Carroll Creek Stream Restoration - CIP# 350007 (MWBE Goals)
Description
The City of Frederick (City) is seeking bids from qualified vendors to provide construction services for a Stream Restoration plan at Carroll Creek in the City of Frederick. The project consists of tree planting, grading, landscaping, and installation of rock sills, riffles/pools, and other stream stabilization measures in the existing Carroll Creek west of Monocacy Boulevard, along with associated erosion and sediment control measures. Construction stakeout survey controls (only) will be provided by the Owner. Construction Materials Testing and Inspections to be provided by the Contractor. As-Builts shall be provided by the Owner. The permit includes requirements self-inspection and record keeping - the Contractor SHALL BE responsible for providing the City of Frederick with inspection reports as outlined in the permit. SCOPE OF WORK and SPECIFICATIONS Carroll Creek Stream Restoration Scope of Work Information for Bidders: It is the intention of the City of Frederick to bid this project Carroll Stream Restoration, as one complete project. Construction stakeout survey controls only will be provided by the Owner. The Contractor shall carefully preserve benchmarks, property line and corner survey markers, monuments, location reference points and stakes (collectively, “reference points”). The Contractor shall be responsible for any mistakes or expense that may be caused by the loss or disturbance of any reference points, including, without limitation, the cost to remove and reconstruct improvements constructed by the Contractor in the wrong location. If any such reference point is removed, displaced, damaged, or destroyed, it shall be accurately replaced at the Contractor's expense by a person appropriately licensed by the State of Maryland for Land Surveying before completion of the Work, all subject to the approval and acceptance of the Engineer. Construction Materials Testing and Inspections to be provided by the Contractor. The Contractor shall be responsible for coordinating with the Inspection Consultant to schedule all necessary inspections and testing. Inspections and testing shall be required for all activities including but not limited to; grading, placement of fill, compaction, placement of asphalt, etc. The City and the Inspection Consultant shall meet with the Contractor prior to construction to establish required testing and inspections. As-Builts shall be provided by the Owner. Upon substantial completion, the Owner shall authorize their Consultant to complete the As-Builts. As-Builts shall be utilized in addition to Inspection and Testing reports to determine that work has been completed in accordance with the plans and specifications. Contractor is responsible for keeping record documents identifying any changes to the plans which occurred during construction. Contractor shall provide a copy of these record documents to the City upon request and at the time of As-Built preparation. The permit includes requirements self-inspection and record keeping. The permit also incorporates a section from EPA’s general permit language that states that a permittee must select, install, implement and maintain control measures at a construction site thatminimize pollutants in the discharge as necessary to meet applicable water quality standards and that, in general, the stormwater controls developed, implemented, and updated consistent with the laws and regulations cited in the general permit are considered as stringent as necessary to ensure that discharges covered by this permit do not cause or contribute to an excursion above any applicable water quality standard. The Contractor SHALL BE responsible for providing the City of Frederick with inspection reports as outlined in the permit. The inspections shall be completed on the inspection forms provided and shall, at a minimum, meet the following requirements: Monitoring and Records: For the purposes of monitoring, a permittee must do all of the following: During construction, maintain at the site the approved erosion and sediment control plan, the approved stormwater management plan, a copy of this General Permit, a copy of the NOI application and a copy of the NOI approval form. During the entire period of permit coverage, for all active and inactive sites, conduct inspections of the permitted area at the following intervals: Weekly; The next day after a rainfall event resulting in runoff; and As required in Part IV.B. Maintain at the site written reports of all inspections conducted by the permittee. The permittee shall use the standard written report form as provided by MDE. The permittee shall complete all applicable portions of the form and may attach additional information to the form. The permittee shall ensure that the report includes: the date and time of the inspection; the name(s) of the individual(s) who performed the inspection; whether significant amounts of sediment were observed as described in Part IV.B, Prevention of the Discharge of Significant Amounts of Sediment, above.; an assessment of the condition of erosion and sediment controls and how any deficiencies were or are being addressed; a description and date of any erosion and sediment control implementation and maintenance performed, including identification of any controls that have not been installed as required; and a description of the site's present phase of construction. D. Maintain pertinent data related to the NOI (including all data used to complete the NOI), self-inspection reports and inspection reports and enforcement actions issued to the permittee by the appropriate enforcement authority, including but not limited to all calibration and maintenance records and all original strip chart recordings for continuous monitoring instrumentation, for a period of three (3) years from the date that the site is permanently stabilized as follows: Permittees must retain the records described in Part IV and V and records of all data used to complete the NOI to be covered by this permit. Maintain at the site written reports of all inspections conducted by the permittee as required by Part IV. C. Maintain all inspection reports and enforcement actions issued to the permittee from any appropriate enforcement or approval authority, including MDE, the delegated enforcement authority, or the U.S. Environmental Protection Agency. Records of monitoring information must include: The date, exact place, and time of sampling or measurements; The individual(s) who performed the sampling or measurements; The date(s) analyses were performed; The individual(s) who performed the analyses; The analytical techniques or methods used; and The results of such analyses. E. Ensure that samples and measurements taken for the purpose of monitoring are representative of the monitored activity. F. It is incumbent on the contractor to make themselves familia CHANGES TO CITY STANDARD ENGINEERING SPECIFICATIONS AND CONSTRUCTION DETAILS CHANGES TO CITY STANDARD ENGINEERING SPECIFICATIONS AND CONSTRUCTION DETAILS The work shall conform to the applicable sections of The City of Frederick Standard Construction Specifications (City Specifications) and Standard Construction Details (City Standards), available at https://www.cityoffrederickmd.gov/1320/City-Charter-Codes-Ordinances-and-Resolu , with the following changes. GP-2.04 SITE INVESTIGATION Add the following: Subsurface Information. Boring logs and other subsurface information made available for the inspection of bidders were obtained with reasonable care and recorded in good faith by the Owner. The subsurface information shown was obtained for Owner’s design and estimate purposes. It is made available to bidders so that they may have access to the same information available to the Owner. It is presented in good faith, but as with all subsurface information it represents only a small fraction of the total volume of material at the site. The soil and rock descriptions shown are as determined by a visual inspection of the samples from the various explorations unless otherwise noted. The observed water levels and/or water conditions indicated thereon are as recorded at the time of the exploration. These levels and/or conditions may vary considerably, with time, according to the prevailing climate, rainfall, and other factors. Interpolation between data points may not be indicative of the actual material to be encountered. Existing utilities are shown, on the drawings, from the best available data and may not represent all facilities present or may not represent facilities at their actual location. The locations of utilities or other underground man-made features were ascertained with reasonable care and recorded in good faith from various sources, including the records of municipal and other public service corporations, and therefore the location of known utilities may only be approximate. The Contractor shall be responsible for notifying Miss Utility at 1-800-257-7777 to locate existing facilities. The Contractor is also responsible for performing test pits as needed to confirm the locations and elevations of existing utilities prior to excavation activities. Test pits will be conducted at the Contractor’s expense and shall be considered incidental to other work performed. The Contractor is also advised that the drawings may not represent all surface features that may exist within the area of work, such as fences, shrubs, trees sheds, etc. The Contractor will be responsible for minimizing the disturbed area and for restoring all disturbed or destroyed features. GP-2.07 PROPOSAL PREPARATION Add the following: A. Bids which, in the opinion of the City or Engineer, are not properly balanced among the bid items may be rejected. END SECTION GP-2 SECTION GP-4 SCOPE OF WORK GP-4.02 GENERAL PROVISIONS CONTROLLING Supplement with the following: In case of difference between small and large-scale drawings, the large-scale drawings shall govern. Schedules on any Contract documents shall take precedence over conflicting information on the Contract drawings. Omissions from the drawings or specifications or the misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work, but they shall be performed as if fully and correctly set forth and described in the drawings and specifications at no additional cost to the Owner. Calculations shall be made for missing dimensions. Figures marked on drawings shall in general be followed in preference to scale measurements. The Contractor shall check all drawings furnished him immediately upon their receipt and shall notify the City Engineer of any discrepancies. The Contractor and City Engineer shall compare all drawings and verify the figures before laying out the work. The Contractor will then be responsible for any errors which might occur resulting from said layout. Standard Details are applicable when listed, bound with the specifications, noted on the drawings, or referenced elsewhere in the specifications. Where the notes on the drawings indicate modifications, such modifications shall govern. All documents and publications (such as, but not limited to, manuals, handbooks, codes, standards, and specifications) which are cited in this Contract for the purpose of establishing requirements applicable to equipment, materials, or workmanship under this Contract, shall be deemed to be incorporated herein as fully as if printed and bound herewith. GP-4.03 VARIATIONS IN ESTIMATED QUANTITIES Subsection GP-4.03 of the Specifications, titled "Variations in Estimated Quantities' will not apply to those construction items listed or identified in this Contract Document, and shall be deleted in its entirety. This Section shall be replaced with the following: All bid items listed in the Bid Schedule shall be considered as contingent items, with the quantities provided considered as contingent quantities, whether or not the items or quantities are specifically identified as contingent items or quantities. CONTINGENT ITEMS Construction items identified in these Special Provisions as being Contingent are provided in the contract for use when and as directed by the City Engineer. The quantities for these items shown on the plans and/or the Proposal, are established for the purpose of obtaining a bid price. The quantities for these Contingent items may be increased or decreased without any adjustment to the contract unit price by the Owner or City Engineer without negotiation. The Contractor will not be allowed to submit a claim against the City for any adjustment to the contract unit price bid, should the Contingent item(s) be increased, decreased, or eliminated entirely. Payment for any contingent item(s) used, will be made on the basis of the quantities GENERAL CONDITIONS These General Conditions apply to all City of Frederick (City) Solicitations, including but not limited to, Invitations to Bid (ITB), Request for Proposals (RFP), Request for Quotes (RFQ), and any other procurement (“Solicitation”) issued by the City. The terms Vendor, Contractor, Offeror, and Bidder are used interchangeably throughout the these General Conditions and the Solicitation documents, and each refers to any individual, firm, partnership, corporation, or other entity that submits a Response to a Solicitation. The term Response refers to any submission made by a Vendor in reply to a Solicitation. These General Conditions are intended to apply regardless of the evaluation method used, including low-bid, best value, or qualifications-based selection. NON-DISCRIMINATION The City of Frederick (City) does not discriminate on the basis of race, color, religion, sex, national origin, age, marital status, veteran status, disability, sexual orientation, gender identity, genetic information, or any other legally protected group in employment or in the provisions of services. INTERPRETATIONS Unless otherwise stated in the solicitation, any questions concerning conditions and specifications should be submitted in writing. CLARIFICATION AND ADDENDA TO SOLICITATION DOCUMENTS If any persons contemplating submitting a Response under this Solicitation are in doubt as to the true meaning of the specifications, Solicitation documents or any part thereof, they must submit questions in writing via the City of Frederick's OpenGov Portal no later than 3:00 pm am on Wednesday, November 11, 2026 . Any questions received after that time may or may not be answered at the City’s discretion. The City shall issue an addendum if substantial changes, which impact the technical submission of Responses, are required. In the event of conflict with the original Solicitation Documents, the Addendum shall govern over all other contract documents to the extent specified. Subsequent Addenda shall govern over prior addenda only to the extent specified. Addendum will be issued through the City's OpenGov Portal. Vendors are required to register for an account via the City's OpenGov Portal. Once registered, Vendors will receive addenda notifications to their email by clicking "Follow" on this project. The City will not be responsible for any other explanation or interpretation made verbally or in writing by any other City representative. Ultimately, it is the sole responsibility of each Vendor to periodically check the site for any addenda at the City's OpenGov Portal. SPECIAL CONDITIONS Any and all Special Conditions that may vary from these General Conditions shall have precedence. HEADINGS AND TERMS The headings to the various sections of this Solicitations have been inserted for convenient reference only and shall not in any manner be construed as modifying, amending, or affecting in any way the expressed terms and provisions hereof. Additionally, words such as contract/agreement and bidder/proposer/vendor may be used interchangeably in the various sections of this Solicitation and shall not in any manner be construed as modifying, amending, or affecting in any way the overall intent of the Document. DISCLAIMER The City may accept or reject, in whole or in part, for any reason whatsoever any or all submissions; re-advertise this Solicitation; postpone or cancel at any time this Solicitation process when it is in the best interest of the City to do so. Submissions that are not received on time or do not conform to the City’s requirements will not be considered. The City also reserves the right to contact a proposer for clarifications and may, at its sole discretion, allow a proposer to correct all formalities, informalities, and technicalities in the best interest of the City. The issuance of this Solicitation constitutes only a request to make submissions to the City. The City reserves the right to determine, at its sole discretion, whether any aspect of a submission satisfies the criteria established in this Request. The selection shall be based on the Response, which is in the sole opinion of the City, is in the best interest of the City. The final approval and recommendation for award of this Solicitation shall be in accordance with the City Purchasing Policies. Nothing in this Solicitation or accompanying documents submitted will create any contractual relationship between the City and proposer. The City assumes no obligations, responsibilities, and liabilities, fiscal or otherwise, to reimburse all or part of the costs incurred or alleged to have been incurred by parties considering a Response to and/or responding to this Solicitation. All such costs shall be borne solely by each proposer. The submission of a Response shall be prima facie evidence that the Vendor is familiar with and agrees to comply with the contents of this Solicitation. EXAMINATION OF DRAWINGS, CONTRACT DOCUMENTS AND PROJECT SITE Proposers shall thoroughly examine this Solicitation, and if applicable to this Solicitation, all other drawings, documents or other materials referred to herein and conduct investigations and site visits to completely understand the scope of project, project site conditions, and all other conditions relative to compliance with the Agreement. No plea of ignorance by the Vendor of conditions that exist or that may hereafter exist, as a result of failure or omission on the part of the Vendor to make said investigations and visits, and/or failure to fulfill in every detail the requirements of this Solicitation and the Agreement will be accepted as a basis for varying the requirements of the City or the compensation of the selected Vendor(s). SEALED BIDS The Vendor is required to carefully examine the specifications and be thoroughly informed regarding any and all conditions and requirements that may in any manner affect the work to be performed under the contract. No additional allowances will be made because of lack of knowledge of these conditions. It is further understood and agreed that each Vendor is solely responsible for all assumptions, deductions, or conclusions which they make or obtain from their examination of information made available by the City. Responses received after the closing time and date, for any reason whatsoever, will not be considered. Any disputes regarding timely receipt of Responses shall be decided in favor of The City of Frederick. COST OF PREPARATION OF RESPONSE The City will not be responsible for any cost incurred by any Vendor in the preparation of their Response. PROPRIETARY INFORMATION It shall be the Vendor’s responsibility to duly note on their submittal if any information in their submitted Response contains proprietary information and the context under which same should be handled by reviewers. Vendors shall not mark sections of their Response as proprietary or confidential if they are to be part of the award of the Contract/Agreemen
Published attachments
- CITY OF FREDERICK PERFORMANCE BOND
- CITY OF FREDERICK LABOR & MATERIALMENS BOND
- CITY OF FREDERICK MAINTENANCE BOND
- Stream Restoration Plan
- 1. 100% Carroll Creek Preliminary Opinion of Probable Cost
- 2026_04_Carroll_Creek_Stream_Restoration
- Carroll Creek CAD Files
- Ford Crossing
- Supplemental Specifications_2025_08_Carroll_Creek_SPECS
- Standard Contract Sample 2026
- Boulder Dimension Detail
- pGrading
- Tree Mat
- 2026_11_01_Carroll_Creek_Redlines
- Landscaping Clarifications
- Copy of Sill comps for carroll
- pGrading_Carroll
- Carroll_Creek_Stream_Restoration_-_CIP#_350007_(MWBE_Goals)_(Addendum_#21_Revision).pdf
Addenda and notices
Addendum #1 · 1
Stream Restoration Plan file added to Attachments. Please use the See What Changed link to view all the changes made by this addendum.
Addendum #2 · 2
Please use the See What Changed link to view all the changes made by this addendum. The question deadline has been extended for two weeks to 10/14/26 at 3pm, as well as the IFB due date to 10/30/26 at 3pm.
Addendum #3 · 3
Please use the See What Changed link to view all the changes made by this addendum. To update the quantity in line# 8 of the bid form from 10,000 to 19,500.
Addendum #4 · 4
Please use the See What Changed link to view all the changes made by this addendum. Line item #58 of the bid form has been removed per the design engineer. Two additional documents have been added as attachments.
Addendum #5 · 5
Please use the See What Changed link to view all the changes made by this addendum. Added access road and silt fence line-items to the bid form.
Addendum #6 · 6
CAD files and Ford Crossing detail added to attachments. Please use the See What Changed link to view all the changes made by this addendum.
Addendum #7 · 7
Supplemental Specifications added. Please use the See What Changed link to view all the changes made by this addendum.
Addendum #8 · 8
Please use the See What Changed link to view all the changes made by this addendum. To include a project schedule as a submission requirement.
Addendum #9 · 9
Please use the See What Changed link to view all the changes made by this addendum. To include a contingency line item to the bid form for Furnished Streambed Material per question# 64.
Addendum #10 · 10
Please use the See What Changed link to view all the changes made by this addendum. The bid submission due date has been extended an additional week to 11/6/26 at 3pm.
Addendum #11 · 11
Please use the See What Changed link to view all the changes made by this addendum. To extend the bid submission due date to 11/13/26 at 3pm, to include additional attachments, and to include additional line items.
Addendum #12 · 12
Please use the See What Changed link to view all the changes made by this addendum. To adjust line items on the bid form.
Addendum #13 · 13
Please use the See What Changed link to view all the changes made by this addendum. To include two additional documents to the attachments.
Addendum #14 · 14
Bid Form updated per Q&A. Please use the See What Changed link to view all the changes made by this addendum.
Addendum #15 · 15
Redline plans and landscaping clarifications added. Please use the See What Changed link to view all the changes made by this addendum.
Addendum #16 · 16
Timeline extended due to delayed posting of redline. Please use the See What Changed link to view all the changes made by this addendum.
Addendum #17 · 17
Please use the See What Changed link to view all the changes made by this addendum. To make changes to the bid form and add an additional document as an attachment.
Addendum #18 · 18
Please use the See What Changed link to view all the changes made by this addendum. Sbumission deadline extended an additional week to 11/25/26 at 3pm.
Addendum #19 · 19
Please use the See What Changed link to view all the changes made by this addendum. To update the bid form per the Q&A.
Addendum #20 · 20
Please use the See What Changed link to view all the changes made by this addendum. To extend the bid submission deadline another week, to 12/2/26 at 3pm.
Addendum #21 · 21
Please use the See What Changed link to view all the changes made by this addendum. To include an additional CAD file as an attachment.
Public questions and answers
Can the excess cut from this project be disposed of at the Frederick Landfill or must it go to a location figured by the contractor?
Please coordinate with them to confirm or locate another approved disposal site, the City will not be providing a disposal site.
The Landscape Plans show 2 Rows Soil Lifts at all locations where they are required. However, on the Stream Plans the pattern is drawn in a way that can be construed as having many more rows of soil lifts than 2. Please provide some clarification.
Soil lifts should be 18” thick compacted at 6” lifts on top of toewood (detail on sheet C-405). Soil lifts + toewood is 4’ from toe of slope. After two rows of soil lifts, contractors should tie into existing grade at 3:1 Slope.
Please clarify the locations for the curb/sidewalk/asphalt replacements and provide details for these items.
Answer: Locations of these items are specifically related to access including but not limited to: • Highland Street / Construction Access (Sheet C-117) • Farm Lane / E Church Intersection • Farm Lane Road (Sheet C-120) • Treatment Plan Road / Construction Entrance (Sheet C-121) • Treatment Plan Road / Construction Entrance (Sheet C-122) Contractor should document the existing conditions and repair these items back to the existing conditions unless otherwise directed by City.
Please provide a detail for what is expected of the temporary access road. Is it wood chips? Laminated deck mats? Etc.
Contractor may utilize laminated deck mats and/or mulch depending on specific site conditions along the access path and the equipment conveyed over the access path. Deck Mat Detail provided on sheet C-407. Selected contractor may submit an alternative.
Are Wash Racks required at every Stone Construction Entrance? If so, will Frederick provide access to adjacent hydrants for providing water? Or will the contractor need to provide their own?
Yes they are, the contractor will need to provide their own water, per step 4 of the Sequence of Construction.
Is 48" Orange Mesh Fence w/T-Posts acceptable as the "Safety Fence" on this project?
Safety Fence shall be installed in accordance with SECTION 104.20 of the Maryland Department of Transportation State Highway Administration Standard Specifications for Construction and Materials (July 2025).
Is the Contractor required to conduct and submit a redline/as-built survey to aid in the preparation of as-builts by the Owner, or will the survey be held by others?
Yes, performing the as-built survey to provide to the City to prepare the as-builts is part of the contract.
Can cuttings of the approved species be used in lieu of Bare Root in the Branch layering? The chart on page L-112 calls for bare root but the details on page L-113 allow cuttings 1/2" -2" in diameter and 3-6' in length.
Cuttings are acceptable in accordance with the detail.
Section 2.9 in the IFB states a duration of 180 days/6 months of Notice to Proceed. Please confirm the accuracy of this.
The City should be in a position to issue NTP in late fall of 2026, however given the closure period, we understand that the work may need to be performed starting immediately following the closure period and would continue through calendar year 2027. We are willing to work with the Contractor to establish a mutually agreeable schedule in terms of duration and dates.
Good Morning, Is there an engineer's estimate for this project?
Yes, it can be found under attachments.
Current estimates project over 20,000 CY of excavation, however the bid tab lists 10,000 CY of excavation. Will all additional excavation over 10,000 CY be paid for via the bid tabulation Unit Price?
The bid form will be revised.
The Scope of Work (Section 3.1) says as-builts will be provided by the owner, however the bid tabulation says to include a LS price for As-Builts. Which is correct?
The City will prepare the as-builts, however performing the as-built survey and providing CAD files to the City is part of the contract.
Is there a plan set for this project?
Yes, it can be found under attachments.
Please tell bidders the anticipated start date and completion date that are expected of them. And which stream closure we'd be dealing with
The City should be in a position to issue NTP in late fall of 2026, however given the closure period, we understand that the work may need to be performed starting immediately following the closure period and would continue through calendar year 2027. We are willing to work with the Contractor to establish a mutually agreeable schedule in terms of duration and dates.
Please upload the drawings
The drawings have been uploaded as attachment# 2 - "2026_04_Carroll_Creek_Stream_Restoration".
Where can we access the drawings? We looked through all the current bid documents and could not find them. Thanks!
The drawings have been uploaded as attachment# 2 - "2026_04_Carroll_Creek_Stream_Restoration".
How much are liquidated damages? Section 2.15 states $500 per day while table 108-1 has them tiered from $500 - $7,000
The liquidated damages are $500 per day.
Can the AIA Standard bid bond form be used? Or is there a specific form the City would prefer?
Please use the standard City of Frederick bid bond form, which will need to be executed through Surety 2000.
Could the questions period be extended for this project?
Yes, the question deadline has been extended for two weeks and is now 10/14/26 at 3pm.
Could consideration be given to extending the due date on this project?
Yes, the IFB due date has been extended for two weeks and is now 10/30/26 at 3pm.
It does not appear that there are sufficient suitable logs/woody debris from onsite clearing to meet the requirements of the stream restoration details. Most of the existing trees are in poor condition and not of sufficient length. Should trees from offsite be furnished if suitable material isn't available?
Yes.
Please confirm the following line items are correct -Toewood (Rootwad Logs 15') 1,300 EA -Toewood (Wood Member 15') 1,300 EA
These quantities are per the design engineer's opinion of probable costs.
What is the measure/pay for Item 58 "Commercial Entrance"
Please disregard this item, it is being removed.
The existing Farm Lane is in various states of disrepair, particularly towards the existing bridge. Is this to be completely repaved at the completion of the job? If so, will this be covered under Item 57 "MA Superpave Surface"? If the intent is to only pave a portion, please clarify the limits.
Within the limits of disturbance, Farm Lane should be repaired to existing conditions, or as directed by the City. This would be covered under item 57 “MA Superpave Surface”.
Where are the limits of microtopography installation?
Microtopography is no longer part of the project.
What bid item should the access roads fall under?
Add line items for silt fence and mulch access as needed to bid.
Can CAD files be supplied for the bidding phase of this project?
Yes, we are working on obtaining them from the design engineer.
Could you please provide the standard City of Frederick Bid Bond form you're referencing?
Bonding will be filed and verified through Surety2000. 1-800-660-3263 help@surety2000.com Once a contractor is registered with Surety2000, they will be able to complete the bid bond on the City of Frederick's form through the system.
In the riffle mix, what type of stone is required for "substrate 3-6"? Additionally, can locally sourced quarried rock be used in lieu of cobble etc...?
Angular and rounded rocks is preferred. Quarried rock will also be considered as an alternative.
After talking to vendors, they are not producing the volume of cobble and river jacks to satisfy the requirements of the riffle mix. Please consider an alternate material for the cobble/river jacks.
Alternate materials will also be considered.
Good Afternoon, There does not appear to be any attachments that have the estimate. Can it be added please?
Yes
The existing contours on sheets C-101 through C-106 don't appear to match the existing contours shown on C-302 through C-307 in many cases when overlaid in earthwork software. Could a clarification be made on which existing contours govern, and can CAD files be released during the bid to assist with earthwork quantities?
Yes, we will release the CAD files. The design engineer's comment: "The overbank topo may be slightly different between the two sheets because we start to using a combined survey and LIDAR surface in C-302. The channel topo should for the most part be the same."
What bid item should silt fence be included in? What bid item should access roads be included in?
Line items for silt fence and mulch access will be added.
Can additional details and a profile be provided for the 3 storm drain culverts that are proposed? Can the LOD be expanded to encompass the northernmost culvert crossing (Sheet C-305)?
LOD can be expanded to include northernmost culverts subject to permission from the Frederick County Soil Conservation District. Additional details are provided below: • Length: 16’ • Slope: 0.50% (Upstream to Downstream) • Asphalt: City Detail ST-7.0, Pavement 3 (Elevations to be determined in field) • Pipe Inverts: Field Engineered (based on field determined pavement elevations)
For clarity, could you add a column in the tree inventory list labeling if the the tree is to be removed or not? Also, if the tree to be removed is suitable for reuse in stream features? In many instances on the ESC phase 1 plans, you cannot read which specimen trees are labeled for removal.
ST1 ST26 ST63 ST83 ST5 ST27 ST65 ST84 ST9 ST30 ST70 ST85 ST10 ST33 ST71 ST86 ST11 ST34 ST74 ST87 ST13 ST38 ST75 ST90 ST14 ST52 ST77 ST91 ST20 ST53 ST78 ST92 ST22 ST56 ST79 ST25 ST58 ST82 Contractors should assume that trees rated “Poor” may not be able to be reused for stream features.
Do you have a detail for the Ford Crossing areas? Or is this intended to be a temporary access bridge or similar design to stay out of the water?
Ford Crossing Detail is attached.
Do all areas within the LOD have to be cleared/stripped of topsoil and respread and planted with permanent stabilization? Many areas will not be affected by grading activities and could be left undisturbed otherwise.
No. Areas not impacted by earthwork or grading do not need to be stripped and respread.
The detail shows 12" of salvaged bed material in all pools, with additional bed material to wash in stone structures. Is all of this material anticipated to be available and usable in the existing creek? If additional furnished material is required, what is the composition and what pay item should this be included under?
Native in creek material should be utilized to the maximum extent practical and is anticipated to be available for harvesting and reuse for pools. If additional furnished material is required for pools, it should align with the riffle bed mix specifications shown on sheet C-407. Contractor should add this as a pay item in the bid as needed.
What spec should be followed for Airport Coir Matting? Also, are metal "sod staples" acceptable anchors for coir matting as shown in the detail on sheet C-407 as opposed to wooden stakes?
Airport Coir Matting should utilize detail shown on C-407. Staples in accordance with the manufacturer’s specifications are acceptable. Contractor may propose using a wooden stake alternative also.
Have soil borings been taken on this site? If so, can they be provided. If not, can a contingent item for rock excavation be added to the bid form?
Borings have not been taken. A rock contingency item can be added.
Could consideration be given to lowering the MBE / WBE goals on this project? Total goal is 44% which is a substantial amount of work for a project where most contractors have the capability to self perform the majority of the project.
Once the goals have been calculated and added to the solicitation, they can not be changed. However, if any bidder plans to self perform a significant portion of the scope of work, they can request a waiver of the goals via the form provided and explain the self performance of the work as the reason for the goals not being met. This request will be reviewed by our office and approved or denied based on the participation achieved, the amount of bidder self performance, and the good faith efforts shown to meet to the goals.
For bid items 22 and 23, it is showing a total of 5,000 ton of boulders in the bid form. There are 26 rock sills shown at a width of 51', 4' length, and approximately 3' depth for an approximate volume of 589 CYD which is much less material than what is shown on the bid form. Please advise if these figures (2,500 ton each) accurately represent how much material is expected to be installed in the rock sill line items.
We discussed this with the design engineer, who acknowledged that it was likely overestimated based on the available information. They directed the following approach: "Contractor shall provide costs for quantities provided, with the understanding that quantities will be adjusted during construction based on in field needs for constructing each sill."
Per Addendum 4 there are "two additional documents" that have been added, however they are not available in the portal. Please advise.
The two additional documents per Addendum 4 are under the "Supporting Attachments" section, labeled as E. 1. 100% Carroll Creek Preliminary Opinion of Probable Cost and F. 2026_04_Carroll_Creek_Stream_Restoration
For the branch layering within the soil lifts, should fascines/bundles be used or individual live branches?
Contractor should follow the detail for this for bidding purposes. Selected contractor may provide alternates for consideration.
ST 63 is shown as a 68.5” sugar maple that is to be removed. This would be a MD state champion sugar maple in diameter alone. Please confirm this tree is to be removed.
This tree is proposed to be removed
There is no structure table for the cross vanes. Please provide any additional information that would be necessary to construct these structures.
Structure table to be provided to selected contractor. Contractor should prepare bid based on structure station / elevation and details provided in plans.
The throat of the cross vane structures is very narrow. In a stream this large, this could lead to deeper scour and possible structure failure. Please confirm this is the desired configuration for the structure
Contractor should follow the proposed details. Should adjustments be needed for structures, selected contractor should submit an RFI and field adjustments will be made based on the RFI results.
Due to the proximity of the project to the airport, has the planting plan been reviewed for conformance with FAA requirements, or if an FAA review is not required?
Planting plan has been adjusted with low growing species and adjusted for the flight path. It has not been reviewed by the FAA.
Due to the underlying karst geology, has any subsurface geotechnical investigation been performed in areas where the channel alignment is being shifted to confirm that the stream will neither gain nor lose flow?
Geotechnical Investigation has not been performed for this area, and the City is not aware of any specific Geotechnical related issues in this area, however per the question, it is correct that the area is in Karst geology and the contractor should be cautious regarding this issue and notify the City immediately if any evidence of sinkholes is encountered during construction.
There is only one staging area shown that allows for the storage of equipment and materials overnight and this staging area does not have access to all portions of the stream. Please clarify where materials for other sections of the project are to be stored and clarify why materials and equipment are not allowed to be stored overnight in other staging areas. Non-erodible materials and equipment are typically allowed in the 100yr floodplain and MDE allows for staging of erodible materials in the 100yr floodplain when no other alternatives exist.
Materials and equipment are to be stored in the designated staging areas. Staging areas per the MDE permit are allowed in the 100 yr floodplain.