CDBG-DR HS004 New Escambia County Area Transit (ECAT) Facility

Description

This project is to provide construction services to build five structures (Administration Building, Maintenance Building, Passenger Terminal Transfer Center, Bus Wash, and Fuel Station) along Clarinda Lane in Pensacola, Florida. Scope of Work Overall Scope of Work The following individual scopes are intended to be read together with the complete Bid Package 2 (BP2) Contract Documents and Project Manual. BP2 encompasses architectural work, fire protection, plumbing, HVAC, electrical, safety/security systems, earthwork with exterior improvements, together with the applicable procurement, contracting and general requirements. For each facility, the Contractor shall furnish and coordinate all incidental work reasonably necessary for a complete installation, whether specifically itemized or required by the drawings, specifications, codes, manufacturers’ requirements or authorities having jurisdiction. Work shall include required submittals and shop drawings, coordination drawings, testing and balancing, system commissioning, equipment start-up, demonstrations and training, warranties, O&M data and record documents. The Project Manual specifically requires final O&M manuals before Substantial Completion and organization of the manuals by systems, subsystems and equipment. Lot 1: Administration Building - Scope of Work The Work associated with the Administration Building consists of furnishing all labor, supervision, materials, equipment, tools, transportation, permits, testing, inspections, coordination, and incidentals necessary to complete construction of the new Escambia County Area Transit Administration Building at 20 Clarinda Lane, Pensacola, Florida, in accordance with the Contract Documents. The Project includes, but is not limited to, complete construction of a two-story administrative and operations facility, together with the associated architectural, structural, mechanical, electrical, plumbing, fire protection, communications, technology, security, and life-safety systems necessary to provide a complete and fully operational facility. The building is identified as Business occupancy on the first floor with Assembly occupancy associated with the second floor training area. The facility shall include, at a minimum: Public lobby, vestibules, reception and administrative reception areas; Call Center; Radio Room and Dispatch functions; Safety Manager offices, Chief Safety Officer office, Program Manager office, ADA office and related administrative/support offices; Accounting, Finance, Grants and management offices; Division Manager, Deputy Director, Director and Director’s Aide offices; Conference Room, Meeting Room, and associated presentation areas; Simulation area; Breakroom and employee support spaces; Breakroom and employee support spaces; Mother’s Room and Quiet Room; Men’s and women’s locker rooms; Men’s, women’s and ADA toilet facilities; Office supplies, janitor, general storage and support spaces; IT, electrical, mechanical and plumbing support areas; Second-floor Training Room configured for large-group training and presentations; Second-floor storage, restrooms, corridors and mechanical/support areas; Elevator and stair systems providing vertical circulation between floors; Interior partitions, rated assemblies, ceilings, flooring, wall finishes, millwork, countertops, casework and specialties; Exterior wall assemblies, glazing, doors, entrances, roof assemblies, flashing, drainage components and associated weatherproofing; Structural foundations, slabs, masonry, structural steel, elevated floor framing, roof framing and associated structural components; Complete HVAC systems, ventilation, exhaust, controls and associated mechanical equipment; Domestic water, sanitary waste and vent systems, plumbing fixtures, water heating and associated plumbing specialties; Automatic fire sprinkler/fire-protection systems and associated fire-protection equipment; Complete electrical service and distribution, panelboards, branch circuitry, receptacles, equipment connections, interior and exterior lighting, emergency lighting, exit signage, grounding, lightning protection and associated controls; Fire alarm and life-safety systems; Telecommunications pathways, cabling infrastructure, MDF/IDF infrastructure and equipment connections; Access-control infrastructure, card readers, electric locking interfaces, door contacts, request-to-exit devices and associated security systems; Interior and exterior CCTV infrastructure and cameras as indicated; Mass-notification/paging infrastructure and associated speakers; Code Blue/emergency communication infrastructure where indicated; Digital signage and transit-message-board infrastructure where indicated; Audio/visual infrastructure for the Training Room, Conference Room and Meeting Room, including floor boxes, presentation connections and associated pathways as indicated in the Contract Documents; and All other architectural, structural, mechanical, electrical, plumbing, fire protection, technology, communications, and specialty work necessary for a complete Administration Building. The drawings specifically identify technology provisions for access control, CCTV, mass notification/paging, Code Blue stations, digital signage, training/conference/meeting-room AV systems, and presentation connections for spaces including Radio, Call Center, Accounting, Finance and management offices. Certain AV equipment is identified for coordination with the Owner/Owner’s vendor; the Contractor shall provide the infrastructure and work assigned to the Contractor by the Contract Documents and coordinate all Owner-furnished systems. The Contractor shall provide all work necessary to deliver a complete, code-compliant, fully tested, balanced, commissioned and operational Administration Building, including equipment start-up, controls integration, system testing, inspections, demonstrations, Owner training, warranties, operation and maintenance manuals, record documents, closeout documentation and final acceptance in accordance with the Contract Documents. Liquidated Damages will be calculated based on bid amount and FDOT Liquidated Damages 26-27 in the attachments. See Construction Terms for time for completion per lot. Lot 2: Maintenance Building - Scope of Work The Work associated with the Maintenance Building consists of furnishing all labor, supervision, materials, equipment, tools, transportation, permits, testing, inspections, coordination, and incidentals necessary to construct the new Vehicle Maintenance Building for the Escambia County Area Transit Facility at 20 Clarinda Lane, Pensacola, Florida. The Project includes, but is not limited to, complete construction of a transit-vehicle maintenance and service facility containing heavy bus-maintenance bays, small-vehicle service bays, parts and equipment storage, specialty maintenance rooms, fluid distribution systems, employee support areas, offices and mezzanine storage, together with all architectural, structural, mechanical, electrical, plumbing, fire protection, technology and specialty systems necessary for a complete vehicle-maintenance operation. The facility shall include, at a minimum: Seven (7) bus maintenance bays under the Base Bid configuration; Eight (8) small-vehicle service bays under the Base Bid configuration Tire Storage; Maintenance Supervisor office; Maintenance Manager office; Facility Manager office; Inventory Manager office; Parts Room and Parts Counter; Company Tool storage; Personal Tool storage; Mechanical/Facility Storage; Tire Storage; Fluid Storage/Compressor Room; Clean Room; Battery Storage room; Breakroom; Men’s and women’s locker/restroom facilities; IT room; Janitor space; Mechanical yard; Vestibules, corridors and supporting circulation; Mezzanine storage; Receiving/service functions and associated overhead doors; Heavy-duty and small-vehicle service-bay doors; Structural foundations, slabs, masonry, structural steel and roof framing; Mezzanine framing and concrete-on-metal-deck construction; Special rated construction around hazardous areas, including Battery Storage; Exterior wall, roof, flashing and drainage systems; Interior partitions, ceilings and finishes appropriate to office, employee and industrial/service areas; Vehicle-maintenance equipment infrastructure and utility connections; Compressed-air distribution and hose-reel systems; Motor oil distribution; Gear-oil distribution; Transmission-fluid distribution; Antifreeze distribution; Grease and water reels where indicated; Waste-oil and waste-antifreeze collection/distribution infrastructure as indicated; Specialty service hose reels mounted from the pre-engineered metal-building framing; Emergency eyewash/wash stations; Domestic water, sanitary, waste, vent and plumbing-fixture systems; Floor drains, trench/service drainage and associated oil/service-area drainage provisions where indicated; Mechanical ventilation and vehicle/service-area exhaust systems; HVAC systems serving offices, locker rooms, support areas and specialty spaces; Building automation and mechanical controls; Complete automatic fire-sprinkler system; Fire-alarm and life-safety systems; Electrical service and distribution; Equipment connections for maintenance equipment, compressors, bay equipment, overhead doors and specialty systems; High-bay lighting for maintenance/service spaces; Office/support-area lighting and controls; Emergency lighting and exit signage; Grounding and lightning protection; Telecommunications and data infrastructure, including service provisions for maintenance operations; Access-control, CCTV, intercom, paging and security infrastructure as indicated; Technology systems and equipment pathways; All supports, hangers, curbs, pads, sleeves, penetrations, access provisions and coordination required for equipment installation; and All other architectural, structural, mechanical, electrical, plumbing, fire-protection, technology and specialty systems necessary for a complete and fully operational vehicle-maintenance facility. The project specifically identifies Maintenance Supervisor, Maintenance Manager, Facility Manager and Inventory Manager offices; Parts Room and Parts Counter; locker/restrooms; Breakroom; IT; Fluid Storage/Compressors; Tire Storage; Clean Room; Battery Storage; Personal Tool Storage; Company Tools; Mechanical/Facility Storage; seven bus bays and eight small-vehicle bays. The Maintenance Building contains multiple occupancy/use conditions associated with the maintenance operation. The drawings classify Battery Storage as H-2 high hazard; the bus garage, small-vehicle garage, fluid-storage/compressor room and tire storage as S-1; open shop/parts/delivery/mezzanine areas as S-2; and the entry, breakroom and locker areas as Business occupancy. The building is one story with a mezzanine and is protected by an automatic sprinkler system and fire-alarm system. Specialty fluid-service infrastructure shall include the hose-reel systems indicated for the maintenance bays. The drawings identify motor oil, gear oil, transmission fluid, antifreeze, compressed air, water and grease services at various maintenance locations, with hose reels supported from the pre-engineered metal-building bents. The Base Bid includes seven bus bays and eight small-vehicle bays. The Contract Documents also identify a deductive alternate reducing the bus-bay area to five bays and the small-vehicle area to six bays; if accepted, the affected exterior construction is to accommodate the conditions shown for future expansion. The Contractor shall provide all work necessary to deliver a complete, code-compliant, fully tested, balanced, commissioned and operational Maintenance Building, including coordination and start-up of specialty maintenance systems, testing of MEP and life-safety systems, controls integration, inspections, Owner demonstrations and training, warranties, O&M manuals, record drawings, closeout documentation and final acceptance. Liquidated Damages will be calculated based on bid amount and FDOT Liquidated Damages 26-27 in the attachments. Please see Construction Terms for completion time per lot. Lot 3: Passenger Terminal Transfer Center - Scope of Work The Work associated with the Transfer Building / Transfer Center consists of furnishing all labor, supervision, materials, equipment, tools, transportation, permits, testing, inspections, coordination, and incidentals necessary to complete construction of the new Escambia County Area Transit Transfer Center at 20 Clarinda Lane, Pensacola, Florida, in accordance with the Contract Documents. The Project includes, but is not limited to, construction of the passenger transfer facility, customer-service/ticketing building, public restroom facilities, passenger waiting areas and associated covered canopies, together with all architectural, structural, mechanical, electrical, plumbing, technology, security and life-safety systems required for a complete transit facility. The drawings identify the outdoor passenger waiting area as an S-2 use and the enclosed administrative/customer-service functions as Business occupancy. The facility shall include, at a minimum: Customer Service area and ticketing/service functions; Customer-service office; Secure safe area; Public-facing ticket/transaction windows and associated counters; Impact- and ballistic-resistant exterior transaction-window assemblies as indicated; Men’s and women’s public restrooms; Vestibule and controlled public/staff entrances; Breakroom and employee support areas; Men’s and women’s public restrooms; ADA toilet facilities; Janitor/service rooms; Mechanical/IT room and dedicated HVAC/support areas; Public passenger waiting areas; Covered passenger-loading and waiting canopies; Structural canopy framing, columns, foundations and associated roof construction; Roof systems, roof drainage, gutters and downspouts; Exterior wall systems, impact-resistant storefront/glazing, exterior doors and associated weather-resistant construction; Interior partitions, finishes, ceilings, casework, counters and toilet accessories; Structural foundations, slabs, masonry and structural-steel framing; Complete HVAC systems serving enclosed occupied and support spaces; Domestic water, sanitary waste and vent piping, plumbing fixtures, water heating, floor drains, backflow protection and associated plumbing specialties; Electrical service and distribution, lighting, receptacles, equipment connections and controls; Extensive canopy lighting and exterior passenger-area lighting; Emergency lighting and exit signage; Grounding and lightning-protection systems serving the building and canopies; Fire alarm and life-safety systems; Telecommunications and network infrastructure; Wireless access-point infrastructure; Security/access-control systems and associated door hardware interfaces; CCTV/security-camera infrastructure; Paging, mass-notification and passenger-information infrastructure where indicated; Intercom and emergency communication systems where indicated; and All associated architectural, structural, mechanical, electrical, plumbing, technology and specialty systems necessary to provide a complete and operational transit transfer facility. The drawings specifically identify Customer Service, Safe, Customer Service Office, Break Room, Mechanical/IT, ADA toilets, public men’s and women’s restrooms, janitor and HVAC spaces. The facility also incorporates substantial covered passenger areas; the roof plan identifies multiple canopy sections and associated roof drainage systems. Exterior ticket windows shall include the complete transaction-window assemblies required by the Contract Documents, including framing, glazing, transaction hardware and accessories. The drawings call for impact-resistant construction and UL 752 Level 3 ballistic resistance at the specified ticket windows. The Contractor shall provide all work necessary to deliver a complete, accessible, code-compliant, fully tested, commissioned and operational Transfer Center, including start-up, testing, controls verification, inspections, Owner training, warranties, operation and maintenance manuals, record documents, closeout documentation and final acceptance. Liquidated Damages will be calculated based on bid amount and FDOT Liquidated Damages 26-27 in the attachments. Please see Construction Terms for completion time per lot. Lot 4: Bus Wash - Scope of Work The Work associated with the Bus Wash consists of furnishing all labor, supervision, materials, equipment, tools, transportation, permits, testing, inspections, coordination, and incidentals necessary to construct the new Bus Wash facility for the Escambia County Area Transit Facility at 100 Clarinda Lane, Pensacola, Florida. The Project includes, but is not limited to, construction of the enclosed bus-wash building, associated equipment/support areas, fare-processing functions, vacuum facility, staff restroom and all infrastructure necessary to support the Owner’s bus-washing and vehicle-cleaning operations. The project is new construction housing bus-wash equipment, a cash vault/fare-processing function and staff toilet room, together with a separate vacuum-station function. The facility shall include, at a minimum: Bus Wash Bay; Bus-wash equipment support and coordination; Equipment Room; Fare Processing room; Fare Entrance; Cash/fare-handling support infrastructure; Vacuum station/building; ADA staff restroom; Structural foundations, slabs, walls and roof framing; Concrete masonry construction and associated structural systems; Precast concrete roof construction where indicated; Exterior wall and roof assemblies; Doors, openings, louvers and related architectural components; Interior finishes and accessories appropriate to wet/service environments; Equipment housekeeping pads, curbs and supports; Wash-water supply and associated piping; Domestic cold-water and service-water piping; Sanitary waste and vent piping; Floor drains, floor sinks, cleanouts and drainage systems; Water-heating equipment; Water-softening equipment and associated connections where indicated; Plumbing fixtures and ADA restroom fixtures; Wash-equipment plumbing connections and coordination; Natural-gas service and distribution for heating equipment; Gas-fired radiant tube heaters serving the Wash Bay; Gas furnace and associated condensing unit; Equipment-room unit heater; Exhaust and ventilation systems; Mechanical controls and associated equipment; Electrical service and distribution; Dedicated wash-equipment power connections; Power for air compressor, water heater, water softener and other equipment; Interior, exterior and wash-bay lighting; Emergency lighting and exit signage; Grounding, bonding and lightning-protection systems; Technology/communications infrastructure and IT rack provisions; Security and monitoring infrastructure where indicated; Equipment-control interfaces and emergency controls; Site utility connections and coordination with the surrounding Wash/Fuel Station site work; and All architectural, structural, mechanical, electrical, plumbing, technology and specialty systems necessary to provide a complete and operational Bus Wash facility. The principal spaces are the Wash Bay, Equipment Room, ADA Restroom, Fare Processing, Fare Entrance, and the Vacuum. Mechanical systems include a gas furnace/condensing unit, an electric unit heater and two gas-fired radiant tube heaters serving the Wash Bay. The drawings specifically require coordination of mechanical equipment locations and clearances with the bus-wash equipment. Plumbing work shall be closely coordinated with the wash-equipment requirements and includes service/cold-water distribution, sanitary systems, floor drainage and equipment connections. Electrical work includes dedicated connections for the wash fa

Published attachments
Addenda and notices
  • Official Notice #1: PD 26-27.004 - Reminder Notice · 1

    This notice serves as a reminder that the pre-solicitation meeting for PD 26-27.004 CDBG-DR HS004 New Escambia County Area Transit (ECAT) Facility will be held on 10/29/2026 at 10:00am. You can join us in person at the below address for the Escambia County Office of Purchasing or on Teams using the link below. 213 Palafox Place, 2nd Floor Pensacola, FL 32502 To join us on Teams: Microsoft Teams meeting Join: https://teams.microsoft.com/meet/278191507600543?p=HJleHevhlV1sRKGTFc Meeting ID: 278 191 507 600 543 Passcode: PH2Qx6dk Need help? | System reference Dial in by phone +1 863-333-5817,,718540672# United States, Lakeland Find a local number Phone conference ID: 718 540 672#

  • Addendum #1 · 1

    Added Cone of Silence to General Terms and Conditions

  • Official Notice #2: PD 26-27.004 - Pre-Bid Meeting Attendance · 2

    Please see the attached attendance sheet for the pre-bid meeting of PD 26-27.004.

  • Addendum #2 · 2

    This is to update the time for completion for Lot 1. Please use the See What Changed link to view all the changes made by this addendum.

  • Addendum #3 · 3

    Removed Time for completion in Scope due to glitch in software the days were not showing correct amounts. Please reference Construction Terms for days to completion per lot.

  • Official Notice #3: PD 26-27.004 - Reminder Notice · 3

    This notice serves as a reminder that the question-and-answer period for PD 26-27.004 will close on 11/5/2026 at 12:00pm CST.

  • Addendum #4 · 4

    Please see the updated Construction for updated Time for Completions per Lot.

  • Official Notice #4: No further substitutions will be considered. · 4

    Since the bid due date is less than 7 days away, no further requests for substitutions will be considered. Generally, the substitution request period is only through the Question & Answer deadline.

  • Addendum #5 · 5

    This addendum is to clarify that if your bid on the entire complex is lower than the sum of the individual bids it will all be considered responsive.

  • Official Notice #5: PD 26-27.004 - Fuel Cutsheets · 5

    Please see the attached Fuel Cutsheets which have been submitted by the department to address the RFI's for this project.

  • Addendum #6 · 6

    Updated Lot 2, 5, and 7 Pricing Table Time for Completion to match amounts in Construction Terms.

  • Official Notice #6: PD 26-27.004 - Bus Wash Cutsheets · 6

    Please see the attached Bus Wash Cutsheets which have been submitted by the department to address the RFI's for this project.

  • Addendum #7 · 7

    Corrected Time for Completion titles and dates so Scope, Construction Terms and Pricing Table match.

  • Official Notice #7: PD 26-27.004 - Admin Cutsheets · 7

    Please see the attached Admin Cutsheets which have been submitted by the department to address the RFI's for this project.

  • Addendum #8 · 8

    Updated the Bid Bond question in Vendor Submissions to reflect a 90-day pricing guarantee. Please use the See What Changed link to view all the changes made by this addendum.

  • Official Notice #8: PD 26-27.004 - Example Contracts · 8

    Please see the attached example contracts for PD 26-27.004. Review the terms and conditions carefully because there will be a required turnaround time of 24 hours to return a signed contract to the county at the time of award. Please reach out to the Office of Purchasing should you have any questions.

  • Addendum #9 · 9

    Attachments updated to include Heavy Wage Determinations.

  • Official Notice #9: PD 26-27.004 - Reminder Notice · 9

    This notice serves as a reminder that the bid opening for PD 26-27.004 will take place on 11/25/2026 at 10:00am CST.

  • Addendum #10 · 10

    Included "Add Alternate" pricing table for pricing of additional concrete in case it is required. Please use the See What Changed link to view all the changes made by this addendum.

  • Official Notice #10: PD 26-27.004 - Reminder Notice · 10

    Please be aware that ten minutes before the bid opening, should the amount of submitted bids not meet the grant requirement, the county reserves the right to push the bid due date seven days to allow time for more responses.

  • Addendum #11 · 11

    Posting Question & Answer Report. Please see attached.

  • Official Notice #11: PD 26-27.004 - Bid Tabulations · 11

    Please the attached Bid Tabulation reports for PD 26-27.004.

  • Addendum #12 · 12

    This addendum is for revised construction drawings which have been added to the attachments. A notice will be issued with Cutsheets for individual RFI's that have been submitted.

  • Addendum #13 · 13

    The bid due date has been pushed to 11/25/2026 at 10:00am CST. Please use the See What Changed link to view all the changes made by this addendum.

  • Addendum #14 · 14

    All HVAC Equipment and Controls will be Owner Furnished, Contractor Installed (OFCI). Equipment and controls listed in the project documents are reference only for contractor to coordinate installation of equipment and controls.

  • Addendum #15 · 15

    Added Escambia County Contractor License requirement to Vendor Submission Section

  • Addendum #16 · 16

    Removed document upload for Escambia County License and changed it to a Confirmation.

Public questions and answers
  • Will this part of the project be able to start immediately after phase 1 (Infrastructure) is completed?

    Yes, the intent is for Phase 2 to begin immediately following the completion of Phase 1 (Infrastructure), with no anticipated gap between the two phases.

  • We are requesting that AllMetal Buildings be accepted as an approved Metal Building manufacturer for this project. Product data has been forwarded to Purchasing Grant Coordinator for review.

    AllMetal Buildings is approved as an acceptable Pre-Engineered Metal Building (PEMB) manufacturer, provided all proposed materials, components, and systems fully comply with the requirements of the original project specifications and contract documents.

  • Is this project going to be awarded to one contractor or split between two or more?

    Escambia County reserves the right, at its sole discretion, to award the contract in its entirety to a single offeror on an “all-or-none” basis or to make separate awards on a “lot-by-lot” basis, whichever is determined to be in the best interest of and most advantageous to the County.

  • 1. Battery Storage Room 112 • Is the intent to provide wet-pipe sprinkler protection in accordance with NFPA 855, IFC Section 1207, and applicable UL 9540A test data? • Should we utilize a minimum design density of 0.30 gpm/sq. ft., or will specific sprinkler design criteria be provided based on the battery system? 2. Fluid/Compressor Room 119 • Should this room be classified as Extra Hazard Group I with a design density of 0.30 gpm/sq. ft.? 3. Tire Storage Room 110 Please provide the following information: • Maximum height of tire storage. • Will tires be stored in racks? • What is the anticipated storage arrangement (palletized, open shelving, laced, or pyramid stacked)? • If rack storage is proposed, will in-rack sprinkler protection be required, or is the intent to utilize overhead ESFR sprinkler protection?

    1a. Yes, the intent is to provide wet-pipe sprinkler protection in accordance with NFPA 855, IFC Section 1207, and applicable UL 9540A test data. 1b. Yes, unless the ESS units (groups) exceed 50 kWh, then use a density based on large-scale fire testing complying with Section 1207.1.7 in the IFC. 2. Yes, this room should be classified as Extra Hazard Group I. 3a. Height of the scheduled tire carousel on sheet A114 is 15’-2”. 3b. Tires are stored on the racks in the carousel. 3c. Per cutsheet, arrangement is “The Tire Carousel features a carrier that is made up of 3 pipes in a triangular configuration. The tires sit inside the bottom, with the top limiter bar providing support and a visual for tire sizes that will fit in the carousel.” 3d. Utilize overhead ESFR sprinkler protection per Table 23.5 in NPFA 13.

  • Is a substitution from Johnson Controls to Siemens allowed?

    No

  • I understand that most of the furniture for this facility will be provided by the owner. Looking at the plans there is a call center and a dispatch area I have a general question for. Is the county open to looking at consoles for those areas instead of commercial furniture? Consoles are more expensive than normal office furniture but they last up to 20 years in high use areas.

    At this time, the County will be moving all non-casework furniture from the existing facility to the new facility.

  • RFI – Bid Clarification Request: 1) Due to volatility of steel market (both prices & availability) materials will require advance purchase ASAP after award. Advanced purchased material will require payment once material is received. Is this acceptable? 2) Due to volatility of steel market, some items may have long lead times and scheduling cannot be guaranteed until orders are placed and accepted.

    1) the awarded vendors will receive a PO for the materials within ten days of the award date. 2) Acknowledged.

  • Drawing ES103 - Within the C03.04 square there are (2) W2 fixtures that are shown at the trash enclosure. These fixtures are not shown on drawing ES102. Please confirm they are required. If required, please confirm they are to be fed from panel 'HEF1'.

    Additional clarification regarding this item will be provided in a forthcoming Addendum.

  • Drawing ES103 & EF600 - The product data for fixture type 'F7' does not match. Please indicate which fixture type we are to provide.

    The F7 fixture designation shown on Sheet ES102 is correct and reflects the intended design. The applicable drawings will be revised accordingly, with the correction incorporated into a forthcoming Addendum.

  • Drawing EF501 - Detail 11 - There is a grounding detail shown on the fuel station drawings but there does not appear to be anything shown on the floor plans. Please confirm what grounding is required outside of the LPS.

    The fuel building should have a main ground bar (MGB-1), similar to the other buildings, it will be located near the panels. This will act as the main ground for the building and will be included in an addendum.

  • Drawing TF100 - Where are we to route conduits from the field mounted backboxes for the cameras, speakers & EM Call Station?

    All conduits serving the field-mounted backboxes for the cameras, speakers, and emergency call station shall be routed to the Wash Bay IDF Room. All associated cabling shall terminate within the IDF Room. This routing and termination requirement will be clarified in a forthcoming Addendum.

  • Site Lot (Lot 6) says it has a 30 day duration for substantial completion. It includes both components that would go in before buildings (underground utilities) as well as components that would typically go in after buildings (asphalt, curbs). How does that work with the 30 day duration?

    Acknowledged, we will issue an addenda to allow for additional time to install the concrete/asphalt.

  • - It was stated in the pre-bid meeting that the Build American Buy American regulations do not apply. Please confirm. - Do Davis-Bacon and Section 3 requirements still apply?

    BABA does not apply. Both Davis-Bacon and Section 3 do apply.

  • The lighting drawings show low voltage switches in multiple rooms throughout the project. Per the drawing notes, the specified 8-zone lighting relay panel is dedicated to high bay, exterior, and site lighting only. As a result, no control device appears to be specified for the interior rooms with low voltage switching. We propose providing DLM (Digital Lighting Management) room controllers in each of these spaces. Automatic shutoff will be achieved at the room level through low voltage occupancy/vacancy switches and ceiling-mounted occupancy sensors. Please confirm the following: Are DLM room controllers acceptable for control of the interior rooms with low voltage switching? Since automatic shutoff will be handled locally by occupancy/vacancy sensing, may the room controllers operate as standalone systems, or are they required to be networked together, or tied into the relay panel, for centralized scheduling, time-of-day control, or BAS integration? Please provide a basis of design (manufacturer and model) for the room controllers, including the number of switched and/or dimmed zones required per room. Suggested Resolution: Provide standalone DLM room controllers in each space with low voltage switching, with automatic shutoff via local occupancy/vacancy switches and ceiling sensors. Proposed basis of design: Wattstopper DLM LMRC-100 series (on/off) or LMRC-200 series (0-10V dimming) room controllers, selected per room based on zone count and dimming requirements.

    Additional clarification regarding this item will be provided in a forthcoming Addendum.

  • Main switchboard SWB1 (1600A, 480V) and all three ATSs are located in the Maintenance Building mechanical yard and feed the Administration Building, Transfer Center, Bus Wash and Fuel Station. If lots are awarded to different contractors, which lot carries SWB1, the ATSs, the generator relocation, campus feeders, site lighting and underground duct banks?

    Additional clarification regarding this item will be provided in a forthcoming Addendum.

  • No specification section covers classified-location wiring. Please provide area classification drawings or confirm requirements (seal-offs, explosion-proof fittings, classified boundaries) for: (a) the Fuel Station under NEC 514; (b) Maintenance Building bus and service-vehicle bays and the Fluid Storage/Compressor room under NEC 511; (c) the Battery Storage room (H-2).

    Additional clarification regarding this item will be provided in a forthcoming Addendum.

  • Per Section 23 09 00, Paragraph 2.2A, the specification states "Trane or pre-approved equal" for the Building Automation System. We respectfully request pre-approval to bid an open-architecture, multi-vendor-supported Tridium Niagara Framework front-end that natively integrates the factory-mounted equipment controllers over BACnet protocols, eliminating sole-source vendor lock-in. Approving this open architecture protects the Owner's long-term budget by enabling competitive bidding among multiple certified contractors for maintenance, software, and future expansions—significantly lowering the facility's lifetime total cost of ownership and allow for seamless future system expansion. Please confirm if an open Niagara-based system will be accepted as an approved equal or if additional documentation would need to be submitted for consideration.

    All substitution requests must be submitted, via email, to purchasing@myescambia.com, referencing PD 26-27.004 and the request must be accompanied by all specifications required for the system to function as described in the plans and specifications. If a substitution is approved, an Addendum will be posted.

  • The main IT room for this building is located on the 2nd floor. It is understood we are to route (4) 4" conduit sleeves from the second floor to the first floor. Where shall the (2) 4" service entrance conduits be routed to when entering the building?

    Additional clarification regarding this item will be provided in a forthcoming Addendum.

  • Per spec section 260533 (3.1) (B) minimum conduit size shall be 1/2" & all homerun conduits shall be 3/4". Electrical Cover Pages General Note #14 states Minimum branch conduit size shall be 3/4" UNO & Note #15 states homerun conduits to the first junction box shall be 1". Please confirm 1/2" conduit is acceptable for all branch circuits while all homerun conduits shall be 3/4".

    Additional clarification regarding these items will be provided in a forthcoming Addendum.

  • Drawing EPW100 indicates DT XFRM LW1 to be NEMA 4X. The two power panels within this room are both NEMA 1 rated. Please confirm the NEMA rating for the XFRM on the drawings is correct.

    Everything in this building should be NEMA 4X. This will be addressed in an Addendum.

  • 1. Do these buildings need interconnected fire alarm systems, or should they all be standalone and have their own communicator? 2. The transfer building does not require a fire alarm by code – is this an owner requirement? 3. The bus wash building does not require a fire alarm by code – is this an owner requirement?

    1. Interconnected/networked campus-wide for monitoring and communication. Building-specific alarm/evacuation response, meaning an alarm in one building does not automatically initiate occupant notification throughout every building. Each building can still perform its required local life-safety functions independently. 2. Fire alarm to be included as represented on ELECTRICAL SYSTEMS PLAN on sheet EYT100. 3. Fire alarm to be included as represented on ELECTRICAL SYSTEMS PLAN on sheet EYW100.

  • 1. Are the window roller shades mounted with fascia below the ceiling, or will they be mounted above the ceiling in a recessed pocket? 2. At the Maintenance Building, are the window roller shades at rooms 102 and 104 manual or motorized? See sheet A115

    1. This will be addressed in an addendum. 2. Please refer to RS1 Spec in 115-Finish Plan for Maintenance.

  • - Please provide spec on the diesel fuel tank. - Is the tank to be provided by the Plumbing contractor? - Is Contractor responsible for filling the tank prior to hand-over?

    1. A specification will be provided with the next Addendum. 2. Each 12,000 gal Fuel tank is an Owner Direct Purchase. 3. Filling of the tank and testing for the generator will be coordinated through the County, not the contractor.

  • The bid documents let bidders price each of the six lots on its own and also price the entire complex as Lot 7. In the meeting yesterday, Travis stated questions may be raised if the sum of Lots 1–6 doesn't equal the Lot 7 price. Each lot priced on its own has to carry its own mobilization, general conditions, supervision, equipment, and overhead. Awarding the whole complex under one contract lets those costs be shared across all six lots under one schedule, one site team, and combined purchasing. A Lot 7 price will therefore normally be lower than the sum of the individual lots, and the difference is a real saving from combining the work, not a pricing error or an unbalanced bid. Please confirm: Will a Lot 7 price lower than the sum of Lots 1–6 be considered responsive and eligible for award? Will a bidder stay eligible for award of Lot 7, or of any individual lot, if those prices don't match?

    After consideration, we will issue an addendum clarifying that if your bid on the entire complex is lower than the sum of the individual bids that it will all be considered responsive. Thank you for your question.

  • Are we bidding the equipment that is listed as contractor and owner? Or are we to only bid the equipment listed as contractor? For example, the lubrication system. The reels are listed under the contractor, but the pumps and the tanks are furnished under the owner.

    Your bid should not include any items listed by the Owner, unless it's listed as Owner Furnished, Contractor Installed. In this case, the contractor would be expected to provide a cost for coordinating delivery and installation of the OFCI.

  • Lot definitions. The Construction Terms list Lot 2 as the Transfer Center, Lot 3 as the Fuel Station and Lot 5 as the Maintenance Building. The Scope of Work and the electronic pricing table list Lot 2 as Maintenance and Lot 5 as Fuel, and the Lot 5 pricing line reads "Fuel Island and Bus Wash Building" although Lot 4 is the Bus Wash. Please confirm the governing lot numbers and the lot in which the Bus Wash is to be priced.

    There will be an addendum posted to address this.

  • Contract times (revised after Addendum 5). Addendum 5 directs the lot scopes to the Construction Terms and sets Lots 1 and 2 at 300/330 days, Lots 3-5 at 270/300 and Lot 6 at 30/60, matching the pricing table. Remaining conflicts: (a) Lot 7 is 335 days to Substantial Completion in §2.8 and the Construction Terms, 330 days in the pricing table, and §2.8 also states "The Contract duration is 240 calendar days ... plus 30 calendar days"; (b) the Construction Terms state the Maintenance Building as "Two Hundred Seventy (300)" days. Please confirm the Lot 7 and Maintenance Building durations. Also, Lot 6 Site/Civil at 30 days to Substantial Completion is not achievable for this scope if awarded by itself - please confirm whether Lot 6 time runs from NTP or is coordinated with building completion when awarded separately.

    Addendum 6 updated the Pricing table Time for Completion to match the Construction Terms and Scope 2.8. Lot 6 will not start until after building completion.

  • Alternate numbering. The ITB lists Alternate 1 as the Administration Building and Spec 012300 lists Alternate 1 as the Maintenance Building. Please confirm the alternate numbering used on the bid form.

    This will be addressed in the Addendum.

  • Bid hold period. The bid hold period is stated as 90 days in one location and 60 days in another. Please confirm.

    Please provide specific sections of the solicitation that state 90 and 60.

  • Unit prices and allowance. The ITB references unit prices for asphalt and masonry tuckpointing, Spec 012200 lists four paving unit prices, and the electronic pricing table has no unit price or allowance lines. Please confirm (a) which unit prices are required and how they are to be submitted, and (b) whether Allowance No. 1 ($150,000, Spec 274100) is to be included in the lump sum for Lot 3 and Lot 7 only, or in another lot.

    For the bid, please fill out the pricing tables. See section 2.12 of the Scope to explain the Schedule of Values for the apparent lowest and most responsible/responsive bid.

  • Trench safety. Sheet S001 requires a separate and distinct price for the trench safety system, but the bid form has no line for it. Please advise how the trench safety price is to be stated.

    See section 2.12 of the Scope for the Schedule of Values requirement.

  • EHPA / shelter and generator. The project background references emergency/shelter design, but no building carries an EHPA or ICC 500 designation on its code sheet. Please confirm that no building is designed as an EHPA or storm shelter, and whether Spec 263200 Generators applies to anything other than the relocated existing Kohler generator (EM600).

    This facility was not designed to meet the industry standards to be classified as a shelter. No building is currently designed as an EHPA or emergency storm shelter due to contaminated soils, prohibiting the project location from functioning as such. CONFIRMED: Permanent generator (Kohler) to be relocated. There is also an intention to locate a temporary generator during emergencies at the Fuel Station, as noted in the Site set/ Lot 6 drawings.

  • Wage determination. The Building wage determination dated 5/18/26 is included as a scanned image. Please confirm the modification number that will apply at bid time and whether a Heavy or Highway determination applies to the site work and Clarinda Ln roadway work. Several trades have no Davis-Bacon classification on WD FL20260203 (drywall hanger/finisher, floor layer/resinous applicator, bricklayer, low-voltage/FA technician, controls/TAB technician, abrasive-blast/HPC applicator); the carpenter and electrician rates are far below market. Please confirm the County/HUD will process SF-1444 conformance requests post-award and that bidders price at prevailing market rates not less than the WD.

    The building wage determination modification 1 dated 05/18/2026 will apply at bid time. An addendum will be issued to include the Heavy wage determination modification 2 dated 05/18/2026 for application to the site and roadway work. Contractors must pay laborers and mechanics at a rate no less than those set by the wage determination- bidders may price at prevailing market rates not less than the wage determination. The County will process conformance requests if necessary- the contractor would complete a Wage Decision Form for the County to review, which would be routed to Florida Commerce for additional inputs and then transmitted to the Department of Labor.

  • Geotechnical report. S001 and C00.01 reference Geotechnical Report #26-162 by Larry M. Jacobs & Associates (5/1/2026) and a 9/1/2026 supplemental email. Neither is in the bid documents. Please issue both, including boring logs and groundwater levels.

    This will be posted in an Addendum.

  • Contaminated soil. The plumbing sheets for every building state that soil on site is contaminated and cannot be removed from the site, and the civil sheets identify the parcels as Escambia Treating Company Superfund tracts with monitoring wells. Please provide the environmental requirements for BP2 excavation: soil management plan, sampling, worker training/PPE (including whether HAZWOPER applies), stockpile location and cover, whether excavated soil may be reused as fill, disposal of excess soil, protection of monitoring wells, and who bears these costs.

    This will be covered in an Addendum.

  • Bid Package 1 status. Please provide the BP1 contract scope and schedule, and describe the site condition expected at BP2 Notice to Proceed: rough grade elevations, completed storm and utilities, detention ponds, Clarinda Ln base, and erosion control devices in place. Who is responsible for repairing BP1 work damaged before BP2 acceptance?

    BP1 is in the Blackout Period because it hasn't been awarded yet. Questions regarding BP1 should be sent to purchasing@myescambia.com.

  • NPDES permit. Who is the NPDES/FDEP Construction Generic Permit holder, and will BP2 become a co-permittee or file a new NOI when BP1 maintenance ends?

    The County is the Permit Holder, and the County will fund these permits. This project will be filed as a one permit, no co-permittee intended.

  • Technology and security scope. The technology responsibility matrices (EA503, EM503, TT501, TW501, TF501, T500) assign many items to "Security Engineering" or mark them "Owner checking" / "Facilities working on this." Please identify who Security Engineering is (County department, Owner's vendor, or contractor's subcontractor) and confirm the contractor's scope. Our understanding is that the contractor provides conduit, boxes, pathways and rough-in only, and that horizontal CAT6, fiber, racks, patch panels, WAPs, access control panels and devices, CCTV cameras, intercoms, code blue units, and meeting room AV are by the Owner. If any of these are contractor-provided, please issue specifications; no access control or CCTV section is in the manual, and Section 282300 is referenced but not included.

    Security Engineering is an Owner-contracted Consultant/Vendor retained by the Escambia County Facilities Management Department to provide audiovisual (AV), access control, security, and network systems integration services. Security Engineering is not a subcontractor to the General Contractor. The Contractor, through its electrical and applicable low-voltage subcontractors, shall furnish and install all required conduits, pull strings, junction boxes, pathways, and associated infrastructure and rough-ins necessary to accommodate the Owner-provided technology and security systems, as indicated in the Contract Drawings and responsibility matrices. Security Engineering and the Owner's designated AV integrator shall be responsible for furnishing and installing the cabling, equipment, devices, and associated systems specifically assigned to them in the technology responsibility matrices, including applicable networking, access control, CCTV, intercom, and audiovisual systems. The Contractor shall furnish and install all materials, equipment, and systems specifically identified as Contractor-provided in the Contract Drawings and applicable Specification Sections. Where no corresponding technical specification is provided for equipment or systems assigned to Security Engineering or the Owner's AV integrator, such equipment and systems shall be considered Owner-provided and excluded from the Contractor's Base Bid, except for the required infrastructure and rough-ins.

  • Door hardware. The door schedules (A900) for the Administration, Maintenance, Transfer Center and Bus Wash buildings do not assign hardware sets. Please issue hardware set assignments for each opening.

    Door schedules will be revised to include hardware sets in a forthcoming Addendum.

  • Missing sheets. The following sheets are referenced but not included: A116 Room Finish Schedule (Admin A113, Maintenance A900), X900 and X950 (Maintenance), and EA502 (Maintenance and Fuel Station). Please issue them or confirm they are void.

    Sheets A116, X900, X950, and EA502 are void and are not part of the Contract Documents. All references to these sheets within the applicable drawing sets will be revised or removed, as appropriate, in a forthcoming Addendum.

  • Missing specification sections. The drawings call for work with no specification section: precast hollow-core plank, cast stone, fences/gates/operators (C02.00 notes "ref project manual"), site earthwork, aggregate base, asphalt paving, vehicular concrete paving, curb and gutter, pavement markings, erosion control, lube equipment and hose reels, bridge crane, generator relocation, and access control/CCTV. Please confirm that the Escambia County Technical Specifications and FDOT Standard Specifications govern the site items and manufacturer standards govern the others, or issue the sections.

    The County confirms that the Escambia County Technical Specifications and applicable Florida Department of Transportation (FDOT) Standard Specifications shall govern the sitework and civil construction items identified in the RFI, including earthwork, aggregate base, asphalt paving, vehicular concrete paving, curb and gutter, pavement markings, and erosion control, as applicable. The following clarifications and revisions will be incorporated into the Contract Documents through a forthcoming Addendum: 1. Precast Hollow-Core Plank: Specification Section 03 4100 – Precast Structural Concrete will be added to the Project Manual. 2. Cast Stone Coping: Specification Section 04 2000 – Unit Masonry will be revised to include an additional article addressing cast stone coping units and associated material and installation requirements. 3. Fencing: Chain-link fencing indicated on the Civil Drawings shall comply with the applicable Escambia County Standard Fence Specifications. Specification Section 32 3119 – Decorative Metal Fences will be added to the Project Manual. 4. Gates and Operators: Applicable specification sections addressing gates and gate operators have been added to the Project Manual and will be included in the forthcoming Addendum. 5. Lubrication Equipment: A separate specification section is not required. Refer to the Contract Drawings and applicable manufacturer requirements. 6. Hose Reels: A separate specification section is not required. Refer to the Contract Drawin

  • Structural redesign contingency. S001 General Note 9 requires the contractor to carry a contingency for structural redesign and construction if MEP or elevator equipment differs from the pre-bid basis. Bidders cannot price an undefined redesign. Please delete the note or define the basis to be carried.

    Note #9 on general notes will be omitted from S001 in addendum.

  • Exterior building signage. No exterior building identification signage or lettering is shown on any building elevation. Please confirm whether any is required and, if so, provide the design. Also confirm whether a site monument/entry identification sign is required (none shown on site or landscape sheets).

    All exterior building identification signage, lettering, and site monument/entry identification signage, if required, shall be furnished and installed by Escambia County. These items are excluded from the Contractor’s Scope of Work and shall not be included in the Contractor’s Base Bid. The applicable signage Specification Section will be removed from the Project Manual through a forthcoming Addendum.

  • Gas service. MT000/MW000 state that the gas service, meter and regulator are by the utility and paid by the Owner. MT500/MW500 state that the mechanical contractor is responsible for all new service and meter fees. Underground gas from the meter is noted "see civil" but is not shown on the civil sheets. Please confirm that Pensacola Energy service lines, meters and fees are by the Owner.

    Note on MT500/MW500 will be removed. Meter and regulator will be by utility and paid for by the owner. Gas utility company is responsible for installing services to be coordinated with GC.

  • Electric utility. EM600 names "American Midwest Power" while other sheets reference FPL. Please confirm the electric utility, and that utility fees, primary service and transformer are by the Owner/utility.

    Will be coordinated to FPL via Addendum

  • Inter-building fiber and conduit. Fire alarm panels connect to the master FACP in the Maintenance Building by fiber, and IDFs connect to the MDF. Please confirm that the inter-building conduits are BP1 and identify who furnishes and pulls the fire alarm and telecom fiber.

    The inter-building conduits required for fire alarm and telecommunications backbone connectivity are included in Bid Package 1 (BP1). Security Engineering, the Owner's designated technology and security systems vendor under contract with the Escambia County Facilities Management Department, shall furnish, install, and terminate the inter-building fiber-optic cabling. The fiber-optic backbone shall consist of twenty-four (24) strands of single-mode fiber, sized to accommodate the fire alarm, telecommunications, and other systems requiring backbone connectivity between the buildings. The Contractor shall coordinate the required conduit pathways and associated infrastructure with Security Engineering to ensure compatibility with the Owner-provided fiber-optic system.

  • Elevator. Spec 142400 calls for a holeless hydraulic elevator with the machine in an adjacent machine room, but the basis of design (TK Elevator endura) is machine-room-less, and no machine room is shown on A110. The door type is also stated as both single panel and center opening. In addition: (a) the specified 150 fpm exceeds the typical holeless hydraulic range (125 fpm max for some named products); (b) the spec requires a car large enough for a stretcher, which a 3,000 lb car in the hoistway shown cannot accommodate; and (c) the spec requires standby (emergency) power operation, but no generator or ATS serves the Administration Building elevator - is battery lowering acceptable? Please confirm MRL, door configuration, speed, car size and the emergency power method.

    The Architect of Record (ADG) has evaluated elevator configurations from two manufacturers to verify compliance with Florida's ambulance stretcher accommodation requirements. The Administration Building elevator shall be served by emergency power supplied from the Maintenance Building generator. The Design Team will revise the applicable Contract Drawings and Specification Section 14 2400 to clarify the elevator configuration, including machine-room requirements, door arrangement, operating speed, car dimensions and capacity, stretcher accommodation, and emergency power provisions. All applicable revisions and clarifications will be issued through a forthcoming Addendum.

  • Hardened and ballistic glazing. GL3 is described as a "1-inch IGU (hardened area)" at doors 112 and 150A and other lites, and A110 shows a "bullet-proof glass window" at Reception. Please define the criteria (UL 752 level, impact rating, forced-entry rating) and the extent of each.

    The Design Team will revise the Administration Building drawing sheets, along with the applicable Project Manual specifications, to clarify the requirements for hardened and ballistic-resistant glazing. The revisions will identify the required glazing locations and extent of protection, including applicable ballistic-resistance classifications, impact-resistance criteria, and forced-entry requirements, as applicable. The revised drawings and specifications will be issued through a forthcoming Addendum.

  • 1-hour floor assembly. G001 requires a 1-hour horizontal assembly between the 2nd floor (A-3) and 1st floor (B), with SFRM per Spec 078100. Please provide the UL design number and the extent of SFRM, and confirm how it relates to the PT6 painted exposed structure called for on A113.

    Revision to 'UL-Rated...' note on 2/G001 to read: "UL D902: 4-1/2" NORMAL-WEIGHT CONCRETE OVER 2", 20 GA VULCRAFT 2VLI COMPOSITE METAL DECK. PROVIDE SFRM AT SUPPORTING STRUCTUAL STEEL AS REQUIRED BY UL DESIGN FOR 1-HOUR RATING. METAL DECK TO REMAIN UNPROTECTED."

  • PEMB envelope. Spec 133419 requires a standing-seam roof with a 20-year weathertightness warranty and corrugated wall panels over sheathing, WRB and continuous insulation. The drawings show a PBU exposed-fastener roof, MBCI FW-120 and PBU wall panels, and vinyl-backed insulation. Please confirm which governs. A 20-year weathertightness warranty is not available on a PBU roof.

    The Maintenance Building is designed to utilize a Pre-Engineered Metal Building (PEMB) manufacturer-furnished standing-seam metal roof panel system. PBU or other exposed-fastener roof panels are not the intended or acceptable roof system. The standing-seam roof system shall comply with the applicable requirements of Specification Section 13 3419, including the specified 20-year weathertightness warranty. The Design Team will revise the applicable Contract Drawings and specifications to resolve discrepancies between the specified and illustrated roof and wall panel assemblies, including panel types, insulation systems, and associated building envelope requirements. These revisions and clarifications will be issued through a forthcoming Addendum.

Plain text

OpenGov categories

  • 90921 · Building Construction, Industrial (Warehouse, etc.)
  • 90922 · Building Construction, Non-Residential (Office Bldg., etc.)
  • 90924 · Building Construction, Commercial and Institutional
  • 90930 · Building Construction (Not Otherwise Classified)