Development of the Tampa International Airport Central Warehouse and Logistics Center
Description
The Authority is seeking Responses from qualified Respondents to design, construct, and manage the development of the Central Warehouse and Logistics Center. Introduction The Hillsborough County Aviation Authority (Authority), an independent special district, issues this Invitation to Negotiate (Solicitation) for Development of the Tampa International Airport Central Warehouse and Logistics Center at Tampa International Airport (Airport). The Authority welcomes responses to this Solicitation (Responses) from all national, regional and Florida firms. The firms who submit a Response to this Solicitation (singularly Respondent, collectively Respondents) must meet the minimum qualification requirements as specified in the Respondent Questionnaire, Minimum Qualifications on the Authority’s e-Procurement Portal hosted by OpenGov Procurement at https://procurement.opengov.com/portal/tampaairport . Summary Background Contact Information Timeline Solicitation Documents This Solicitation is comprised of multiple documents each with a specific purpose as detailed below. The Solicitation Documents are posted on the Authority website and are available for download at www.TampaAirport.com Business & Careers Business Opportunities Solicitations. Attachments A through C are attached hereto and made a part hereof. Attachment A - Project Manual A comprehensive compilation of preliminary specifications to assist Respondents in reviewing and guiding them to what the Authority is looking for with this development. Attachment B - Ground Lease Agreement The lease agreement between the Awarded Respondent and the Authority for the development of the proposed Central Warehouse and Logistics Center building. Attachment C - Scoring Ranges Provides the scores associated with each technical evaluation criterion that will be used to score Responses. Scope of Work The proposed Central Warehouse and Logistics Center will include dedicated space for the Authority Procurement Department’s warehouse operations, as well as flexibility for future expansion or integration of additional Authority functions. The Scope of Work includes, but is not limited to, comprehensive design, site preparation, permitting, construction, utility connections, paving, stormwater management, landscaping, leasing, management, and coordination with existing infrastructure and adjacent properties. Additionally, within five years after Authority purchases the Central Warehouse and Logistics Center, the Authority reserves the right to negotiate with the Awarded Respondent to develop an additional warehouse building. A more detailed description of the Scope of Work, a conceptual site plan, renderings, technical requirements, and performance specifications are provided in Attachment A, Project Manual. Ground Lease Agreement and Development Overview The approximate 11.41-acre site is north of W. Osborne Ave., east of N. Westshore Blvd., west of Air Cargo Rd., and south of the CAE campus. The site will be delivered in its current condition. A survey is included with the Project Manual (Attachment A) as Exhibit G, Site Survey. Based on preliminary review by the Authority, the site could potentially accommodate approximately 150,000 +/- square feet of warehouse space, of which the Authority would occupy approximately 60,000 +/- square feet of such warehouse space. The Awarded Respondent will provide all outdoor storage, parking, vehicular use areas, utilities, and any other required site improvements. The Term of the Ground Lease Agreement (Attachment B) will be fifty (50) years. The Authority will enter into an Authority Lease Agreement (Exhibit B to the Ground Lease Agreement) with the Awarded Respondent for approximately 60,000 +/- square feet of space in the proposed Central Warehouse and Logistics Center building. The exact square footage will be determined upon completion of the design for the Authority’s tenant improvements. The Awarded Respondent will be responsible for the design and construction of the proposed Central Warehouse and Logistics Center building. As part of the Project Manual (Attachment A), the Authority has provided an outline of specifications that set out the Authority’s expectations for the proposed Central Warehouse and Logistics Center building. Since the Authority will be purchasing the proposed Central Warehouse and Logistics Center building, the Authority will have input throughout the design process of the proposed Central Warehouse and Logistics Center building. The Awarded Respondent will construct the Authority’s tenant improvements as part of the construction of the proposed Central Warehouse and Logistics Center building. Additionally, the Authority may wish to acquire a second warehouse building in the future. Within five years after the Authority’s purchase of the proposed Central Warehouse and Logistics Center building, the Authority reserves the right to negotiate with the Awarded Respondent to develop a second warehouse building for the Authority. Authority has provided the Awarded Respondent with roadway drawings for improvements to W. Osborne Avenue (included as Exhibit M to the Project Manual). It is the responsibility of the Awarded Respondent to have a licensed engineer verify, sign, and seal drawings for use in the Awarded Respondent’s permitting. Awarded Respondent must provide Authority with a projected cost for improving W. Osborne Avenue as part of the cost summary as provided in Section 13.3(A) of this Solicitation. Authority will either provide Awarded Respondent with credit at closing or will pay Awarded Respondent directly for the cost of the W. Osborne Avenue agreed-upon roadway work. Awarded Respondent must install storage racks supplied by the Authority within the Authority space as part of the development of the proposed Central Warehouse and Logistics Center building. Awarded Respondent must deliver the proposed Central Warehouse and Logistics Center building to the Authority with a certificate of substantial completion or a certificate of occupancy by December 2028. Definitions Airport Tampa International Airport. Airside Terminals The five buildings designated as A, C, D, E and F supporting passenger airline operations which are connected to the Main Terminal and through which passenger aircraft are loaded or unloaded. Attic Stock Extra, uninstalled building materials or replacement parts left over from a construction or renovation project and saved for future repairs. Authority Business Days 8:00 a.m. to 5:00 p.m., Eastern Time Zone, Monday through Friday, with the exception of Authority holidays. Awarded Respondent The Respondent that is awarded the Ground Lease Agreement. Board The Hillsborough County Aviation Authority Board of Directors. Central Warehouse and Logistics Center The centralized facility designed to support the Authority and its tenants' storage, handling, distribution, and logistics needs including, but not limited to, materials management, supply chain operations, and related support services. CEO The Hillsborough County Aviation Authority Chief Executive Officer. Key Personnel The essential employees, managers, or project leaders whose specialized skills, leadership, and daily decisions are critical to the success and smooth operation of a specific project. Main Terminal The nine-level central passenger terminal building at the Airport that contains: Level 1-baggage claim; Level 2-airline ticket counters; Level 3-transfer to Airside Terminals; Levels 4 through 9 - six (6) short-term parking levels; and Levels 1 through 8 – eight (8) long-term parking levels. Project Manager The individual designated by Respondent who will be responsible for coordinating and overseeing the Ground Lease Agreement including, but not limited to, monitoring and interpreting the Services with regard to the quality and manner of performance, and Authority and customer satisfaction with performance levels. Services The services detailed in the Scope of Work. Solicitation Documents All documents related to this Solicitation including, but not limited to, addenda, attachments, and exhibits. Tampa Bay Market The commercial and residential economic landscape covering the Tampa-St. Petersburg-Clearwater metropolitan area. Timeline List of dates, times and locations of various meetings and postings at Section 1, Introduction, above. Pre-Solicitation Meeting Mandatory Pre-Solicitation Conference A Mandatory Pre-Solicitation Conference will be held on the date, time, and location listed in the Timeline. Questions relating to the Solicitation process will be answered at that time. At least one representative for each potential Respondent must attend the Mandatory Pre-Solicitation Conference. Responses submitted by Respondents that did not have a representative in attendance at the Mandatory Pre-Solicitation Conference will be rejected. 1. In-Person Attendance The Mandatory Pre-Solicitation Conference may be attended in person at the location specified in the Timeline. To be considered as attending in person, prospective Respondents must have signed in on a sign-in sheet prior to the start of the Mandatory Pre-Solicitation Conference. Attendees are warned that sign-in sheets will be collected at the start of the Mandatory Pre-Solicitation Conference. Any attendees arriving after the sign-in sheets are collected will not be considered to have attended the Mandatory Pre-Solicitation Conference. 2. Microsoft Teams® Attendance The Mandatory Pre-Solicitation Conference may be attended via online meeting utilizing Microsoft Teams®. To be considered as attending via Microsoft Teams®, the attendee must enter their company name in the chat and be identified by the Procurement Agent at the start of the Mandatory Pre-Solicitation Conference. Online attendees are warned that if the Procurement Agent does not identify the company name before the start of the meeting, they will not be considered to have attended the Mandatory Pre-Solicitation Conference. Online attendance information is provided in the Timeline. Note: If a potential Respondent loses online connection during the Mandatory Pre-Solicitation Conference, that potential Respondent must immediately log back in to the online meeting site. If the potential Respondent is unable to log back in, they should contact the Procurement Agent. Mandatory Site Tour The Authority will conduct a Mandatory Site Tour following the Mandatory Pre-Solicitation Conference. Only two representatives per company will be allowed to attend the Mandatory Site Tour. To be considered as attending the Mandatory Site Tour, a potential Respondent must have signed in on a sign-in sheet prior to the start of the Mandatory Site Tour. The Mandatory Site Tour must be attended in person at the location specified in the Timeline. Attendees arriving after the sign-in sheets are collected will not be considered to have attended the Mandatory Site Tour. Meeting Rooms Any person requiring a special accommodation to attend a public meeting because of a disability or physical impairment should contact the Procurement Agent at least 48 hours prior to the scheduled public meeting. Authority Boardroom - SkyCenter Authority Boardroom - SkyCenter is located on the fourth floor of the SkyCenter Office Building. Access to the Boardroom is through the SkyCenter Atrium by going to the fourth floor of the Atrium and then going to the north side of the Atrium where the Atrium meets the SkyCenter Office Building. The Boardroom is located to the left of the Authority receptionist counter. Parking: Parking for the public to access SkyCenter is in the Economy Parking Garage. Respondent will follow signs to Economy Parking Garage. Once parked in the Economy Parking Garage, Respondent will access SkyConnect by taking the elevators located on Level 1 of the Economy Parking Garage. Respondent will then take SkyConnect to the Rental Car Center and exit SkyConnect. Turn right and follow the signs to SkyCenter. Central Warehouse Conference Room Central Warehouse Conference Room is located at 5008 N. West Shore Blvd., Tampa, FL 33614. Parking : Parking for the public is available in the surface lot directly outside the lobby. RCC Conference Room - Rental Car Center RCC Conference Room is located on the third floor of the Rental Car Center. Upon exiting SkyConnect, walk towards the Remote Baggage drop-off area. The door to the RCC Conference Room is immediately across the main hall on the left of the Remote Baggage drop-off area. Parking : Parking for the public to access RCC is in the Economy Parking Garage. Respondent will follow signs to the Economy Parking Garage. Once parked in the Economy Parking Garage, Respondent will access SkyConnect by taking the elevators located on Level 1 of the Economy Parking Garage. Then take SkyConnect to the Rental Car Center and exit SkyConnect. Response Evaluation Objective Per the negotiation process provided below, it is the intention of the Authority to evaluate the qualifications of the Respondents, taking into consideration the evaluation criteria set forth in this Solicitation, negotiate exclusively with the top scored Respondent or concurrently with the highest-scored Respondents, and award of the Ground Lease Agreement to the Respondent whose terms are most favorable to the Authority and whose Response is determined to serve in the best interest of the Authority. The Authority reserves the right to request additional information and clarification of any information submitted, including any omission from the original Response. All Responses will be treated equally with regard to this item. All Responses that meet the minimum qualifications will be evaluated as defined in Section 13, Evaluation Criteria below. Evaluation Criteria The evaluation criteria have been established to determine which Response best meets the requirements and overall goals of the Authority and provides the best value to the Authority. The evaluation criteria are defined in Section 13, Evaluation Criteria. The evaluation will determine which Respondent or Respondents will be included in the negotiation phase. Technical Evaluation A technical evaluation committee, consisting of Authority staff and, as applicable, industry representatives, will evaluate all qualified Responses. Each evaluation criterion will be evaluated based on the factors set forth in Section 13, Evaluation Criteria, and scored from 0 (non-responsive) to the maximum points for that criterion, as listed in Section 13. The criteria and associated maximum points are listed under Section 13, Evaluation Criteria. Shortlisting Process A shortlisting process will be used if four or more Responses are received. The Vice President of Procurement will determine a shortlist of no less than three Respondents based on the following calculation. NOTE: This calculation process is solely to determine the shortlisted Respondents and will not change scores given to each Respondent in each evaluation criterion by the technical evaluation committee. The score associated with the lower end of the Good to Adequate range for the Interviews evaluation criterion will be added to the score of the Response, which is, at that time, ranked third. For this Solicitation, the value of the lower end of the Good to Adequate range is 5. (See Attachment C, Scoring Ranges); and The maximum score associated with the Best range for the Interviews evaluation criterion will be added to all Responses that are, at that time, ranked fourth and below. For this Solicitation, the maximum score for the Best range is 10. (See Attachment C, Scoring Ranges); and Responses that were ranked fourth and below prior to the above calculations, whose score now equal or exceed the scores of the third-ranked Response, will be included in the shortlist. Where the shortlisting process is utilized, only shortlisted Respondents will be scheduled for an interview with the technical evaluation committee. A shortlisted respondent may elect, in writing, not to participate in the interview and will receive a score of zero for the Interviews evaluation criterion. The final ranking of the shortlisted Respondents will be used to determine the Respondent(s) selected for negotiations. Interviews The Authority will schedule interviews with the short-listed Respondents or, if the short-list process is not utilized, all qualified Respondents, as part of its technical evaluation process. Information provided by Respondents, including content and style, will be part of the evaluation process. The individual identified in the Response as the person who is authorized to make representations for the Respondent, and the proposed Project Manager must attend the interview. All Respondent’s representatives are expected to participate in the interview. Participation from Respondent’s representatives will be included in the evaluation scoring. A copy of any written information covered during the interview, whether hard copy or electronic format, must be furnished to the Authority at the time of the interview. Interviews are not open to the public. A Respondent may elect, in writing, not to participate in the interviews and will receive a score of zero for the Interviews evaluation criterion. Following interviews, the technical evaluation committee will conduct a public meeting to evaluate the qualifications of each Respondent, based on all information supplied in the Responses and the results of the interview. The technical evaluation committee will score the Respondents in order from the most qualified to least qualified to provide the requested Services and will determine the recommended short list of Respondent(s) with which the Authority may negotiate upon approval by the Vice President of Procurement. Negotiation Process The Authority intends to negotiate with the highest-scoring Respondent(s), as the case may be, either in exclusive or concurrent negotiations. All written communications during the Solicitation process and negotiation phase will only be conducted between the Procurement Agent and the Respondent(s). Following the Vice President of Procurement’s approval of the intent to negotiate with shortlisted Respondents, the Authority will distribute the Ground Lease Agreement in Microsoft® Word form to shortlisted Respondents and request their redlined changes. The Authority may also request additional information at this time. Following that, the Authority negotiation team will begin exclusive or concurrent negotiations, as the case may be, with the Respondent(s). The Authority's negotiation team, which may include one or more members of the technical evaluation committee, additional Authority staff, external technical experts, consultants or outside counsel, Authority Procurement staff, and Authority Legal Affairs staff, as needed, will conduct the negotiations in person, via telephone, or via Microsoft Teams. If a Respondent intends to be accompanied at any of the negotiation meetings by legal counsel, the Respondent shall give the Procurement Agent at least three (3) business days’ notice of such. The negotiations will be conducted to review the terms and conditions of the Ground Lease Agreement, clarify necessary details and responsibilities, emphasize important issues, resolve minor differences and typographical errors, and obtain the best value for the Authority. Negotiations will not constitute an award, nor will they confer any rights on the Respondent(s). Further, the Authority reserves the right to terminate the negotiation process with any Respondent at any time or to terminate all negotiations at any time up to the Notice of Intent to Select and Award, without prior notice and without liability of any kind or amount. Negotiations will occur prior to selection and award by the Authority Board. Any Respondent exception, stipulation, counteroffer, r
Published attachments
Addenda and notices
Addendum #1 · 1
Please use the See What Changed link to view all the changes made by this addendum.
Official Notice #1: Pre-Solicitation Conference Presentation and Sign-In Sheets (Mandatory) · 1
Addendum #2 · 2
Please use the See What Changed link to view all the changes made by this addendum.
Addendum #3 · 3
Addendum #4 · 4
Please use the See What Changed link to view all the changes made by this addendum.
Addendum #5 · 5
Please use the See What Changed link to view all the changes made by this addendum.
Public questions and answers
Regarding the Tampa International Airport Central Warehouse and Logistics Center solicitation: Please clarify whether third-party structural steel/welding inspection (AWS-CWI) and nondestructive testing (NDT) services, if required, will be procured directly by the Hillsborough County Aviation Authority or furnished by the selected developer, general contractor, or specialty subcontractors. If these services are developer/contractor-furnished, please identify any applicable inspection requirements or specifications in the Project Manual.
This question will be answered in an addendum.
Section 14.1.8 states 3 project in Fl only that represent 75,000 sq ft(note your form asks for 60,000 sq ft) We have a national footprint in this type of work including 1 million sq ft logistics center for General Motors in Kentucky My question is, are we to only include Fl projects and if not will our scoring be affected. Thank you
This question will be answered in an addendum.
Section 14.1.8 of the Invitation to Negotiate for Development of the Tampa International Airport Central Warehouse and Logistics Center requests demonstration by the Respondent to have served as developer or prime contractor on at least three projects within the State of Florida within the past ten (10) years, meeting certain use and size requirements. With respect to the Respondent, in this context, does that include the principal entity only or is it acceptable for a partnering prime general contractor as part of the Respondent’s project team to hold this minimum qualification?
This question will be answered in an addendum.
Will you be posting a list of the people that attended both pre-bid meetings?
Yes.
Does the Authority intend to purchase the entire warehouse before its rental obligations commence under Exhibit B? Is Exhibit B intended solely as an interim lease pending the Authority's acquisition? If so, what happens to the lease upon acquisition? Will the Authority consider commencing rent upon CO or otherwise compensating the developer for carrying costs before acquisition? Does the Authority anticipate an acquisition price based on development costs plus a return, stabilized property value, or another methodology? Will the purchase price account for rental rates, lease terms, tenant credit, and NOI, or solely the percentage of space leased? Does the 93% leasing threshold apply to the entire building or only non-Authority space? Do executed leases count before rent commencement? Will the Authority consider proposals for ground lease terms longer than 50 years, including a 99-year term? Will the Authority consider a long-term ground lease under which the developer retains ownership of the warehouse rather than requiring the Authority to purchase it under Article 55? What funding source will support the Authority's purchase, and will any additional approvals be required? Does the authority have an anticipated budget for this development? Will the Authority enter into a direct agreement with the construction lender addressing the purchase obligation, lender rights, and acquisition proceeds? Will the purchase price account for additional ground rent, financing, and carrying
This question will be answered in an addendum.
Will the authority provide a copy of the sign in sheets from the pre-solicitation meeting and the mandatory site tour?
Yes.
Will the Authority accept qualifying projects on which the Respondent’s principal(s) personally served as lead developer while employed by a prior development firm, where the Respondent is a newly formed entity controlled by those principals? Alternatively, may the Respondent satisfy 14.1.8 through a combination of its principal’s development experience and its proposed prime general contractor’s experience?
This question will be answered in an addendum.
1. Is LEED certification required for this project? If yes, what level (Certified, Silver, Gold)? If no, will HCAA accept a building designed to energy-code minimums, or to specific sustainable features listed in the Project Manual? 2. The Project Manual says the building envelope must be “Cat 3 hurricane-rated.” Please confirm which of these HCAA means: (a) ASCE 7 Risk Category III for the whole structure; (b) a hurricane wind or impact standard for the envelope only (for example, large-missile impact-rated openings); or (c) something else. 3. On the future rooftop solar: Does HCAA intend to own and install the system, or should the landlord plan for it? 4. Does HCAA have security, access-control or fire-separation requirements for the demising wall between its space (about 60,000 SF) and the spec space, beyond what code requires? 5. What will HCAA store in the 6,400 SF covered outdoor storage area? Does it need fencing, security, lighting or power? 6. Does HCAA want its whole warehouse conditioned, or only the A/C storage and office areas? If partial, what area needs conditioning, and are there temperature or humidity requirements for the stored inventory? 7. Is rooftop HVAC acceptable to HCAA? 8. The HCAA space shows 5 motorized doors. Are they dock-high, grade-level or a mix? For any dock positions, what are HCAA’s leveler capacity and dock package requirements (seals or shelters, vehicle restraints, bumpers)? Do any doors need special lifts or heavier loading? 9. Will st
This question will be answered in an addendum.
On the Acknowledgement of Response, the Respondent is a single-member LLC, may the "Attested By" line be completed by a witness or notary?
This question will be answered in an addendum.
On the Attestation Financial Capacity Form, should the first blank, shown as "Company" be the name of the Respondent's Authorized Signatory?
This question will be answered in an addendum.
Our team is local and has Florida experience however, projects were completed range from 20,000 - 72,000 sf. We were in discussions with a partner who has much larger experience, 75,000+ sf, but not in FL. Can the committee consider loosening these requirements?
This question will be answered in an addendum.
ITN Section 13 (Criterion 2.F) and Section 14.4.13 refer to leasing “the remaining +/-94,000 square feet.” The Ground Lease defines the Building as approximately 150,000 square feet. The Authority Lease (Basic Terms ¶1) describes the Authority Premises as approximately 60,000 rentable square feet, including approximately 6,400 square feet of covered exterior storage. Please confirm (a) whether the 6,400 square feet of covered exterior storage counts toward the Building’s 150,000 square feet, and (b) the leasable area, excluding the Authority Premises, that Respondents should assume in their financial proposals.
This question will be answered in an addendum.
ITN Section 8.4 refers to “Attachment E, Scoring Ranges,” but the Solicitation lists the scoring ranges as Attachment C. Please confirm that Attachment C is the correct reference.
Attachment C is the correct reference.
ITN Section 4 requires delivery with a certificate of substantial completion or certificate of occupancy by December 2028. The Ground Lease allows a 150-day Permitting Period after plan approval (§10.04), construction start within two months after permits (§8.05), and 18 months to complete construction (§8.05). Please confirm (a) which deadline controls, (b) whether the December 2028 date will be extended day-for-day for Authority design-review time and Authority-caused delays, and (c) what consequence, if any, applies if the December 2028 date is missed for reasons other than Company default.
This question will be answered in an addendum.
ITN Section 9.4 states that joint responses will not be accepted. Please confirm that (a) a Respondent may sign the Ground Lease through a newly formed single-purpose affiliate, and (b) the experience of the Respondent’s parent, affiliates, and named team members (general contractor, architect, leasing firm) may be used to satisfy the Minimum Qualifications in Section 14.1.8.
This question will be answered in an addendum.
ITN Section 8.6 says the Ground Lease will be distributed in Word to shortlisted Respondents for redlines. Please confirm (a) whether Respondents should list requested Ground Lease modifications in their Response or hold them for the negotiation phase, and (b) whether listing exceptions in the Response will affect technical scoring.
This question will be answered in an addendum.
Will the Authority provide any existing environmental site assessments (Phase I/II), geotechnical reports, wetland determinations, or title commitments for the Premises before the Response Deadline? These reports are needed to price site work and to establish a baseline environmental condition (see Questions 13 and 14).
This question will be answered in an addendum.
Please identify (a) the current zoning and land use designation for the site and the governing permitting jurisdiction, (b) any known FAA Part 77 height limit for the site, and (c) whether the Authority expects NEPA review to be required (Ground Lease §8.02). If NEPA review is required, please state who will prepare the environmental documentation and the expected duration.
This question will be answered in an addendum.
Ground Lease §16.01 places the burden of verifying utility availability and capacity on the Company. Please provide any information the Authority has on water, sewer, and electric capacity at the site. Please also state whether the site may connect to an existing Authority master stormwater system or must provide all stormwater management on site.
This question will be answered in an addendum.
ITN Section 4 says the Authority will either give a credit at closing or pay the Awarded Respondent directly for the agreed W. Osborne Avenue roadway work. The Ground Lease does not address this. Please confirm (a) that this obligation will be added to the Ground Lease, (b) when direct payments would be made if that option is chosen, and (c) whether the roadway cost should be shown separately from, and excluded from, the Purchase Price in Section 55.02.
This question will be answered in an addendum.
Please confirm whether the W. Osborne Avenue improvements are in public right-of-way and, if so, which agency issues the permits and accepts the improvements. Please also confirm whether delays in that off-site work will extend the delivery date.
This question will be answered in an addendum.
Regarding the Authority-supplied storage racks (ITN Section 4), please describe the expected quantity, type, and delivery date. Please also confirm whether rack anchoring and engineering, slab design loads, and fire-suppression requirements for high-piled storage are the Respondent’s responsibility and should be included in the Purchase Price.
This question will be answered in an addendum.
Authority Lease §17.1.2 requires the Landlord to build the Tenant Improvements at its sole cost in turnkey condition, under a work letter (Exhibit F). Please provide the Exhibit F work letter or the Authority’s TI scope and specifications, so Respondents can price the Tenant Improvements. Please also confirm that the TI cost may be included in the Purchase Price.
This question will be answered in an addendum.
Please confirm that the Authority’s obligation to purchase the Company’s Interest under Section 55.01 is a binding obligation once the Ground Lease is approved by the Board. Please also confirm whether it is subject to any further Board appropriation, bond issuance, FAA approval, or other condition beyond those in Section 55.03.
This question will be answered in an addendum.
The Ground Lease does not provide a remedy or an outside closing date if the Authority does not close under Article 55. Respondent requests that the Ground Lease add (a) a firm outside closing date, and (b) a remedy, such as specific performance or reimbursement of the Company’s documented development costs. Justification: the purchase is the primary source of repayment for construction financing, and lenders will need certainty of the takeout.
This question will be answered in an addendum.
Section 55.03 makes the purchase conditional on an environmental site assessment showing no new recognized environmental condition since the date the Ground Lease is signed. Respondent requests that the parties set a baseline environmental condition at the Effective Date, for example through a Phase I/II commissioned before signing, and that the baseline be attached to the Ground Lease. Justification: without a documented baseline, it cannot be determined whether a condition is “new.”
This question will be answered in an addendum.
For the Purchase Price grid in Section 55.02 and the 93% test in Section 55.01, please define when space is “leased.” For example, is it a fully executed lease, rent commencement, or occupancy? Please also confirm whether the Authority Premises count toward the 93% figure.
This question will be answered in an addendum.
Please confirm whether the Purchase Price should assume that the Company pays ground rent from the Commencement Date through closing, or whether ground rent paid before closing will be credited at closing.
This question will be answered in an addendum.
Section 5.02(c) starts the Term and Rent 20 months after the Effective Date, even if construction is not complete. Respondent requests that the Commencement Date be the earlier of (a) the certificate of occupancy or (b) occupancy, with clause (c) removed or extended to match the construction schedule in Section 8.05. Justification: the Authority’s own review periods and the 150-day Permitting Period may push completion past 20 months through no fault of the Company.
This question will be answered in an addendum.
Section 6.01(C) applies the 3.25% annual increases from anniversaries of the Effective Date. Respondent requests that increases run from anniversaries of the Commencement Date. Justification: tying increases to the Effective Date raises rent before any rent is payable.
This question will be answered in an addendum.
Since the Authority will buy the Company’s Interest shortly after the certificate of occupancy, Respondent requests that ground rent paid by the Company before closing be credited against the Purchase Price.
This question will be answered in an addendum.
Section 20.01 requires Payment Security equal to three months of Rent on or before the Effective Date, although rent may not begin for up to 20 months. Respondent requests that the Payment Security be due on the Commencement Date and be released at closing under Article 55.
This question will be answered in an addendum.
Article 60 refers to a guaranty “if needed.” Please state whether a guaranty will be required and, if so, its scope. Please also confirm that any guaranty would terminate at closing under Article 55.
This question will be answered in an addendum.
Section 12.01 treats failure to sign the Authority Lease within 180 days of the Effective Date as a Company default. Since signing requires both parties, Respondent requests that this be changed to a mutual obligation, or to a condition that does not create a Company default. Respondent also asks whether the Authority Lease can be signed at the same time as the Ground Lease.
This question will be answered in an addendum.
The Authority Lease Commencement Date is the later of Authority occupancy or six months after the certificate of occupancy for the Premises. The Initial Closing Date under Section 55.01 is three months after the certificate of occupancy. Please confirm (a) the Authority’s intent for how these dates relate, and (b) that the Authority will pay Basic Rent and Tenant’s Share of Expenses under the Authority Lease if closing is extended to the Extended Closing Date.
This question will be answered in an addendum.
The Ground Lease sets a 150-day Permitting Period (§10.04) but gives no remedy if Governmental Approvals cannot be obtained despite the Company’s good-faith efforts. Respondent requests a right for either party to terminate in that event, with return of the Payment Security and no further liability. Justification: entitlement risk on Authority-owned land is partly outside the Company’s control.
This question will be answered in an addendum.
Please confirm that the two-month construction-start period in Section 8.07(A) runs from the date all permits are obtained, as in Section 8.05, and is extended for Force Majeure and Authority delays.
This question will be answered in an addendum.
Section 12.02 makes it an Event of Default to lease to third parties on any form other than Exhibit C. Respondent requests the ability to make commercially reasonable changes to Exhibit C in individual leases, with Authority approval of material changes within a stated period (for example, 10 business days). Justification: individual tenant negotiations will require some changes to the form.
This question will be answered in an addendum.
For Permitted Subleases that need Authority approval of financial terms under Section 32.01, please state how long the Authority will take to respond, and whether a deemed-approval mechanism like the one in Section 10.04 will apply.
This question will be answered in an addendum.
Respondent requests that the following be excluded from the change-of-control provision in Section 32.01 and the Right of First Refusal in Section 32.05: (a) transfers to affiliates, (b) admission of capital or JV equity partners where the Respondent or its affiliate keeps management control, and (c) transfers to or by a Leasehold Mortgagee through foreclosure or deed in lieu. Please also confirm that the ROFR does not apply to the Authority’s own purchase under Article 55.
This question will be answered in an addendum.
Section 33.01 limits construction loans secured by Leasehold Mortgages to 80% of actual cost. Please confirm (a) whether mezzanine financing or preferred equity that is not secured by the leasehold is permitted and outside the 80% limit, and (b) which costs count as “actual costs incurred,” for example whether soft costs, financing costs, and carried ground rent are included.
This question will be answered in an addendum.
Section 19.02(F) requires the Company to indemnify the Authority for losses from any interruption of the Company’s operations “regardless of the cause” if the Company does not carry business interruption insurance. Please clarify what Authority losses this is meant to cover. Respondent requests that this indemnity be deleted, or limited to interruptions caused by the Company.
This question will be answered in an addendum.
Article 18 requires indemnity and defense for claims caused in part by the Authority’s own negligence. Respondent requests that indemnity be limited to the extent a claim is caused by the Company or persons acting for it, consistent with Fla. Stat. §725.06.
This question will be answered in an addendum.
Under Sections 21.03 and 21.06(B), the Authority decides whether to rebuild after a major casualty, and leftover insurance proceeds are shared with the Authority pro rata over the 50-year Term. Respondent requests that, for a casualty before closing under Article 55, the Company may choose to rebuild, the purchase obligation stays in effect, and proceeds go to the Company and its Leasehold Mortgagee.
This question will be answered in an addendum.
Section 8.11 gives access to records of parent, affiliate, and subsidiary companies. Respondent requests that this be limited to records directly related to the Project. Please also confirm that the record-keeping and audit obligations in Sections 8.10 and 8.11 end, as to post-closing periods, at closing under Article 55.
This question will be answered in an addendum.
Please confirm the Authority’s understanding of how ad valorem taxes will apply to the Company’s leasehold interest and Improvements before closing. Please also confirm whether the Authority Premises are expected to be exempt, as Exhibit C, Basic Terms ¶6 suggests.
This question will be answered in an addendum.
Article 51 says the Ground Lease may require FAA approval. Please confirm whether FAA approval is expected, the expected timing, and whether it must be obtained before the Effective Date or before construction starts.
This question will be answered in an addendum.
ITN Section 14.4.13 asks Respondents to address revenue from exterior tenant signage. Ground Lease Section 4.03(K) prohibits outdoor advertising from which the Authority would normally earn revenue. Please confirm that tenant identification signage on the Building is allowed, subject to approval under Article 31, and that the Company may keep any related revenue.
This question will be answered in an addendum.
OpenGov categories
- 90610 · Buildings - Architectural Design
- 90625 · Design Build Services
- 90638 · General Construction - Architectural
- 90910 · Airport Facility Construction
- 90921 · Building Construction, Industrial (Warehouse, etc.)
- 90930 · Building Construction (Not Otherwise Classified)
- 91200 · Construction Services, General (Incl. Maintenance And Repair Services)
- 92537 · Facilities Design Services, Engineering
- 96791 · Warehouse and Storage Equipment Manufacturing Services
- 97191 · Warehouse Rental or Lease