliminary concepts, or other reference information. Existing Underground Service Laterals AMP has previously installed underground service lateral conduit from AMP secondary/service boxes toward the affected properties. AMP will provide the UUD-38 as-built electrical trench design drawing as a Reference Document. Based on AMP's current Service Conversions worksheet, 189 standard service lateral locations total approximately 8,082 LF and 6 service lateral locations installed with 3-inch conduit total approximately 307 LF, for approximately 8,389 LF overall. The as-built drawing and conduit-size information are provided for bidding and planning. They do not establish the required conversion method, existing service rating, required conductor size, suitability of existing customer-owned equipment, or actual field condition. In particular, AMP does not represent that the 189 standard service lateral locations are 200A or less, nor that the 6 locations with 3-inch conduit have a particular service rating. The Contractor shall verify conditions before installation. Extension or Relocation of Existing Service Lateral Stub-Up The existing underground service lateral stub-up is intended to be used as installed wherever reasonably practicable. If the Contractor determines during the site assessment that the stub-up location cannot reasonably support a compliant and practical conversion, the Contractor shall identify the condition and the proposed extension or relocation in the Conversion Strategy Plan (CSP) . No excavation, extension, or relocation of the existing stub-up shall proceed without prior written authorization from AMP. When authorized, the work shall be paid under Bid Item 10. This optional work is intended for rare locations where physical modification of the previously installed underground lateral is necessary; it does not apply merely because another conversion method would be more convenient to the Contractor. The Contractor shall use the existing stub-up when a compliant, practical conversion can reasonably be completed without relocating it. Existing Service Rating AMP has not independently verified the existing electrical service rating at each property. The Service Location Information therefore identifies the existing service rating as Contractor to Verify unless a rating is specifically shown. As part of the site assessment and CSP, the Contractor shall verify the existing service equipment rating, terminal/conductor compatibility, available conductor and bending space, and other relevant equipment characteristics, and shall identify the proposed service conductor size and material. Conductor sizing shall be based on the verified existing service rating, conductor material, installation conditions, service lateral length, applicable voltage-drop criteria, equipment ratings, and applicable code requirements. The conversion is not intended to require additional service capacity or future 200A capability where doing so would force replacement or modification of otherwise serviceable customer-owned equipment. The proposed conductor size and material shall be documented in the CSP and validated with AMP and the City Building Division as required by the project permit/inspection process. Service Conductor Material Unless otherwise approved or required, service conductors shall be aluminum . Copper conductors shall be used only where required because of equipment listing, terminal compatibility, available conductor/bending space, physical fit, or another condition that prevents compliant installation of aluminum conductors. The Contractor shall identify any proposed use of copper conductors in the CSP and obtain AMP approval before installation. Copper shall not be substituted solely at the Contractor's preference when an approved aluminum installation is feasible. Site Assessment and Conversion Strategy Plan Before construction at each location, the Contractor shall perform a site assessment and prepare a Conversion Strategy Plan (CSP) using AMP's form. The CSP shall document the existing service configuration, proposed conversion method, proposed routing, conductor size, anticipated visible impacts, special conditions, and photographs/sketches as appropriate. Where more than one compliant conversion method is feasible, the Contractor shall recommend the method that minimizes property-owner disruption, visual impact, and inconvenience while also minimizing overall cost to AMP. The final conversion method is subject to AMP approval. No conversion work shall begin until AMP has approved the CSP, except for preliminary investigation expressly authorized by AMP. Preliminary AMP Conversion Concepts AMP may provide a preliminary, non-binding conversion concept for individual locations based on available photographs, records, and prior observations. Such information is provided for bidding and planning only. The Contractor remains responsible for field verification, code compliance, constructability, and the final recommendation through the CSP. Existing Customer-Owned Equipment Existing meter sockets, meter-main equipment, service panels, and associated customer-side service equipment are customer-owned. The purpose of this Project is to convert the existing electric service from overhead to underground by modifying the service-conductor routing and associated raceway/connection configuration. The Project is not intended to constitute replacement, upgrade, enlargement, or modernization of the existing customer service equipment. Existing customer-owned service equipment shall therefore be retained and reused where it can safely continue in service and where it is suitable for the approved overhead-to-underground conversion. New work performed as part of the conversion shall comply with applicable code, listing, manufacturer, AMP, and City requirements. The Contractor shall not replace, relocate, enlarge, or upgrade existing customer-owned meter or service equipment at AMP expense solely to provide additional capacity, modernize the installation, or bring otherwise acceptable existing equipment into conformance with requirements applicable to a completely new service installation. If the City Building Division determines that existing equipment cannot safely or legally remain in service as part of the proposed conversion, the Contractor shall stop work at that location, notify AMP, and obtain written direction before performing corrective or replacement work. AMP-directed replacement or significant modification of existing service equipment, when authorized, will be administered under the Bid Item 11 allowance. Separately requested and privately funded customer panel upgrades are governed by Section 1.16. Typical Conversion Methods The typical service-conversion methods for this Project are shown in Appendix B – Typical Service Conversion Options . The Contractor shall evaluate actual field conditions at each service location and recommend the proposed conversion method in the location-specific Conversion Strategy Plan (CSP). Where more than one compliant method is practical, the Contractor shall generally use the first practical and compliant method in the following order of preference: Direct bottom entry into existing meter/service equipment; Direct side entry into existing meter/service equipment; Existing service-entrance raceway intercept using an AMP-approved sealable conduit body or fitting ; AMP-approved meter adapter ; Sealable pull/termination box ; and Weatherhead-to-weatherhead conversion . A lower-priority method may be proposed where justified by actual field conditions, equipment compatibility, available space, constructability, property-owner impacts, restoration requirements, or overall cost to AMP. The Contractor shall identify the reason for selecting a lower-priority method in the CSP. The final conversion method is subject to AMP approval. Existing meter sockets, meter-main equipment, service panels, and associated customer-owned service equipment shall be retained and reused wherever reasonably feasible and where the City Building Division determines that the equipment can safely remain in service as part of the overhead-to-underground conversion. The intent of this Project is to modify the routing and connection of the existing electrical service from overhead to underground, not to replace, enlarge, upgrade, or modernize otherwise serviceable customer-owned service equipment. Replacement or significant relocation of existing meter or service equipment is therefore a last-resort condition , is not a standard conversion method, and shall not proceed at AMP expense without prior written AMP authorization. Extension or relocation of an existing underground service-lateral stub-up is supplemental work and shall be considered only where a practical and compliant conversion cannot reasonably be accomplished using the existing stub-up location. Conduit bodies, including LB, LL, LR, or similar fittings, may be used for the approved raceway-intercept method where they are appropriately listed and sized for the conductors, suitable for the installation, accessible after completion, and approved by AMP through the CSP. Long-sweep bends shall be used where reasonably feasible. The Contractor may propose another compliant conversion method where none of the methods identified above is reasonably suitable. Any alternate method requires AMP approval through the CSP before construction. 3.7.1 Appendix B and Legacy Details Appendix B includes certain drawings and details developed for prior AMP underground-conversion programs. Legacy notes concerning property-owner responsibilities, materials, permitting, inspection procedures, or other administrative requirements may no longer apply. The current Contract Documents, Special Conditions, and approved CSP govern over conflicting legacy notes. AMP may issue an updated service-conversion standard or revised detail set to remove or clarify obsolete notes. AMP expects the conversion methods and general method-selection priority stated above to remain substantially unchanged. Any revision issued before Bid opening will be incorporated by Addendum. After award, any revision that materially changes the Contractor's scope, cost, or Contract Time will be administered in accordance with the Contract provisions governing changes. 8.9.1 Weatherhead-to-Weatherhead Conversion Materials Where the weatherhead-to-weatherhead conversion method is approved through the location-specific CSP, the Contractor shall furnish and install a complete, code-compliant conversion using the requirements below. The final configuration, conductor size, conduit size, routing, and connection details are subject to AMP and City Building Division approval. Service Riser. The new exposed service riser shall be threaded rigid metal conduit (RMC), 2-inch trade size minimum. Larger conduit, including 3-inch conduit where required, shall be provided as necessary for conductor size and quantity, conduit fill, bending space, equipment compatibility, listing requirements, or other applicable installation conditions. Weatherhead / Service Head. The new weatherhead or service head shall be a new listed fitting suitable for the raceway size, conductors, and wet-location exposure. No specific manufacturer is required unless otherwise identified in the Contract Documents. Fittings and Couplings. Raceway fittings and couplings shall be threaded and suitable for the installation. Compression fittings or compression couplings are not permitted for the service riser. Conductor Connections. Connections or splices between the new and existing service conductors shall use listed connectors suitable for the conductor sizes, conductor materials, and location. Where aluminum and copper conductors are joined, connectors shall be specifically listed for the conductor materials used. Connections shall be protected from weather and moisture as required by the connector listing and applicable code. Conductor Tails. Service conductors shall extend a minimum of 18 inches beyond the weatherhead/service head unless a different length is specifically approved by AMP for the installation. Support, Bonding, and Weatherproofing. Raceway supports, clamps, bonding, grounding, sealing, drip-loop configuration where applicable, and protection from water entry shall comply with the current California Electrical Code, City of Alameda requirements, AMP requirements, and the listing and installation instructions for the materials used. Penetrations. Roof, eave, soffit, siding, or other building penetrations shall be sealed and weatherproofed. Where the approved method requires a roof overhang/eave penetration, compensation shall be in Service Conductors The Contractor shall furnish, pull, install, and terminate service conductors from the AMP secondary/service box or designated service point to the existing customer meter/service equipment, unless otherwise directed by AMP. The Contractor shall determine the proposed conductor size based on the verified existing service rating, conductor material, service lateral length, voltage drop, compatibility with existing customer-owned service equipment, and applicable code requirements. The Contractor shall coordinate with AMP and City Building inspectors to validate conductor sizing as required by the project-specific permit and inspection process. AMP does not intend to increase the customer's service capacity as part of this Contract unless specifically authorized by AMP. Copper conductors shall be used only where AMP determines that aluminum cannot be installed in a compliant manner because of equipment listing or terminal compatibility, available conductor/bending space, physical fit, or another documented installation condition. Proposed use of copper shall be identified in the CSP and approved by AMP before installation. Copper shall not be substituted solely at the Contractor's preference when a compliant aluminum installation is feasible. Bid Item 4A provides the incremental price adjustment for authorized copper conductors. Weatherhead and Overhead Service Removal The Contractor shall remove abandoned customer-side overhead service entrance components made unnecessary by the approved conversion, including the weatherhead and associated raceway to the extent shown in the approved CSP. Openings shall be capped, sealed, patched, and weatherproofed in a neat and workmanlike manner. Where AMP approves leaving a portion of an existing raceway in place to minimize disturbance, the remaining portion shall be safely capped and made weather-tight. Roof Overhang / Eave Penetration Where an approved weatherhead-to-weatherhead conversion requires the new service raceway to pass through an existing roof overhang, soffit, or eave, the Contractor shall identify the condition in the CSP. The applicable bid adder includes additional labor, fittings, cutting/drilling, flashing or sealing, weatherproofing, and minor finish restoration associated with the penetration. Significant concealed deterioration, hazardous materials, or structural reconstruction is excluded unless separately authorized by AMP. Existing Communications Facilities The Contractor shall minimize disturbance to existing telephone, cable television, fiber, and similar communications facilities. Minor relocation of existing surface-mounted communications boxes and associated wiring is included in the Standard Service Conversion when necessary to accommodate the approved electrical work and when the box or wiring can be repositioned a short distance on the same general mounting surface without disconnecting, splicing, extending, replacing, or otherwise modifying the communications service. The Contractor shall restore mounting penetrations resulting from such minor relocation. If a communications facility cannot reasonably be relocated without disconnecting, splicing, extending, replacing, or materially modifying the communications service, the Contractor shall notify AMP and obtain direction before proceeding. Property Owner Contact and Coordination Following award, AMP will provide the Contractor with available property-owner contact information for the service locations. The information is provided for coordination purposes and may be incomplete, outdated, or inaccurate. The Contractor shall perform routine owner coordination, including scheduling site visits, explaining the proposed CSP when reasonably possible, coordinating access, and scheduling the conversion. The Contractor shall document contact attempts. If the Contractor is unable to contact an owner after at least two reasonable documented attempts using available contact information, or determines that the information supplied by AMP is inaccurate or unusable, the Contractor shall notify AMP. AMP will provide reasonable assistance in attempting to establish contact or provide updated information when available. The Contractor is not required to make repeated or extraordinary attempts to locate an unresponsive owner. AMP will determine how to proceed when reasonable contact efforts have been unsuccessful, including whether to defer the location or authorize work to proceed where property-owner participation is not required. Property Owner Acknowledgment Where reasonably obtainable, the Contractor shall obtain the property owner's acknowledgment that the proposed work has been explained and the owner has had an opportunity to ask questions. Owner acknowledgment does not transfer design responsibility to the owner and does not authorize the owner to require work beyond the Contract scope. Customer-Requested Service Panel Upgrades AMP has identified 37 properties where the property owners have expressed interest in receiving an individual quotation for replacement or upgrade of their existing customer-owned electrical service panel in conjunction with the overhead-to-underground service conversion. These properties will be identified in Appendix C under the field 'Panel Upgrade Quote Requested.' Identification of a property does not obligate the owner to proceed with an upgrade. For each property identified in Appendix C as requesting a panel-upgrade quotation, the Contractor shall evaluate the existing service equipment and provide the property owner with an individual written quotation for the requested panel upgrade or replacement after award. Because site conditions and required work vary by property, quotations shall be property-specific. The Bidder shall not submit a unit price, lump-sum price, or other competitive bid price for customer-requested panel upgrades in the Bid Schedule. Preparation of the individual quotations and ordinary coordination necessary to provide them shall be incidental to the AMP Contract and shall not be separately compensated by AMP. Any customer-requested panel upgrade is separate from the AMP Contract. The property owner may accept or reject the Contractor's

Published attachments
Addenda and notices
  • Official Notice #1: Mandatory Pre-Bid Meeting this Thursday 11/5/26 · 1

    This is a friendly reminder that we will have a mandatory pre-bid meeting on 11/5/26 at 1pm (Pacific Standard Time). This is virtual and link to the meeting is provided in the Timeline of the IFB. We take attendance and all bidders must participate in the meeting in order for them to submit the bid. Otherwise, those who do not attend the meeting will be disqualified. We look forward to meeting with you virtually then.

  • Addendum #1 · 1

    Addendum #1 - Prebid Meeting Attendance Thank you for participating in the meeting.

  • Addendum #2 · 2

    Please use the See What Changed link to view all the changes made by this addendum.

  • Official Notice #2: Reminder of Bid Due tomorrow 11/25/2026 at 9:00am PST · 2

    Friendly reminder of bid due - at 9:00am in Pacific Standard Time on Wednesday, November 25, 2026. We strongly suggest that all bidders start submittal process early in case of any system issues, glitches, or any unforeseen event.

  • Addendum #3 · 3

    Clarification and performance requirements for Small and Large Pull/Termination Boxes

  • Addendum #4 · 4

    Addendum#4 - Revised service-conductor pricing, standard conductor-set definitions, multi-meter/non-standard conductor material allowance, and conforming Bid Schedule clarifications. Please use the See What Changed link to view all the changes made by this addendum.

Public questions and answers
  • Is there an engineer's estimate or budget/range for this project?

    AMP is not providing an Engineer’s Estimate or project budget range as part of this solicitation. Bidders are responsible for developing their own independent pricing based on the Contract Documents, Bid Schedule quantities, appendices, reference information, and applicable addenda. If a bidder believes additional information is necessary to reasonably price a specific portion of the Work, the bidder should submit a question through OpenGov by the stated question deadline.

  • Please provide project address.

    The project is located in the City of Alameda, CA. There are 195 contiguous residential addresses which are listed in Appendix C.

  • Please confirm that all underground conduits are completed based on the Asbuilt plan.

    Yes. The as-built plan accurately shows the installed service conduit.

  • Please furnish the details and approved materials for the weather head to weather head conversion.

    Appendix B, Section B.8 provides the representative configuration for the weatherhead-to-weatherhead conversion. Addendum 2 clarifies the project-specific material requirements for this method, including a minimum 2-inch threaded rigid metal service riser, with larger conduit where required by the installation. Bidders should use the addendum requirements for pricing. The City of Alameda Residential Electrical Services requirements are also available as a general reference; where general City guidance conflicts with the project-specific Contract Documents, the Contract Documents govern.

  • What is the size of the small Pull/Termination boxes?

    AMP will issue Addendum #3 establishing performance requirements for the pull/termination boxes. For bidding purposes: Small Pull/Termination Box: 8 in. × 12 in. × 4 in. minimum. Large Pull/Termination Box: 12 in. × 26 in. × 6 in. minimum. The stated dimensions are minimums. The Contractor shall provide a larger enclosure where required by conductor size or quantity, raceway size or configuration, conductor bending space, splice/connector configuration, equipment listing, or applicable California Electrical Code requirements. For bid-evaluation purposes, locations with three or more meters are classified under the Large Pull/Termination Box Bid Item. The final enclosure size shall be verified for each installation and identified through the CSP. The Large Pull/Termination Box unit price shall include reasonable upsizing necessary for a typical residential or multi-meter service conversion. Unusually large or specialized enclosures resulting from unforeseen conditions may be considered extra work only when authorized by AMP in advance.

  • What is the size of the big Pull/Termination boxes?

    AMP will issue Addendum #3 establishing performance requirements for the pull/termination boxes. For bidding purposes: Small Pull/Termination Box: 8 in. × 12 in. × 4 in. minimum. Large Pull/Termination Box: 12 in. × 26 in. × 6 in. minimum. The stated dimensions are minimums. The Contractor shall provide a larger enclosure where required by conductor size or quantity, raceway size or configuration, conductor bending space, splice/connector configuration, equipment listing, or applicable California Electrical Code requirements. For bid-evaluation purposes, locations with three or more meters are classified under the Large Pull/Termination Box Bid Item. The final enclosure size shall be verified for each installation and identified through the CSP. The Large Pull/Termination Box unit price shall include reasonable upsizing necessary for a typical residential or multi-meter service conversion. Unusually large or specialized enclosures resulting from unforeseen conditions may be considered extra work only when authorized by AMP in advance.

  • Please furnish the approved type of meter adaptor.

    Where a meter-adapter conversion is approved through the CSP, the meter adapter shall be a utility-grade meter socket adapter specifically suitable for an overhead-to-underground service conversion and compatible with the existing meter socket, meter configuration, service rating, and proposed conduit entry. For bidding purposes, the following products are acceptable as a basis of design where suitable for the specific installation: Cooper B-Line MARR20L45GRSD, 160A; or Ekstrom/Brooks 722B, 175A, with the appropriate left, right, or bottom hub configuration; or an AMP-approved equal. The Contractor shall verify that the proposed adapter is appropriately rated and compatible with the existing service equipment before installation. Use of a meter adapter is subject to AMP approval through the CSP. An adapter shall not be used where its rating, configuration, listing, or physical compatibility is unsuitable for the existing service. The Contractor shall submit manufacturer data for each proposed meter-adapter type for AMP review and approval before installation. Meter adapters shall not be used on services exceeding the manufacturer's applicable rating. Where an approved meter adapter is not available or appropriate for the verified service, the Contractor shall use another approved conversion method in accordance with the Appendix B priority.

  • Where can we find the size of feeder cables for every unit?

    AMP does not have a verified service-conductor size for each individual service location, and Appendix C does not provide verified service ratings or conductor sizes. To provide a common and competitive bidding basis, AMP is revising the Bid Schedule to provide separate pricing for a complete #2 aluminum service-conductor set and a complete 4/0 aluminum service-conductor set. Each standard bid set consists of two ungrounded conductors and one full-size neutral of the same size, using 600-volt Type XHHW-2, stranded AA-8000-series aluminum alloy conductors. The revised Bid Schedule also provides a separate pricing mechanism and a $40,000 AMP-fixed conductor-material allowance for multi-meter or otherwise non-standard service configurations. The evaluation quantities are provided solely for bid comparison and are not guaranteed or address-specific service determinations. The Contractor shall verify the existing service rating and applicable field conditions during the site assessment/Conversion Strategy Plan (CSP) process. The final conductor size and material shall be based on the verified existing service rating, service-lateral length, voltage-drop requirements where applicable, equipment ratings and compatibility, and applicable code requirements. Payment will be based on the conductor configuration actually approved through the CSP in accordance with this Addendum and the Contract Documents.